Building Estimation in Excel Sheet
Building Estimation in Excel Sheet
Building Estimation in Excel Sheet
Length
Sr. No. Item Description No. (m) Breadth Depth Quantity
(m) (m)
1 Earthwork in Excavation in
Foundation:
48.9 -0.90/2*6 1 46.20 0.90 1.10 45.74 cu m
46.2 45.74 cu m
2 P. C.C. for Foundation
48.9-0.90/2*6 1 46.20 0.90 0.20 8.32 cu m
46.2 8.32 cu m
Brickwork in Cement
3 Mortar in Foundation
Plinth:
**Foundation:
1st Step:
48.9-0.5/2*6 1 47.40 0.50 0.30 7.11 cu m
47.4
2nd Step:
48.9-0.4/2*6 1 47.70 0.40 0.30 5.72 cu m
47.7
3rd Step:(up to plinth)
48.9-0.3/2*6 1 48.00 0.30 0.85 12.24 cu m
48 SE
25.07 cu m
1st Class Brickwork in Lime
4 Mortar in Superstructure:
48.9-0.3/2*6 1 48.00 0.20 3.00 28.80 cu m
48
Dividing wall between w.c & Bath 1 3.00 0.10 3.00 0.90 cu m
Wall infornt of W/C 1 1.10 0.10 3.00 0.33 cu m
30.03 cu m
**Deduction:
DOOR
D 3 1.10 0.20 2.10 1.39 cu m
D1 2 0.90 0.20 2.10 0.76 cu m
G1 1 1.20 0.20 2.10
WINDOW
W1 4 1.80 0.20 1.40 2.02 cu m
W2 1 1.20 0.20 1.40 0.34 cu m
W3 1 1.50 0.20 1.40 0.42 cu m
V 2 0.60 0.20 0.60 0.14 cu m
5.06 cu m
Net Quantity 24.97 cu m
5 Earthfilling in Plinth:
Drawing Room 1 4.00 4.00 0.55 8.80 cu m
Bed Room 1 4.00 3.00 0.55 6.60 cu m
Kitchen 1 3.00 4.00 0.55 6.60 cu m
Bath , W/C & Open Space 1 3.00 3.00 0.55 4.95 cu m
26.95 cu m
7 R. C. C. Work in Slab:
L = 11.4 1 11.40 10.10 0.15 17.27 cu m
B = 10.1 17.27 cu m
Deduction
Net
JAYVANTRAI HARRAI DESAI POLYTECHNIC [686], PALSANA
CIVIL ENGINEERING DEPARTMENT (06)
QUANTITY SHEET
Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity
(m) (m) (m)
1 Excavation for Foundation:
L.W.= 9+.8=9.8m 3 9.80 0.80 1.10 25.87 cu m
SW1=3.5-.8=2.7m 4 2.70 0.80 1.10 9.50 cu m
SW2=3.8-.8=3m 3 3.00 0.80 1.10 7.92 cu m
H.W.=2.1-.8=1.3m 1 1.30 0.80 1.10 1.14 cu m
44.44 cu m
2 P. C. C. For Foundation:
L.W.= 9+.8=9.8m 3 9.80 0.80 0.20 4.70 cu m
SW1=3.5-.8=2.7m 4 2.70 0.80 0.20 1.73 cu m
SW2=3.8-.8=3m 3 3.00 0.80 0.20 1.44 cu m
H.W.=2.1-.8=1.3m 1 1.30 0.80 0.20 0.21 cu m
8.08 cu m
3 1st Class Brick Masonry in CM
(1:6) up to Plinth:
**Foundation:
1st Step:
L.W.= 9+.6=9.6m 3 9.60 0.60 0.30 5.18 cu m
