Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

T&C Progress report

Pre T&C progress


Floor Description 2nd Fix Remainning Work 2nd Fix Obstruction Work Status Site Progres (%) T&C progress %) Total T&C Progress (%) Remark
(%)

Date: 21 - July -2020 Date: 21-July-2020

A. Lighitng system

B2 Installation lighting system along staircase Basement 2 Not yet install lighting fixture all points Waiting installation lighting fixtures 70% 0% 0% 0%

Installation Lighting system at Basement 1, Complete pulling


B1 cable, testing insulation and continuity of cable, and all connection Not yet install lighting fixture all points Waiting installation lighting fixtures 70% 0% 0% 0%
in distribution board.

Installation Lighting system at Ground Floor, Complete pulling


GF cable, testing insulation and continuity of cable, and all connection Not yet install lighting fixture all points Waiting installation lighting fixtures 70% 0% 0% 0%
in distribution board.

Installation Lighiting system at Mezzanine 1, Complete pulling


MF1 cable, testing insulatand continuity of cable, and all connection in Not yet install lighting fixture all points Waiting installation lighting fixtures 70% 0% 0% 0%
distribution board.

Installation Lighting system at Mezzanine 2, Complete pulling


MF2 cable, testing insulation and continuity of cable, and all connection Not yet install lighting fixture all points Waiting installation lighting fixtures 70% 0% 0% 0%
in distribution board.

Installation Lighting system at 1st floor, Complete pulling cable,


1F testing insulation and continuity of cable, and all connection in Not yet install lighting fixture all points Waiting installation lighting fixtures 70% 0% 0% 0%
distribution board.

Installation Lighting system at 2nd floor, Complete pulling cable,


2F testing insulation and continuity of cable, and all connection in Not yet install lighting fixture all points. Waiting installation lighting fixtures 70% 0% 0% 0%
distribution board.

B Power socket Outlet system

Installation Power socket system at Basement 1, Complete pulling


cable, Testing insulation and continuity of cable, installed all
B1 1. Waiting EDC supply / 2. labelling for each socket Waiting finishing 2nd Fix remaining works 90% 0% 0% 0%
devices follow drawing, all connection include for each power
socket and in Distribution board.

Installation Power socket system at Ground Floor, Complete


pulling cable, Testing insulation and continuity of cable, installed
GF 1. Waiting EDC supply / 2. labelling for each socket Waiting finishing 2nd Fix remaining works 90% 0% 0% 0%
all devices follow drawing, all connection include for each power
socket and in Distribution board.

Installation Power socket system at Mezzanine 1, Complete pulling


cable, Testing insulation and continuity of cable, installed all
MF1 1. Waiting EDC supply / 2. labelling for each socket Waiting finishing 2nd Fix remaining works 90% 0% 0% 0%
devices follow drawing, all connection include for each power
socket and in Distribution board.

Installation Power socket system at Mezzanine 2, Complete pulling


cable, Testing insulation and continuity of cable, installed all
MF2 1. Waiting EDC supply / 2. labelling for each socket Waiting finishing 2nd Fix remaining works 90% 0% 0% 0%
devices follow drawing, all connection include for each power
socket and in Distribution board.

Installation Power socket system at 1st Floor, Complete pulling


cable, Testing insulation and continuity of cable, installed all
1F 1. Waiting EDC supply / 2. labelling for each socket Waiting finishing 2nd Fix remaining works 90% 0% 0% 0%
devices follow drawing, all connection include for each power
socket and in Distribution board.

Installation Power socket system at 2nd Floor, Complete pulling


cable, Testing insulation and continuity of cable, installed all
2F 1. Waiting EDC supply / 2. labelling for each socket Waiting finishing 2nd Fix remaining works 90% 0% 0% 0%
devices follow drawing, all connection include for each power
socket and in Distribution board.

C. Distribution Borad

Installation Distribution board at Basement 1, Complete pulling


Waiting EDC supply and labelling for all cable in distribution
B1 main cable, all cable of lighting circuit, power socket, Air Waiting finishing 2nd Fix remaining works 80% 0% 0% 0%
board.
conditioner system, All connection in board.

Revision00
Installation Distribution board at Ground Floor, Complete pulling
Waiting EDC supply and Identified labelling for all cable in
GF main cable, all cable of lighting circuit, power socket, Air Waiting finishing 2nd Fix remaining works 80% 0% 0% 0%
distribution board.
conditioner system, All connection in board.

