New Paratransit Facility

July Board
1
July 21, 2020
Project Development Team

 Sam Marra - V.P. Fleet and Facilities


 Tom Carrasco - Project Manager
 Charles Haile - Project Architect
 Kevin Schnitzer - Project Engineer
 Various - VIA Stakeholders
 HNTB - Private Consultants

2
Transguide
Project Goal:
Consolidate Paratransit Operations

Future Paratransit Facility

Main Campus

3
Main Campus (VIA Bus Yard) Project Benefits
• Consolidation of Operations
* Improves communication
* Improves efficiency & effectiveness

• Improves vehicle movement &


parking at the VMC

• Various other efficiencies:


*Non-revenue maintenance
* Needed admin workspace
* Warehouse storage

4
Site/Building Facts

• 4902 Fredericksburg Road


• Originally built as a K-mart
• Formerly known as Graham
Central Station
• 11 Acre Site
• Large Building approximately
100,000 sf
• Small Building approximately
10,000 sf

5
Repurpose / Renovation

• Renovating existing
building
• Repurpose Historical
artifacts
• Repurpose existing
entertainment rooms to
conference rooms/offices
• Repurpose mezzanine for
storage and/or other uses
• Reuse/renovate existing
operational restrooms

6
Procurement Method

• Used Design Build Approach


• Qualify Interested Firms
• Request Proposals from
Qualified Firms
• Evaluate Proposals and Select
Contractor based on Quality,
Safety, Security, Aesthetics,
• Note – Meeting held pre-COVID Schedule, Experience and
Price

7
Project Cost Funding
• Real Estate Acquisition $ 8,050,449
• Architect/Engineer/Misc. $ 1,950,581
• Construction Cost $ 23,006,460
• Total Project Cost $ 33,007,490
Construction Cost Funding
• Federal 5339 Discretionary Grant $ 6,000,000
• TXDot Funds $ 17,006,460
• Total Construction Funding $ 23,006,490

8
Procurement Timeline
Issued Request for Qualifications (RFQs): July 22, 2019

Response Deadline for RFQ: August 23, 2019

Issue Request for Proposals (RFPs) to Shortlisted Firms: December 5, 2019

Deadline for submitting Proposals to VIA: April 1, 2020

Best and Final Offer: June 1, 2020

Final Selection of Contractor: June 2, 2020

9
Schedule
• Board Action - July 2020
• Notice to Proceed (NTP) - August 2020
• Construction Complete - August 2021
• Facility Operational - October 2021

10
ANY QUESTIONS?