Professional Documents
Culture Documents
MS For Storage Tank Erection Work (Rev.B) PDF
MS For Storage Tank Erection Work (Rev.B) PDF
MS For Storage Tank Erection Work (Rev.B) PDF
Owner’s Engineer
Contractor
Sub-Supplier
LILAMA CORPORATION
Project
CONTENTS
1. PURPOSE................................................................................................................................ 3
2. SCOPE ..................................................................................................................................... 3
3. GENERAL .............................................................................................................................. 3
4. ORGANIZATION .................................................................................................................. 5
RECORD OF REVISION
1. PURPOSE
The purpose of this method statement is to have a procedural activity for all Tank Fabrication &
Erection for Nghi Son 2 BOT Thermal Power Plant with Safety, Quanlity and consistently.
2. SCOPE
This method is made for following storage Tank installation guidance :
3. GENERAL
a. Select a proper erection sequence as per the latest revision of the erection drawing
d. Arrange the temporary supports, Jigs, guys, braces, clips and etc.
f. Arrange for the scaffolding materials in advance ; if the same is required during the
progression activities.
g. Ensure the availability of proper lifting tackles, drift pins, wedges and torque
wrenches for tensioning.
This method statement is applied to the above mentioned works. If there are any matters not
mentioned in this procedure, then that will be carried out according to relative drawings and
standards.
Capacity: 2x600 MW
Owner: NS2PC.
4. ORGANIZATION
Organization Chart Of Lilama Corporation
6. PREPARATION WORK
6.1 Material Storage
Make sure the conditions such as the access road for heavy equipment (crane, truck,
and trailer), the storage capacity, ground condition, and other materials may affect to
the tank material, etc.
Make the conditions before working such as the access road in and beside the tank
area, the land for laying down material, wet or dry land, etc.
6.3 Manpower
Base on the progress and manpower for erection work of tank will arrange as follow:
6 Welding supervisor 1
7 Quality supervisor 1
8 Staffs 1
9 Documentation management 1
10 First Aid 1
11 Guardian 2
12 Material manager 1
13 Material procurer 1
14 Safety man 1
15 Surveyor 2
16 Storekeeper 1
17 Welding storekeeper 1
18 Crane driver 2
19 Truck driver 2
II Site management board
3 Welding team leader 1
4 Erection team leader 1
5 Pipe team leader 1
6 Painting team leader 1
Operation men for Semi- Automatic
7 welding machine 6
8 Electrical Welders 24
9 Erection men 30
10 Painters 6
11 Service cranes 6
12 Oxy gas welders 2
13 Scaffolding men 12
14 Electrical men 2
Total 115
- Cross checks the foundation, anchor bolt, lay-out and bolt holes.
- Bolt Holes Shell be straddle the nominated north south Tank centerline and The
Horizontal Tank Centerline.
- Clean the foundation bolts with wire brush. Any scraps, concrete blocks or other
obstacles shall not be on the surface of foundation.
- All such equipment shall be inspected prior to its use on each shift, and as necessary
during its use, to ensure that it is safe. Remove from service immediately any rigging
equipment found to be detective.
7. INSTALLATION
7.1 Flow Chart
TANK CALIBRATION
(L.D.O TANK ONLY)
- When arranging the annular plate, outside radius should be increased respective to the
quantity of annular plate from the drawing the dimension to compensate for the
welding shrinkage. This increasing to be calculated before install.
- Fit-up shall make for all the annular plate except last piece which shall be left for
- Either strong back or back pieces should be installed at the welding joints to prevent the
plate from welding distortion.
- The first, bottom gauge to be made. And it is datum lines for arrangement of the bottom
plate on the foundation.
- The bottom plate shall be arranged from the centre toward the outside.
- The lap with of the bottom plate will be increased from the dimension of design
drawing to compensate the welding shrinkage.
- In arrangement the bottom plate, use fit-up jigs as shown in below figure
Dog plate
Wedge
Welding of
back side
Bottom plate
o When the plate corners are flame cut, the upper plate shall be lifted up above
the lower plate, or a temporary plate shall be placed between the two to prevent
damage to lower plate.
o Any drain sump inserted in the tank bottom shall be firmly bedder full care on
the foundation, taking to eliminate any void under bottom of the sump it self.
o Fit-up the annular plate in order to obtain the proper gap. Lay the plate at a
slightly larger radius than the given radius to compensate the welding
shrinkage.
o After completion of laying out the bottom plate, tack-weld only should be
performed from center to circumference.
o Check again the dimension of tank bottom before performing full weld.
o General welding sequence of bottom annular plate is as follows:
Welding of the bottom annular plate together.