Installation Distribution board at Mezzanine 1, Complete pulling


Waiting EDC supply and Identified labelling for all cable in
MF1 main cable, all cable of lighting circuit, power socket, Air Waiting finishing 2nd Fix remaining works 80% 0% 0% 0%
distribution board.
conditioner system, All connection in board.

Installation Distribution board at Mezzanine 2, Complete pulling


Waiting EDC supply and Identified labelling for all cable in
MF2 main cable, all cable of lighting circuit, power socket, Air Waiting finishing 2nd Fix remaining works 80% 0% 0% 0%
distribution board.
conditioner system, All connection in board.

Installation Distribution board at 1st Floor, Complete pulling main


Waiting EDC supply and Identified labelling for all cable in
1F cable, all cable of lighting circuit, power socket, Air conditioner Waiting finishing 2nd Fix remaining works 80% 0% 0% 0%
distribution board.
system, All connection in board

Installation Distribution board at 2nd Floor, Complete pulling main


Waiting EDC supply and Identified labelling for all cable in
2F cable, all cable of lighting circuit, power socket, Air conditioner Waiting finishing 2nd Fix remaining works 80% 0% 0% 0%
distribution board.
system, All connection in board.

D. Fire Alarm System

Installation Fire alarm system, Complete pulling cable for all each
Waiting install Control panel, all equipment of system, include
BF - 8F floor(From Basement 1 to 8th Floor), Complete Testing Insulation Waiting finishing 2nd Fix remaining works 20% 0% 0% 0%
smoke, Heat, alarm Bell, SCM, TRM etc.
and Continuity for Cable

E. CCTV System

Installation CCTV system, Complete pulling cable for all each


Waiting install all camera on each floor, Install Rack for
BF - 8F floor(From Basement 1 to 8th Floor), Complete Testing Insulation Waiting finishing 2nd Fix remaining works 20% 0% 0% 0%
CCTV, Switch, UPS, NVR etc.
and Continuity for Cable

F. Data System

Installation Data system, Complete pulling cable for all each


BF - 8F floor(From Basement 1 to 8th Floor), Complete Testing Insulation Waiting install all equipments, Rack, Data Socket,Switchetc. Waiting finishing 2nd Fix remaining works 20% 0% 0% 0%
and Continuity for Cable.

G. Telephone System

Installation Telephone system, Complete pulling cable for all each


Waiting install all equipments, Rack, Telephone
BF - 8F floor(From Basement 1 to 8th Floor), Complete Testing Insulation Waiting finishing 2nd Fix remaining works 20% 0% 0% 0%
Socket,Switchetc.
and Continuity for Cable.

H. MVAC System

1. Waiting EDC supply / 2. Connection of Motor / 3. Install


B2 Installation Exhaust Air Fan, Complete Duct work, install Fan. Waiting finishing 2nd Fix remaining works 50% 0% 0% 0%
Control panel of Fan

1. Waiting EDC supply / 2. Connection of Motor / 3. Install


B1 Installation Exhaust Air Fan, Complete Duct work, install Fan. Waiting finishing 2nd Fix remaining works 50% 0% 0% 0%
Control panel of Fan

1. Waiting EDC supply / 2. Connection of Motor / 3. Install


GF Installation Exhaust Air Fan, Complete Duct work, install Fan. Waiting finishing 2nd Fix remaining works 50% 0% 0% 0%
Control panel of Fan

1. Waiting EDC supply / 2. Connection of Motor / 3. Install


MF1 Installation Exhaust Air Fan, Complete Duct work, install Fan. Waiting finishing 2nd Fix remaining works 50% 0% 0% 0%
Control panel of Fan

1. Waiting EDC supply / 2. Connection of Motor / 3. Install


MF2 Installation Exhaust Air Fan, Complete Duct work, install Fan. Waiting finishing 2nd Fix remaining works 50% 0% 0% 0%
Control panel of Fan

1. Waiting EDC supply / 2. Connection of Motor / 3. Install


1F Installation Exhaust Air Fan, Complete Duct work, install Fan. Waiting finishing 2nd Fix remaining works 50% 0% 0% 0%
Control panel of Fan

1. Waiting EDC supply / 2. Connection of Motor / 3. Install


2F Installation Exhaust Air Fan, Complete Duct work, install Fan. Waiting finishing 2nd Fix remaining works 50% 0% 0% 0%
Control panel of Fan

Revision00
I. Plumbing System

Installation Submersible pump at Basement 2, Complete installed


B1 1. Waiting EDC Supply Waiting finishing 2nd Fix remaining works 90% 0% 0% 0%
pump, all connection of piping system

Revision00

You might also like