Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 80

Republic of the Philippines Undertaking of Surety 8 holding themselves personally liable for the accountabilities of

SUPREME COURT FCC.


Baguio
THIRD DIVISION Also, FCC procured Performance Bond No. 31915 amounting to ₱ 6,828,329.00 from
G.R. No. 180898               April 18, 2012 petitioner Philippine Charter Insurance Corporation (PCIC) to secure full and faithful
PHILIPPINE CHARTER INSURANCE CORPORATION, Petitioner, performance of its obligation under the Building Contract. 9
vs.
PETROLEUM DISTRIBUTORS & SERVICE CORPORATION Respondent.
DECISION The construction of the Park ‘N Fly started on February 1, 1999.
MENDOZA, J.:
Pursuant to the Building Contract, PDSC sourced out construction materials and
Before the Court is a petition for review under Rule 45 of the Rules of Court seeking the subcontracted various phases of the work to help obtain the lowest cost of the
reversal of the July 31, 2007 Decision 1 and the December 28, 2007 Resolution2 of the construction and speed up the work of the project. These resulted in the reduction of the
Court of Appeals (CA) in CA-G.R. CV No. 82417, which affirmed with modification the contract price.10
January 12, 2004 Decision of the Regional Trial Court, Branch 111, Pasay City (RTC).
During the Phase 1 of the project, PDSC noticed that FCC was sixteen (16) days behind
The Facts: schedule. In a Letter 11 dated March 25, 1999, it reminded FCC to catch up with the
schedule of the projected work path, or it would impose the penalty of 1/10 of the 1% of
the contract price. The problem, however, was not addressed, as the delay increased to
On January 27, 1999, respondent Petroleum Distributors and Services Corporation (PDSC), 30 days12 and ballooned to 60 days.13
through its president, Conrado P. Limcaco, entered into a building contract 3 with N.C.
Francia Construction Corporation (FCC), represented by its president and chief executive
officer, Emmanuel T. Francia, for the construction of a four-story commercial and parking Consequently, on September 10, 1999, FCC executed a deed of assignment, 14 assigning a
complex located at MIA Road corner Domestic Road, Pasay City, known as Park ‘N Fly portion of its receivables from Caltex Philippines, Inc. (Caltex), and a chattel mortgage, 15 
Building (Park ‘N Fly). Under the contract, FCC agreed to undertake the construction of conveying some of its construction equipment to PDSC as additional security for the
Park ‘N Fly for the price of ₱ 45,522,197.72. faithful compliance with its obligation.

The parties agreed that the construction work would begin on February 1, 1999. Under On even date, PDSC and FCC likewise executed a memorandum of agreement (MOA),16 
the Project Evaluation and Review Technique Critical Path Method (PERT-CPM), the wherein the parties agreed to revise the work schedule of the project. As a consequence,
project was divided into two stages: Phase 1 4 of the construction work would be finished Performance Bond No. 31915 was extended up to March 2, 2000. 17
on May 17, 1999 and Phase 2 5 would begin on May 18, 1999 and finish on October 20,
1999. The project should be turned over by October 21, 1999. 6 It was further stipulated For failure of FCC to accomplish the project within the agreed completion period, PDSC, in
that in the event FCC failed to finish the project within the period specified, liquidated a letter18 dated December 3, 1999, informed FCC that it was terminating their contract
damages equivalent to 1/10 of 1% of the contract price for every day of delay shall accrue based on Article 12, Paragraph 12.1 of the Building Contract. Subsequently, PDSC sent
in favor of PDSC.7 demand letters19 to FCC and its officers for the payment of liquidated damages amounting
to ₱ 9,149,962.02 for the delay. In the same manner, PDSC wrote PCIC asking for
To ensure compliance with its obligation, FCC’s individual officers, namely, Natividad remuneration pursuant to Performance Bond No. 31915. 20
Francia, Emmanuel C. Francia, Jr., Anna Sheila C. Francia, San Diego Felipe G. Bermudez,
Emmanuel T. Francia, Charlemagne C. Francia, and Ruben G. Caperiña, signed the Despite notice, PDSC did not receive any reply from either FCC or PCIC, constraining it to
file a complaint21 for damages, recovery of possession of personal property and/or
foreclosure of mortgage with prayer for the issuance of a writ of replevin and writ of Nonetheless, in the event that PCIC would be made liable, its liability should be in
attachment, against FCC and its officers before the RTC. PDSC later filed a supplemental proportion to the liabilities of the other sureties.
complaint22 impleading PCIC, claiming coverage under Performance Bond No. 31915 in the
amount of ₱ 6,828,329.66. On January 12, 2004, the RTC rendered its Decision 25 in favor of PDSC. The RTC found FCC
guilty of delay when it failed to finish and turn over the project on October 15, 1999. It
In its Amended Answer with affirmative defense and counterclaim, 23 FCC admitted that it pronounced FCC and PCIC jointly and severally liable and ordered them to pay PDSC the
entered into a contract with PDSC for the construction of the Park ‘N Fly building. It, amount of ₱ 9,000,000.00 as damages and ₱ 50,000.00 as attorney’s fees plus interest.
however, asserted that due to outsourcing of different materials and subcontracting of
various phases of works made by PDSC, the contract price was invariably reduced to ₱ FCC and PCIC filed their respective notice of appeal 26 with the RTC. On February 12, 2004,
19,809,822.12. the RTC issued its Order27 giving due course to the notice of appeal.

FCC denied any liability to PDSC claiming that any such claim by the latter had been On July 31, 2007, the CA modified the RTC’s decision. 28 The CA agreed that FCC incurred
waived, abandoned or otherwise extinguished by the execution of the September 10, delay in the construction of the project. It, however, found that the computation of the
1999 MOA. FCC claimed that in the said MOA, PDSC assumed all the obligations originally liquidated damages should be based on the reduced contract price of ₱ 19,809,822.12.
reposed upon it. FCC further explained that the PERT-CPM agreed upon by the parties The dispositive portion reads:
covering the first phase of the work project was severely affected when PDSC deleted
several scopes of work and undertook to perform the same. In fact, the PERT-CPM was
evaluated and it was concluded that the delay was attributable to both of them. FCC WHEREFORE, the Decision dated 12 January 2004 of the Regional Trial Court of Pasay City,
added that after Phase I of the project, it sent a progress billing in the amount of ₱ Branch 111 is AFFIRMED with MODIFICATION in that appellants N.C. Francia Construction
939,165.00 but PDSC approved the amount of ₱ 639,165.00 only after deducting the cost Corporation, Natividad Francia, Emmanuel Francia, Jr., Anna Sheila Francia San Diego,
of the attributable delay with the agreement that from then on, PDSC should shoulder all Felipe Bermudez, Emmanuel Francia, Charlemagne Francia, Ruben Caperiña, and
expenses in the construction of the building until completion; that FCC would provide the Philippine Charter Insurance Corporation are hereby held solidarily liable to pay appellee
workers on the condition that they would be paid by PDSC; and that it would allow PDSC Petroleum Distributors & Services Corporation (1) liquidated damages in the sum of ₱
free use of the construction equipments that were in the project site. 3,882,725.13, which shall earn legal interest at the rate of 6% per annum from 10 January
2000 until finality of this judgment; (2) attorney’s fees amounting to ₱ 50,000.00; and (3)
cost of suit. Pursuant to Performance Bond No. 31915, the liability of appellant Philippine
For its part, PCIC averred that as a surety, it was not liable as a principal obligor; that its Charter Insurance Corporation should not exceed ₱ 6,828,329.66.
liability under the bond was conditional and subsidiary and that it could be made liable
only upon FCC’s default of its obligation in the Building Contract up to the extent of the
terms and conditions of the bond. PCIC also alleged that its obligation under the Appellants N.C Francia Construction Corporation, Emmanuel Francia and Natividad Francia
performance bond was terminated when it expired on October 15, 1999 and the are adjudged liable to pay appellant Philippine Charter Insurance Corporation for the
extension of the performance bond until March 2, 2000 was not binding as it was made amount the latter may have paid under Performance Bond No. 31915.
without its knowledge and consent.
SO ORDERED.29
PCIC added that PDSC’s claim against it had been waived, abandoned or extinguished by
the September 10, 1999 MOA. It also argued that its obligation was indeed extinguished FCC and PCIC filed their separate motions for reconsideration 30 but the CA denied them in
when PDSC terminated the contract on December 3, 1999 and took over the construction its December 28, 2007 Resolution.31
and it failed to file its claim within ten (10) days from the expiry date or from the alleged
default of FCC.24 Hence, this petition.
It is well to note that only PCIC appealed the CA’s decision. It became final and executory claims that it is unlawful and iniquitous to hold FCC responsible for the delay of the
with regard to FCC and the other parties in the case. Hence, the Court shall limit its subcontractor commissioned by PDSC.
discussion to the liability of PCIC.
PCIC adds that the act of PDSC of subcontracting the various stages of the project resulted
In its Memorandum,32 PCIC anchored its petition on the following issues: in a revision of work schedule and extension of the completion date that ultimately
released both FCC and PCIC of whatever claims PDSC may have against them. PCIC is of
1. Whether or not the Court of Appeals, in adjudging Petitioner liable for liquidated the impression that since the subcontracting made by PDSC was made without its consent
damages, expanded liability under Performance Bond No. 31915 which on its face and knowledge, its liability under the performance bond should be extinguished.
answers only for actual and compensatory damages, not liquidated damages.
PCIC also pointed out that the receivable in the amount of ₱ 2,793,000.00 acquired by
Assuming arguendo liability for liquidated damages under the performance bond, PDSC from Caltex and the proceeds from the auction sale in the sum of ₱ 662,836.50
whether or not the Court of Appeals erred in not declaring that the award of liquidated should be deducted from the award of ₱ 3,882,725.13.
damages is iniquitous and unconscionable and in not applying the provisions of Article
2227, Civil Code, and Palmares v. Court of Appeals, 288 SCRA 422. The Court finds no merit in the petition.

2. Whether or not the Memorandum of Agreement dated Sept. 10, 1999 entered into by The Building Contract entered into by PDSC and FCC provides that:
respondent and Francia Construction, confirmed in a letter dated Sept. 20, 1999, ---
without Petitioner’s knowledge or consent---, the effect that all costs, expenses, payments Art. 2 ESSENCE OF THE CONTRACT
and obligations shall be deemed paid, performed and fully settled as of Sept. 10, 1999,
discharged Petitioner from liability under the performance bond under Article 2079, Civil
Code. 2.1 It is understood that time, quality of work in accordance with the OWNER’s
requirements, and reduced construction costs are the essence of this Contract.

3. Whether or not the Court of Appeals, having made the finding of fact that the sums of
Php2,793,000.00 and Php662,836.50 should be deducted from Php3,882,725.13, erred in 2.2 The CONTRACTOR shall commence the construction for the first two (2) levels not
not deducting the amounts in the dispositive portion of the decision. 33 later than five (5) days immediately after the date of execution of this Contract and shall
regularly proceed and complete the construction within Two Hundred Fifty-Nine (259)
calendar days reckoned from the date of signing of this Contract or not later than October
In sum, the issues before the Court are (1) whether or not PCIC is liable for liquidated 15, 1999, whichever is earlier. To ensure completion of the work within the time given
damages under the performance bond; (2) whether or not the September 10, 1999 MOA herein, construction work shall be conducted at least twenty hours each day with at least
executed by PDSC and FCC extinguished PCIC’s liability under the performance bond; and two (2) work shift for every day actually worked.
(3) whether or not the amounts of ₱ 2,793,000.00 and ₱ 662,836.50 are deductible from
the liquidated damages awarded by the CA.
2.3 In the event that the construction is not completed within the aforesaid period of
time, the OWNER is entitled and shall have the right to deduct from any amount that may
PCIC argues that in case of a breach of contract, the performance bond is answerable only be due to the CONTRACTOR the sum of one-tenth (1/10) of one percent (1%) of the
for actual or compensatory, not for liquidated damages. The terms of the bond are clear contract price for every day of delay in whatever stage of the project as liquidated
that the liability of the surety is determined by the contract of suretyship and cannot be damages, and not by way of penalty, and without prejudice to such other remedies as the
extended by implication beyond the terms of the contract. Nonetheless, even assuming OWNER may, in its discretion, employ including the termination of this Contract, or
that it is liable under the performance bond, the liability should be based on equity. It replacement of the CONTRACTOR.
2.4 Furthermore, the CONTRACTOR agrees not to request any extension of time due to TWENTY EIGHT THOUSAND THREE HUNDRED TWENTY NINE &
any delay in the procurement of materials needed in the construction other than due to 66/100 ONLY (₱ 6,828,329.66) Philippine Currency for the payment of
circumstances of "Force Majeure". Force Majeure is hereby defined as any war, civil which sum well and truly to be made, we bind ourselves, our heirs,
commotion and disturbance, acts of God or any other cause beyond the CONTRACTOR’s executors, administrators, successors, and assigns, jointly and
control and without any contributing fault on the part of the CONTRACTOR. severally, firmly by these presents.

2.5 Contractor shall arrange, schedule and carry on the work so as not to interfere with THE CONDITION OF THIS OBLIGATION ARE AS FOLLOWS:
the delivery and erection of the work of others. To facilitate the erection of such other
work, the CONTRACTOR shall cease or resume work at any point or stage of the Project, WHEREAS, the above bounden principal, on the ____ day of
when so directed by the OWNER or his duly authorized representative. [Emphasis ________ 19___ entered into an ________________ with
supplied] ___________, to fully and faithfully guarantee that the above-named
Principal shall furnish, deliver, place and complete any and all
Paragraph 2.3 of the Building Contract clearly provides a stipulation for the payment of necessary materials, labor, plant, tools appliances and equipment,
liquidated damages in case of delay in the construction of the project. Such is in the supplies, utilities transportation, superintendence, supervision and all
nature of a penalty clause fixed by the contracting parties as a compensation or substitute other facilities in connection with the construction of a 4-storey
for damages in case of breach of the obligation. 34 The contractor is bound to pay the commercial/parking complex situated at MIA Road cor. Domestic
stipulated amount without need for proof of the existence and the measures of damages Road, Pasay City as per attached Building Contract dated January 27,
caused by the breach.35 1999.

Article 2226 of the Civil Code allows the parties to a contract to stipulate on liquidated Provided, however, that the liability of the Surety Company under
damages to be paid in case of breach. It is attached to an obligation in order to insure this bond shall in no case exceed the face value hereof.
performance and has a double function: (1) to provide for liquidated damages, and (2) to
strengthen the coercive force of the obligation by the threat of greater responsibility in WHEREAS, said oblige requires said principal to give a good and
the event of breach.36 As a general rule, contracts constitute the law between the parties, sufficient bond in the above stated sum to secure the full and faithful
and they are bound by its stipulations.37 For as long as they are not contrary to law, performance on its part of said undertaking.
morals, good customs, public order, or public policy, the contracting parties may establish
such stipulations, clauses, terms and conditions as they may deem convenient. 38
NOW THEREFORE, if the principal shall well and truly perform and
fulfill all the undertakings, covenants, terms conditions and
In the case at bench, the performance bond issued by PCIC specifically provides that: agreements stipulated in said undertakings then this obligation shall
be null and void; otherwise it shall remain in full force and effect.
KNOW ALL MEN BY THESE PRESENTS: [Emphasis Supplied]

That we, N.C. FRANCIA CONSTRUCTION CORPORATION of Merryland By the language of the performance bond issued by PCIC, it guaranteed the full and
Corporate Offices, 3250 Gracia St., cor. Edsa, Brgy. Pinagkaisahan, faithful compliance by FCC of its obligations in the construction of the Park ‘N Fly. In fact,
Makati City, as Principal and PHILIPPINE CHARTER INSURANCE the primary purpose for the acquisition of the performance bond was to guarantee to
CORPORATION, a corporation duly organized and existing under and PDSC that the project would proceed in accordance with the terms and conditions of the
by virtue of the laws of the Philippines, as Surety, are held and firmly contract and to ensure the payment of a sum of money in case the contractor would fail in
bound unto PETROLEUM DISTRIBUTORS & SERVICES CORPORATION, the full performance of the contract. 39 This guaranty made by PCIC gave PDSC the right to
as obligee in the sum of PESOS SIX MILLION EIGHT HUNDRED proceed against it (PCIC) following FCC’s non-compliance with its obligation.
A contract of suretyship is an agreement whereby a party, called the surety, guarantees A surety agreement has two types of relationship: (1) the principal relationship between
the performance by another party, called the principal or obligor, of an obligation or the obligee and the obligor; and (2) the accessory surety relationship between the
undertaking in favor of another party, called the obligee. 40 Although the contract of a principal and the surety. The obligee accepts the surety’s solidary undertaking to pay if
surety is secondary only to a valid principal obligation, the surety becomes liable for the the obligor does not pay. Such acceptance, however, does not change in any material way
debt or duty of another although it possesses no direct or personal interest over the the obligee’s relationship with the principal obligor. Neither does it make the surety an
obligations nor does it receive any benefit therefrom. 41 This was explained in the case active party in the principal obligor-obligee relationship. It follows, therefore, that the
of Stronghold Insurance Company, Inc. v. Republic-Asahi Glass Corporation,42 where it was acceptance does not give the surety the right to intervene in the principal contract. The
written: surety’s role arises only upon the obligor’s default, at which time, it can be directly held
liable by the obligee for payment as a solidary obligor.46
The surety’s obligation is not an original and direct one for the performance of his own
act, but merely accessory or collateral to the obligation contracted by the principal. Furthermore, in order that an obligation may be extinguished by another which
Nevertheless, although the contract of a surety is in essence secondary only to a valid substitutes the same, it is imperative that it be so declared in unequivocal terms, or that
principal obligation, his liability to the creditor or promisee of the principal is said to be the old and new obligation be in every point incompatible with each other. 47 Novation of a
direct, primary and absolute; in other words, he is directly and equally bound with the contract is never presumed. In the absence of an express agreement, novation takes place
principal. only when the old and the new obligations are incompatible on every point. 48

