Professional Documents
Culture Documents
Part 1: Insurance: Insurances - in General
Part 1: Insurance: Insurances - in General
PART 1: INSURANCE
Insurances – in general :
• To deal with ‘risks’ (eg accidents, fire, flood
collapse, damage, etc)/general public
• To enable the Contractor to overcome the
financial impact of realised risks, so he can
finish the job!
• The requirement for Insurance is stipulated in
Contract, because Employer also wants
Contractor to finish the job!
Insurances :
1. The INSURANCES required under Cl. 19 & 20 are to
‘backup’ / ’support’ – and do not prejudice - the
INDEMNITIES that the Contractor shields the
Employer with (against 3rd party claims) under Cl.18,
for:
(such that contractor is liable –
Does not mean the contractor can pay up -> ir unable to pay up,
The remaining amount comes back to the employer ->
Hence employer wants to be insured against this.)
- 18(1) Personal Injuries
- 18(2) Damage to Property
1. Cl. 19 requires insurance against injury to persons
and damage to property – ie “Public / 3rd-Party
Liability” insurance.
2. Cl. 20 requires insurance to pay for replacement of
destroyed / damaged Works – ie “CAR” insurance..
Insurances … a recap:
The Insurances usually have two modes
(reflecting different risk profiles to the insurer):
1. Occurrences ‘pre-completion’ – ie Work Site activities.
2. Occurrences ‘post-completion’ – ie Occupied
premises
Note that Employer’s insurance usually only kicks in for
‘occupancy’ (ie upon ‘handover’) …
… so contract documents often specify coverage
periods such that ‘pre-completion’ insurance overlaps
‘handover’.
(take value of 100% completion. Fire may come just before u finish.)
Sub-Contractor cf Supplier
» SUB-CONTRACTORS (Designated or Nominated)-
• 28(1)(a) : carry out works or carry out works and
supply materials or goods
» SUPPLIERS (Designated or Nominated)-
• 28(1)(b) : for the provision or supply of goods or
materials only, without any work of fixing
installation, erection or construction.
Nomination cf Designation
• The difference between ‘designated’ and
‘nominated’ sub-contractors or suppliers?
» DESIGNATED Sub-Contractors or Suppliers
• Clause 28(1)(c) : where the identity of the subcontractor
is stated in the Specification or other
Contract Documents./ tender documents
• [May include persons with whom the Employer or
the Architect on his behalf has entered into
contractual relations before this Main Contract on
terms that such prior contracts with the Employer
will be novated in favour of the Contractor.]
Hence, DESIGNATED & NOMINATED is sameish, just WHEN the identity is disclosed to the
contractor.
• Note:
Such prior contracts with the Employer
typically involves in practice:
1. the Employer (or Architect on his behalf) issuing an
invitation to quote to potential designated
subcontractors (including to state the terms of subcontract
- eg citing the SIA standard form of subcontract,
plus particular terms of scope of works, etc,
and stating that the contract will be ‘novated’ to the Main
Contractor once appointed).
2. obtaining ‘quotations’ then selecting one and issuing a
‘letter of award’ (stating acceptance of the quoted offer
and confirming they will be ‘designated’ in the main
contract documents).
Nomination of a NSC/S
» Clause 29(1) explains how;
• An NSC/S is nominated through an “instruction
from the Architect … [that] shall identify with
sufficient particularity the works or materials to be
carried out or supplied … [and that] shall identify
the Sub-contractor or Supplier selected by him...”
• This is referred to as a “Nomination Instruction”
Things that the main contractor is responsible for, thus needs support from sub contractors for him to comply to his
obligations. No acceptable for sub contractor to deny responsibility for these n leave the main contractor in the
lurch, if they were to do something wrong.
Consider …
• Be careful of 'down payment' terms in NSC/S
quotations – this exposes the Main Contractor to
up-front payments!
• Should requirements for Performance Bond be
clearly stated as a requirement when calling for
quotes from potential NSC/S?
A “Contingency Sum” :
“shall be valued on the basis that neither the
Contract Period nor the preliminary items of
expenditure in the Schedule of Rates have been
calculated or priced in the expectation of this
work being ordered…”
ie the Contingency Sum represents unknown and
undefined work / supply.
