PROPOSED DEVELOPMENT OF

MATERIAL OFF-LOADING
FACILITIES (MOLF) IN PANTAI
PUTERI, KAMPUNG PENGKALAN
PERIGI, MELAKA
BY

EC GLOBAL SDN BHD


 Preliminaries and general works
 Earthworks and general Infrastructures
 Sheet pile and temporary works

COMPONENT  Pilings and sub-structure works

DEVELOPMENTS  Concrete works for beams, platforms and slabs


 Winches and mechanical works
&
 Electrical, ancilliaries and and associated works
CONSTRUCTIONS
 Engineering consultancy and project managements
WORKS  Navigational aids
 Contingencies
PROPOSAL - DESIGN

 THE PROPOSED MATETRIAL LANDING


FACILITIES IS LOCATED AT PANTAI
PUTERI, KAMPUNG PENGKALAN PERIGI,
TANJUNG KELING MELAKA, IT IS
APPROXIMATELY 14 KM FROM MELAKA
TOWN.
PROPOSAL - DESIGN

 THE MATERIAL LANDING FACILITIES


SHALL BE CONSTRUCTED FROM LAYERS
OF BOULDERS/BROKEN CUT=OFF PILES,
CRUSHER RUN AND FINISHES WITH
LAYER OF ASPHALT WITH CONCRETE
BLOCKS AT THE LANDING END AND
PROCTECTED BY PNEUMATIC FENDERS.
 THE LANDING SITE SHALL BE
COMPACTED UP TO THE REQUIRED
COMPACTION RATIO TO WITHSTAND
THE WEIGHT OF LORRY AND MATERIAL
TO BE DISCHARGED FROM THE VESSEL
ONTO THE STORAGE AREA.
PROPOSAL - SITE

 PROPOSED BEACH SITE APPROACH WAY


HAS A SUFFICIENT WATER DEPTH
DURING 4 HOURLY TIDAL CHANGE.
 GENERAL APPROACH TO THE FACILITIES
SHALL BE ON A SOUTH EASTERLY AND
ESTERLY COURSE.
PROPOSAL – INITIAL PHASE

 SITE INVESTIGATION SHALL BE


CARRIED IN ADVANCE BY
CONSULTING ENGINEERS TO
AQUIRE DATA FOR THE DETAIL
SCHEMATIC, ENGINERING DESIGN
COST ESTIMATES AND APPROVAL
PROCESSES. HYDRAULIC STUDIES
SHALL BE CARRIED OUT TO
COMPLY WITH JPS AND JKR
REQUIREMENT
PLANNING, ENGINEERING CONSULTANCY AND WORKS SERVICES

NO SCOPE OF WORKS FEES/PRICE (RM)


1 Site recognition and inspections 4,000
2 Preliminary studies and preparation of master plan 20,000
3 Preparation of preliminary cost estimates 4,000
4 Detailed engineering design, technical drawings, specifications, 80,000
Bill of Quantities, documentations,, approvals.
5 Prepare contract document. 4,000
6 Reports and documentation 4,500
7 Construction phase-Clearing of unused debris, obstruction on- 100,000
shore and off-shore (approach channel way)
PLANNING, ENGINEERING CONSULTANCY AND WORKS SERVICES

NO SCOPE OF WORKS FEES/PRICE (RM)


8 Construction phase – reclamation works, sub-base preparation,
Preliminaries and general works ,Earthworks and general 760,000
Infrastructures, Sheet pile and temporary works, Pilings and sub-
structure works, Concrete works for breakwater, broken cut-off
piles, crusher run, asphalt and slabs, Winches and mechanical works,
Electrical, ancillaries and associated works, Navigational aids

TOTAL 976,500
PROPOSED SCHEDULE
MONTHS
ITEM DESCRIPTION OF MAJOR TASK MTH 1 MTH 2 MTH 3 MTH 4 MTH 5
WK 1 WK 2 WK 3 WK 4 WK 1 WK 2 WK 3 WK 4 WK 1 WK 2 WK 3 WK 4 WK 1 WK 2 WK 3 WK 4 WK 1 WK 2 WK 3 WK 4
1 APPOINTMENT

2 SITE VISIT AND APPRAISAL

3 PRELIMANARY STUDIES AND DEVELOPMENT OF MASTERPLAN

4 DETAILED ENGINEERING DESIGN AND APPROVAL SUBMISSION

5 DRAWINGS AND SPECIFICATION AND APPROVAL SUBMISSION

6 CONTRACT DOCUMENTATION

7 CONSTRUCTION STAGE

8 TESTING AND COMMISSIONING