Professional Documents
Culture Documents
Integrating Uncertainty in Block Cave Production Scheduling: E. Rubio & W.S. Dunbar
Integrating Uncertainty in Block Cave Production Scheduling: E. Rubio & W.S. Dunbar
Integrating Uncertainty in Block Cave Production Scheduling: E. Rubio & W.S. Dunbar
ABSTRACT: The long term plan in a block cave mine is based upon a number of assumptions about the
behavior of the rock mass. Production forecasts will rely on these assumptions even when data is available to
suggest modifications to those assumptions. This can compromise not only the economics of the project but
also the global geomechanical stability of the mine. Even though there might be several goals that a production
schedule of a block cave mine could follow, at the moment, there is no tool to measure how precisely those goals
are met. Reliability theory introduces a new metric to production schedules which ultimately will measure the
ability of different production strategies to achieve production targets. In this approach the reliability of a draw
point can be computed using historical forecasts versus historical production data. The individual draw point
reliabilities can then be linked though a set of equations to compute the overall block cave reliability. This aims to
provide a different means to schedule block cave mines adding an index of uncertainty to the overall production
schedule as well as the factors that contribute to it. Several examples will be presented as a proof of concept.
635
the grade distribution within the ore body; and dilution 0.60
Ja 0
Ju 1
2
M 1
M 1
N 1
Ja 1
N 2
Ja 2
3
M 2
M 2
M 3
M 03
Se 1
Se 2
,0
,0
,0
0
,0
,0
0
,0
,0
0
,0
0
l,0
l,0
n,
p,
p,
n,
n,
,
ov
ay
ay
ar
ov
ar
ov
ay
ar
Ju
formance. However, it has been observed that some
N
Period
block cave operations perform better than others when
facing these uncertainties. It seems that the amount of Figure 1. Production back-analysis of an existent operation.
planning and its ability to integrate the above men-
tioned issues plays a significant role in the success of
a block caving operation.
point productivity clearly reflects the uncertainty in
predicting rock mass behavior to plan the production
3 PLANNING AND SCHEDULING METHODS associated with a particular schedule.
APPLIED TO CAVING METHODS Production from a draw point depends on several
rock mass and design parameters such as: equipment
In order to ensure that the ore production rate meets size, layout configuration, stresses on the production
requirements and to efficiently allocate resources such tunnels, haulage infrastructure, seismic activity. One
as capital, equipment and labor, a block cave mine plan of the most relevant parameters, however, appears to be
and schedule must be defined. The aspects of mine the ultimate fragmentation of the rock mass. Fragmen-
planning that need to be fully considered to properly tation models such as BCF developed by Esterhuinzen
plan a block cave mine are as follows: (1994), Brown (2003) and Wang et al (2003) could be
used to estimate the fragmentation curve of a given
• Draw point sequence: i.e. the order and timing by rock type and thus forecast the frequency of oversize
which the draw points should be incorporated in and hang ups occurring at draw points. These frag-
production. mentations models will finally affect the draw point
• Active area: i.e. the number of draw points that productivity. However, current practice is to employ a
should be developed per period. trial and error process until full production is achieved
• Draw rate: i.e. how fast can material be extracted without introducing the interruptions that the sec-
from these draw points to provide the best value to ondary blasting activity adds to the production system.
the operations. Generally by adding the secondary blasting activity
• Draw constraints: i.e. identification of the main then the productivity of a block or a production unit
operational constraints that limit the productivity of decreases and therefore the time to achieve full produc-
a draw point. tion is usually longer than planned. The impact of this
• Draw profile: i.e. what should be the distribution situation on the economics of the mine is significant.
of tonnages within an active panel to guaranty the Fragmentation models are also used to define other
global stability of the mine. aspects of the design and planning of a block cave
• Geotechnical constraints: i.e. how does the draw mine, such as: draw point layouts (Laubscher, 1994);
profile affect the geomechanical response of the mixing within the caved zone; amount of secondary
rock mass. blasting activity (Dessureault, Scoble, Rubio, 2000).