Erection the 1st course shell plate and welding of vertical joint.
Erection the 2nd course shell plate and welding of vertical joint.
Welding bottom annular plate to shell plate (inside 1st past will be welded
and full completed outside weld joint and continuous welding will be
adopted on the subsequent passes inside).
Mentioned test requirement for shell and bottom annular plate joints as per
API 650 for in/out side joint.
4
Shell plate
Annular plate
3 5
Bottom plate
1
- Butt joint welding of the bottom annular plate shall be inspected and start erection of
1st course shell plate.
- The prevent welding distortion, reinforcing beam should be installed in parallel to the
welding line.
Bottom Plate
- The welding should be performed from the center toward the outside in principle.
- The welding seam for bottom plate shall be performed vacuum box test to ensure no
B
leak is appeared
o The radius marking should be for reference marking (from tank center as per
foundation checking).
o This marking is shell erection marking as per drawing shell in-diameter and the
fit-up of shell plate with tolerance considering weld shrinkage.
o The marking of the vertical joints of the 1st course shell plate (Shell plate
gauge line).
Spread bar
Vertical Clamp
Shell plate
Tack weld
turnbukle 1''
Plumb bob
welding
support
1/5
L
W
1/2
- Level, roundness and plumbness measurements of shell course shall be carried out in
B
accordance with the ITP (Inspection and Test Plan) for Tank, document No NS2-
DH01-P0ZEN-740005.
- After completion of vertical welding of first course and second course, horizontal
joints between first and second course shell be fitted up and welded.
- Scaffoldings will be used for erection, welding and inspection work at inside of the
shell plate and travelling cages will be used for the work at outside
- The scaffolding system for shell plate installation has been installed following below
sketch :
- During installation, the curvatures of the joints shall be checked with a correct
curvature gauge.
- After completion of the small erection, the preassembled top girder installed on the top
of shell plate
- The erection of roof plate will start after installation and fit up roof steel structure
according to approval drawing.
- Make sure that all person involve in any activity must be fully awared regarding with
the scope of work.
- Install, fitup and welding roof plate together or roof plate to the top angle has to
strickly follow approval drawing.
All lifting gear devices must be had CO-CQ and got certificated from The third party.
- The welding seam for roof plate shall be carried out vacuum box test after finish all
B
welding work.
7.7 Appurtenances
- Stair way, plateform, shell stiffener, internal pipe, roof and shell fitting, ladder, etc.
shall be completed before water filling test.
- Double check for tank orientation of the tank layout and fitting, stair way and other
appurtenances as tank construction continue.
- Install, fitup and welding appurtenances in accordance with the approval drawing and
welding sequence.
- Make sure all tool/ equipment, temporary materials are to be removed except for
scaffolding system inside the tank, its shall be kept until completed of water filling test
with the purpose of supporting to blasting and painting work inside the tank.
Scaffolding system shall be checked by authorized person after water filling test and
before start of blasting and painting work
- Tank foundation shall be checked and recorded before, during and after water filling.
- The test water will be filled inside the tank following the steps as below:
o Step 1: Check Tank erection and inspection, check the tank foundation level
and record the result (before water filling);
o Step 2: Fill water up to the ¼ Max. Liquid level of the tank, measure the
foundation level and record the result; At least 02 hours of holding time.
o Step 3: Fill water up to the ½ Max. Liquid level of the tank, measure the
foundation level and record the result; At least 02 hours of holding time.
o Step 4: Fill water up to the 3/4 Max. Liquid level of the tank, measure the
foundation level and record the result; At least 02 hours of holding time.
o Step 5: Fill water up to the Max. liquid level (full) of the tank, the holding time
at least 24 hours after the tank has been filled from the 3/4 Max. Liquid level
of the tank to the maximum test height. Measure the foundation level and
record the result;
o Step 6: Drain the test water and clean the tank. Measure the foundation level
and record the result.