SW1=3.5-.6=2.9m 4 2.90 0.60 0.30 2.09 cu m
SW2=3.8-.6=3.2m 3 3.20 0.60 0.30 1.73 cu m
H.W.=2.1-.6=1.5m 1 1.50 0.60 0.30 0.27 cu m
2nd Step:
L.W.= 9+.5=9.5m 3 9.50 0.50 0.30 4.28 cu m
SW1=3.5-.5=3m 4 3.00 0.50 0.30 1.80 cu m
SW2=3.8-.5=3.3m 3 3.30 0.50 0.30 1.49 cu m
H.W.=2.1-.5=1.6m 1 1.60 0.50 0.30 0.24 cu m
3rd Step:
L.W.= 9+.4=9.4m 3 9.40 0.40 0.30 3.38 cu m
SW1=3.5-.4=3.1m 4 3.10 0.40 0.30 1.49 cu m
SW2=3.8-.4=3.4m 3 3.40 0.40 0.30 1.22 cu m
H.W.=2.1-.4=1.7m 1 1.70 0.40 0.30 0.20 cu m
**Plinth:
L.W.= 9+.3=9.3m 3 9.30 0.30 0.60 5.02 cu m
SW1=3.5-.3=3.2m 4 3.20 0.30 0.60 2.30 cu m
SW2=3.8-.3=3.5m 3 3.50 0.30 0.60 1.89 cu m
H.W.=2.1-.3=1.8m 1 1.80 0.30 0.60 0.32 cu m
**Steps:
Bottom 1 2.70 0.90 0.15 0.36 cu m
Middle 1 2.70 0.60 0.15 0.24 cu m
Top 1 2.70 0.30 0.15 0.12 cu m
33.64 cu m
4 1st Class Brick Masonry in CM
(1:6) in Superstructure:
L.W.= 9+.3=9.3m 3 9.30 0.30 3.00 25.11 cu m
SW1=3.5-.3=3.2m 4 3.20 0.30 3.00 11.52 cu m
SW2=3.8-.3=3.5m 3 3.50 0.30 3.00 9.45 cu m
H.W.=2.1-.3=1.8m 1 1.80 0.30 3.00 1.62 cu m
Parapet wall:
L= 9+.3=9.3m 2 9.30 0.30 0.70 3.91 cu m
B=7m 2 7.00 0.30 0.70 2.94 cu m
54.55 cu m
**Deduction:
D 6 1.20 0.30 2.10 4.54 cu m
D1 1 0.90 0.30 2.00 0.54 cu m
W 6 1.50 0.30 1.40 3.78 cu m
V 3 0.60 0.30 0.45 0.24 cu m
Lintels:(.15m bearing)
D 6 1.50 0.30 0.10 0.27 cu m
D1 1 1.20 0.30 0.10 0.04 cu m
W 6 1.80 0.30 0.10 0.32 cu m
V 3 0.90 0.30 0.10 0.08 cu m
9.81 cu m
Net Quantity 44.74 cu m
5 Sand filling in Plinth:
Drawing Room 1 4.20 3.50 0.575 8.45 cu m
Dinning Room 1 4.20 3.50 0.575 8.45 cu m
Toilet 1 1.80 1.70 0.575 1.76 cu m
Kitchen 1 2.10 3.20 0.575 3.86 cu m
Bed Room 1 4.20 3.20 0.575 7.73 cu m
Passage 1 1.80 1.20 0.575 1.24 cu m
31.50 cu m
6 12 mm thick plaster in CM (1:4)
in internal walls and Ceiling of
Drawing Room, Bed Room and
Dinning Room:
Walls:
Drawing Room 2 4.20 1.00 3.00 25.20 sq m
2 3.50 1.00 3.00 21.00 sq m
Bed Room 2 4.20 1.00 3.00 25.20 sq m
2 3.20 1.00 3.00 19.20 sq m
Dinning Room 2 4.20 1.00 3.00 25.20 sq m
2 3.50 1.00 3.00 21.00 sq m
136.80 sq m
Ceiling:
Drawing Room 1 4.20 3.50 1.00 14.70 sq m
Bed Room 1 4.20 3.20 1.00 13.44 sq m
Dinning Room 1 4.20 3.50 1.00 14.70 sq m
