Republic of the Philippines

BILIRAN PROVINCE STATE UNIVERSITY


(formerly NAVAL STATE UNIVERSITY)
ISO 9001:2015 CERTIFIED

ENGINEERING AND GENERAL SERVICES OFFICE

PERT-CPM

Project Name: RENOVATION/ REPAIR OF BIPSU GYMN MAIN CAMPUS


Location: BiPSU Main Campus, Naval, Biliran
Duration: 90 Calendar Days

Event Duration ES (Earliest EF LS LF TF FF


Scope of Works
ID (day) Start) (Earliest Finish) (Latest Start) (Latest Finish) (Total Float) (Free Float)
A Mobilization 1 0 1 26 27 26 0
B Occupational Safety And Health 20 1 21 1 21 0 0
C BiPSU Standard Project Billboard 1 1 2 27 28 26 0
D Removal of Structure and Obstruction 16 2 18 41 57 39 0
E PLUMBING WORKS & FIXTURES INSTALLATION 21 18 39 68 89 50 50
F CARPENTRY WORKS 20 18 38 18 38 0 0
G TILEWORKS 32 18 50 57 89 39 39
H INSTALLATION OF SOUND PROOF WALLING 7 38 45 43 50 5 5
I ELECTRICAL WORKS 30 18 48 59 89 41 41
J STAINLESS STEEL RAILINGS, STAINLESS STEEL GATE & STEEL STAIR REHAB 15 18 33 35 50 17 17
K DOORS AND WINDOWS INSTALLATION 12 38 50 38 50 0 0
L CONCRETE CANOPY WATERPROOFING 7 2 9 82 89 80 80
M PAINTWORKS 39 50 89 50 89 0 0
N GYM TAPPING POINT REHABILITATION 15 9 24 35 50 26 26
O EXCAVATION 2 2 4 28 30 26 0
P FILLING 2 7 9 33 35 26 0
Q CONSTRUCTION OF ADDITONAL SEPTIC TANK 7 4 11 26 33 22 0
R GRAVEL BEDDING 3 4 7 30 33 26 0
S Demobilization 1 89 90 89 90 0 0

CRITICAL PATH = A-C-D-F-K-M-S R, 3 days


Total Duration = 90 Calendar Days O, 2 days
P, 2 days
4 6
7
Q, 7 days
N, 15 days
J, 15 days

A, 1 day C, 1 day
D, 16 days F, 20 days K, 12 days M, 39 days S, 1 day
1 2 3 5 7 8 9 10

H, 7 days

I, 30 days

G, 32 days

E, 21 days
L, 7 days

B, 20 days