Note: Detail Method Statement for filling test shall be separately submit to
Owner/WSP for approval. B
7.9 Calibration
Calibration of the Tank shall be applied for Light Diesel Oil Storage Tank and performed
B
after water filling test by 3rd party who will carry out the calibration work.
7.10 NDE
All NDE works shall be carry out in accordance with the Inspection and Test Plan for
B
Tank Fabrication & Erection No. NS2-DH01-P0ZEN-740005 and NDE procedure No.
NS2-QE03-P0ZEN-040010.
- Execution and combination equipment at the site must be checked, maintained, load-
tested in accordance with regulations on elevation equipment safety under TCVN
4244-86, the inspection certificate must be still effective.
o Being trained in execution process, safety measures and being tested, issued
safety cards by competent agencies.
o Being medically examined by competent medical agencies and issued certificate
of good health before working.
o Being provided with a full range of equipment and personal protective equipment
in line with the working conditions (shoes, protective clothing, hard hats, gloves,
anti-dust masks, seat belts) and bring all of them when working.
o Being strictly forbidden to use alcohol, beer and other drugs before and during
working hours as well as at the site.
o Being only traveled in their working area, prohibited to travel to other areas
outside their execution premises when they have yet been permitted.
- The equipment and supplies have strict requirements on safety when put to use in the
field, such as cranes, electric hoists, oxygen bottle, gas cylinders, pneumatic cylinders
in the construction process must be licensed to use issued by the competent State.
- The equipment and materials on the site must be collected and fully protected when
the working hours finishes.
- Necessary barricades, plates at the execution site must be arranged and guarded to
prevent people from entering into dangerous areas.
o Only related persons are allowed to use and operate electrical-run equipment and
machinery.
o Cabinets and appliances are certainly earthed.
o The power distribution cabinet must have intermediate switches, lid and full
safety equipment such as circuit breaker, fuses, arc devices.
o All power cable system and wires for execution must be good insulated, wiring
positions must be arranged neatly so that travel, material and equipment
transportation cannot be prevented.s
o While working in the dungeon and cellar, only using the device with the voltage
36V.
o When the machinery and equipment is stopped working or stopped for repairs, it
is vital cut off all power source to the machine. While repairing, it is necessary to
hang signal "No opening power source, it is in repair.".
o When electricity-related work is conducted, it is vita to appoint those having
power expertise. Each team must have 02 or more.
o The circuit breakers for supplying power for execution are placed in a covered
box to protect against rain and on the stand > 0.7 m above the ground under
construction.
- For emergency rescuing before working must be sured all of workers who take part in
task must be known and training about Confined space work and method for rescuing
in case emergency and ERT persons should be available during workers are working
inside confined space. And must be installed tripod and pulley and rope for rescuing in
case emergency. All worker must be worn safety harness with D ring. 02 watchman
must be available inside and outside of coal silo and communication in/out by walkies
–talkies.
o Only allow people having enough health to climb (listed in the certificate of
health issued by competent authorities) for working.
o If anyone is found using alcohol, beer and other stimulants, they are prohibited
from working and taken away from the working area immediately.
o Workers wear tidy clothes (protective clothing, hats with straps, protective shoes).
o All equipment and operation location of workers must be absolutely insulated.
o Wearing seat belts, which are checked by functional departments and load-tested
before putting into use.
o Seat belts are definitely hooked, reliability (Lifeline as shown in the figure),
position for hooking belts must be higher than or equal to 2/3 the height of the
person to ensure convenience in working.
o Electric welder and oxyacetylene welder use leather belts.
o Tools for the execution must be neatly placed in boxes, free from dropping down.
o Do not throw materials and tools from bottom to top and vice versa.
o Around the working location, it is necessary to stretch wire and hang signboard
“Prohibit people to travel” in a radius of 5m.
o When travelling in the operation floor with high danger, it is vital to stretch wire
or cable to hook safely.
o It is vital to cover the working platform to prevent waste materials from falling in
the working process and industrial hygiene.
- Flame is strictly prohibited in the workplace (except for brazing, welding), all
flammable equipment and chemicals should be placed in the prescribed locations,
away from heat sources > 10m, carefully shielded warned: "No fire".
