VIA - New Paratransit Facilty Reno - July 2020
VIA - New Paratransit Facilty Reno - July 2020
VIA - New Paratransit Facilty Reno - July 2020
July Board
1
July 21, 2020
Project Development Team
2
Transguide
Project Goal:
Consolidate Paratransit Operations
Main Campus
3
Main Campus (VIA Bus Yard) Project Benefits
• Consolidation of Operations
* Improves communication
* Improves efficiency & effectiveness
4
Site/Building Facts
5
Repurpose / Renovation
• Renovating existing
building
• Repurpose Historical
artifacts
• Repurpose existing
entertainment rooms to
conference rooms/offices
• Repurpose mezzanine for
storage and/or other uses
• Reuse/renovate existing
operational restrooms
6
Procurement Method
7
Project Cost Funding
• Real Estate Acquisition $ 8,050,449
• Architect/Engineer/Misc. $ 1,950,581
• Construction Cost $ 23,006,460
• Total Project Cost $ 33,007,490
Construction Cost Funding
• Federal 5339 Discretionary Grant $ 6,000,000
• TXDot Funds $ 17,006,460
• Total Construction Funding $ 23,006,490
8
Procurement Timeline
Issued Request for Qualifications (RFQs): July 22, 2019
9
Schedule
• Board Action - July 2020
• Notice to Proceed (NTP) - August 2020
• Construction Complete - August 2021
• Facility Operational - October 2021
10
ANY QUESTIONS?