Corollary, when PDSC communicated to FCC that it was terminating the contract, PCIC’s Undoubtedly, a surety is released from its obligation when there is a material alteration of
liability, as surety, arose. The claim of PDSC against PCIC occurred from the failure of FCC the principal contract in connection with which the bond is given, such as a change which
to perform its obligation under the building contract. As mandated by Article 2047 of the imposes a new obligation on the promising party, or which takes away some obligation
Civil Code, to wit: already imposed, or one which changes the legal effect of the original contract and not
merely its form.49 In this case, however, no new contract was concluded and perfected
Article 2047. By guaranty, a person, called the guarantor, binds himself to the creditor to between PDSC and FCC. A reading of the September 10, 1999 MOA reveals that only the
fulfill the obligation of the principal debtor in case the latter should fail to do so. revision of the work schedule originally agreed upon was the subject thereof. The parties
saw the need to adjust the work schedule because of the various subcontracting made by
PDSC. In fact, it was specifically stated in the MOA that "all other terms and conditions of
If a person binds himself solidarily with the principal debtor, the provisions of Section 4, the Building Contract of 27 January 1999 not inconsistent herewith shall remain in full
Chapter 3, Title I of this Book shall be observed. In such case, the contract is called a force and effect."50 There was no new contract/agreement which could be considered to
suretyship. have substituted the Building Contract. As correctly ruled by the CA, thus:

Thus, suretyship arises upon the solidary binding of a person deemed the surety with the At first blush, it would seem that the parties agreed on a revised timetable for the
principal debtor for the purpose of fulfilling an obligation. 43 A surety is considered in law construction of Park ‘N Fly. But then, nowhere in the voluminous records of this case
as being the same party as the debtor in relation to whatever is adjudged touching the could We find the Annex "A" mentioned in the above-quoted agreement which could have
obligation of the latter, and their liabilities are interwoven as to be inseparable. 44  shed light to the question of whether a new period was indeed fixed by the parties. The
Therefore, as surety, PCIC becomes liable for the debt or duty of FCC although it possesses testimony of appellant Emmanuel Francia, Sr., President and Chief Executive Officer of
no direct or personal interest over the obligations of the latter, nor does it receive any appellant N.C, Francia, candidly disclosed what truly happened to Annex "A", as he
benefit therefrom.45 admitted that no new PERT/CPM was actually attached to the Memorandum of
Agreement.
The Court also found untenable the contention of PCIC that the principal contract was
novated when PDSC and FCC executed the September 10, 1999 MOA, without informing
the surety, which, in effect, extinguished its obligation.
Accordingly, We find no compelling reason to declare that novation ensued under the proceeds from the auction sale in the sum of ₱ 662,836.50 should be deducted from the
prevailing circumstances. The execution of the Building Contract dated 27 January 1999 award of ₱ 3,882,725.13.
does not constitute a novation of the Memorandum of Agreement dated 10 September
1999. There lies no incompatibility between the two contracts as their principal object and SO ORDERED.
conditions remained the same. While there is really no hard and fast rule to determine
what might constitute to be a sufficient change that can bring about novation, the
touchtone for contrariety, however, would be an irreconcilable incompatibility between
the old and the new obligations.51

It must likewise be emphasized that pursuant to the September 10, 1999 MOA, PCIC
extended the coverage of the performance bond until March 2, 2000. 52

Finally, as pointed out by PCIC, the receivable in the amount of ₱ 2,793,000.00 acquired
by PDSC from Caltex and the proceeds from the auction sale in the sum of ₱ 662,836.50
should be deducted from the award of ₱ 3,882,725.13. There is no quibble on this point.
The ruling of the CA on the matter is very clear. It reads:

With these points firmly in mind, We proceed to the next question raised by appellants –
whether the value of the securities given as well as the proceeds of the sale of chattels
should be deducted from the claim of liquidated damages.

We answer in the affirmative.

There is no quibble that appellant N.C Francia assigned a portion of its receivables from
Caltex Philippines, Inc. in the amount of ₱ 2,793,000.00 pursuant to the Deed of
Assignment dated 10 September 1999. Upon transfer of said receivables, appellee
Petroleum Distributors automatically stepped into the shoes of its transferor. It is in
keeping with the demands of justice and equity that the amount of these receivables be
deducted from the claim for liquidated damages.

So too, vehicles and equipment owned by appellant N.C. Francia were sold at public
auction at ₱ 1,070,000.00. After deducting storage fees, the amount of ₱ 662,836.50 was
deposited before the court a quo. The latter amount accrues in favor of appellee
Petroleum Distributors as partial payment of its claim for liquidated damages.

WHEREFORE, the petition is DENIED. The July 31, 2007 Decision and December 28, 2007
Resolution of the Court of Appeals (CA) in CA-G.R. CV No. 82417 are AFFIRMED. The
receivable in the amount of ₱ 2,793,000.00 acquired by PDSC from Caltex and the
2110006344 499,890.00 12/04/2000 03/12/2001

2110006557 798,010.00 12/18/2000 04/23/2001

2110100189 496,521.00 01/11/2001 05/07/20016


Republic of the Philippines
SUPREME COURT
Manila The above promissory notes (PN) were later consolidated under a single promissory note,
THIRD DIVISION PN No. SADDK001014188, for ₱4,246,310.00, to mature on February 28, 2002. 7 Yulim
G.R. No. 203133               February 18, 2015 defaulted on the said note. On April 5, 2002, iBank sent demand letters to Yulim, through
YULIM INTERNATIONAL COMPANY LTD., JAMES YU, JONATHAN YU, and ALMERICK its President, James, and through Almerick, 8 but without success. iBank then filed a
TIENG LIM, Petitioners, Complaint for Sum of Money with Replevin 9 against Yulim and its sureties. On August 8,
vs. 2002, the Court granted the application for a writ of replevin. Pursuant to the Sheriff’s
INTERNATIONAL EXCHANGE BANK (now Union Bank of the Philippines), Respondent. Certificate of Sale dated November 7, 2002, 10 the items seized from Yulim’s warehouse
were worth only ₱140,000.00, not ₱500,000.00 as the petitioners have insisted. 11
DECISION
REYES, J.: On October 2, 2002, the petitioners moved to dismiss the complaint insisting that their
In the assailed Decision1 dated February 1, 2012 in CA-G.R. CV No. 95522, the Court of loan had been fully paid after they assigned to iBank their Condominium Unit No. 141,
Appeals (CA) modified the Decision 2 dated December 21, 2009 of the Regional Trial Court with parking space, at 20 Landsbergh Place in Tomas Morato Avenue, Quezon City. 12 They
(RTC) of Makati City, Branch 145, in Civil Case No. 02-749, holding that James Yu (James), claimed that while the pre-selling value of the condominium unit was ₱3.3 Million, its
Jonathan Yu (Jonathan) and Almerick Tieng Lim (Almerick), who were capitalist partners in market value has since risen to 5.5 Million. 13 The RTC, however, did not entertain the
Yulim International Company Ltd. (Yulim), collectively called as the petitioners, were motion to dismiss for non-compliance with Rule 15 of the Rules of Court.
jointly and severally liable with Yulim for its loan obligations with respondent International
Exchange Bank (iBank).
On May 16, 2006, the petitioners filed their Answer reiterating that they have paid their
loan by way of assignment of a condominium unit to iBank, as well as insisting that iBank’s
The Facts
penalties and charges were exorbitant, oppressive and unconscionable. 14
On June 2, 2000, iBank, a commercial bank, granted Yulim, a domestic partnership, a
credit facility in the form of an Omnibus Loan Line for ₱5,000,000.00, as evidenced by a
Credit Agreement3 which was secured by a Chattel Mortgage 4 over Yulim’s inventories in Ruling of the RTC
its merchandise warehouse at 106 4th Street, 9th Avenue, Caloocan City. As further
guarantee, the partners, namely, James, Jonathan and Almerick, executed a Continuing After trial on the merits, the RTC rendered judgment on December 21, 2009, the
Surety Agreement5 in favor of iBank. dispositive portion of which reads, as follows:

Yulim availed of its aforesaid credit facility with iBank, as follows: WHEREFORE, in view of the foregoing considerations, the Court finds the individual
defendants James Yu, Jonathan Yu and Almerick Tieng Lim, not liable to the plaintiff,
iBank, hence the complaint against them is hereby DISMISSED for insufficiency of
Promissory Note No. Face Value PN Date Date of Maturity
evidence, without pronouncement as to cost.
2110005852 ₱1,298,926.00 10/26/2000 01/29/2001

2110006026 1,152,963.00 11/18/2000 02/05/2001


This court, however, finds defendant corporation Yulim International Company Ltd. liable; [YULIM] FOR COSTS OF SUIT INCURRED BY [iBANK] IN ORDER TO PROTECT ITS RIGHTS.21
and it hereby orders defendant corporation to pay plaintiff the sum of ₱4,246,310.00 with
interest at 16.50% per annum from February 28, 2002 until fully paid plus cost of suit. Chiefly, the factual issue on appeal to the CA, raised by petitioners James, Jonathan and
Almerick, was whether Yulim’s loans have in fact been extinguished with the execution of
The counterclaims of defendants against plaintiff iBank are hereby DISMISSED for a Deed of Assignment of their condominium unit in favor of iBank, while the corollary
insufficiency of evidence. SO ORDERED.15 legal issue, raised by iBank, was whether they should be held solidarily liable with Yulim
for its loans and other obligations to iBank.
Thus, the RTC ordered Yulim alone to pay iBank the amount of ₱4,246,310.00, plus
interest at 16.50% per annum from February 28, 2002 until fully paid, plus costs of suit, The CA ruled that the petitioners failed to prove that they have already paid Yulim’s
and dismissed the complaint against petitioners James, Jonathan and Almerick, stating consolidated loan obligations totaling 4,246,310.00, for which it issued to iBank PN No.
that there was no iota of evidence that the loan proceeds benefited their families. 16 SADDK001014188 for the said amount. It held that the existence of a debt having been
established, the burden to prove with legal certainty that it has been extinguished by
The petitioners moved for reconsideration on January 12, 2010; 17 iBank on January 19, payment devolves upon the debtors who have offered such defense. The CA found the
2010 likewise filed a motion for partial reconsideration.18 In its Joint Order19 dated March records bereft of any evidence to show that Yulim had fully settled its obligation to iBank,
8, 2010, the RTC denied both motions. further stating that the so-called assignment by Yulim of its condominium unit to iBank
was nothing but a mere temporary arrangement to provide security for its loan pending
the subsequent execution of a real estate mortgage. Specifically, the CA found nothing in
Ruling of the CA the Deed of Assignment which could signify that iBank had accepted the said property as
full payment of the petitioners’ loan. The CA cited Manila Banking Corporation v. Teodoro,
On March 23, 2010, Yulim filed a Notice of Partial Appeal, followed on March 30, 2010 by Jr.22 which held that an assignment to guarantee an obligation is in effect a mortgage and
iBank with a Notice of Appeal. not an absolute conveyance of title which confers ownership on the assignee.

Yulim interposed the following as errors of the court a quo: Concerning the solidary liability of petitioners James, Jonathan and Almerick, the CA
disagreed with the trial court’s ruling that it must first be shown that the proceeds of the
I. THE LOWER COURT ERRED IN ORDERING [YULIM] TO PAY [iBANK] THE AMOUNT OF loan redounded to the benefit of the family of the individual petitioners before they can
₱4,246,310.00 WITH INTEREST AT 16.5% PER ANNUMFROM FEBRUARY 28, 2002 UNTIL be held liable. Article 161 of the Civil Code and Article 121 of the Family Code cited by the
FULLY PAID. RTC apply only where the liability is sought to be enforced against the conjugal
II. THE LOWER COURT ERRED IN NOT ORDERING [iBANK] TO PAY ATTORNEY’S FEES, partnership itself. In this case, regardless of whether the loan benefited the family of the
MORAL DAMAGES AND EXEMPLARY DAMAGES.20 individual petitioners, they signed as sureties, and iBank sought to enforce the loan
obligation against them as sureties of Yulim.

For its part, iBank raised the following as errors of the RTC:
Thus, the appellate court granted the appeal of iBank, and denied that of the petitioners,
as follows:
I. THE TRIAL COURT ERRED IN NOT HOLDING INDIVIDUAL [PETITIONERS JAMES,
JONATHAN AND ALMERICK] SOLIDARILY LIABLE WITH [YULIM] ON THE BASIS OF THE
CONTINUING SURETYSHIP AGREEMENT EXECUTED BY THEM. WHEREFORE, the foregoing considered, [iBank’s] appeal is PARTLY GRANTED while [the
II. THE TRIAL COURT ERRED IN NOT HOLDING ALL THE [PETITIONERS] LIABLE FOR PENALTY petitioners’] appeal is DENIED. Accordingly, the appealed decision is hereby MODIFIED in
CHARGES UNDER THE CREDIT AGREEMENT AND PROMISSORY NOTES SUED UPON. that [petitioners] James Yu, Jonathan Yu and A[l]merick Tieng Lim are hereby held jointly
III. THE TRIAL COURT ERRED IN NOT HOLDING [THE PETITIONERS] LIABLE TO [iBANK] FOR and severally liable with defendant-appellant Yulim for the payment of the monetary
ATTORNEY’S FEES AND INDIVIDUAL [PETITIONERS] JOINTLY AND SEVERALLY LIABLE WITH awards. The rest of the assailed decision is AFFIRMED. SO ORDERED.23
Petition for Review to the Supreme Court If a person binds himself solidarily with the principal debtor, the provisions of Section 4,
Chapter 3, Title I of this Book shall be observed. In such case the contract is called a
In the instant petition, the following assigned errors are before this Court: suretyship.

1. The CA erred in ordering petitioners James, Jonathan and Almerick jointly and severally In a contract of suretyship, one lends his credit by joining in the principal debtor’s
liable with petitioner Yulim to pay iBank the amount of ₱4,246,310.00 with interest at obligation so as to render himself directly and primarily responsible with him without
16.5% per annum from February 28, 2002 until fully paid. reference to the solvency of the principal. 26 According to the above Article, if a person
2. The CA erred in not ordering iBank to pay the petitioners moral damages, exemplary binds himself solidarily with the principal debtor, the provisions of Articles 1207 to 1222,
damages, and attorney’s fees.24 or Section 4, Chapter 3, Title I, Book IV of the Civil Code on joint and solidary obligations,
shall be observed. Thus, where there is a concurrence of two or more creditors or of two
or more debtors in one and the same obligation, Article 1207 provides that among them,
The petitioners insist that they have paid their loan to iBank. They maintain that the letter "[t]here is a solidary liability only when the obligation expressly so states, or when the law
of iBank to them dated May 4, 2001, which "expressly stipulated that the petitioners shall or the nature of the obligation requires solidarity."
execute a Deed of Assignment over one condominium unit No. 141, 3rd Floor and a
parking slot located at 20 Landsbergh Place, Tomas Morato Avenue, Quezon City," was
with the understanding that the Deed of Assignment, which they in fact executed, "A surety is considered in law as being the same party as the debtor in relation to
delivering also to iBank all the pertinent supporting documents, would serve to totally whatever is adjudged touching the obligation of the latter, and their liabilities are
extinguish their loan obligation to iBank. In particular, the petitioners state that it was interwoven as to be inseparable." 27 And it is well settled that when the obligor or obligors
their understanding that upon approval by iBank of their Deed of Assignment, the same undertake to be "jointly and severally" liable, it means that the obligation is solidary, 28 as
"shall be considered as full and final payment of the petitioners’ obligation." They further in this case. There can be no mistaking the same import of Article I of the Continuing
assert that iBank’s May 4, 2001 letter expressly carried the said approval. Surety Agreement executed by the individual petitioners:

The petitioner invoked Article1255 of the Civil Code, on payment by cession, which ARTICLE I
provides: Art. 1255. The debtor may cede or assign his property to his creditors in LIABILITIES OF SURETIES
payment of his debts. This cession, unless there is stipulation to the contrary, shall only
release the debtor from responsibility for the net proceeds of the thing assigned. The SECTION 1.01. The SURETIES, jointly and severally with the PRINCIPAL, hereby
agreements which, on the effect of the cession, are made between the debtor and his unconditionally and irrevocably guarantee full and complete payment when due, whether
creditors shall be governed by special laws. at stated maturity, by acceleration, or otherwise, of any and all credit accommodations
that have been granted or may be granted, renewed and/or extended by the BANK to the
Ruling of the Court PRINCIPAL. The liability of the SURETIES shall not be limited to the maximum principal
amount of FIVE MILLION PESOS (₱5,000,000.00) but shall include interest, fees, penalty
and other charges due thereon.
The petition is bereft of merit. Firstly, the individual petitioners do not deny that they
executed the Continuing Surety Agreement, wherein they "jointly and severally with the
PRINCIPAL [Yulim], hereby unconditionally and irrevocably guarantee full and complete SECTION 1.02. This INSTRUMENT is a guarantee of payment and not merely of collection
payment when due, whether at stated maturity, by acceleration, or otherwise, of any and and is intended to be a perfect and continuing indemnity in favor of the BANK for the
all credit accommodations that have been granted" to Yulim by iBank, including interest, amounts and to the extent stated above.
fees, penalty and other charges. 25 Under Article 2047 of the Civil Code, these words are
said to describe a contract of suretyship. It states: Art. 2047. By guaranty a person, called The liability of the SURETIES shall be direct, immediate and not contingent upon the
the guarantor, binds himself to the creditor to fulfill the obligation of the principal debtor pursuit of the BANK of whatever remedies it may have against the PRINCIPAL of the other
in case the latter should fail to do so. securities for the Accommodation.29
Thereunder, in addition to binding themselves "jointly and severally" with Yulim to the condominium unit has been delivered to iBank. This is so because the petitioners
"unconditionally and irrevocably guarantee full and complete payment" of any and all would then execute a Deed of Real Estate Mortgage over the property in favor of iBank as
credit accommodations that have been granted to Yulim, the petitioners further warrant security for their loan obligations.
that their liability as sureties "shall be direct, immediate and not contingent upon the
pursuit [by] the BANK of whatever remedies it may have against the PRINCIPAL of other Respondent iBank certainly does not share the petitioners’ interpretation of its May
securities." There can thus be no doubt that the individual petitioners have bound 4,2001 letter. Joy Valerie Gatdula, Senior Bank Officer of iBank and the Vice President of
themselves to be solidarily liable with Yulim for the payment of its loan with iBank. iBank’s Commercial Banking Group, declared in her testimony that the purpose of the
Deed of Assignment was merely to serve as collateral for their loan:
As regards the petitioners’ contention that iBank in its letter dated May 4, 2001 had
"accepted/approved" the assignment of its condominium unit in Tomas Morato Avenue as Q: And during the time that the defendant[,] James Yu[,] was negotiating with your bank,
full and final payment of their various loan obligations, the Court is far from persuaded. [is it] not a fact that the defendant offered to you a [condominium] unit so that – that will
On the contrary, what the letter accepted was only the collaterals provided for the loans, constitute full payment of his obligation?
as well as the consolidation of the petitioners’ various PN’s under one PN for their A: No ma’am. It was not offered that way. It was offered as security or collateral to pay
aggregate amount of ₱4,246,310.00. The letter goes on to spell out the terms of the new the outstanding loans. But the premise is, that he will pay x x x in cash. So, that property
PN, such as, that its expiry would be February 28, 2002 or a term of 360 days, that interest was offered as a security or collateral.
would be due every 90 days, and that the rate would be based on the 91-day Treasury Bill Q: That was your position?
rate or other market reference. A: That was the agreement and that was how the document was signed. It was worded
out[.]
Nowhere can it be remotely construed that the letter even intimates an understanding by
iBank that the Deed of Assignment would serve to extinguish the petitioners’ loan. xxxx
Otherwise, there would have been no need for iBank to mention therein the three
"collaterals" or "supports" provided by the petitioners, namely, the Deed of Assignment,
the Chattel Mortgage and the Continuing Surety Agreement executed by the individual Q: Do you remember if a real estate mortgage was executed over this property that was
petitioners. In fact, Section 2.01 of the Deed of Assignment expressly acknowledges that it being assigned to the plaintiff?
is a mere "interim security for the repayment of any loan granted and those that may be A: To my recollection, none at all.
granted in the future by the BANK to the ASSIGNOR and/or the BORROWER, for Q: Madam Witness, this Deed of Assignment was considered as full payment by the
compliance with the terms and conditions of the relevant credit and/or loan documents plaintiff bank, what document was executed by the plaintiff bank?
thereof."30 The condominium unit, then, is a mere temporary security, not a payment to A: It should have been a Dacion en Pago.
settle their promissory notes.31 Q: Was there such document executed in this account?
A: None.33