42.84 sq m
Deduction: (From Walls)
(Common Door Shared)D 0.5*4 + 1*1 1.20 1.00 2.10 7.56 sq m
D1 0.5*1 0.90 1.00 2.00 0.90 sq m
W 0.5*6 1.50 1.00 1.40 6.30 sq m
14.76 sq m
Net Quantity 164.88 sq m
7 20mm thick outside plaster:
Horizontal Wall 2 9.30 1.00 4.80 89.28 sq m
Vertical Wall 2 7.60 1.00 4.80 72.96 sq m
Steps:
Sides 2 1.00 0.90 0.15 0.27 sq m
2 1.00 0.60 0.15 0.18 sq m
2 1.00 0.30 0.15 0.09 sq m
Riser 3 2.70 1.00 0.15 1.22 sq m
Trade 3 2.70 0.30 1.00 2.43 sq m
166.43 sq m
Deduction: (From Walls)
D 0.5*2 1.20 1.00 2.10 2.52 sq m
W 0.5*6 1.50 1.00 1.40 6.30 sq m
8.82 sq m
Net Quantity 157.61 sq m
Deduction
Net
JAYVANTRAI HARRAI DESAI POLYTECHNIC [686], PALSANA
CIVIL ENGINEERING DEPARTMENT (06)
QUANTITY SHEET
Widht/ Height/
Length
Sr. No. Item Description No. (m) Breadth Depth Quantity
(m) (m)
1 Earthwork in Excavation:
L.W.= 8.8+.8=9.6m 3 9.60 0.80 1.10 25.34 cu m
SW1=3.3-.8=2.5m 3 2.50 0.80 1.10 6.60 cu m
SW2=4.3-.8=3.5m 4 3.50 0.80 1.10 12.32 cu m
44.26 cu m
2 Materials for Foundation
Concrete (1:3:6)
L.W.= 8.8+.8=9.6m 3 9.60 0.80 0.40 9.22 cu m
SW1=3.3-.8=2.5m 3 2.50 0.80 0.40 2.40 cu m
SW2=4.3-.8=3.5m 4 3.50 0.80 0.40 4.48 cu m
16.10 cu m
Materials:
Total = 1 + 3 + 6 = 10 Parts
Cement= (1/10)*1.52*16.10= 2.4472 cu m = 70 Bags
Sand=(3/10)*1.52*16.10= 7.3416 cu m
Aggregate= (6/10)*1.52*16.10= 14.6832 cu m
3 1st Class Brick Masonry in CM
(1:6) up to Plinth:
**Foundation:
1st Step:
L.W.= 8.8+.6=9.4m 3 9.40 0.60 0.30 5.08 cu m
SW1=3.3-.6=2.7m 3 2.70 0.60 0.30 1.46 cu m
SW2=4.3-.6=3.7m 4 3.70 0.60 0.30 2.66 cu m
2nd Step:
L.W.= 8.8+.5=9.3m 3 9.30 0.50 0.20 2.79 cu m
SW1=3.3-.5=2.8m 3 2.80 0.50 0.20 0.84 cu m
SW2=4.3-.5=3.8m 4 3.80 0.50 0.20 1.52 cu m
3rd Step:
L.W.= 8.8+.4=9.2m 3 9.20 0.40 0.20 2.21 cu m
SW1=3.3-.4=2.9m 3 2.90 0.40 0.20 0.70 cu m
SW2=4.3-.4=3.9m 4 3.90 0.40 0.20 1.25 cu m
**Plinth:
L.W.= 8.8+.3=9.1m 3 9.10 0.30 0.50 4.10 cu m
SW1=3.3-.3=3m 3 3.00 0.30 0.50 1.35 cu m
SW2=4.3-.3=4m 4 4.00 0.30 0.50 2.40 cu m
26.35 cu m
4 1st Class Brick Masonry in CM
(1:6) in Superstructure:
L.W.= 8.8+.3=9.1m 3 9.10 0.30 2.90 23.75 cu m
SW1=3.3-.3=3m 3 3.00 0.30 2.90 7.83 cu m