- Gas and oxygen bottle must be placed machine warehouse, separated and away from
heat sources at least 10m.
- When welding or cutting in areas near flammable materials such as paint, gasoline,
oil ... covering measures must be carefully taken.
- When working in easily explosive environments, it is necessary to make plans for fire
and explosion prevention, and fully equip with fire fighting equipment such as fire
extinguisher (foam bottle, CO2 bottle), sand container, water and other tools such as
shovels, buckets, pots, bill hooks, woolen blanket .
- Be trained in the safe operation of the lifting equipment and issued card by the
competent authorities.
- Must have been fully equipped with personal protective equipment in line with the
work.
- Complying with shift hand-over process, before they control machines, they must
check whether safe equipment (such as brakes, brake ratchet ...), control structure are
safe or not.
- During operation, they must pay attention to the alarm clock: load (bearing and
allowed) and flip torque of lifting equipment. If the alarm clock shows 80% load or
more, they must report to the direct leader to assign observers to see balance of lifting
equipment, materials and they must perform each operation only, not combine them to
avoid instability of lifting equipment and materials.
- When lifting or lowering, moving the lifting device or load, they must show signal to
inform everyone around.
- When operating, they must observe the cables (chains, cylinder - lift tables) moving
through the pulley (gear), to prevent it from being twisted, disordered or trapped.
- Only using lifting equipment to lift and lower volumes of materials in the vertical
position, prohibiting using it in oblique direction or drag volumes of materials on the
floor.
- Prohibiting moving below, or stand on the volume of materials when it is lifted, moved.
- Signal between the turn signal and the operator of lifting equipment must be consistent,
prohibiting letting beak hook deviate from the focus of the material volume when
lifting, lowering and assembling it.
- Cable hook points, muffle hook, anchor winch must be solid and appropriate, crane
cable must be in accordance with Vietnamese standard 4244-86.
- The direct leader at the site must understand the exact weight, size of each volume of
materials, clearly writing these parameters on at least 2 sides (deviation of 900) of the
volume of materials before assembly and removal, and understand the load
characteristics of the lifting device to be used at the construction site.
- When materials are loaded onto carts, its shaft must be chocked tightly and loaded
with correct volume of materials.
- When two porters or more involve in loading materials, their signal must be consistent,
and their height must be around equal. They must carry materials on the same shoulder
(right or left).
- When transporting equipment by car, it is necessary to calculate the width and height
- When transporting materials and equipment by roller, it is vital to choose roller with
equal diameter, its length must be suitable with equipment to be transported.
o Welder at work must be fully equipped with personal protective equipment for
them.
o At work, the welder must wear leather shoes, his clothes have buttons grabbed
at the wrists, feet, his coat must not be left in the trousers, refractory, insulation,
mechanical action-resistant gloves, wrapping with leather coat or canvas,
wearing welding mask.
o When welding in damp places, he must be more careful, not to touch electrical
parts of the welding equipment.
o The metal casing of welding machines and welding equipment must be earthed,
space-connected in accordance with Vietnam standards in the "Rules for earth
connection and space connection of electrical equipment".
o Welding plier grid and other electrical conductors of the 4-head machine must
be well insulated, check once every 3 months for insulation.
o Within 10m, it is prohibited people to look directly at the welding spark without
o Oil, gasoline or other flammable substances must not be placed around the
welding place. It must weld away on flammable substances at least 10 meters
and away from the explosive materials at least 20m.
o When welding operation is conducted at the high place, the operation floor must
be solid, and signals hung below the welding place to prevent people from
travelling around it. Pieces of welding rod are not thrown or dropped.
o Welding machine must have circuit breaker opened or closed, not using power
outlets in such circuits as in bulb circuit.
o Chain of welding pliers is insulated, heat resistant. Welding plier must keep
welding rod.
o Using the stand to place welding plier, not place it on other materials or on
ground.
o Oxyacetylene welding:
Only those who are trained and assigned can use welding machine. When they
work, they must have sufficient and labor protection equipment.