Contingency Sum
(as defined and used in the SIA form of Contract),
… a ‘known unknown’ ! **
- The nature of the work / supply is known, but the
specifics are unknown.
eg a Contingency Sum for ‘structural repairs’ to be
determined during the works when damage is
discovered upon being uncovered
** whereas an ‘unknown unknown’ is a totally unforeseeable event /
condition for which an amount is reserved
u might wna put aside some money that might occur even if u cant be sure if it will. But put the money aside
just in case.
Provisional Sum
(as defined and used in the SIA form of Contract):
eg refer to Standard Method of Measurement (SMM):
- whereas items of work / supply under a Provisional Sum
may not be “sufficiently precisely described for pricing at
the time of tendering…”
… but as distinct to a ‘Contingency Sum’ :
… they are sufficiently defined / described
such that ‘programming,’ ‘planning,’ and
‘preliminaries’ {ie ‘attendance’} + ‘profit’
can be priced for by the Main Contractor.
Definite scope of work, but not enough detail for price in tender, so just put a provisional
sum to cover for that works in tender first.
Typically required in
description of work item:
• Nature & construction
• How & where included
in the building
• Quantity (extent)
• Specific limitations
Examples:
“Prime Cost Sum” or “Provisional Sum”
- eg Signage, Ironmongery, Sanitary & Plumbing
Wares, Waterproofing, Curtain Walls, Tiles & Stone,
etc
“Contingency Sum” -unforseeable scopes of work
- eg repairs to existing buildings (eg structures,
waterproofing, etc) – of specifics and extent to be
‘discovered’ or ‘determined’ during the works.
• Of particular note:
» Article 4.1: Where Main Contract Conditions are to
apply “mutatis mutandis”
[Latin phrase meaning "by changing those things which need
to be changed" or more simply "the necessary changes
having been made"]
- Contractor …. Sub-Contractor
- Architect / QS / Employer …. Contractor
Allow employer to tell architect -> tell main con -> subcon (so the info is passed down the
chain.)
• Consideration
(ie of mutual benefit or exchange of something of value)
(ie the 'price' of the 'promise')
TERMINATION
(under SIA form of Main Contract)
"https://www.google.com.sg/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&ved=0CB4QFj
AA&url=https%3A%2F%2Fwww.ashurst.com%2Fdoc.aspx%3Fid_Resource%3D4638&e
i=2rO7VLv4HYX78QW_gYLACw&usg=AFQjCNFTkBBJXViGPJ2Q5QsFuOU_vB16Ww "
informs that:
(a) "Strictly speaking "termination" means that the contract is
"discharged", that is, the future, unaccrued obligations owed by the
parties fall away. The contract does not actually cease to exist. Rather,
upon the innocent party electing to treat his liabilities to perform as at an
end, the primary obligations of the party in breach to perform the contract
are replaced by secondary obligations to pay damages for the loss arising
from the breach."
(b) ""Rescission" ... refers to the retrospective avoidance of a voidable
contract. Here the contractual rights and obligations remain in place until
the innocent party opts to rescind the contract, at which point the
rescission operates to render the contract a nullity."
... but what is ‘repudiation by the Contractor ' and ‘general law ' referring to?
" http://www.singaporelaw.sg/sglaw/laws-of-singapore/commercial-law/chapter-26 ”
explains that:
"In the absence of express agreement or contractual termination
provisions, the common law enables an innocent party to terminate a
contract in the following circumstances [of repudiation]:
(a). a defaulting party commits a fundamental breach of the contract;
(b). a defaulting party evinces a subjective intention not to be bound
by the contact or an objective indication of inability to execute the
contract properly, for instance by deliberately and consistently
breaching the contract despite repeated warnings or notices by the
innocent party;
(c). where a party informs the other that he does not intend to
perform the contract any longer, or conducts himself in such a manner
as to render his own future performance impossible. This is known as
anticipatory breach."
> WHY? ... In the SIA form: Contractor's 'employment'
is terminated, not the Contract per se : -- keep the contractor running
... because after "termination of the employment of
the Contractor" ...
1. ... the Works still need to be completed by another contractor,
Also: retain NSC/S|DSC/S (to finish off the work, and provide
warranties, etc)
2. ... and the Contractor is subject to a "Cost of Termination
Certificate";
3. ... ie the 'termination terms/clause' still operates after
termination of the employment of the Contractor.