SW2=4.3-.3=4m 4 4.00 0.30 2.90 13.92 cu m
Parapet wall:
L= .3+3+.3+4+.3=7.9m 2 7.90 0.30 0.80 3.79 cu m
B=4+.3+4.2=8.5m 2 8.50 0.30 0.80 4.08 cu m
53.37 cu m
**Deduction:
D 6 1.20 0.30 2.00 4.32 cu m
D1 2 0.75 0.30 2.00 0.90 cu m
W 2 1.50 0.30 1.20 1.08 cu m
W1 6 0.90 0.30 1.20 1.94 cu m
V 2 0.60 0.30 0.40 0.14 cu m
Lintels:(.15m bearing)
D 6 1.20 0.30 0.10 0.22 cu m
D1 2 0.75 0.30 0.10 0.05 cu m
W 2 1.50 0.30 0.10 0.09 cu m
W1 6 0.90 0.30 0.10 0.16 cu m
V 2 0.60 0.30 0.10 0.04 cu m
8.94 cu m
Net Quantity 44.44 cu m
5 Sand filling in Plinth:
Room-1 1 3.00 4.20 0.50 6.30 cu m
Room-2 1 3.00 4.00 0.50 6.00 cu m
Room-3 1 4.00 3.00 0.50 6.00 cu m
Room-4 1 4.00 3.00 0.50 6.00 cu m
Passage 1 4.00 1.90 0.50 3.80 cu m
28.10 cu m
6 Internal Wall Plaster and Ceilling
Plaster for Room 1, 2, 3, 4:
Walls:
Room-1 2 3.00 1.00 2.90 17.40 sq m
2 4.20 1.00 2.90 24.36 sq m
Room-2 2 3.00 1.00 2.90 17.40 sq m
2 4.00 1.00 2.90 23.20 sq m
Room-3 2 4.00 1.00 2.90 23.20 sq m
2 3.00 1.00 2.90 17.40 sq m
Room-4 2 4.00 1.00 2.90 23.20 sq m
2 3.00 1.00 2.90 17.40 sq m
163.56 sq m
Ceiling:
Room-1 1 3.00 4.20 1.00 12.60 sq m
Room-2 1 3.00 4.00 1.00 12.00 sq m
Room-3 1 4.00 3.00 1.00 12.00 sq m
Room-4 1 4.00 3.00 1.00 12.00 sq m
48.60 sq m
**Deduction: (From Walls)
D .5*6 1.20 1.00 2.00 7.20 sq m
W .5*2 1.50 1.00 1.20 1.80 sq m
W1 .5*6 0.90 1.00 1.20 3.24 sq m
12.24 sq m
Net Quantity 199.92 sq m
7 20mm thick outside plaster:
Horizontal Wall 2 7.90 1.00 4.45 70.31 sq m
Vertical Wall 2 8.50 1.00 4.45 75.65 sq m
145.96 sq m
**Deduction: (From Walls)
D .5*2 1.20 1.00 2.00 2.40 sq m
W .5*2 1.50 1.00 1.20 1.80 sq m
W1 .5*6 0.90 1.00 1.20 3.24 sq m
7.44 sq m
Net Quantity 138.52 sq m
8 D. P. C. (1:2:4) Over Plinth Walls:
L.W.= 8.8+.3=9.1m 3 9.10 0.30 1.00 8.19 sq m
SW1=3.3-.3=3m 3 3.00 0.30 1.00 2.70 sq m
SW2=4.3-.3=4m 4 4.00 0.30 1.00 4.80 sq m
15.69 sq m
**Deduction:
D 6 1.20 0.30 1.00 2.16 sq m
D1 2 0.75 0.30 1.00 0.45 sq m
2.61 sq m
Number of Tiles for Room 1, 2, 3, Net Quantity 13.08 sq m
9 4 (Size: 25 cm X 25 cm):
Room-1 1 3.00 4.20 1.00 12.60 sq m
Room-2 1 3.00 4.00 1.00 12.00 sq m
Room-3 1 4.00 3.00 1.00 12.00 sq m