Even more unmistakably, Section 2.02 of the Deed of Assignment provides that as soon as
title to the condominium unit is issued in its name, Yulim shall "immediately execute the To stress, the assignment being in its essence a mortgage, it was but a security and not a
necessary Deed of Real Estate Mortgage in favor of the BANK to secure the loan satisfaction of the petitioners’ indebtedness. 34 Article 125535 of the Civil Code invoked by
obligations of the ASSIGNOR and/or the BORROWER." 32 This is a plain and direct the petitioners contemplates the existence of two or more creditors and involves the
acknowledgement that the parties really intended to merely constitute a real estate assignment of the entire debtor’s property, not a dacion en pago. 36 Under Article 1245 of
mortgage over the property.1âwphi1 In fact, the Deed of Assignment expressly states, by the Civil Code, "[d]ationin payment, whereby property is alienated to the creditor in
way of a resolutory condition concerning the purpose or use of the Deed of Assignment, satisfaction of a debt in money, shall be governed by the law on sales." Nowhere in the
that after the petitioners have delivered or caused the delivery of their title to iBank, the Deed of Assignment can it be remotely said that a sale of the condominium unit was
Deed of Assignment shall then become null and void. Shorn of its legal efficacy as an contemplated by the parties, the consideration for which would consist of the amount of
interim security, the Deed of Assignment would then become functus officio once title to
outstanding loan due to iBank from the petitioners. WHEREFORE, premises considered, proceedings on the mortgaged property on 26 November 1999. 12 From the extrajudicial
the petition is DENIED. SO ORDERED. sale, it realized only Pl.5 million as evidenced by a Certificate of Sale. 13 This amount, when
applied to the total outstanding loan obligation of Pl,865,345.77, would still leave a
deficiency of P365,345.77. For that reason, the bank prayed that the court order the
payment of the deficiency amount with interest at 12% per annum computed from 13
January 2000; attorney's fees equal to 10% of the deficiency amount; and litigation
FIRST DIVISION expenses and costs of suit. 14
February 24, 2016
G.R. No. 210542
ROSALINA CARODAN, Petitioner, Barbara and Rebecca filed their Answer. They interposed the defense that although they
vs. both stood as principal borrowers, they had entered into an oral agreement with
CHINA BANKING CORPORATION, Respondent. Madeline and Rosalina. Under that agreement which was witnessed by China Bank's loan
officer and branch manager, they would equally split both the proceeds of the loan and
DECISION the corresponding obligation and interest pertaining thereto, and they would secure the
SERENO, CJ: loan with the properties belonging to them. 15 Barbara and Rebecca used as security their
This is a Petition for Review on Certiorari1  seeking to set aside the Decision2 dated 9 July real properties covered by TCT Nos. T-93177, T-93176, T-93174, T-93167, T-93169, T-
2013 and the Resolution3 dated 29 November 2013 rendered by the Court of Appeals 93170, T-93171 and T-93172; while Rosalina and Madeline used for the same purpose the
(CA), Ninth Division, Manila, in CA-G.R. CV No. 95835. The CA denied petitioner's appeal former's property covered by TCTNo. T-10216. 16
assailing the Decision4 dated 23 June 2010 issued by the Regional Trial Court (RTC) of
Tuguegarao City, Branch 2, in Civil Case No. 5692. Barbara and Rebecca further alleged that while Rosalina and Madeline obtained their
share of Pl.4 million of the loan amount, the latter two never complied with their
THE ANTECEDENT FACTS obligation to pay interest. It was only Rebecca's account with China Bank that was
automatically debited in the total amount of Pl,002,735.54. 17 Barbara and Rebecca asked
China Bank for the computation of their total obligation, for which they paid Pl.5 million
The records reveal that on 6 June 2000, China Banking Corporation (China Bank) instituted aside from the interest payments, and respondent bank thereafter released the Real
a Complaint5 for a sum of money against Barbara Perez (Barbara), Rebecca Perez-Viloria Estate Mortgage over their properties.18
(Rebecca), Rosalina Carodan (Rosalina) and Madeline Carodan (Madeline). China Bank
claimed that on 15 January 1998, Barbara and Rebecca, for value received, executed and
delivered Promissory Note No. TLS-98/0076 to respondent bank under which they By way of crossclaim, Barbara and Rebecca asked Rosalina and Madeline to pay half of
promised therein to jointly and severally pay the amount of P2.8 million. 7 China Bank Pl,002,735.54 as interest payments, as well as the deficiency amount plus 12% interest per
further claimed that as security for the payment of the loan, Barbara, Rebecca and annum and attorney's fees, the total amount of which pertained to the loan obligation of
Rosalina also executed a Real Estate Mortgage 8 over a property registered in the name of the latter two. 19 By way of counterclaim, Barbara and Rebecca also asked China Bank to
Rosalina and covered by Transfer Certificate Title (TCT) No. T-10216. 9 Respondent alleged pay Plmillion as moral damages, P500,000 as exemplary damages, plus attorney's fees and
that a Surety Agreement10 in favor of China Bank as creditor was also executed by Barbara costs of suit.20
and Rebecca as principals and Rosalina and her niece Madeline as sureties. Through that
agreement, the principals and sureties warranted the payment of the loan obligation China Bank filed its Reply and Answer to Counterclaim clarifying that it was suing Barbara
amounting to P2.8 million including interests, penalties, costs, expenses, and attorney's and Rebecca as debtors under the Promissory Note and as principals in the Surety
fees. 11 Agreement, as well as Rosalina and Madeline as sureties in the Surety Agreement. 21 It
claimed that equal sharing of the proceeds of the loan was "a bat at misrepresentation"
Barbara and Rebecca failed to pay their loan obligation despite repeated demands from and "a self-serving prevarication," because what was clearly written on the note was that
China Bank. Their failure to pay prompted the bank institute extrajudicial foreclosure Rebecca and Barbara were the principal debtors. 22 It reiterated that the two were liable
for the full payment of the principal amount plus the agreed interest, charges, penalties modified whether tacitly or expressly, by any agreement made after the execution
and attorney's fees, with recourse to reimbursement from Rosalina and Madeline. 23 thereof."34

China Bank also disputed the claim of Rebecca and Barbara that upon their payment to Finally, Rosalina stated that she had made demands on Barbara and Rebecca to cause the
the bank of Pl.5 million, the Real Estate Mortgage over their properties was cancelled. rectification of the illegal and unjust deprivation of her property in payment of the
Their claim was disputed because, even after their payment of Pl.5 million, Rebecca and indemnity. Allegedly, Barbara and Rebecca simply ignored her demands, so, she prayed
Barbara were still indebted in the amount of P1.3 million exclusive of interest, charges, that the two be held solidarily liable for the total amount of damages and for the
penalties and other legitimate fees. 24 Furthermore, respondent stated that if there was a deficiency judgment sought in this Complaint. 35
cancellation of mortgage, it referred to other mortgages securing other separate loan
obligations of Barbara and Rebecca; more particularly, that of Barbara. 25 China Bank filed its Reply and Answer to Counterclaim. 36 It alleged that the issue of
whether Rosalina obtained material benefit from the loan was not material, since she had
Rosalina filed her Answer with Counterclaim and Crossclaim. 26 She alleged that on 2 July voluntarily and willingly encumbered her property; 37 that the indivisibility of mortgage
1997, she and Barbara executed (1) a Real Estate Mortgage covering Rosalina's lot and does not apply to the case at bar, since Article 208938 of the Civil Code presupposes
ancestral house, as well as Barbara's eight residential apartments, annotated as an several heirs, a condition that is not present in this case; 39 that nothing short of payment
encumbrance at the back of the TCTs corresponding to the properties as evidenced by the of the debt or an express release would operate to discharge a mortgage; 40 and that, as
Annexes to the Answer; and (2) a Surety Agreement to secure the credit facility granted by surety, Rosalina was equally liable as principal debtor to pay the deficiency obligation in
the bank to Barbara and Rebecca up to the principal amount of P2.8 million. 27 Rosalina the sum of P365,345.77 41 The bank also filed its Comment/Opposition 42 to the Entry of
further stated that the execution of the contracts was "made in consideration of the long- Appearance of Atty. Edwin V. Pascua as counsel for Rosalina. It said that Atty. Pascua had
time friendship" between Barbara and Rebecca, and Madeline, and that "no monetary or once been its retained lawyer pursuant to a Retainer Agreement dated 5 September
material consideration whatsoever passed between [Barbara and Rebecca], on the one 1997.43 Because of its Opposition, Rosalina was subsequently represented by Atty.
hand, and [Rosalina], on the other hand." 28 Reynaldo A. Deray.

Rosalina acknowledged that on 15 January 1998, Barbara and Rebecca executed a All the parties submitted their Pre-Trial Briefs with the exception of Madeline, whose case
Promissory Note for the purpose of evidencing a loan charged against the loan facility had been archived by the RTC upon motion of China Bank for the court's failure to acquire
secured by the mortgage.29 She averred, though, that when Barbara and Rebecca paid half jurisdiction over her person. The issues of the case were thereafter limited to the
of the loan under the Promissory Note, the properties of Barbara covered by the following: (1) whether the defendants were jointly and severally liable to pay the
mortgage were released by the bank from liability. The cancellation of the mortgage lien deficiency claim; (2) whether the surety was still liable to the bank despite the release of
was effected by an instrument dated 27 May 1999 and reflected on the TCTs evidenced by the mortgage of the principal borrower; (3) whether there was a previous agreement
the Annexes to the Answer. 30 among the defendants that Barbara and Rebecca would receive half and Rosalina and
Madeline, the other half; and (4) whether respondent bank still had a cause of action
This cancellation, according to Rosalina, illegally and unjustly caused her property to against the surety after the mortgage of the principal borrower had been released by the
absorb the singular risk of foreclosure. 31 The result, according to her, was the bank.44
extinguishment of the indivisible obligation contained in the mortgage pursuant to Article
121632 of the Civil Code.33 THE RULING OF THE RTC

Rosalina further averred that when the bank instituted the foreclosure proceedings, it The RTC ruled that although no sufficient proof was adduced to show that Rosalina had
misrepresented that her property was the only one that was covered by the mortgage; obtained any pecuniary benefit from the loan agreement between Rebecca and Barbara
omitted from the schedule of mortgaged properties those of Barbara; and misrepresented and China Bank, the mortgage between Rosalina and China Bank was still valid. 45 The trial
that "the terms and condition of the aforesaid mortgage have never been changed or
court declared that respondent bank had therefore lawfully foreclosed the mortgage over Before this Court, petitioner Rosalina now imputes error to the CA' s affirmance of the RTC
the property of Rosalina, even if she was a mere accommodation mortgagor. 46 Decision. She says that the CA Decision was not in accord with law and jurisprudence in
holding that petitioner, jointly and severally with Barbara and Rebecca, was liable to pay
The RTC also declared Rosalina's claim to be without merit and without basis in law and China Bank's deficiency claim after the bank's release of the collateral of the principal
jurisprudence. She claimed that because the Real Estate Mortgage covering her property debtors. Respondent bank's alleged act of exposing Rosalina's property to the risk of
was a single and indivisible contract, China Bank's act of releasing the principal debtors' foreclosure despite the indivisible character of the Real Estate Mortgage supposedly
properties resulted in the extinguishment of the obligation. 47 The trial court held that the violated Article 2089 of the New Civil Code. 57
creditor had the right to proceed against any one of the solidary debtors, or some or all of
them simultaneously; and that a creditor's right to proceed against the surety exists China Bank filed its Comment58 claiming that all the grounds cited by petitioner were
independently of the creditor's right to proceed against the principal. 48 "mere reiterations, repetitions, or rehashed grounds and arguments raised in the
Appellant's Brief x x x which were exhaustively passed upon and considered by the CA in
Finally, the RTC ordered Rebecca, Barbara and Rosalina to be jointly and severally liable to its Decision";59 and that the petition "is wanting of any new, substantial and meritorious
China Bank for the deficiency between the acquisition cost of the foreclosed real estate grounds that would justify the reversal of the CA Decision affirming the RTC decision." 60
property and the outstanding loan obligation of Barbara and Rebecca at the time of the
foreclosure sale. Interest was set at the rate of 12% per annum from 13 January 2000 until THE ISSUE
full payment. Rebecca and Barbara were also ordered to reimburse Rosalina for the
amount of the deficiency payment charged against her including interests thereon. 49 The sole issue to be resolved by this Court is whether petitioner Rosalina is liable jointly
and severally with Barbara and Rebecca for the payment of respondent China Bank's
THE RULING OF THE CA claims.

Rosalina filed a timely Notice of Appeal and imputed error to the trial court in finding her, THE RULING OF THIS COURT
together with Rebecca and Barbara, jointly and severally liable to pay the deficiency claim;
in finding that she was still liable as surety even if the bank had already released the Loan transactions in banking institutions usually entail the execution of loan documents,
collateral of the principal borrower; and in not annulling the foreclosure sale of the typically a promissory note, covered by a real estate mortgage and/or a surety
property, not reconveying the property to her, and not awarding her damages as prayed agreement.61 In the instant case, petitioner Rosalina admitted that she was a party to
for in her counterclaim. She said that these were done by the court despite the fact that these loan documents although she vehemently insisted that she had received nothing
China Bank had deliberately and maliciously released the properties of the principal from the proceeds of the loan. 62 Meanwhile, respondent bank offered in evidence the
borrowers, thereby exposing her property to risk. 50 Promissory. Note, the Real Estate Mortgage and the Surety Agreement signed by the
parties.
The CA found the appeal bereft of merit. 51 It qualified Rosalina as a surety who had
assumed or undertaken a principal debtor's responsibility or obligation. As such, she was We find that Rosalina is liable as an accommodation mortgagor.
supposed to be principally liable for the payment of the debt in case the principal debtors
did not pay, regardless of their financial capacity to do so. 52 As for the deficiency, the CA
cited BPI Family Savings Bank v. Avenido.  53 The Supreme Court had ruled therein that the In Belo v. PNB,63  we had the occasion to declare:
creditor was not precluded from recovering any unpaid balance on the principal obligation
if the extrajudicial foreclosure sale of the property, subject of the real estate mortgage, An accommodation mortgage is not necessarily void simply because the accommodation
would result in a deficiency. 54 The CA ultimately affirmed the RTC Decision in toto55  and mortgagor did not benefit from the same. The validity of an accommodation mo1igage is
denied the Motion for Reconsideration. 56 Hence, this Petition. allowed under Article 2085 of the New Civil Code which provides that (t)hird persons who
are not parties to the principal obligation may secure the latter by pledging or mortgaging
their own property. An accommodation mortgagor, ordinarily, is not himself a recipient of and benefits which pertain to him by reason of the fiansa;  while a solidary co-debtor has
the loan, otherwise that would be contrary to his designation as such. 64 no other rights than those bestowed upon him in Section 4, Chapter 3, title I, Book IV of
the Civil Code.
Apart from being an accommodation mortgagor, Rosalina is also a surety, defined under
Article 2047 of the Civil Code in this wise: Section 4, Chapter 3, Title I, Book IV of the Civil Code states the law on joint and several
obligations. Under Art. 1207 thereof, when there are two or more debtors in one and the
Art. 2047. By guaranty a person, called a guarantor, binds himself to the creditor to fulfill same obligation, the presumption is that the obligation is joint so that each of the debtors
the obligation of the principal debtor in case the latter should fail to do so. is liable only for a proportionate part of the debt. There is a solidarity liability only when
the obligation expressly so states, when the law so provides or when the nature of the
obligation so requires.67 (Citations omitted)
If a person binds himself solidarily with the principal debtor, the provisions of Section 4,
Chapter 3, Title I of this Book shall be observed. In such case the contract is called a
suretyship. Further discussion on the same legal concept proceeded thusly:

A contract of suretyship (second paragraph of Article 2047) has been juxtaposed against a A contract of surety is an accessory promise by which a person binds himself for another
contract of guaranty (first paragraph of Article 2047) as follows: already bound, and agrees with the creditor to satisfy the obligation if the debtor does
not. A contract of guaranty, on the other hand, is a collateral undertaking to pay the debt
of another in case the latter does not pay the debt.
A surety is an insurer of the debt, whereas a guarantor is an insurer of the solvency of the
debtor. A suretyship is an undertaking that the debt shall be paid; a guaranty, an
undertaking that the debtor shall pay. Stated differently, a surety promises to pay the Strictly speaking, guaranty and surety are nearly related, and many of the principles are
principal's debt if the principal will not pay, while a guarantor agrees that the creditor, common to both. However, under our civil law, they may be distinguished thus: A surety is
after proceeding against the principal, may proceed against the guarantor if the principal usually bound with his principal by the same instrument, executed at the same time, and
is unable to pay. A surety binds himself to perform if the principal does not, without on the same consideration. He is an original promissor and debtor from the beginning,
regard to his ability to do so. A guarantor, on the other hand, does not contract that the and is held, ordinarily, to know every default of his principal. Usually, he will not be
principal will pay, but simply that he is able to do so. In other words, a surety undertakes discharged, either by the mere indulgence of the creditor to the principal, or by want of
directly for the payment and is so responsible at once if the principal debtor makes notice of the default of the principal, no matter how much he may be injured thereby. On
default, while a guarantor contracts to pay if, by the use of due diligence, the debt cannot the other hand, the contract of guaranty is the guarantor's own separate undertaking, in
be made out of the principal debtor. 65Citations omitted) which the principal does not join. It is usually entered into before or after that of the
principal, and is often supported on a separate consideration from that supporting the
contract of the principal. The original contract of his principal is not his contract, and he is
In Inciong, Jr. v. CA,  66 we elucidated further in this wise: not bound to take notice of its non-performance. He is often discharged by the mere
indulgence of the creditor to the principal, and is usually not liable unless notified of the
While a guarantor may bind himself solidarily with the principal debtor, the liability of a default of the principal.
guarantor is different from that of a solidary debtor. Thus, Tolentino explains:
Simply put, a surety is distinguished from a guaranty in that a guarantor is the insurer of
A guarantor who binds himself in solidum  with the principal debtor under the provisions the solvency of the debtor and thus binds himself to pay if the principal is  unable to
of the second paragraph does not become a solidary co-debtor to all intents and pay  while a surety is the insurer of the debt, and he obligates himself to pay if the
purposes. There is a difference between a solidary co-debtor, and  a fiador in principal does not pay.  68(Citations omitted)
solidum  (surety). The latter, outside of the liability he assumes to pay the debt before the
property of the principal debtor has been exhausted, retains all the other rights, actions
When Rosalina affixed her signature to the Real Estate Mortgage as mortgagor and to the We disagree.
Surety Agreement as surety which covered the loan transaction represented by the
Promissory Note, she thereby bound herself to be liable to China Bank in case the A resort to the terms of the Surety Agreement can easily settle the question of whether
principal debtors, Barbara and Rebecca, failed to pay. She consequently became liable to Rosalina should still be held liable. The agreement expressly contains the following
respondent bank for the payment of the debt of Barbara and Rebecca when the latter two stipulation:
actually did not pay.

The Surety(ies) expressly waive all rights to demand for payment and notice of non-
China Bank, on the other hand, had a right to proceed after either the principal debtors or payment and protest, and agree that the securities of every kind that are now and may
the surety when the debt became due. It had a right to foreclose the mortgage involving hereafter be left with the Creditor its successors, indorsees or assigns as collateral to any
Rosalina's property to answer for the loan. evidence of debt or obligation, or upon which a lien may exist therefor, may be
substituted, withdrawn or surrendered at any time, and the time for the payment of
The proceeds from the extrajudicial foreclosure, however, did not satisfy the entire such obligations extended, without notice to or consent by the Surety(ies) x
obligation. For this reason, respondent bank instituted the present Complaint against xx. 72 (Emphases supplied)
Barbara and Rebecca as principals and Rosalina as surety.
We therefore find no merit in Rosalina's protestations in this petition. As provided by the
A mortgage is simply a security for, and not a satisfaction of indebtedness. 69 If the quoted clause in the contract, she not only waived the rights to demand payment and to
proceeds of the sale are insufficient to cover the debt in an extrajudicial foreclosure of receive notice of nonpayment and protest, but she also expressly agreed that the time for
mortgage, the mortgagee is entitled to claim the deficiency from the debtor. 70 We have payment may be extended. More significantly, she agreed that the securities may be
already recognized this rule: "substituted, withdrawn or surrendered at any time" without her consent or without
notice to her. That China Bank indeed surrendered the properties of the principal debtors
While Act No. 3135, as amended, does not discuss the mortgagee's right to recover the was precisely within the ambit of this provision in the contract. Rosalina cannot now
deficiency, neither does it contain any provision expressly or impliedly prohibiting contest that act in light of her express agreement to that stipulation.
recovery. If the legislature had intended to deny the creditor the right to sue for any
deficiency resulting from the foreclosure of a security given to guarantee an obligation, There have been similar cases in which this Court was tasked to rule on whether a surety
the law would expressly so provide. Absent such a provision in Act No. 3135, as amended, can be discharged from liability due to an act or omission of the creditor. A review of
the creditor is not precluded from taking action to recover any unpaid balance on the these rulings reveals though, that in the absence of an express stipulation, the surety was
principal obligation simply because he chose to extrajudicially foreclose the real estate discharged from liability if the act of the creditor was such as would be declared negligent
mortgage.71 or constitutive of a material alteration of the contract. On the other hand, in the presence
of an express stipulation in the surety agreement allowing these acts, the surety was not
The creditor, respondent China Bank in this Petition, is therefore not precluded, from considered discharged and was decreed to be bound by the stipulations.
recovering any unpaid balance on the principal obligation if the extrajudicial foreclosure
sale of the property, subject of the Real Estate Mortgage, would result in a deficiency. In PNB v. Manila Surety, 73  the Court en banc  declared the surety discharged from liability
on account of the creditor's negligence. In that case, the creditor failed to collect the
Rosalina protests her liability for the deficiency. She claims that China Bank cancelled the amounts due to the debtor contrary to the former's duty to make collections as holder of
mortgage lien and released the. principal borrowers from liability. She contends that this an exclusive and irrevocable power of attorney. The negligence of the creditor allowed the
act violated Article 2089 of the Civil Code on the indivisibility of mortgage and ultimately assigned funds to be exhausted without notice to the surety and ultimately resulted in
discharged her from liability as a surety. depriving the latter of any possibility of recourse against that security.
Also, in PNB v. Luzon Surety, 74  the Court hinted at the possibility of the surety's discharge This is a Continuing Guaranty and shall remain in force and effect until written notice shall
from liability.1avvphi1 It was recognized in that case that in this jurisdiction, alteration can have been received by you that it has been revoked by the undersigned, but any such
be a ground for release. The Court clarified, though, that this principle can only be notice shall not be released the undersigned from any liability as to any instruments,
successfully invoked on the condition that the alteration is material. Failure to comply loans, advances or other obligations hereby guaranteed, which may be held by you, or in
with this requisite means that the surety cannot be freed from liability. Applying this which you may have any interest, at the time of the receipt of such notice. No act or
doctrine in that case, the Court ruled that the alterations in the form of increases in the omission of any kind on your part in the premises shall in any event affect or impair this
credit line with the full consent of the surety did not suffice to release the surety. guaranty, nor shall same be affected by any change which may arise by reason of the
death of the undersigned, of any partner(s) of the undersigned, or of the Borrower, or of
Meanwhile, in Palmares v. CA,  75 the Court ruled: the accession to any such partnership of any one or more new partners. 77

It may not be amiss to add that leniency shown to a debtor in default, by delay permitted Another illustrative case is Gateway Electronics Corporation and Geronimo delos Reyes v.
by the creditor without change in the time when the debt might be demanded, does not Asianbank,  78 in which the surety similarly asked for his discharge from liability. He
constitute an extension of the time of payment, which would release the surety. In order invoked the creditor's repeated extensions of maturity dates to the principal debtor's
to constitute an extension discharging the surety, it should appear that the extension of request, without the surety's knowledge and consent. Still, this Court ruled:
the time was for a definite period, pursuant to an enforceable agreement between the
principal and the creditor, and that it was made without the consent of the surety or with Such contention is unacceptable as it glosses over the fact that the waiver to be notified of
the reservation of rights with respect to him. The contract must be one which precludes extensions is embedded in surety document itself, built in the ensuing provision:
the creditor from, or at least hinders him in, enforcing the principal contract with the
period during which he could otherwise have enforced it, and which precludes the surety In case of default by any/or all of the DEBTOR(S) to pay the whole part of said
from paying the debt. (Citations omitted) indebtedness herein secured at maturity, I/WE jointly and severally, agree and engage to
the CREDITOR, its successors and assigns, the prompt payment, without demand or notice
In E. Zobel Inc. v. CA, et al.,76  the Court upheld the validity of the provision on the from said CREDITOR of such notes, drafts, overdrafts and other credit obligations on which
continuing guaranty - which we had earlier interpreted as a surety consistent with its the DEBTOR(S) may now be indebted or may hereafter become indebted to the
contents and intention of the parties. The Court upheld the validity of the provision CREDITOR, together with interest, penalty and other bank charges as may accrue thereon
despite the insistence of the surety that he should be released from liability due to the and all expenses which may be incurred by the latter in collecting any or all such
failure of the creditor to register the mortgage. In particular, the Court decreed: instruments. 79

SOLIDBANK's failure to register the chattel mortgage did not release petitioner from the On Rosalina's argument that the release of the mortgage violates the indivisibility of
obligation. In the Continuing Guaranty executed in favor of SOLID BANK, petitioner bound mortgage as enunciated in Article 208980 of the Civil Code, People's Bank and Trust
itself to the contract irrespective of the existence of any collateral. It even released SOLID Company v. Tambunting et al.  81 is most instructive. In that case, the surety likewise
BANK from any fault or negligence that may impair the contract. The pertinent portions of argued that he should be discharged from liability. He alleged that the creditor had
the contract so provides: extended the time of payment and released the shares pledged by the principal debtors
without his consent. The Court en banc  found his argument unpersuasive and decreed:
the undersigned (petitioner) who hereby agrees to be and remain bound upon this
guaranty, irrespective of the existence, value or condition of any collateral, and 1. It is thus obvious that the contract of absolute guaranty executed by appellant Santana
notwithstanding any such change, exchange, settlement, compromise, surrender, release, is the measure of rights and duties. As it is with him, so it is with the plaintiff bank. What
sale, application, renewal or extension, and notwithstanding also that all obligations of was therein stipulated had to be complied with by both parties. Nor could appellant have
the Borrower to you outstanding and unpaid at any time(s) may exceed the aggregate any valid cause for complaint. He had given his word; he must live up to it. Once the
principal sum herein above prescribed. validity of its terms is conceded, he cannot be indulged in his unilateral determination to
disregard his commitment. A promise to which the law accords binding force must be
fulfilled. It is as simple as that. So the Civil Code explicitly requires: "Obligations arising
from contracts have the force of law between the contracting parties and should be
complied with in good faith."

2. It could have been different if there were no such contract of absolute guaranty to
which appellant was a party under the aforesaid Article 2080. He would have been freed
from the obligation as a result of plaintiff releasing to the Tambuntings without his
consent the 135 shares of the International Sports Development Corporation pledged to
plaintiff bank to secure the overdraft line. For thereby subrogation became meaningless.
Such a provision is intended for the benefit of a surety. That was a right he could avail of.
He is not precluded however from waiving it. That was what appellant did precisely when
he agreed to the contract of absolute guaranty. Again the law is clear. A right may be
waived unless it would be contrary to law, public order, public policy, morals or good
customs. There is no occasion here for the exceptions corning into play xxx 82

While we rule that Rosalina, along with the principal debtors, Barbara and Rebecca, is still
liable as a surety for the deficiency amount, we modify the RTC's imposition of interest
rate at 12% per annum, which the CA subsequently affirmed. We must modify the rates
according to prevailing jurisprudence. Hence, the 12% legal interest should be imposed on
the deficiency amount from 13 January 2000 until 30 June 2013 and 6% legal interest from
1 July 2013 until full payment.

WHEREFORE, premises considered, the assailed CA Decision and Resolution finding


Rosalina Carodan jointly and severally liable with Barbara Perez and Rebecca Perez-Viloria
for the deficiency amount are AFFIRMED WITH MODIFICATIONS. Rebecca, Barbara and
Rosalina are held jointly and severally liable to China Bank for the deficiency amount of
P365,345.77 and interest thereon at the rates of 12% per annum from 13 January 2000
until 30 June 2013 and 6% per annum from 1 July 2013 until full payment; and that
Rebecca and Barbara are also ordered to reimburse Rosalina for the amount charged
against her including interests thereon. 83

SO ORDERED.
called the DEBTOR(S), of such amounts whether due or not, as indicated opposite their
respective names, to wit:

NAME OF DEBTOR(S) AMOUNT OF OBLIGATION

GATEWAY *P10,000,000.00 *US$3,000,000.00


ELECTRONICS *DOMESTIC BILLS *OMNIBUS CREDIT LINE
CORPORATION [PURCHASED LINE]
Republic of the Philippines
SUPREME COURT
Manila owing to the said ASIANBANK CORPORATION, hereafter called the CREDITOR, as
SECOND DIVISION evidenced by all notes, drafts, overdrafts and other [credit] obligations of every kind and
G.R. No. 172041             December 18, 2008 nature contracted/incurred by said DEBTOR(S) in favor of said CREDITOR.
GATEWAY ELECTRONICS CORPORATION and GERONIMO B. DELOS REYES,
JR., petitioners,
In case of default by any and/or all of the DEBTOR(S) to pay the whole part of said indebt            
vs.
nbsp         nbsp         nbsp         nbsp         erein secured at maturity, I/WE BR
ASIANBANK CORPORATION, respondent.
vs.
and severally agree and engage to the CREDITOR, its successors and assigns, the prompt
DECISION
payment, x x x of such notes, drafts, overdrafts and other credit obligations on which the
VELASCO, JR., J.:
DEBTOR(S) may now be indebted or may hereafter become indebted to the CREDITOR,
This petition for review under Rule 45 seeks to nullify and set aside the Decision 1 dated
together with all interests, penalty and other bank charges as may accrue thereon x x x.
October 28, 2005 of the Court of Appeals (CA) in CA-G.R. CV No. 80734 and its
Resolution2 of March 17, 2006 denying petitioners’ motion for reconsideration.
I/WE further warrant the due and faithful performance by the DEBTOR(S) of all obligations
to be performed under any contracts evidencing indebtedness/obligations and any
The Facts
supplements, amendments, changes or modifications made thereto, including but not
limited to, the due and punctual payment by the said DEBTOR(S).
Petitioner Gateway Electronics Corporation (Gateway) is a domestic corporation that used
to be engaged in the semi-conductor business. During the period material, petitioner
MY/OUR liability on this Deed of Suretyship shall be solidary, direct and immediate and
Geronimo B. delos Reyes, Jr. was its president and one Andrew delos Reyes its executive
not contingent upon the pursuit by the CREDITOR x x x of whatever remedies it or they
vice-president.
may have against the DEBTOR(S) or the securities or liens it or they may possess; and I/WE
hereby agree to be and remain bound upon this suretyship, x x x and notwithstanding also
On July 23, 1996, Geronimo and Andrew executed separate but almost identical deeds of that all obligations of the DEBTOR(S) to you outstanding and unpaid at any time may
suretyship for Gateway in favor of respondent Asianbank Corporation (Asianbank), exceed the aggregate principal sum hereinabove stated. 3
pertinently providing:
Later developments saw Asianbank extending to Gateway several export packing loans in
I/We Geronimo B. de los Reyes, Jr. x x x warrant to the ASIANBANK CORPORATION, x x x the total aggregate amount of USD 1,700,883.48. This loan package was later consolidated
due and punctual payment by the following individuals/companies/firms, hereinafter with Dollar Promissory Note (PN) No. FCD-0599-2749 4 for the amount of USD
1,700,883.48 and secured by a chattel mortgage over Gateway’s equipment for USD 2 WHEREFORE then, in view of the foregoing, judgment is rendered holding defendants
million. Gateway Electronics Corporation, Geronimo De Los Reyes and Andrew De Los Reyes
jointly and severally liable to pay the plaintiff the following:
Gateway initially made payments on its loan obligations, but eventually defaulted. Upon
Gateway’s request, Asianbank extended the maturity dates of the loan several times. a) The sum of $2,235,452.17 United States Currency with interest to be added on at the
These extensions bore the conformity of three of Gateway’s officers, among them prevailing market rate over a given thirty day London Interbank Offered Rate (LIBOR) plus
Andrew. a spread of 5.5358 percent or ten and [45,455/100,000] percent per annum for the first 35
days and every thirty days beginning November 23, 1999 until fully paid;
On July 15 and 30, 1999, Gateway issued two Philippine Commercial International Bank
checks for the amounts of USD 40,000 and USD 20,000, respectively, as payment for its b) a penalty charge after November 23, 1999 of two percent (2%) per month until fully
arrearages and interests for the periods June 30 and July 30, 1999; but both checks were paid;
dishonored for insufficiency of funds. Asianbank’s demands for payment made upon
Gateway and its sureties went unheeded. As of November 23, 1999, Gateway’s obligation c) attorney’s fees of twenty percent (20%) of the total amount due and unpaid; and
to Asianbank, inclusive of principal, interest, and penalties, totaled USD 2,235,452.17.

d) costs of the suit.