- Complying with the requirements for storage and working with gas cylinders and oxygen
bottles:
o Storing it in cool places with average temperature <500 C. Preventing it from
exposing corrosive chemicals and flammable materials.
o Premises for placing GAS cylinder must be flat, not able to create sparks
when friction, collision, gas cylinders must be placed in a vertical position.
o When transporting gas cylinders, they must be placed vertically, its valve
turned upward; absolutely not rolling it, to avoid collisions with other GAS
cylinders, GAS cylinders with other objects.
its valves must be tightened and turned in one side. The maximum number of
cylinders arranged is equal to 2/3 of the volume of body of trunks, body of
trunks must be made of soft materials.
o When welding and cutting, it is vital to ensure that the minimum distance
between GAS cylinder and OXYGEN bottle is 10 m, the minimum distance
between the welding flame to GAS cylinder as well as OXYGEN bottle is
10m.
o Before cutting and welding, connectors must be tightened, avoid leak of GAS
or OXYGEN. Although gas is ignited slowly, it is necessary to comply with
procedures for opening the valve as acetylene welding "OXY go ahead, come
back later".
o Before using, it is vital to thoroughly inspect the technical and working condition
of equipment such as hardness, solidity of mechanical structure, reliability of
brake structure, cross chain, load chain and hook beak; if they meet requirements,
they are allowed to be used.
o When lifting and lowering equipment, it is vital to check whether the structure of
the hoist brakes are in good condition or not by lifting a volume of goods to a
height of less than 100 mm and within 5 minutes, if it is not "drifted", it can be
continuously used.
o Maintenance and checking of the reliability of chain hoist must be regularly
conducted.
o All the power supply cable must be insulated absolutely, connections and wiring
points shall be insulated, wiring box of motors must be covered with lids.
o Machine cover must be earthed firmly.
o Machine installation position must be placed at silent locations and not in moving
road.
o Operators of machines must be assigned by the responsible person and instructed
how to operate.
o When stopping working for repairs, it is vital to cut off all power to the machine.
o Machinery, equipment must have adequate safety devices such as fuses, relays,
Automatic circuit breakers....
o Grinding and cutting machines have been protected from flying stones, grinding
- Hand tools:
o Hand tools such as spanner, wrench, chisel ... must be grasped firmly in control
range.
o Daily checking must be conducted before putting into use relating to following
damages:
o Whether handle is not cracked or not.
o Whether cutting edge is damaged or not.
o Adjusted details ...
o Hammer handle must be packed firmly with medium length for easy use.
o Bore bit, turbidity is smooth without burrs.
o Shipping tools in containers and storage bags provided.
o Tools used for working on high places must have been tied to avoid falling down.
RISK ASSESSEMENT
BASE RISK
RESIDUAL RISK
(WITHOUT
(WITH CONTROL)
Cause CONTROL)
People at of Resi
Job / Task Risk Mitigating Controls
Risk Adverse dual
Effect L Rate
S1 L2 S2 Rate
1 (RF
(RR
N)
N)
worker
abnomal
Slip/
physical Check the health condition during
Trip/Fal 3 2 6 1 1 1
condition ( the TBM
l
Drunken &
fatigue)
Workers
Worker not
familiar with
the scope of TBM to be filled and discussed by
1 2 2 1 1 1
works or supervisor to workers
workplace
hazards
checking the access roand before
2 4 8
passing the area
Transportat Traffic Collisio Designate a signaman when
3 3 9 1 2 2
ion of accident n moving the equipment
equipemnt
& delivery keep the speed limmited 10km/h
of materials
Defective/Faul Ensure all required pre-start
Falling
ty machinery checklist are carried out prior to 1 3 3
object
or tools start any work
Only a qualified and Certified
operators. Signalman, riggers
should be in-place
Resi
Cause Risk
dual
People at of L Rate
Job / Task S1 Mitigating Controls L1 S1 Rate
Risk Adverse 1 (RF
(RR
Effect N)
N)
All scaffolders must be trained
and tested with scaffolding
course in training centre of
DVN’s Training and trained
Lack of
person entering working at height
experien
only.
falling hazard, ce and
Scafolding All scaffolders must be had
falling from knowled 4 2 8 2 2 4
work scaffolding certificate from the
height ge/ not
third party. And qualified by
adequat
DVN EHS scaffold supervisor.
e PPE
All scaffolders who is working at
height shall be inducted and got
certificate from MOLISA (
Circular 44)
Resi
Cause Risk
dual
People at of L Rate
Job / Task S1 Mitigating Controls L1 S1 Rate
Risk Adverse 1 (RF
(RR
Effect N)
N)
Provide the adequate ventilation:
Use mechanical air movers
(in/out) for ventilation.