-- we still want certain terms of the contract to operate even tho we have gotten rid of the incumbent
contractor.
Clause 32:
Termination [of Contractor’s employment/services] by Employer
Clause 33:
Termination and Suspension [of Contractor’s employment/services] by
Contractor
Now looking at Clause 32(1): Termination by Employer
without Default by the Contractor:
Clause 32(1) - Employer may terminate the
Contractor's employment/services at any time
and for any reason! (by giving a written ‘Notice
of Termination’ to the Contractor)
Note: if -
» no “Termination Certificate” from Architect …
» no entitlement under general law for Employer to treat
the Contract as repudiated …
… then Contractor is entitled to compensation.
(and Architect has no certifying power as to the amount
of compensation).
Other Clauses:
Clause 32(5) - Damages Contractor’s Only
Remedy
The only remedy to a contractor shall be by :
(a) if 32(1) is applicable: compensation*, else
(b) “in damages.”
*Note: 32(1) states that the Contractor’s entitlement
shall be to “compensation for all damage and loss
suffered by him as a consequence of the termination of
his employment, including loss of profit (if any) on any
uncompleted parts of the Works.”
SO Instructions
» Ref: Clause 2.5
» In PSSCOC there is no type of ‘order’ called a
‘direction’ (only Instructions, but which can operate in
similar way).
» Contractor may, within 7 days, confirm in writing any
oral instruction of the SO and if such confirmation is
not contradicted in writing within 7 days by the SO, it
shall be deemed to be an instruction of the SO.
Security Deposit
» Ref: Clause 4.5
» In PSSCOC there is no Retention Monies
» SITE INFORMATION
• Generally, the Contractor may rely upon site info provided
by the Principal,
• Site Info could be construed as 'misrepresentation' if
found to have errors or inaccuracies –
• Hence the Principal may wish to make a disclaimer on
any liability through disclaiming any warranty on the
accuracy and correctness of the info (making the
tendering contractor take the risk on the accuracy of the
info, else conduct his own surveys and investigations).
• The Principal may also make a term of tendering that the
tenderer shall bear all costs in preparing the tender
submission (ie including the cost of all surveys and
investigations, etc, although the Principal should also
make access to the site available).
Programme
» Ref: Clause 9
» To be submitted within 30d of LOA
» Shall be in the form and in compliance with the
requirements specified in the Contract or otherwise
required in writing by the SO.
[cf “order” and “sequence” req’d in SIA form]
» SO may instruct Contractor to supply additional
particulars or to submit a revised or modified
programme (or both) in order to show and to ensure
completion of the Works within the Time for
Completion.
» Failure to (re)submit Programme: In lieu of termination
of Contract; 10% of interim payments may be retained.
Liquidated Damages
» Ref: Clause 16
» There is no ‘Delay Certificate’
(presumedly as there is no ‘independent certifier).
» If the Works shall not have been substantially
completed within the Time for Completion or any
extended time made pursuant to Clause 14, the
Contractor shall pay or allow to the Employer
liquidated damages calculated at the rate or rates
stated in the Appendix for the period during which the
Works shall so remain incomplete and the Employer
may recover the amount of such liquidated damages
from the Contractor.
Submission of Quotations
No such in SIA
» Ref: Clause 19.3
» The Superintending Officer may, before issuing an
instruction for any variation, require the Contractor to
submit a quotation for any proposed variation and the
Contractor shall be obliged to submit such quotation
in writing at his own cost.
Fluctuations
SIA have, but no standard / mandatory (is optional)
» Ref: Clause 33
» Standard clause, not ‘optional’
» The Contract Sum shall be adjusted upwards or
downwards to take account of any rise or fall
respectively during the currency of the Contract in the
price of each of the materials specified in the
Appendix.
Settlement of Disputes
No such thing in SIA / tho MWC has sth similar in nature.
» Ref: Clause 35
» If a dispute or difference of whatsoever kind shall
arise between the Employer or the Superintending
Officer or the Superintending Officer's Representative
and the Contractor in connection with or arising out of
the Contract or the execution of the Works, ... it shall
in the first place be referred by either party in writing
to the Superintending Officer for his decision.
More Recently:
As part of the government's effort to obtain greater
value for money in government building and
construction procurement, the PSSCOC has
incorporated a new provision (Clause 19.4) to provide
incentives for contractors to offer innovative
proposals which could result in cost savings:
Alternative Proposals by Contractor -
• The Contractor may submit in writing to the
Employer, at his own cost, a detailed proposal for
variations to the Works, which is likely to offer
significant benefits (including long-term or lifecycle
cost benefits) to the Employer.
The payment claim is an activation of a dispute settlement scheme under SOP Act adjudication.
Unlike 9th edition of SIA – no need for a payment claim in MWC to trigger a payment scheme. IT
simply operates under contractual terms, at a particular time, then architect must issue a interim
certificate for payment. Does not have to be a payment claim to trigger that process.
PART 6: SITE MEETING AGENDAS
Things recommended to deal w at site meetings, either as
discussion or things to monitor, because they relate directly to
Contract Administration.
General discussion on
- Site Meeting topics
• Site Meetings are used by the Contract Administrator to, inter
alia :
• (a) monitor compliance with the Contract:
• (i) diligent & expeditious progress (eg on schedule);
• (ii) quality of materials & workmanship -> direction to redo ..
• (iii) proper work methods and site organization
• (iv) proper planning and coordination of the works
• (v) anticipate and avoid delays and problems
• (b) establish records (ie evidence) to support taking of
corrective ‘action’ ... eg 1(7) 9th edn, termination, deductions, etc (Cl. 1(6) in BC2016)
• (c) manage the execution of duties (as contract
administrator) as required under the terms of contract.
Note: Termination of the Contractor’s Employment is either on the grounds for termination
set out in the Conditions, or Common Law rights of fundamental breach of contract. Site
Meetings (and other correspondence) should form documentary evidence of Contractor’s
fault.
In the articles of SIA conditions of contract, architect whose supervision will be carried out.. (as
architect n QP to do supervision n inspection) use site meeting as basis to undertake those
supervisory duties.
there are these other people helping out the Architect w his Contract administration.
So, what does a Contract Administrator do?
- ‘roles’ and ‘duties’ as set-out in the Conditions
of Contract, including to enforce or facilitate
procedure required under the Conditions.
- protect the Employer’s rights (although the
Architect is called upon to act impartially in
some instances), eg to promote the ‘product’
being of required quality, on time, and correct.
- enforce the Contractor’s obligations under the
Contract.
Typical duties:
• Supervision:
» Inspect the Works ;
• to verify that the Works appear to be in
accordance with the requirements of the Contract.
• to verify that the method of working (including site
management and organisation, etc) to be
conducive to a good ‘product.’
• Administrative Control:
» Certification, Orders and Notices
» Supply of Information (to contractor that is needed for contractor to carry out the works
properly)
Orders:
... empowered to give orders ( in the interests of
the project ):
• Instructions
• Directions
Certify:
• Cost of other Contractor’s Work
• Revised Commencement Date
• Delay & Termination of Delay
• Completion
• Partial Re-Entry or Occupation
• Schedule of Defects
• Maintenance
• Interim & Final Payment
• Termination, Cost of Termination and Termination Delay
Notify / Inform:
• Decision on In-Principle Entitlement to EOT
• Decision on EOT
Important reminder:
• Architect is only ‘administrator’ of the contract
– the Employer and Contractor are the
‘parties’ to the Contract.
• Architect only has powers / authority (to the
extent and type) as given under the Contract!
Warning: Acting in excess of powers may render the Contractor
entitled to compensation, or invalidate certificates, etc.
--if the contract does not bestow the power / authority upon u, you do not have any
such power/ authority. Don’t work beyond ur powers. If u work in excess of your
powers -> contractor entitled to compensation / invalidate some of the things you
have done. Always check CONTRACT.
#2
• As 'contract administrator' with bestowed powers,
the Architect assumes a position of 'leadership'
... setting the tone/culture of the project,
... establishing ethical standards,
... applying professional competence and technical
know-how in the design & supervision of the Works
(c.f. Articles 3, 4 & 5 wrt Architect, QS &
Consultants ... 'design' and 'supervision' roles).
• Which also gives the Architect status in the wider
construction industry.
#3
• Professional competency in contract administration
is a significant part of 'architectural services'
... business opportunity.
... (c.f. SIA Scope Matrix: Design, QP, CA, PA/DM)