There is a lack of published work dealing with the rela-
The above factors are linked through several pro- tionship of fragmentation to production scheduling.
duction rules that traditionally have been derived Fragmentation tends to vary across the active area due
from heuristics and experience at different operations. to factors such as discontinuity frequency, rock mass
Figure 1 shows an operating mine that has successfully strength, and other geomechanical factors such as the
forecast its production ramp-up as a result of using the stresses acting in the rock mass. In turn, the stresses
factors above and the appropriate heuristic rules. are related to rock mass properties, the rate of draw,
Currently, when a production plan is computed then the draw pattern and the location of draw points as
all draw points have the same chance of being part the operation proceeds. These relationships are com-
of the schedule. However, in every block cave opera- plex and are likely to be site-dependent. Thus it seems
tion there are draw points that tend to produce more clear that a robust production planning tool should
easily than others or the productivity of draw points be empirically based and should integrate available
varies across the active area. This variance in draw production data with measured geomechanical data,
636
70%
Pull
8000 60%
50%
6000
40%
4000 30%
Over 20%
2000
Pull 10%
0
0%
0 2000 4000 6000 8000 10000 12000
01 01F
03 01F
03 02F
05 01F
05 02F
07 01F
07 02F
09 01F
09 02F
11 01F
11 02F
13 01F
13 02F
15 01F
15 02F
17 01F
17 02F
19 01F
19 02F
21 02F
Observed Tonnage
Draw Point Name
Figure 2. One month of tonnage reconciliation per draw
point. Figure 3. Monthly average relative deviations between
forecast and actual tonnages.
637
0.6
Tonnage Reliability
09 01H 1500 2500 3500 3000 0.5
0.1
N 9
Ja 9
M 0
M 0
0
Se 0
N 0
Ja 0
M 1
M 1
1
Se 1
N 1
Ja 1
M 2
M 2
2
Se 2
02
9
-9
0
-0
-0
l-0
-0
-0
-0
l-0
-0
0
-0
-0
l-0
p-
n-
p-
n-
p-
n-
p-
Table 2. Actual tonnage drawn.
ov
ar
ay
ov
ar
ay
ov
ar
ay
Ju
Ju
Ju
Se
Period
0.6
be established. Then an analogy with electric circuits
0.5
0.4
is used to compute the system reliability. For example,
0.3 the reliability of two dependant processes is computed
0.2 as if these two processes were connected in series. The
0.1 same applies for two independent processes in which
0
the reliability is computed as if the processes were con-
F
01
02
01
02
01
02
01
02
01
02
01
02
01
05
07
11
13
17
19
03
05
09
11
15
17
638
D14
reliability would be R = 0.487. Now consider two
cases:
Panel 1 Panel 2 Panel 3 Case 1: Suppose that the reliability of any draw
point in panel 1 decreases to 0.5 due to poor draw
Figure 7. Representation of a block cave mine. control and operational factors. Then the reliability of
the production area would be R = 0.486 (See Table 5),
to it, as shown in Figure 7. Each of the panels has to not a significant difference from the base case.
produce an equal tonnage at any given period to main- Case 2: If instead the reliability of any draw point
tain the uniform draw pattern in order to avoid early in panel 3 (the cave front) decreases to 0.5, then the
dilution as well as high stresses in the production area. reliability of the entire system would be R = 0.456.
The ore passes, numbered from 1 to 3, and draw This is an interesting result; since the reliability model
points are indexed according to position with respect to suggests that it is more important to keep draw points
ore pass and draw point, e.g. Dij would be the jth draw at the cave front in proper operation rather than old
point in ore pass i. Draw points in the same panel will draw points to enhance the performance of the produc-
be in parallel and in series with the ore pass. Therefore tion area.
the reliability of a panel is given by: The reliability model could also be used to help
decide where to open a new draw point by showing
in which way the system becomes more reliable. For
example, consider Case 2 above where there is a draw
point in the cave front with low reliability and it is
desired to open a new draw point (with reliability 0.8)
where RPi is the reliability of panel i, ROPi is the so that the entire production area becomes more reli-
reliability of ore pass i, and RDij is the reliability of the able. Suppose also that operational constraints in panel
jth draw point located on panel i. J (i) is the number 2 mean that the new draw point can only be located in
of draw points in panel i. Since the three panels in panels 1 or 3. The calculation of the system reliability
Figure 7 operate in series, then the reliability of the for both these scenarios is shown in Tables 6 and 7
system shown is given by: respectively.
The results in Tables 6 and 7 show that the effect
of opening a new draw point at the cave front is much
greater than opening it at the back of the active area.
The base case scenario will consist of having the This is because the contribution of the extra draw point
same reliability for all elements equal to 0.8, i.e. in panel 3 to the overall reliability is much larger than
ROPi = RDij = 0.8 for all i and j. Then the system in panel 1.
639
640
80%
70%
3000 tpd pute the required mine flexibility to achieve a given
60% target. Also this technique allows mine operations to
50%
5000 tpd
integrate the operational upsets as part of the mine
40%
planning methodology.
30%
20%
10%
0% ACKNOWLEDGEMENTS
0 5 10 15 20 25
Number of Dpts in the Schedule ( nt)
The authors are grateful to Gemcom Software Interna-
Figure 8. Draw point scheduling using k out of n method. tional Inc. for time and funding to complete the work
and submit this paper.
641
642