Check the oxygen level prior to
entry on confined space.
Ventilation and extraction should
be performed at least (30) minute
before the entrants are allowed to
go inside the CS.
Ensure atmosphere is safe by
having oxygen concentration
between 19.5% & 23.5% and
should be monitored and
maintained.
Workers should undergo a
mandatory Confined Space
training before allowing to enter
the CS.
Gas free test tobe conducted by a
competent person before and
during the work confirm the level
suffocation,Pre of toxic substances does not
Failure
Confine sence of exceed the permissible exposure
to
space residual 5 3 15 limit. 2 2 4
properly
entry work harmful fume, The confined space shall be
ventilate
dust, smoke... monitor continuously using at
least 1 no of 4 in 1
Gas monitor.
Ensure the 4 in 1 gas meter is
having a valid calibration cert.
( All workers shall be brief
everyday about hazards of
confined spaces and its control
measures before commencing of
work- all works shall be stopped
and all workers shall
evacuate immediately from the
gas monitor and inform the person
in charge
2 people 1 team or 3 people
1team do work and have to sign
on the paper when out the
entrance and exit times. (You
should check the time when you
wear an oxygen mask, work the
work up to the given time, and
end the shift and work.)
Severity S1 : Severity as i
1.Negligible S2 : Severity with mitigating controls in place
2.Slight
3.Moderate
4.Critical/High
5.Catastrophic/Very high
Risk Factor Number ( RFN) Residual Risk number ( RRN)
1-2 Trivial/Acceptable 1-2 Trivial/Acceptable
3.5: Tolerable 3-5 Tolerable
6.-9: Moderate/Acceptable with review 6-9: Moderate/Acceptable with review
10-15 Substantial 10-15: Substatial
16-25:Intolerable/Unacceptable
Task:
Prepared by Mr. Le Thanh Hai Reviewed by Mr. Approved by Mr.
Original date: Revised by: Revised date: Revision: A
PPE required (Tick as applicable – state > category/specific type)
Safety Gloves: Face shield Barricade Lock out: Dust Mask:
googles: needed Tack out:
Safety Long sleeves Hearing MSDS Group fault Others
harness protection need/Review interrupter
Other safety equipment required:
Remark:
LIST OF ALL JOB STEPS LIST OF ALL KNOWN HAZARDS HOW TO ELIMINATE HAZARDS
Transportation of Equipment & Crash/Traffic accident 1. All Truck and trailer operators must be
Delivery of Materials Falling marials and equipment from got EHS conduction from DNV EHS
trailer or truck. training center and had certificate
following Vietnam Molisa regulations
2. Check The access road before passing
area
3.Designate a signalman when moving
equipment
4. Lashings (such as webbing, chains,
cables or clamps) should be in
serviceable condition and be checked for
damage at regular intervals to ensure
their tension has not been lost. Use
sleeves and/or corner protectors to
prevent damage to both the load and the
lashing or sheet if it passes over a sharp
edge or corner.
5. Ropes and buckle straps suspended
from a roof rail and/or the curtains of a
standard curtain-sided vehicle are
generally not suitable for securing a load.
Heavy lifting work - loading and Potential fatality and serious injury due to 1.Regular inspection and maintenace
unloading lifting work shall be carried out and a register kept by
Fataliy/Serious injury to workers a qualitied person, for the lifting tackle
under DVN EHS control.
This equipement checking for
deformation, cracks or any faults
includes: Wire slings, Hooks, Shackles,
swivels, spreader bars, Shear –Legs or
Soft/unevent ground may cause crane similar equipment.
topple 1. Ground bearing to be tested and
Potential fatality to workers property endorsed by competent person.( Crane
damage operators and lifting supervisors ensure
safe condition positioning of crane)
Over loading of crane’s SWL may cause 2.Steel plates to be laid for the
crane toppled positioning of crane, if necessary.
Damaged sling –unsecured loose 3.Lifting supervisor to maintain visibility
materials and supervision during lifing work.