Room-4 1 4.00 3.00 1.00 12.00 sq m
24.60 sq m
Cement Concrete for Lintels, Number of Tiles= 394 Tiles
10 Slabs and Chajja:
Lintels:
D 6 1.20 0.30 0.10 0.22 cu m
D1 2 0.75 0.30 0.10 0.05 cu m
W 2 1.50 0.30 0.10 0.09 cu m
W1 6 0.90 0.30 0.10 0.16 cu m
V 2 0.60 0.30 0.10 0.04 cu m
Widht/ Height/
Sr. No. Item Description No. Length Breadth Depth Quantity
(m)
(m) (m)
1 Cement Concrete for Slab 1 3.40 4.40 0.12 1.80 cu m
L=3+.2+.2=3.4m
B=4+.2+.2=4.4m
2
Centering and Shuttering for Slab
Bottom 1 3.00 4.00 1.00 12.00 sq m
Sides 2 3.40 1.00 0.12 0.82 sq m
2 4.40 1.00 0.12 1.06 sq m
13.87 sq m
3 Reinforcement
12mm dia. Main straight bars: 23 3.52m @ 0.88kg/m 71.24 kg
L=3+2*.2+2(hook)-2(cover)
L=3+2*.2+2(9*0.012)-2(0.05)
L=3.52m
**Here min. Hook should be 0.110m
Span= 4+2*.2-2(cover)
Span= 4+2*.2-2(0.05)
Span=4.3m
x= 120-2(20)-12=68mm=0.068m
L=4+2*.2+2(9*0.006)-2(0.05)
L=4.45m
**Here min. Hook should be 0.075m
Span= 3+2*.2-2(cover)
Span= 3+2*.2-2(0.05)
Span=3.3m
Span=.2+.6-cover-0.068
Span=.2+.6-0.05-0.068
Span= 0.68m
No.
No. Of
Of Bars=
Bars= (Span/Spacing)+1
(0.68/.15)+1=6 Bars
(One Side)
Total Weight of 6mm Dia. Bars 34.27 kg
JAYVANTRAI HARRAI DESAI POLYTECHNIC [686], PALSANA
CIVIL ENGINEERING DEPARTMENT (06)
QUANTITY SHEET
Widht/ Height/
Sr. No. Item Description No. Length Breadth Depth Quantity
(m)
(m) (m)
1 Cement Concrete for Beam 1 6.40 0.30 0.75 1.44 cu m
L=6+.2+.2=6.4m
B=.3m
H=.75m
2
Centering and Shuttering for Slab
Bottom 1 6.00 0.30 1.00 1.80 sq m
Sides 2 6.40 1.00 0.75 9.60 sq m
Ends 2 1.00 0.30 0.75 0.45 sq m
11.85 sq m
3 Reinforcement
25mm Dia. Straight Bars: 4 6.80 m @ 3.85kg/m 104.72 kg
L=6.4+2*.2+2(hook)-2(cover)
L=6.4+2*.2+2(9*0.025)-2(0.025)
L=6.8m
L=6.8+ 2(.45x)
L=6.8+ 2(.45*.663)
L=7.4m
Total Weight of 25 mm Dia. Bars 161.70 kg
12mm Dia. Anchor Bar: 2 6.57 m @ 0.88kg/m 11.56 kg
L= 6.4-2(0.025)+2(9*.012)
L=6.57m
Total Weight of 25 mm Dia. Bars 11.56 kg
Stirrups: 6 mm dia. Bars: 23 2.00 m @ 0.22kg/m 10.12 kg
l=.3-2(cover)-2(stirrup dia.)
l=.3-2(.025)-2(.006)
l=0.238m
b=.75-2(cover)-2(stirrup dia.)
b=.75-2(0.025)-2(.006)
b=0.688m
L=2(l+b)+24d
L=2(.238+.688)+ 24*.006=2 m