S.

No Task Predecessor Duration


1 Establishing the background of the project 4
2 Project CTQ, High Level Scope and Business Case 1 1
Assessing risks and benefits of the project-possibly assign 1 1
3 financial value to the project
4 Team Identification and formation 2 1
5 Project Charter and Project Plan 3,4 2
6 CTQ Definition 2 1
7 Measurement System Analysis 6 4
8 Baseline Current Performance 7,5 1