High potential fâtl incident and damage 3.Adhere to approved lifting plan
to property. 4. Ensure a valid permit to work
5.All necessary check list to be update
6.Wire slings must be properly srored off
the ground without casing kinking
7.Wire slings must be cleaned and
inspected before and after using.
8The issuing and control of slings shall
be performed by a qualifỉed person.
Gratting installation and removal 1.High potential falling object due to fall 1. All workers must be trained by DVN
or material drop down. EHS and comply with safety regulations
with working at height.
1.1 comply with P.T.W ( Grating and
handrail removal permit)
1.2 Before removal grating on the floor
of Boiler must be identified gratting’s
location exactly and install hardbarricade
for isolated and prevent worker
access.install warning signalboard
“ Warning oppening hole – keep away”
1.3.Workers in this task have to using the
hooks for falling protection - hanging
gratting during the time remove or
2.Pinch point, serious ịnury hand installation.
1.4 All portable handtool machine or
tools as scratch spanner, or portable
drilling machine must be secure with
layards for falling protection.
Ergonomic and manual handling must be
trained and TBM before working in this
task.
Equipment and material preparation 1.Collision between machine, overturing 1.Alway keep the site clear of any
for temporary facilities may cause death or permanent injury, obstruction
collased 1.2.Toolbox talks on daily basic
Working and operation during night 1.working operation of the equipments 1.Must provide sufficient lighning on the
time may cause serious injury to personnel due entire working area
to: 1.2 All equipments must be ensure all
lights are operation
1.3Supervisor must always be present for
entire working
1.4 All workers must be wearing proper
PPE ( Hi –Vest)
1.5First aid box should be prepared for
the first aid in case injury.
1.6.Temporary electrical system must be
used and connect 03 core and separated
distribution panel ( with ELCB with
electrical leakage 30ma) and avoid from
2.Generator (Diesel equiment oil any water effect
leakage) 1.7 provide safe accessway and exit
access road for the workforces passing
1.8All kinds of electrical cable must be
hanged over ground at least 2m and must
be industrial socket and flugs
2.Daily check of the equipment prior to
3.Chemical storage start work
2.1.Regular inspection and monitering of
the equipment prior to use.
2.2 Provide secondery containment
protection under the equipement to
prevent contamination soil by oil spillage
3.Diezel chemical shell be stored in
secondary containment and MSDS must
be showed and communicated to all
workers who concerned.
All hazardous waste must be collected
and keep inside the hazardous waste
disposal bin and handover to DVN EHS
to treatment by the Nghison Environment
company following Vietnam evironment
regualtions.
Welding and cutting work Electrical shock, fire, burn to body and All workers must be trained with special
injury to eye may cause death or hot work training from DVN EHS
permanent injury training center and also equiped with
Fire accident due to electrical wire aging PPE as: Safety mask for face protection
during welding and face mask for welding or cutting,
leather gloves,Arpon.
1. Proper earthing and connection of
welding machines and generators.
2.Flash bask arrestor and Gas flow
regulator should be installed to Gas
cylinder and cutting gears or cutting
torch prior to using cutting.
Confined space entry work Death due to reduced oxygen 1.All workers who working inside
concentrasion cofined space must be attend and safety
Or toxic gas. training at DVN EHS training center and
must be carry out before working
2.Complied with PTW following DVN
EHS procedures.
3. before entering confined space must be
using ventilation air force for gas
monitering and using multi-gas device 4
in 1 for checking ( Apply with oxygen
form 19.5% to 23.5%) and checking
every 02 hours one time ( but no
limmited for checking atmosphere inside
confined space following DVN EHS
requested or instructed on site)
4. Establish for comunication system
from inside and outside of confined
space.
5. Do not working alone and at least
working inside confined space 03
persons.
6. Establish a tripod and pulley for
rescuse in case emergency
When workers working inside must be
used safety harness for rescuse reasons
and ERT menber must be available
during the time workers working inside
and comply with Emergency procedure
of DVN EHS.
Rescuse in emergency case Fatal or death for worker if not in time Any case in emergency contact to
DVN’EHS Department and LILMA
HSSE Department with Telephone
number: 0974.39.33.99 or DVN EHS
023.7386.2595
Following procedures and actions are to
be followed
in a case a victim is to be rescued from
an enclosed space: