Project Planning and Control Template For Exercise 10

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Project planning and Control

Template for Exercise 10

Student Name: ________________________________ Group name: _________________


Early start Gantt Chart
Week 1 Week 2 Week 3
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Duration Cost/day Budget
A 3
B 6
C 5
D 5
E 3
F 5
G 3
H 2
Total
Late start Gantt Chart
Week 1 Week 2 Week 3
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A
B
C
D
E
F
G
H

Critical path:

Week 2 Earned Value Analysis


Activity Budget % BCWP BCWS ACWP SV CV SPI CPI
A
B
C
D
E
F
G
H
Total

Progress Report

1
Cost Estimate at Completion (at week 2)
Original Approach Revised Approach Stick to the Original schedule
EAC = BAC - CV EAC = BAC / CPI EAC=
EAC = EAC =
Time estimation at Completion (at week 2)
We need to do EV analysis again along the critical path. See the table below.
Activity Budget % BCWP BCWS SPI

Total
1. For the whole project approach:
2. Individual approach:
3. Stick to the original approach:
Week 3 Earned Value Analysis
Activity Budget % BCWP BCWS ACWP SV CV SPI CPI
A
B
C
D
E
F
G
H
Total

Progress Report

2
Cost Estimate at Completion (At week 3)
Original Approach Revised Approach Stick to the Original schedule
EAC = BAC - CV EAC = BAC / CPI EAC=
EAC = EAC =
Time estimation at Completion (at week 3)
We need to do EV analysis again along the critical path. See the table below.
Activity Budget % BCWP BCWS SPI

Total
1. For the whole project approach:
2. Individual approach:
3. Stick to the original approach:

You might also like