Thus, on December 15, 1999, Asianbank filed with the Regional Trial Court (RTC) in Makati
City a complaint for a sum of money against Gateway, Geronimo, and Andrew. The
complaint, as later amended, was eventually raffled to Branch 60 of the court and SO ORDERED.
docketed as Civil Case No. 99-2102 entitled Asian Bank Corporation v. Gateway Electronics
Corporation, Geronimo B. De Los Reyes, Jr. and Andrew S. De Los Reyes. Thereafter, Gateway, Geronimo, and Andrew appealed to the CA, their recourse docketed
as CA-G.R. CV No. 80734. Following the filing of its and Geronimo’s joint appellants’ brief,
In its answer to the amended complaint, Gateway traced the cause of its financial Gateway filed on November 10, 2004 a petition for voluntary insolvency 6 with the RTC in
difficulties, described the steps it had taken to address its mounting problem, and faulted Imus, Cavite, Branch 22, docketed as SEC Case No. 037-04, in which Asianbank was listed
Asianbank for trying to undermine its efforts toward recovery. in the attached Schedule of Obligations as one of the creditors. On March 16, 2005,
Metrobank, as successor-in-interest of Asianbank, via a Notice of Creditor’s Claim, prayed
that it be allowed to participate in the Gateways’s creditors’ meeting.
Andrew also filed an answer alleging, among other things, that the deed of suretyship he
executed covering the PhP 10 million-Domestic Bills Purchased Line and the USD 3 million-
Omnibus Credit Line did not include PN No. FCD-0599-2749, the payment of which was In its Decision dated October 28, 2005, the CA affirmed the decision of the Makati City
extended several times without his consent. RTC. In time, Gateway and Geronimo interposed a motion for reconsideration. This was
followed by a Supplemental Motion for Reconsideration dated January 20, 2006, stating
that in SEC Case No. 037-04, the RTC in Imus, Cavite had issued an Order dated December
Geronimo, on the other hand, alleged that the subject deed of suretyship, assuming the 2, 2004, declaring Gateway insolvent and directing all its creditors to appear before the
authenticity of his signature on it, was signed without his wife’s consent and should, thus, court on a certain date for the purpose of choosing among themselves the assignee of
be considered as a mere continuing offer. Like Andrew, Geronimo argued that he ought to Gateway’s estate which the court’s sheriff has meanwhile placed in custodia
be relieved of his liability under the surety agreement inasmuch as he too never legis.7 Gateway and Geronimo thus prayed that the assailed decision of the Makati City
consented to the repeated loan maturity date extensions given by Asianbank to Gateway. RTC be set aside, the insolvency court having acquired exclusive jurisdiction over the
properties of Gateway by virtue of Section 60 of Act No. 1956, without prejudice to
After due hearing, the RTC rendered judgment dated October 7, 2003 5 in favor of Asianbank pursuing its claim in the insolvency proceedings.
Gateway, the dispositive portion of which states:
In its March 17, 2006 Resolution, however, the CA denied the motion for reconsideration V
and its supplement.
In Agcaoili v. GSIS, this Honorable Court had occasion to state that in determining the
Hence, Gateway and Geronimo filed this petition anchored on the following grounds: precise relief to give, the court will "balance the equities" or the respective interests of
the parties and take into account the relative hardship that one relief or another may
I occasion to them. Upon a balancing of interests of both petitioner GBR and respondent
The [CA] erred in disregarding the established rule that an action commenced by a Asianbank, greater and irreparable harm and injury would be suffered by petitioner GBR
creditor against a judicially declared insolvent for the recovery of his claim should be than respondent Asianbank if the assailed Decision and Resolution of the [CA] would be
dismissed and referred to the insolvency court. Where, therefore, as in this case, upheld x x x. This Honorable Court x x x should thus exercise its equity jurisdiction in the
petitioner GEC [referring to Gateway] has been declared insolvent x x x, respondent instant case to the end that it may render complete justice to both parties and declare
Asianbank’s claim for the payment of GEC’s loans should be ventilated before the petitioner GBR as released and discharged from any liability in respect of respondent
insolvency court x x x. Asianbank’s claims.8
II
The [CA] erred in admitting as evidence the Deed of Surety purportedly signed by The Ruling of the Court
petitioner GBR [referring to Geronimo] despite the unexplained failure of respondent
Asianbank to present the originals of the Deed of Surety during the trial. Gateway May Be Discharged from Liability But Not Geronimo
III
The [CA] erred in holding that the repeated extensions granted by respondent Asianbank
to GEC without notice to and the express consent of petitioner GBR did not discharge Gateway, having been declared insolvent, argues that jurisdiction over all claims against
petitioner GBR from his liabilities as surety GEC in that: all of its properties and assets properly pertains to the insolvency court. Accordingly,
A. An extension granted to the debtor by the creditor without the consent of the Gateway adds, citing Sec. 60 of Act No. 1956, 9 as amended, or the Insolvency Law, any
guarantor extinguishes the guaranty. pending action against its properties and assets must be dismissed, the claimant relegated
B. The [CA] interpreted the supposed Deed of Surety of petitioner GBR as "too to the insolvency proceedings for the claimant’s relief.
comprehensive and all encompassing as to amount to absurdity."
C. The repeated extensions granted by Asianbank to GEC prevented petitioner GBR from The contention, as formulated, is in a qualified sense meritorious. Under Sec. 18 of Act No.
exercising his right of subrogation under Article 2080 of the Civil Code. As such, petitioner 1956, as couched, the issuance of an order declaring the petitioner insolvent after the
GBR should be released from his obligations as surety of GEC. insolvency court finds the corresponding petition for insolvency to be meritorious shall
stay all pending civil actions against the petitioner’s property. For reference, said Sec. 18,
IV setting forth the effects and contents of a voluntary insolvency order, 10 pertinently
provides:

It is a well-settled rule that when a bank deviates from normal banking practice in a
transaction and sustains injury as a result thereof, the bank is deemed to have assumed Section 18. Upon receiving and filing said petition, schedule, and inventory, the court x x x
the risk and no right of payment accrues to the latter against any party to the transaction. shall make an order declaring the petitioner insolvent, and directing the sheriff of the
By repeatedly extending the period for the payment of GEC’s obligations and granting GEC province or city in which the petition is filed to take possession of, and safely keep, until
other loans after the suretyship agreement despite GEC’s default and in failing to the appointment of a receiver or assignee, all the deeds, vouchers, books of account,
foreclose the chattel mortgage constituted as security for GEC’s loan contrary to normal papers, notes, bonds, bills, and securities of the debtor and all his real and personal
banking practices, Asianbank failed to exercise reasonable caution for its own protection property, estate and effects x x x. Said order shall further forbid the payment to the
and assumed the risk of non-payment through its own acts, and thus has no right to creditor of any debts due to him and the delivery to the debtor, or to any person for him,
proceed against petitioner GBR as surety for the payment of GEC’s loans. of any property belonging to him, and the transfer of any property by him, and shall
further appoint a time and place for a meeting of the creditors to choose an assignee of
the estate. Said order shall [be published] x x x. Upon the granting of said order, all civil action for a sum of money filed by Asianbank against Gateway. In net effect, the
proceedings pending against the said insolvent shall be stayed. When a receiver is proceedings before the CA in CA-G.R. CV No. 80734, but only insofar as the claim against
appointed, or an assignee chosen, as provided in this Act, the sheriff shall thereupon Gateway was concerned, was, or ought to have been, suspended after December 2, 2004,
deliver to such receiver or assignee, as the case may be all the property, assets, and Asianbank having been duly notified of and in fact was a participant in the insolvency
belongings of the insolvent which have come into his possession x x x. (Emphasis proceedings. The Court of course takes stock of the proviso in Sec. 60 of Act No. 1956
supplied.) which in a way provided the CA with a justifying tool to continue and to proceed to
judgment in CA-G.R. CV No. 80734, but only for the purpose of ascertaining the amount
Complementing Sec. 18 which appropriately comes into play "upon the granting of [the] due from Gateway. At any event, on the postulate that jurisdiction over the properties of
order" of insolvency is the succeeding Sec. 60 which properly applies to the period "after the insolvent-declared Gateway lies with the insolvency court, execution of the CA
the commencement of proceedings in insolvency." The two provisions may be insolvency judgment against Gateway can only be pursued before the insolvency court.
harmonized as follows: Upon the filing of the petition for insolvency, pending civil actions Asianbank, no less, tends to agree to this conclusion when it stated: "[E]ven it if is
against the property of the petitioner are not ipso facto stayed, but the insolvent may assumed that the declaration of insolvency of petitioner Gateway can be taken cognizance
apply with the court in which the actions are pending for a stay of the actions against the of, such fact does relieve petitioner Geronimo and/or Andrew delos Reyes from
insolvent’s property. If the court grants such application, pending civil actions against the performing their obligations based on the Deeds of Suretyship x x x." 11
petitioner’s property shall be stayed; otherwise, they shall continue. Once an order of
insolvency nevertheless issues, all civil proceedings against the petitioner’s property are, Geronimo, however, is a different story.
by statutory command, automatically stayed. Sec. 60 is reproduced below:
Asianbank argues that the stay of the collection suit against Gateway is without bearing
SECTION 60. Creditors proving claims cannot sue; Stay of action.–No creditor, proving his on the liability of Geronimo as a surety, adding that claims against a surety may proceed
debt or claim, shall be allowed to maintain any suit therefor against the debtor, but shall independently from that against the principal debtor. Pursuing the point, Asianbank avers
be deemed to have waived all right of action and suit against him, and all proceedings that Geronimo may not invoke the insolvency of Gateway as a defense to evade liability.
already commenced, or any unsatisfied judgment already obtained thereon, shall be
deemed to be discharged and surrendered thereby; and after the debtor’s discharge, Geronimo counters with the argument that his liability as a surety cannot be separated
upon proper application and proof to the court having jurisdiction, all such proceedings from Gateway’s liability. As surety, he continues, he is entitled to avail himself of all the
shall be, dismissed, and such unsatisfied judgments satisfied of record: Provided, x x x. A defenses pertaining to Gateway, including its insolvency, suggesting that if Gateway is
creditor proving his debt or claim shall not be held to have waived his right of action or eventually released from what it owes Asianbank, he, too, should also be so relieved.
suit against the debtor when a discharge has have been refused or the proceedings have
been determined to the without a discharge. No creditor whose debt is provable under
this Act shall be allowed, after the commencement of proceedings in insolvency, to Geronimo’s above contention is untenable.
prosecute to final judgment any action therefor against the debtor until the question of
the debtor’s discharge shall have been determined, and any such suit proceeding shall, Suretyship is covered by Article 2047 of the Civil Code, which states:
upon the application of the debtor or of any creditor, or the assignee, be stayed to await
the determination of the court on the question of discharge: Provided, That if the By guaranty a person, called the guarantor, binds himself to the creditor to fulfill the
amount due the creditor is in dispute, the suit, by leave of the court in insolvency, may obligation of the principal debtor in case the latter should fail to do so.
proceed to judgment for purpose of ascertaining the amount due, which amount, when
adjudged, may be allowed in the insolvency proceedings, but execution shall be stayed
aforesaid. (Emphasis supplied.) If a person binds himself solidarily with the principal debtor, the provisions of Section 4,
Chapter 3, Title I of this Book shall be observed. In such case the contract is called a
suretyship.
Applying the aforequoted provisions, it can rightfully be said that the issuance of the
insolvency order of December 2, 2004 had the effect of automatically staying the civil
The Court’s disquisition in Palmares v. Court of Appeals on suretyship is instructive, thus: proceeding before the Securities and Exchange Commission (SEC). As we held
in Commercial Banking Corporation v. CA, a surety of the distressed corporation can be
A surety is an insurer of the debt, whereas a guarantor is an insurer of the solvency of the sued separately to enforce his liability as such, notwithstanding an SEC order declaring the
debtor. A suretyship is an undertaking that the debt shall be paid x x x.  Stated differently, former under a state of suspension of payment. 15
a surety promises to pay the principal’s debt if the principal will not pay, while a guarantor
agrees that the creditor, after proceeding against the principal, may proceed against the Geronimo also states that, as things stand, his liability, as compared to that of Gateway, is
guarantor if the principal is unable to pay. A surety binds himself to perform if the contextually more onerous and burdensome, precluded as he is from seeking recourse
principal does not, without regard to his ability to do so. x x x  In other words, a surety against the insolvent corporation. From this premise, Geronimo claims that since Gateway
undertakes directly for the payment and is so responsible at once if the principal debtor cannot, owing to the order of insolvency, be made to pay its obligation, he, too, being just
makes default x x x. a surety, cannot also be made to pay, obviously having in mind Art. 2054 of the Civil Code,
as follows:
xxxx
A guarantor may bind himself for less, but not for more than the principal debtor, both as
A creditor’s right to proceed against the surety exists independently of his right to regards the amount and the onerous nature of the conditions.
proceed against the principal. Under Article 1216 of the Civil Code, the creditor may
proceed against any one of the solidary debtors or some or all of them simultaneously. Should he have bound himself for more, his obligations shall be reduced to the limits of
The rule, therefore, is that if the obligation is joint and several, the creditor has the right that of the debtor.
to proceed even against the surety alone. Since, generally, it is not necessary for the
creditor to proceed against a principal in order to hold the surety liable, where, by the The Court is not convinced. The above article enunciates the rule that the obligation of a
terms of the contract, the obligation of the surety is the same as that of the principal, then guarantor may be less, but cannot be more than the obligation of the principal debtor.
soon as the principal is in default, the surety is likewise in default, and may be sued The rule, however, cannot plausibly be stretched to mean that a guarantor or surety is
immediately and before any proceedings are had against the principal. Perforce, x x x a freed from liability as such guarantor or surety in the event the principal debtor becomes
surety is primarily liable, and with the rule that his proper remedy is to pay the debt and insolvent or is unable to pay the obligation. This interpretation would defeat the very
pursue the principal for reimbursement, the surety cannot at law, unless permitted by essence of a suretyship contract which, by definition, refers to an agreement whereunder
statute and in the absence of any agreement limiting the application of the security, one person, the surety, engages to be answerable for the debt, default, or miscarriage of
require the creditor or obligee, before proceeding against the surety, to resort to and another known as the principal. 16 Geronimo’s position that a surety cannot be made to
exhaust his remedies against the principal, particularly where both principal and surety pay when the principal is unable to pay is clearly specious and must be rejected.
are equally bound.12

The CA Did Not Err in Admitting


Clearly, Asianbank’s right to collect payment for the full amount from Geronimo, as the Deed of Suretyship as Evidence
surety, exists independently of its right against Gateway as principal debtor; 13 it could thus
proceed against one of them or file separate actions against them to recover the principal
debt covered by the deed on suretyship, subject to the rule prohibiting double recovery Going to the next ground, Geronimo maintains that the CA erred in admitting the Deed of
from the same cause.14 This legal postulate becomes all the more cogent in case of an Suretyship purportedly signed by him, given that Asianbank failed to present its original
insolvency situation where, as here, the insolvency court is bereft of jurisdiction over the copy.
sureties of the principal debtor. As Asianbank aptly points out, a suit against the surety,
insofar as the surety’s solidary liability is concerned, is not affected by an insolvency This contention is bereft of merit.
proceeding instituted by or against the principal debtor. The same principle holds true
with respect to the surety of a corporation in distress which is subject of a rehabilitation As may be noted, paragraph 6 of Asianbank’s complaint alleged the following:
6. The loan was secured by the Deeds of Suretyship dated July 23, 1996 that were Sec. 8. How to contest such documents.–When an action or defense is founded upon a
executed by defendants Geronimo B. De Los Reyes, Jr. and Andrew S. De Los Reyes. written instrument, copied in or attached to the corresponding pleading as provided in the
Attached as Annexes "B" and "C," respectively, are photocopies of the Deeds of Suretyship preceding section, the genuineness and due execution of the instrument shall be
executed by defendants Geronimo B. De Los Reyes, Jr. and Andrew S. De Los Reyes. deemed admitted unless the adverse party, under oath, specifically denies them, and
Subsequently, a chattel mortgage over defendant Gateway’s equipment for $2 million, sets forth what he claims to be the facts; but the requirement of an oath does not apply
United States currency, was executed.17 when the adverse party does not appear to be a party to the instrument or when
compliance with an order for an inspection of the original instrument is refused.
Geronimo traversed in his answer the foregoing allegation in the following wise: "2.5. (Emphasis supplied.)
Paragraph 6 is denied, subject to the special and affirmative defenses and allegations
hereinafter set forth." Given the above perspective, Asianbank, by attaching a photocopy of the Deed of
Suretyship to its underlying complaint, hewed to the requirements of the above twin
The ensuing special and affirmative defenses were raised in Gateway’s answer: provisions. Asianbank, thus, effectively alleged the due execution and genuineness of the
said deed. From that point, Geronimo, if he intended to contest the surety deed, should
have specifically denied the due execution and genuineness of the deed in the manner
15. Granting even that [Geronimo] signed the Deed of Suretyship, his wife x x x had not provided by Sec. 10, Rule 8 of the Rules of Court, thus:
given her consent thereto. Accordingly, the security created by the suretyship shall be
construed only as a continuing offer on the part of [Geronimo] and plaintiff and may only
be perfected as a binding contract upon acceptance by Mrs. Delos Reyes. x x x Sec. 10. Specific denial.–A defendant must specify each material allegation of fact the
truth of which he does not admit and, whenever practicable, shall set forth the
substance of the matters upon which he relies to support his denial. Where a defendant
17. Moreover, assuming, gratia argumenti, that [Geronimo] may be bound by the desires to deny only a part of an averment, he shall specify so much of it as is true and
suretyship agreement, there is no showing that he has consented to the repeated material and shall deny only the remainder. Where a defendant is without knowledge or
extensions made by plaintiff in favor of GEC or to a waiver of notice of such extensions. It information sufficient to form a belief as to the truth of a material averment made in the
should be pointed out that Mr. Geronimo delos Reyes executed the suretyship agreement complaint, he shall so state, and this shall have the effect of a denial. (Emphasis supplied.)
in his personal capacity and not in his capacity as Chairman of the Board of GEC. His
consent, insofar as the continuing application of the suretyship agreement to GEC’s
obligations in view of the repeated extension extended by plaintiff [is concerned], is In the instant case, Geronimo should have categorically stated that he did not execute the
therefore necessary. Obviously, plaintiff cannot now hold him liable as a surety to GEC’s Deed of Suretyship and that the signature appearing on it was not his or was falsified. His
obligations.18 Answer does not, however, contain any such statement. Necessarily then, Geronimo had
not specifically denied, and, thus, is deemed to have admitted, the genuineness and due
execution of the deed in question. In this regard, Sec. 11, Rule 8 of the Rules of Court
The Rules of Court prescribes, under its Secs. 7 and 8, Rule 8, the procedure should a suit states:
or defense is predicated on a written document, thus:

Sec. 11. Allegations not specifically denied deemed admitted.–Material averment in the


Sec. 7. Action or defense based on document.–Whenever an action or defense is based complaint, other than those as to the amount of unliquidated damages, shall be deemed
upon a written instrument or document, the substance of such instrument or document admitted when not specifically denied. x x x
shall be set forth in the pleading, and the original or a copy thereof shall be attached to
the pleading as an exhibit, which shall be deemed to be a part of the pleading, or said
copy may with like effect be set forth in the pleading. Owing to Geronimo’s virtual admission of the genuineness and due execution of the deed
of suretyship, Asianbank, contrary to the view of Gateway and Geronimo, need not
present the original of the deed during the hearings of the case. Sec. 4, Rule 129 of the
Rules says so:
Sec. 4. Judicial admissions.–An admission, verbal or written, made by the party in the that obligations which are subject to a condition precedent are valid and binding before
course of the proceedings in the same case, does not require proof.  The admission may the occurrence of the condition precedent.
be contradicted only by showing that it was made through palpable mistake or that no
such admission was made. (Emphasis supplied.) Comprehensive or continuing surety agreements are in fact quite commonplace in
present day financial and commercial practice. A bank or financing company which
Geronimo Is Liable for PN No. FCD-0599-2749 anticipates entering into a series of credit transactions with a particular company,
under His Deed of Suretyship commonly requires the projected principal debtor to execute a continuing surety
agreement along with its sureties. By executing such an agreement, the principal places
This brings us to the third ground which involves the issue of the coverage of the itself in a position to enter into the projected series of transactions with its creditor;
suretyship. Preliminarily, an overview on the process of taking out loans should first be with such suretyship agreement, there would be no need to execute a separate surety
made. Generally, especially for large loans, banks first approve a line or facility out of contract or bond for each financing or credit accommodation extended to the principal
which a client may avail itself of loans in the form of promissory notes without need of debtor."20
further processing and/or approval every time a draw down is made. In the instant case,
Asianbank approved in favor of Gateway the PhP 10 million-Domestic Bills Purchased Line In Diño vs. Court of Appeals,21 we again had occasion to discourse on continuing
and the USD 3 million-Omnibus Credit Line. Asianbank approved these credit lines which guaranty/suretyship thus:
were covered by a chattel mortgage as well as the deeds of suretyship, such that loans
extended from these lines would already be secured and pre-approved. In other words, "x x x A continuing guaranty is one which is not limited to a single transaction, but which
these facilities are not financial obligations yet. Asianbank did not yet lend out any money contemplates a future course of dealing, covering a series of transactions, generally for an
to Gateway with the approval of these lines. The loan transaction occurred or the principal indefinite time or until revoked. It is prospective in its operation and is generally intended
obligation, as secured by a surety agreement, was born after the execution of loan to provide security with respect to future transactions within certain limits, and
documents, such as PN No. FCD-0599-2749. contemplates a succession of liabilities, for which, as they accrue, the guarantor becomes
liable. Otherwise stated, a continuing guaranty is one which covers all transactions,
Geronimo now excepts from the ruling that the deed of suretyship he executed covered including those arising in the future, which are within the description or contemplation of
PN No. FCD-0599-2749 which embodied several export packing loans issued by Asianbank the contract, of guaranty, until the expiration or termination thereof. A guaranty shall be
to Gateway. He claims that the deed only secured the PhP 10 million-Domestic Bills construed as continuing when by the terms thereof it is evident that the object is to give a
Purchased Line and the USD 3 million-Omnibus Credit Line. Geronimo describes as absurd standing credit to the principal debtor to be used from time to time either indefinitely or
the notion that a deed of suretyship would secure a loan obligation contracted three (3) until a certain period x x x.
years after the execution of the surety deed.
In other jurisdictions, it has been held that the use of particular words and expressions
Geronimo’s thesis that the deed in question cannot be accorded prospective application is such as payment of ‘any debt,’ ‘any indebtedness,’ ‘any deficiency,’ or ‘any sum,’ or the
erroneous. To be sure, the provisions of the subject deed of suretyship indicate a guaranty of ‘any transaction’ or money to be furnished the principal debtor ‘at any time,’
continuing suretyship. In Fortune Motors (Phils.) v. Court of Appeals,19 the Court, citing or ‘on such time’ that the principal debtor may require, have been construed to indicate a
cases, defined and upheld the validity of a continuing suretyship in this wise: continuing guaranty." (Emphasis supplied.)

"x x x Of course, a surety is not bound under any particular principal obligation until that By its nature, a continuing suretyship covers current and future loans, provided that, with
principal obligation is born. But there is no theoretical or doctrinal difficulty inherent in respect to future loan transactions, they are, to borrow from Diño, as cited above, "within
saying that the suretyship agreement itself is valid and binding even before the principal the description or contemplation of the contract of guaranty." The Deed of Suretyship
obligation intended to be secured thereby is born, any more than there would be in saying Geronimo signed envisaged a continuing suretyship when, by the express terms of the
deed, he warranted payment of the PhP 10 million-Domestic Bills Purchased Line and the Geronimo’s allegation that an export packing credit loan is separate and distinct from an
USD 3 million-Omnibus Credit Line, as evidenced by: omnibus credit line is but a bare and self-serving assertion bereft of any factual or legal
basis. One who alleges something must prove it: a mere allegation is not
x x x notes, drafts, overdrafts and other credit obligations on which the DEBTOR(S) may evidence.25 Geronimo has not discharged his burden of proof. His contention cannot be
now be indebted or may hereafter become indebted to the CREDITOR, together with all given any weight.
interests, penalty and other bank charges as may accrue thereon and all expenses which
may be incurred by the latter in collecting any or all such instruments. 22 As a final and major ground for his release as surety, Geronimo alleges that Asianbank
repeatedly extended the maturity dates of the obligations of Gateway without his
Evidently, under the deed of suretyship, Geronimo undertook to secure all obligations knowledge and consent. Pressing this point, he avers that, contrary to the findings of the
obtained under the Domestic Bills Purchased Line and Omnibus Credit Line, without any CA, he did not waive his right to notice of extensions of Gateway’s obligations.
specification as to the period of the loan.
Such contention is unacceptable as it glosses over the fact that the waiver to be notified of
Geronimo’s application of Garcia v. Court of Appeals, a case covering two separate loans, extensions is embedded in surety document itself, built in the ensuing provision:
denominated as SWAP Loan and Export Loan, is quite misplaced. There, the Court ruled
that the continuing suretyship only covered the SWAP Loan as it was only this loan that In case of default by any and/or all of the DEBTOR(S) to pay the whole part of said
was referred to in the continuing suretyship. The Court wrote in Garcia: indebtedness herein secured at maturity, I/WE jointly and severally, agree and engage to
the CREDITOR, its successors and assigns, the prompt payment, without demand or
Particular attention must be paid to the statement appearing on the face of the Indemnity notice from said CREDITOR of such notes, drafts, overdrafts and other credit obligations
[Suretyship] Agreement x x x "evidenced by those certain loan documents dated April 20, on which the DEBTOR(S) may now be indebted or may hereafter become indebted to
1982" x x x. From this statement, it is clear that the Indemnity Agreement refers only to the CREDITOR, together with all interests, penalty and other bank charges as may accrue
the loan document of April 20, 1982 which is the SWAP loan. It did not include the thereon and all expenses which may be incurred by the latter in collecting any or all such
EXPORT loan. Hence, petitioner cannot be held answerable for the EXPORT instruments.26 (Emphasis supplied.)
loan.23 (Emphasis supplied.)
In light of the above provision, Geronimo verily waived his right to notice of the maturity
The Indemnity Agreement in Garcia specifically identified loan documents evidencing of notes, drafts, overdraft, and other credit obligations for which Gateway shall become
obligations of the debtor that the agreement was intended to secure. In the present case, indebted. This waiver necessarily includes new agreements resulting from the novation of
however, the suretyship Geronimo assumed did not limit itself to a specific loan document previous agreements due to changes in their maturity dates.
to the exclusion of another. The suretyship document merely mentioned the Domestic
Bills Purchased Line and Omnibus Credit Line as evidenced by "all notes, drafts x x x Additionally, Geronimo’s lament about losing his right to subrogation is erroneous. He
contracted/incurred by [Gateway] in favor of [Asianbank]." 24 As explained earlier, such argues that by virtue of the order of insolvency issued by the insolvency court, title and
credit facilities are not loans by themselves. Thus, the Deed of Suretyship was intended to right to possession to all the properties and assets of Gateway were vested upon
secure future loans for which these facilities were opened in the first place. Gateway’s assignee in accordance with Sec. 32 of the Insolvency Law.

Lest it be overlooked, both the trial and appellate courts found the Omnibus Credit Line The transfer of Gateway’s property to the insolvency assignee, if this be the case, does not
referred to in the Deed of Suretyship as covering the export packing credit loans negate Geronimo’s right of subrogation, for such right may be had or exercised in the
Asianbank extended to Gateway. We agree with this factual determination. By the very insolvency proceedings. The possibility that he may only recover a portion of the amount
use of the term "omnibus," and in practice, an omnibus credit line refers to a credit facility he is liable to pay is the risk he assumed as a surety of Gateway. Such loss does not,
whence a borrower may avail of various kinds of credit loans. Defined as such, an omnibus however, render ineffectual, let alone invalidate, his suretyship.
line is broad enough to refer to or cover an export packing credit loan.
Geronimo’s other arguments to escape liability are puerile and really partake more of a The Court’s Equity Jurisdiction
plea for liberality. They need not detain us long. In gist, Geronimo argues:  first, that he is a Finds No Application to the Instant Case
gratuitous surety of Gateway; second, Asianbank deviated from normal banking practice,
such as when it extended the period for payment of Gateway’s obligation and when it Geronimo urges the Court to release and discharge him from any liability arising from
opted not to foreclose the chattel mortgage constituted as guarantee of Gateway’s loan Asianbank’s claims if what he terms as "complete justice" is to be served. He cites, as
obligation; and third, implementing the appealed CA’s decision would cause him great supporting reference, Agcaoili v. GSIS,29 presenting in the same breath the following
harm and injury. arguments: first, the Deed of Suretyship is a gratuitous contract from which he did not
benefit; second, Asianbank assured him that the deed would not be enforced against
Anent the first argument, suffice it to state that Geronimo was then the president of him;  third, the enforcement of the judgment of the CA would reduce Geronimo and his
Gateway and, as such, was benefited, albeit perhaps indirectly, by the loan thus granted family to a life of penury; and fourth, Geronimo would be unable to exercise his right of
by Asianbank. And as we said in Security Pacific Assurance Corporation, the surety is liable subrogation, Gateway having already been declared as insolvent.
for the debt of another although the surety possesses no direct or personal interest over
the obligation nor does the surety receive any benefit from it. 27 The first and last arguments have already been addressed and found to be without merit.
The second argument is a matter of defense which has remained unproved and even
Whether or not Asianbank really deviated from normal banking practice by extending the belied by Asianbank by its filing of the complaint. We see no need to further belabor any
period for Gateway to comply with its loan obligation or by not going after the chattel of them.
mortgage adverted to is really of no moment. Banks are primarily in the business of
extending loans and earn income from their lending operations by way of service and As regards the third allegation, suffice it to state that the predicament Geronimo finds
interest charges. This is why Asianbank opted to give Gateway ample opportunity to pay himself in is his very own doing. His misfortune is but the result of the implementation of
its obligations instead of foreclosing the chattel mortgage and in the process holding on to a bona fide contract he freely executed, the terms of which he is presumed to have
assets of which the bank has really no direct use. thoroughly examined. He was not at all compelled to act as surety; he had a choice. It may
be more offensive to public policy or good customs if he be allowed to go back on his
The following excerpts from Palmares  are in point: undertaking under the surety contract. The Court cannot be a party to the contract’s
impairment and relieve a surety from the effects of an unwise but nonetheless a valid
We agree with respondent corporation that its mere failure to immediately sue petitioner surety contract.
on her obligation does not release her from liability. Where a creditor refrains from
proceeding against the principal, the surety is not exonerated. In other words, mere want WHEREFORE, the instant petition is hereby DENIED. The appealed Decision dated October
of diligence or forbearance does not affect the creditor’s rights vis-à-vis the surety, unless 28, 2005 of the CA and its March 17, 2006 Resolution in CA-G.R. CV No. 80734 are
the surety requires him by appropriate notice to sue on the obligation. Such gratuitous hereby AFFIRMED with the modification that any claim of Asianbank or its successor-in-
indulgence of the principal does not discharge the surety whether given at the principal’s interest against Gateway, if any, arising from the judgment in this suit shall be pursued
request or without it, and whether it is yielded by the creditor through sympathy or from before the RTC, Branch 22 in Imus, Cavite as the insolvency court.
an inclination to favor the principal x x x. The neglect of the creditor to sue the principal at
the time the debt falls due does not discharge the surety, even if such delay continues Costs against petitioners.
until the principal becomes insolvent.  And, in the absence of proof of resultant injury, a
surety is not discharged by the creditor’s mere statement that the creditor will not look to
the surety, or that he need not trouble himself.  The consequences of the delay, such as SO ORDERED.
the subsequent insolvency of the principal,  or the fact that the remedies against the
principal may be lost by lapse of time, are immaterial.28
Mortgage5 over the condominium unit as collateral, and the same was annotated at the
back of CCT No. 2130.

On October 3, 1995, respondents again borrowed One Million One Hundred Thousand
Pesos (₱1,100,000.00) from petitioner bank, which was also secured by a mortgage over
the same property annotated at the back of CCT No. 2130.6

On January 2, 1996, respondents paid One Million Eleven Thousand Five Hundred Fifty-
Five Pesos and 54 centavos (₱1,011,555.54), as evidenced by Official Receipt No.
1477417 issued by petitioner bank. On the face of the receipt, it was written that the
payment was "in full payment of the loan and interest." Respondents then asked
petitioner bank to cancel the mortgage annotations on CCT No. 2130 since the loans
secured by the real estate mortgage were already paid in full. However, the bank refused
Republic of the Philippines to cancel the same and demanded payment of Four Million Six Hundred Thirty-Three
SUPREME COURT Thousand Nine Hundred Sixteen Pesos and Sixty-Seven Centavos (₱ 4,633,916.67),
Manila representing the outstanding obligation of respondents as of February 27, 1998.
SECOND DIVISION Respondents requested for an accounting which would explain how the said amount was
G.R. No. 174006               December 8, 2010 arrived at. However, instead of heeding respondents’ request, petitioner bank applied for
BANK OF COMMERCE and STEPHEN Z. TAALA, Petitioners, extra-judicial foreclosure of the mortgages over the condominium unit. The public auction
vs. sale was scheduled on September 4, 1998. Petitioner Stephen Z. Taala, a notary public,
Spouses ANDRES and ELIZA FLORES, Respondents. was tasked to preside over the auction sale. 8

DECISION Respondents filed suit with the RTC, Quezon City, assailing the validity of the foreclosure
NACHURA, J.: and auction sale of the property. They averred that the loans secured by the property had
Before the Court is a petition for review on certiorari under Rule 45 of the Rules of Court, already been paid in full. Furthermore, they claimed that the Notice of Auction Sale by
assailing the Decision1 dated February 28, 2006 and the Resolution 2 dated August 9, 2006 Notary Public9 failed to comply with the provisions of Act No. 3135, as amended by Act
of the Court of Appeals (CA) in CA-G.R. CV No. 80362. No. 4118, requiring the publication and posting of the notice of auction sale in at least
three (3) public places in Quezon City. 10 Respondents likewise prayed for the payment of
The facts of the case are as follows: moral and exemplary damages, and attorney’s fees, and for the issuance of a temporary
restraining order and/or writ of preliminary injunction to enjoin the extra-judicial
foreclosure sale of the property. 11
Respondents filed a case for specific performance against petitioners before the Regional
Trial Court (RTC) of Quezon City, docketed as Civil Case No. Q-98-35425. Respondents are
the registered owners of a condominium unit in Embassy Garden Homes, West Triangle, On October 23, 1998, the RTC granted respondents’ prayer for issuance of a writ of
Quezon City, registered under Condominium Certificate of Title (CCT) No. 2130, 3 issued by preliminary injunction, restraining petitioner bank from foreclosing on the mortgage. 12
the Register of Deeds of Quezon City.4
Petitioner bank admitted that there were only two (2) mortgage loans annotated at the
On October 22, 1993, respondents borrowed money from petitioner bank in the amount back of CCT No. 2130, but denied that respondents had already fully settled their
of Nine Hundred Thousand Pesos (₱900,000.00). Respondents executed a Real Estate outstanding obligations with the bank. 13 It averred that several credit lines were granted
to respondent Andres Flores by petitioner bank that were secured by promissory notes
executed by him, and which were either increased or extended from time to time. The Respondents filed a motion for reconsideration, which was, however, denied by the RTC in
loan that was paid on January 2, 1996, in the amount of ₱1,011,555.54, was only one of a decision18 dated August 8, 2003.
his loans with the bank. There were remaining loans already due and demandable, and
had not been paid by respondents despite repeated demands by petitioner bank. The Aggrieved, respondents appealed to the CA.
remaining loans, although not availed of at the same time, were similarly secured by the
subject real estate mortgage as provided in the continuing guaranty agreement therein. 14
Meanwhile, on March 25, 2004, the auction sale of the subject property was conducted,
and petitioner bank was awarded the property, as the highest bidder.
Petitioner bank alleged that respondents requested and were granted an increase in their
Bills Discounted Line from Nine Hundred Thousand Pesos (₱900,000.00) to Two Million
Pesos (₱2,000,000.00), which was secured by the same real estate mortgage on CCT No. On February 28, 2006, the CA rendered a Decision 19 reversing the decision and the
2130. However, the subject condominium unit commanded only a market value of One resolution of the RTC. The dispositive portion of the CA Decision reads:
Million Seven Hundred Twenty-Three Thousand Six Hundred Pesos (₱1,723,600.00), and a
loan value of Nine Hundred Fifty-Nine Thousand Six Hundred Sixteen Pesos (₱959,616.00). IN VIEW OF ALL THE FOREGOING, the instant appeal is GRANTED; the challenged Decision
Since the market value of the condominium unit was lower than the combined loans, the dated December 4, 2002, is REVERSED and SET ASIDE; and a new one entered:
parties agreed to fix the amount of the real estate mortgage at ₱1,100,000.00. Moreover,
petitioner bank stressed that under the terms of the two real estate mortgages, future (a) ordering the cancellation of the real estate mortgage annotations on the dorsal side of
loans of respondents were also covered. 151avvphi1 CCT No. 2130 of the Registry of Deeds of Quezon City;
(b) ordering appellee Bank to issue a corresponding release of mortgages to plaintiffs-
On December 4, 2002, the RTC rendered a resolution,16 the fallo of which reads: appellants’ CCT No. 2130;
(c) declaring null and void the challenged extra-judicial foreclosure and public auction sale
FROM THE FOREGOING MILIEU, the present case for specific performance with damages held on March 25, 2004 together with the Certificate of Sale dated April 14, 2004 issued in
and injunction filed by plaintiffs, Sps. Andres and Eliza Flores against defendants, Bank of favor of appellee Bank; and,
Commerce and Stephen Z. Taala, is hereby DISMISSED. Likewise, the counterclaim filed by (d) appellees’ counterclaims are ordered dismissed, for lack of sufficient basis therefor.
defendants, Bank of Commerce and Stephen Z. Taala against plaintiffs, Sps. Andres and
Eliza Flores is DISMISSED for insufficiency of evidence. No costs. SO ORDERED.20

SO ORDERED.17 The CA ratiocinated that the principal obligation or loan was already extinguished by the
full payment thereof. Consequently, the real estate mortgages securing the principal
In denying respondents’ complaint for specific performance, the RTC ratiocinated that obligation were also extinguished. A real estate mortgage, being an accessory contract,
respondents’ right of action hinged mainly on the veracity of their claim that they cannot survive without the principal obligation it secures. The CA also noted that the two
faithfully complied with their loan obligations and had fully paid them in January 1996. mortgages were individually annotated at the back of CCT No. 2130. Thus, the CA opined
The RTC stated that the evidence submitted by petitioner bank, specifically the promissory that the individual annotations clearly indicated that the said mortgages were not meant
notes and statement of account dated February 27, 1998, negated this contention. The to serve as a continuing guaranty for any future loan that respondents would obtain from
RTC declared that respondents incurred other debts from petitioner bank, which must be petitioner bank.
paid first before they could be absolved of liability, and, consequently, demand the
release of the mortgage. The RTC also struck down respondents’ assertion that petitioner Petitioners filed a motion for reconsideration. On August 9, 2006, the CA issued a
bank did not comply with the posting and publication requirements under Act No. 3135, Resolution21 denying the same.
as amended.
Hence, the instant petition.
The sole issue for resolution is whether the real estate mortgage over the subject interest to that parcel(s) of land, together with all the buildings and
condominium unit is a continuing guaranty for the future loans of respondent spouses improvements now existing or which may hereafter be erected or
despite the full payment of the principal loans annotated on the title of the subject constructed thereon, including all other rights or benefits annexed to
property. or inherent therein now existing or which may hereafter exist,
situated in Embassy Garden Homes, Quezon City, Philippines, and
We resolve this issue in the affirmative. more particularly described in Original/Transfer Certificate(s) of Title
No. CCT No. 2130 of the Registry of Deeds [of] Quezon City, as
follows:
The contested portion of the Deed of Real Estate Mortgage dated October 22, 1993 for
the principal obligation of ₱900,000.00 and of the second one dated October 3, 1995 for
the sum of ₱1,100,000.00, uniformly read: CCT No. 2130

Unit No. L-2, located on Building L, consisting of Ninety Five point


Twenty (95.20) Square Meters, more of less, with Parking Space No.
L-2.22
WITNESSETH: That

It is petitioner bank’s contention that the said undertaking, stipulated in the Deed of Real
for and in consideration of the credit accommodations granted by Estate Mortgage dated October 22, 1993 and October 3, 1995, is a continuing guaranty
the MORTGAGEE [Bank of Commerce] to the MORTGAGOR [Andres meant to secure future debts or credit accommodations granted by petitioner bank in
Flores] and/or _____________________ hereby initially fixed at favor of respondents. On the other hand, respondents posit that, since they have already
_____________________________PESOS: (P____________), paid the loans secured by the real estate mortgages, the mortgage should not be
Philippine Currency, and as security for the payment of the same, on foreclosed because it does not include future debts of the spouses or debts not annotated
demand or at maturity as the case may be, be the interest accruing at the back of CCT No. 2130.
thereon, the cost of collecting the same, the cost of keeping the
mortgaged property(ies), of all amounts now owed or hereafter
owing by the MORTGAGOR to the MORTGAGEE under this or A continuing guaranty is a recognized exception to the rule that an action to foreclose a
separate instruments and agreements, or in respect of any bill, note, mortgage must be limited to the amount mentioned in the mortgage contract. 23 Under
check, draft accepted, paid or discounted, or advances made and all Article 2053 of the Civil Code, a guaranty may be given to secure even future debts, the
other obligations to every kind already incurred or which may amount of which may not be known at the time the guaranty is executed. This is the basis
hereafter be incurred, for the use or accommodation of the for contracts denominated as a continuing guaranty or suretyship. A continuing guaranty
MORTGAGOR, as well as the faithful performance of the terms and is not limited to a single transaction, but contemplates a future course of dealing, covering
conditions of this mortgage and of the separate instruments and/or a series of transactions, generally for an indefinite time or until revoked. It is prospective
documents under which credits have been or may hereafter be in its operation and is generally intended to provide security with respect to future
advanced by the MORTGAGEE to the MORTGAGOR, including their transactions within certain limits, and contemplates a succession of liabilities, for which,
renewals, extensions and substitutions, any and all of which separate as they accrue, the guarantor becomes liable. In other words, a continuing guaranty is one
instruments and/or documents and their renewals, extensions and that covers all transactions, including those arising in the future, which are within the
substitutions are hereunto incorporated and made integral parts description or contemplation of the contract of guaranty, until the expiration or
hereof, the MORTGAGOR [Andres Flores] has transferred and termination thereof.24
conveyed, as by these presents it/he does hereby transfer and
convey, by way of First Mortgage, to the MORTGAGEE [Bank of A guaranty shall be construed as continuing when, by the terms thereof, it is evident that
Commerce], its successors and assigns, all its/ his rights, title and the object is to give a standing credit to the principal debtor to be used from time to time
either indefinitely or until a certain period, especially if the right to recall the guaranty is
expressly reserved. In other jurisdictions, it has been held that the use of particular words
and expressions, such as payment of "any debt," "any indebtedness," "any deficiency," or
"any sum," or the guaranty of "any transaction" or money to be furnished the principal
debtor "at any time" or "on such time" that the principal debtor may require, has been
construed to indicate a continuing guaranty. 25

In the instant case, the language of the real estate mortgage unambiguously reveals that
the security provided in the real estate mortgage is continuing in nature. Thus, it was
intended as security for the payment of the loans annotated at the back of CCT No. 2130,
and as security for all amounts that respondents may owe petitioner bank. It is well
settled that mortgages given to secure future advance or loans are valid and legal
contracts, and that the amounts named as consideration in said contracts do not limit the
amount for which the mortgage may stand as security if from the four corners of the
instrument the intent to secure future and other indebtedness can be gathered. 26

A mortgage given to secure advancements is a continuing security and is not discharged


by repayment of the amount named in the mortgage until the full amounts of the
advancements are paid.27 Respondents’ full payment of the loans annotated on the title of
the property shall not effect the release of the mortgage because, by the express terms of
the mortgage, it was meant to secure all future debts of the spouses and such debts had
been obtained and remain unpaid. Unless full payment is made by the spouses of all the
amounts that they have incurred from petitioner bank, the property is burdened by the
mortgage.

WHEREFORE, in view of the foregoing, the Decision dated February 28, 2006 and the
Resolution dated August 9, 2006 of the Court of Appeals in CA-G.R. CV No. 80362 are
hereby REVERSED and SET ASIDE. The decision of the Regional Trial Court dated December
4, 2002 is hereby REINSTATED.

SO ORDERED.
In turn, the Continuing Suretyship4 executed by petitioner stipulated that:

3. Liability of the Surety. - The liability of the Surety is solidary and not contingent upon
the pursuit of the Bank of whatever remedies it may have against the Debtor or the
collaterals/liens it may possess. If any of the Guaranteed Obligations is not paid or
performed on due date (at stated maturity or by acceleration), the Surety shall, without
need for any notice, demand or any other act or deed, immediately become liable
therefor and the Surety shall pay and perform the same. 5

Guaranteed Obligations are defined in the same document as follows:

a) "Guaranteed Obligations" - the obligations of the Debtor arising from all credit
accommodations extended by the Bank to the Debtor, including increases, renewals, roll-
overs, extensions, restructurings, amendments or novations thereof, as well as (i) all
obligations of the Debtor presently or hereafter owing to the Bank, as appears in the
accounts, books and records of the Bank, whether direct or indirect, and (ii) any and all
Republic of the Philippines expenses which the Bank may incur in enforcing any of its rights, powers and remedies
SUPREME COURT under the Credit Instruments as defined hereinbelow. 6
Manila
THIRD DIVISION The debtor, Raul Arroyo, defaulted on his loan obligation. Thereafter, petitioner received a
G.R. No. 188539               March 12, 2014 Notice of Final Demand dated August 2, 2001, informing him that he was liable to pay the
MARIANO LIM, Petitioner, loan obtained by Raul and Edwina Arroyo, including the interests and penalty fees
vs. amounting to ₱7,703,185.54, and demanding payment thereof. For failure of petitioner to
SECURITY BANK CORPORATION,* Respondent. comply with said demand, respondent filed a complaint for collection of sum of money
against him and the Arroyo spouses. Since the Arroyo spouses can no longer be located,
DECISION summons was not served on them, hence, only petitioner actively participated in the case.
PERALTA, J.:
This deals with the Petition for Review on Certiorari under Rule 45 of the Rules of Court
praying that the Decision 1 of the Court of Appeals (CA), promulgated on July 30, 2008, and After trial, the Regional Trial Court of Davao (RTC) rendered judgment against
the Resolution2 dated June 1, 2009, denying petitioner's motion for reconsideration petitioner.7 The dispositive portion of the RTC Decision reads as follows:
thereof, be reversed and set aside.
Wherefore, judgment is hereby rendered ordering defendant Lim to pay the following
Petitioner executed a Continuing Suretyship in favor of respondent to secure "any and all sums.
types of credit accommodation that may be granted by the bank hereinto and
hereinafter" in favor of Raul Arroyo for the amount of ₱2,000,000.00 which is covered by 1. The principal sum of two million pesos plus nineteen percent interest of the
a Credit Agreement/Promissory Note. 3 Said promissory note stated that the interest on outstanding principal interest due and unpaid to be computed from January 28, 1997 until
the loan shall be 19% per annum, compounded monthly, for the first 30 days from the fully paid, plus two percent interest per month as penalty to be computed from February
date thereof, and if the note is not fully paid when due, an additional penalty of 2% per 28, 1997 until fully paid.
month of the total outstanding principal and interest due and unpaid, shall be imposed. 2. Four hundred thousand pesos as attorney's fees.
3. Thirty thousand pesos as litigation expenses. A contract of suretyship is an agreement whereby a party, called the surety, guarantees
the performance by another party, called the principal or obligor, of an obligation or
SO ORDERED.8 undertaking in favor of another party, called the obligee. Although the contract of a surety
is secondary only to a valid principal obligation, the surety becomes liable for the debt or
duty of another although it possesses no direct or personal interest over the obligations
Petitioner appealed to the CA, but the appellate court, in its Decision dated July 30, 2008, nor does it receive any benefit therefrom. This was explained in the case of Stronghold
affirmed the RTC judgment with the modification that interest be computed from August Insurance Company, Inc. v. Republic-Asahi Glass Corporation, where it was written:
1, 1997; the penalty should start only from August 28, 1997; the award of attorney's fees
is set at 10% of the total amount due; and the award for litigation expenses increased to
₱92,321.10.9 The surety's obligation is not an original and direct one for the performance of his own
act, but merely accessory or collateral to the obligation contracted by the principal.
Nevertheless, although the contract of a surety is in essence secondary only to a valid
Petitioner's motion for reconsideration of the CA Decision was denied per Resolution principal obligation, his liability to the creditor or promisee of the principal is said to be
dated June 1, 2009. direct, primary and absolute; in other words, he is directly and equally bound with the
principal.
Petitioner then elevated the matter to this Court via a petition for review on certiorari,
where the main issue is whether petitioner may validly be held liable for the principal xxxx
debtor's loan obtained six months after the execution of the Continuing Suretyship.

Thus, suretyship arises upon the solidary binding of a person deemed the surety with the
The other issues, such as the proper computation of the total indebtedness and the principal debtor for the purpose of fulfilling an obligation. A surety is considered in law as
amount of litigation expenses are factual matters that had been satisfactorily addressed being the same party as the debtor in relation to whatever is adjudged touching the
by the CA, to wit: (1) the CA ruled that respondent should recompute the total amount obligation of the latter, and their liabilities are interwoven as to be inseparable. x x x. 12
due, since the proceeds from the foreclosure of the real estate and chattel mortgages
were deducted only on June 20, 2001, when the public auctions were conducted on
August 26, 1998 and September 7, 1999, respectively, thus, the amount of the proceeds In this case, what petitioner executed was a Continuing Suretyship, which the Court
from the foreclosure of the mortgaged properties should have been deducted from the described in Saludo, Jr. v. Security Bank Corporation13 as follows:
amount of indebtedness on the date the public auction was held; and (2) the CA likewise
pointed out that as can be seen from the Legal Fees Form, 10 the litigation expense The essence of a continuing surety has been highlighted in the case of Totanes v. China
incurred by respondent was ₱92,321.10, the amount it paid as filing fee. It is hornbook Banking Corporation in this wise:
principle that this Court is not a trier of facts, hence, such issues will not be revisited by
this Court in the present petition. With regard to the propriety of making petitioner a Comprehensive or continuing surety agreements are, in fact, quite commonplace in
hostile witness, respondent is correct that the issue cannot be raised for the first time on present day financial and commercial practice. A bank or financing company which
appeal. Thus, the Court will no longer address these issues which had been improperly anticipates entering into a series of credit transactions with a particular company,
raised in this petition for review on certiorari. normally requires the projected principal debtor to execute a continuing surety
agreement along with its sureties. By executing such an agreement, the principal places
The main issue deserves scant consideration, but the matter of the award of attorney's itself in a position to enter into the projected series of transactions with its creditor; with
fees deserves reexamination. such suretyship agreement, there would be no need to execute a separate surety contract
or bond for each financing or credit accommodation extended to the principal debtor. 14
The nature of a suretyship is elucidated in Philippine Charter Insurance Corporation v.
Petroleum Distributors & Service Corporation 11 in this wise:
The terms of the Continuing Suretyship executed by petitioner, quoted earlier, are very However, even if such attorney's fees are allowed by law, the courts still have the power
clear.1âwphi1 It states that petitioner, as surety, shall, without need for any notice, to reduce the same if it is unreasonable. In Trade & Investment Corporation of the
demand or any other act or deed, immediately become liable and shall pay "all credit Philippines v. Roblett Industrial Construction Corp., 19 the Court equitably reduced the
accommodations extended by the Bank to the Debtor, including increases, renewals, roll- amount of attorney's fees to be paid since interests and penalties had ballooned to thrice
overs, extensions, restructurings, amendments or novations thereof, as well as (i) all as much as the principal debt. That is also the case here. The award of attorney's fees
obligations of the Debtor presently or hereafter owing to the Bank, as appears in the amounting to ten percent (10%) of the principal debt, plus interest and penalty charges,
accounts, books and records of the Bank, whether direct or indirect, and would definitely exceed the principal amount; thus, making the attorney's fees manifestly
exorbitant. Hence, we reduce the amount of attorney's fees to ten percent (10%) of the
(ii) any and all expenses which the Bank may incur in enforcing any of its rights, powers principal debt only.
and remedies under the Credit Instruments as defined hereinbelow." 15 Such stipulations
are valid and legal and constitute the law between the parties, as Article 2053 of the Civil WHEREFORE, the petition is PARTIALLY GRANTED. The Decision of the Court of Appeals,
Code provides that "[a] guaranty may also be given as security for future debts, the dated July 30, 2008, in CA-G.R. CV No. 00462, is AFFIRMED with MODIFICATION in that the
amount of which is not yet known; x x x." Thus, petitioner is unequivocally bound by the award of attorney's fees is reduced to ten percent (10%) of the principal debt only.
terms of the Continuing Suretyship. There can be no cavil then that petitioner is liable for
the principal of the loan, together with the interest and penalties due thereon, even if said SO ORDERED.
loan was obtained by the principal debtor even after the date of execution of the
Continuing Suretyship.

With regard to the award of attorney's fees, it should be noted that Article 2208 of the
Civil Code does not prohibit recovery of attorney's fees if there is a stipulation in the
contract for payment of the same. Thus, in Asian Construction and Development
Corporation v. Cathay Pacific Steel Corporation (CAPASCO), 16 the Court, citing Titan
Construction Corporation v. Uni-Field Enterprises, Inc., 17 expounded as follows:

The law allows a party to recover attorney's fees under a written agreement. In Barons
Marketing Corporation v. Court of Appeals, the Court ruled that:

[T]he attorney's fees here are in the nature of liquidated damages and the stipulation
therefor is aptly called a penal clause. It has been said that so long as such stipulation does
not contravene law, morals, or public order, it is strictly binding upon defendant. The
attorney's fees so provided are awarded in favor of the litigant, not his counsel.

On the other hand, the law also allows parties to a contract to stipulate on liquidated
damages to be paid in case of breach. A stipulation on liquidated damages is a penalty
clause where the obligor assumes a greater liability in case of breach of an obligation. The
obligor is bound to pay the stipulated amount without need for proof on the existence
and on the measure of damages caused by the breach. 18
On December 23, 2008, the appellate court denied herein petitioner’s motion for
reconsideration.

Antecedent Facts

Private respondent-complainant Engr. Ingersol L. Santia (Santia) loaned the amount of


₱2,500,000.00 to Pacific Lending & Capital Corporation (PLCC), through its Manager,
petitioner Fideliza J. Aglibot (Aglibot). The loan was evidenced by a Promissory Note dated
July 1, 2003, issued by Aglibot in behalf of PLCC, payable in one year subject to interest at
24% per annum. Allegedly as a guaranty or security for the payment of the note, Aglibot
also issued and delivered to Santia eleven (11) post-dated personal checks drawn from her
own demand account maintained at Metrobank, Camiling Branch. Aglibot is a major
stockholder of PLCC, with headquarters at 27 Casimiro Townhouse, Casimiro Avenue,
Zapote, Las Piñas, Metro Manila, where most of the stockholders also reside. 4
Republic of the Philippines
SUPREME COURT Upon presentment of the aforesaid checks for payment, they were dishonored by the
Manila bank for having been drawn against insufficient funds or closed account. Santia thus
FIRST DIVISION demanded payment from PLCC and Aglibot of the face value of the checks, but neither of
G.R. No. 185945               December 05, 2012 them heeded his demand. Consequently, eleven (11) Informations for violation of Batas
FIDELIZA J. AGLIBOT, Petitioner, Pambansa Bilang 22 (B.P. 22), corresponding to the number of dishonored checks, were
vs. filed against Aglibot before the Municipal Trial Court in Cities (MTCC), Dagupan City,
INGERSOL L. SANTIA, Respondent. Branch 3, docketed as Criminal Case Nos. 47664 to 47674. Each Information, except as to
the amount, number and date of the checks, and the reason for the dishonor, uniformly
DECISION alleged, as follows:
REYES, J.:
Before the Court is a Petition for Review on Certiorari  under Rule 45 of the 1997 Rules of That sometime in the month of September, 2003 in the City of Dagupan, Philippines and
Civil Procedure seeking to annul and set aside the Decision 1 dated March I 8, 2008 of the within the jurisdiction of this Honorable Court, the above-named accused,  FIDELIZA J.
Court of Appeals (CA) in CA-G.R. SP No. 100021, which reversed the Decision 2 dated April AGLIBOT, did then and there, willfully, unlawfully and criminally, draw, issue and deliver
3, 2007 of the Regional Trial Court (RTC) of Dagupan City, Branch 40, in Criminal Case Nos. to one Engr. Ingersol L. Santia, a METROBANK Check No. 0006766, Camiling Tarlac Branch,
2006-0559-D to 2006-0569-D and entered a new judgment. The fallo  reads as follows: postdated November 1, 2003, in the amount of ₱50,000.00, Philippine Currency, payable
to and in payment of an obligation with the complainant, although the said accused knew
WHEREFORE, the instant petition is GRANTED and the assailed Joint Decision dated April fully well that she did not have sufficient funds in or credit with the said bank for the
3, 2007 of the RTC of Dagupan City, Branch 40, and its Order dated June 12, 2007 payment of such check in full upon its presentment, such that when the said check was
are REVERSED AND SET ASIDE and a new one is entered ordering private respondent presented to the drawee bank for payment within ninety (90) days from the date thereof,
Fideliza J. Aglibot to pay petitioner the total amount of ₱3,000,000.00 with 12% interest the same was dishonored for reason "DAIF", and returned to the complainant, and
per annum from the filing of the Informations until the finality of this Decision, the sum of despite notice of dishonor, accused failed and/or refused to pay and/or make good the
which, inclusive of interest, shall be subject thereafter to 12% annual interest until fully amount of said check within five (5) days banking days [sic], to the damage and prejudice
paid. SO ORDERED.3 of one Engr. Ingersol L. Santia in the aforesaid amount of ₱50,000.00 and other
consequential damages.5
Aglibot, in her counter-affidavit, admitted that she did obtain a loan from Santia, but cases;
claimed that she did so in behalf of PLCC; that before granting the loan, Santia demanded 2. In concluding that it is the Pacific Lending and Capital Corporation and not the private
and obtained from her a security for the repayment thereof in the form of the aforesaid respondent which is principally responsible for the amount of the checks being claimed by
checks, but with the understanding that upon remittance in cash of the face amount of the petitioner;
the checks, Santia would correspondingly return to her each check so paid; but despite 3. In finding that the petitioner failed to exhaust all available legal remedies against the
having already paid the said checks, Santia refused to return them to her, although he principal debtor Pacific Lending and Capital Corporation;
gave her assurance that he would not deposit them; that in breach of his promise, Santia 4. In finding that the private respondent is a mere guarantor and not an accommodation
deposited her checks, resulting in their dishonor; that she did not receive any notice of party, and thus, cannot be compelled to pay the petitioner unless all legal remedies
dishonor of the checks; that for want of notice, she could not be held criminally liable against the Pacific Lending and Capital Corporation have been exhausted by the
under B.P. 22 over the said checks; and that the reason Santia filed the criminal cases petitioner;
against her was because she refused to agree to his demand for higher interest. 5. In denying the motion for reconsideration filed by the petitioner."9

On August 18, 2006, the MTCC in its Joint Decision decreed as follows: In its now assailed decision, the appellate court rejected the RTC’s dismissal of the civil
aspect of the aforesaid B.P. 22 cases based on the ground it cited, which is that the
WHEREFORE, in view of the foregoing, the accused, FIDELIZA J. AGLIBOT, is "failure to fulfill a condition precedent of exhausting all means to collect from the
hereby ACQUITTED of all counts of the crime of violation of the bouncing checks law on principal debtor." The appellate court held that since Aglibot’s acquittal by the MTCC in
reasonable doubt. However, the said accused is ordered to pay the private complainant Criminal Case Nos. 47664 to 47674 was upon a reasonable doubt 10 on whether the
the sum of ₱3,000,000.00 representing the total face value of the eleven checks plus prosecution was able to satisfactorily establish that she did receive a notice of dishonor, a
interest of 12% per annum from the filing of the cases on November 2, 2004 until fully requisite to hold her criminally liable under B.P. 22, her acquittal did not operate to bar
paid, attorney’s fees of ₱30,000.00 as well as the cost of suit. SO ORDERED.6 Santia’s recovery of civil indemnity.

On appeal, the RTC rendered a Decision dated April 3, 2007 in Criminal Case Nos. 2006- It is axiomatic that the "extinction of penal action does not carry with it the eradication of
0559-D to 2006-0569-D, which further absolved Aglibot of any civil liability towards Santia, civil liability, unless the extinction proceeds from a declaration in the final judgment that
to wit: the fact from which the civil liability might arise did not exist. Acquittal will not bar a civil
action in the following cases: (1) where the acquittal is based on reasonable doubt as only
preponderance of evidence is required in civil cases; (2) where the court declared the
WHEREFORE, premises considered, the Joint Decision of the court a quo  regarding the accused’s liability is not criminal but only civil in nature[;] and (3) where the civil liability
civil aspect of these cases is reversed and set aside and a new one is entered dismissing does not arise from or is not based upon the criminal act of which the accused was
the said civil aspect on the ground of failure to fulfill, a condition precedent of exhausting acquitted."11 (Citation omitted)
all means to collect from the principal debtor. SO ORDERED.7

The CA therefore ordered Aglibot to personally pay Santia ₱3,000,000.00 with interest at
Santia’s motion for reconsideration was denied in the RTC’s Order dated June 12, 2007. 8  12% per annum, from the filing of the Informations until the finality of its decision.
On petition for review to the CA docketed as CA-G.R. SP No. 100021, Santia interposed the Thereafter, the sum due, to be compounded with the accrued interest, will in turn be
following assignment of errors, to wit: subject to annual interest of 12% from the finality of its judgment until full payment. It
thus modified the MTCC judgment, which simply imposed a straight interest of 12% per
"In brushing aside the law and jurisprudence on the matter, the Regional Trial Court annum  from the filing of the cases on November 2, 2004 until the ₱3,000,000.00 due is
seriously erred: fully paid, plus attorney’s fees of ₱30,000.00 and the costs of the suit.

1. In reversing the joint decision of the trial court by dismissing the civil aspect of these Issue
Now before the Court, Aglibot maintains that it was error for the appellate court to The Court must, however, reject Aglibot’s claim as a mere guarantor of the indebtedness
adjudge her personally liable for issuing her own eleven (11) post-dated checks to Santia, of PLCC to Santia for want of proof, in view of Article 1403(2) of the Civil Code, embodying
since she did so in behalf of her employer, PLCC, the true borrower and beneficiary of the the Statute of Frauds, which provides:
loan. Still maintaining that she was a mere guarantor of the said debt of PLCC when she
agreed to issue her own checks, Aglibot insists that Santia failed to exhaust all means to Art. 1403. The following contracts are unenforceable, unless they are ratified:
collect the debt from PLCC, the principal debtor, and therefore he cannot now be
permitted to go after her subsidiary liability.
xxxx

Ruling of the Court


(2) Those that do not comply with the Statute of Frauds as set forth in this number. In the
following cases an agreement hereafter made shall be unenforceable by action, unless the
The petition is bereft of merit. same, or some note or memorandum thereof, be in writing, and subscribed by the party
charged, or by his agent; evidence, therefore, of the agreement cannot be received
without the writing, or a secondary evidence of its contents:

Aglibot cannot invoke the benefit of excussion a) An agreement that by its terms is not to be performed within a year from the making
thereof;
The RTC in its decision held that, "It is obvious, from the face of the Promissory Note x x x b) A special promise to answer for the debt, default, or miscarriage of another;
that the accused-appellant signed the same on behalf of PLCC as Manager thereof and c) An agreement made in consideration of marriage, other than a mutual promise to
nowhere does it appear therein that she signed as an accommodation party." 12 The RTC marry;
further ruled that what Aglibot agreed to do by issuing her personal checks was merely to d) An agreement for the sale of goods, chattels or things in action, at a price not less than
guarantee the indebtedness of PLCC. So now petitioner Aglibot reasserts that as a five hundred pesos, unless the buyer accept and receive part of such goods and chattels,
guarantor she must be accorded the benefit of excussion – prior exhaustion of the or the evidences, or some of them, or such things in action, or pay at the time some part
property of the debtor – as provided under Article 2058 of the Civil Code, to wit: of the purchase money; but when a sale is made by auction and entry is made by the
auctioneer in his sales book, at the time of the sale, of the amount and kind of property
sold, terms of sale, price, names of purchasers and person on whose account the sale is
Art. 2058. The guarantor cannot be compelled to pay the creditor unless the latter has made, it is a sufficient memorandum;
exhausted all the property of the debtor, and has resorted to all the legal remedies e) An agreement for the leasing of a longer period than one year, or for the sale of real
against the debtor. property or of an interest therein;
f) A representation to the credit of a third person. (Italics ours)
It is settled that the liability of the guarantor is only subsidiary, and all the properties of
the principal debtor, the PLCC in this case, must first be exhausted before the guarantor Under the above provision, concerning a guaranty agreement, which is a promise to
may be held answerable for the debt. 13 Thus, the creditor may hold the guarantor liable answer for the debt or default of another, 17 the law clearly requires that it, or some note
only after judgment has been obtained against the principal debtor and the latter is or memorandum thereof, be in writing. Otherwise, it would be unenforceable unless
unable to pay, "for obviously the ‘exhaustion of the principal’s property’ — the benefit of ratified,18 although under Article 135819 of the Civil Code, a contract of guaranty does not
which the guarantor claims — cannot even begin to take place before judgment has been have to appear in a public document. 20 Contracts are generally obligatory in whatever
obtained."14 This rule is contained in Article 206215 of the Civil Code, which provides that form they may have been entered into, provided all the essential requisites for their
the action brought by the creditor must be filed against the principal debtor alone, except validity are present, and the Statute of Frauds simply provides the method by which the
in some instances mentioned in Article 2059 16 when the action may be brought against contracts enumerated in Article 1403(2) may be proved, but it does not declare them
both the guarantor and the principal debtor.
invalid just because they are not reduced to writing. Thus, the form required under the The appellate court refused to give credence to Aglibot’s claim that she had an
Statute is for convenience or evidentiary purposes only. 21 understanding with Santia that the checks would not be presented to the bank for
payment, but were to be returned to her once she had made cash payments for their face
On the other hand, Article 2055 of the Civil Code also provides that a guaranty is not values on maturity. It noted that Aglibot failed to present any proof that she had indeed
presumed, but must be express, and cannot extend to more than what is stipulated paid cash on the above checks as she claimed. This is precisely why Santia decided to
therein. This is the obvious rationale why a contract of guarantee is unenforceable unless deposit the checks in order to obtain payment of his loan.
made in writing or evidenced by some writing. For as pointed out by Santia, Aglibot has
not shown any proof, such as a contract, a secretary’s certificate or a board resolution, The facts below present a clear situation where Aglibot, as the manager of PLCC, agreed
nor even a note or memorandum thereof, whereby it was agreed that she would issue her to accommodate its loan to Santia by issuing her own post-dated checks in payment
personal checks in behalf of the company to guarantee the payment of its debt to Santia. thereof. She is what the Negotiable Instruments Law calls an accommodation party. 23 
Certainly, there is nothing shown in the Promissory Note signed by Aglibot herself Concerning the liability of an accommodation party, Section 29 of the said law provides:
remotely containing an agreement between her and PLCC resembling her guaranteeing its
debt to Santia. And neither is there a showing that PLCC thereafter ratified her act of Sec. 29. Liability of an accommodation party. — An accommodation party is one who has
"guaranteeing" its indebtedness by issuing her own checks to Santia. signed the instrument as maker, drawer, acceptor, or indorser, without receiving value
therefor, and for the purpose of lending his name to some other person. Such a person is
Thus did the CA reject the RTC’s ruling that Aglibot was a mere guarantor of the liable on the instrument to a holder for value notwithstanding such holder at the time of
indebtedness of PLCC, and as such could not "be compelled to pay [Santia], unless the taking the instrument knew him to be only an accommodation party.
latter has exhausted all the property of PLCC, and has resorted to all the legal remedies
against PLCC x x x."22 As elaborated in The Phil. Bank of Commerce v. Aruego:24

Aglibot is an accommodation party and therefore liable to Santia An accommodation party is one who has signed the instrument as maker, drawer,
indorser, without receiving value therefor and for the purpose of lending his name to
Section 185 of the Negotiable Instruments Law defines a check as "a bill of exchange some other person. Such person is liable on the instrument to a holder for value,
drawn on a bank payable on demand," while Section 126 of the said law defines a bill of notwithstanding such holder, at the time of the taking of the instrument knew him to be
exchange as "an unconditional order in writing addressed by one person to another, only an accommodation party. In lending his name to the accommodated party, the
signed by the person giving it, requiring the person to whom it is addressed to pay on accommodation party is in effect a surety for the latter. He lends his name to enable the
demand or at a fixed or determinable future time a sum certain in money to order or to accommodated party to obtain credit or to raise money. He receives no part of the
bearer." consideration for the instrument but assumes liability to the other parties thereto because
he wants to accommodate another. x x x.25 (Citation omitted)
The appellate court ruled that by issuing her own post-dated checks, Aglibot thereby
bound herself personally and solidarily to pay Santia, and dismissed her claim that she The relation between an accommodation party and the party accommodated is, in effect,
issued her said checks in her official capacity as PLCC’s manager merely to guarantee the one of principal and surety — the accommodation party being the surety. It is a settled
investment of Santia. It noted that she could have issued PLCC’s checks, but instead she rule that a surety is bound equally and absolutely with the principal and is deemed an
chose to issue her own checks, drawn against her personal account with Metrobank. It original promisor and debtor from the beginning. The liability is immediate and direct. 26 It
concluded that Aglibot intended to personally assume the repayment of the loan, pointing is not a valid defense that the accommodation party did not receive any valuable
out that in her Counter-Affidavit, she even admitted that she was personally indebted to consideration when he executed the instrument; nor is it correct to say that the holder for
Santia, and only raised payment as her defense, a clear admission of her liability for the value is not a holder in due course merely because at the time he acquired the
said loan. instrument, he knew that the indorser was only an accommodation party. 27 1âwphi1
Moreover, it was held in Aruego  that unlike in a contract of suretyship, the liability of the Respondent alleged in its Complaint that on 26 March 1997, it entered into an agreement
accommodation party remains not only primary but also unconditional to a holder for with Macrogen Realty, of which petitioner is the President, to construct for the latter the
value, such that even if the accommodated party receives an extension of the period for Shoppers Gold Building, located at Dr. A. Santos Avenue corner Palayag Road, Sucat,
payment without the consent of the accommodation party, the latter is still liable for the Parañaque City. Respondent commenced civil, structural, and architectural works on the
whole obligation and such extension does not release him because as far as a holder for construction project by May 1997. However, Macrogen Realty failed to settle
value is concerned, he is a solidary co-debtor. The mere fact, then, that Aglibot issued her respondent’s progress billings. Petitioner, through his representatives and agents, assured
own checks to Santia made her personally liable to the latter on her checks without the respondent that the outstanding account of Macrogen Realty would be paid, and
need for Santia to first go after PLCC for the payment of its loan. 28 It would have been requested respondent to continue working on the construction project. Relying on the
otherwise had it been shown that Aglibot was a mere guarantor, except that since checks assurances made by petitioner, who was no less than the President of Macrogen Realty,
were issued ostensibly in payment for the loan, the provisions of the Negotiable respondent continued the construction project.
Instruments Law must take primacy in application. WHEREFORE, premises considered, the
Petition for Review on Certiorari  is DENIED and the Decision dated March 18, 2008 of the In August 1998, respondent suspended work on the construction project since the
Court of Appeals in CA-G.R. SP No. I 00021 is hereby AFFIRMED. SO ORDERED. conditions that it imposed for the continuation thereof, including payment of unsettled
accounts, had not been complied with by Macrogen Realty. On 1 September 1999,
Republic of the Philippines respondent instituted with the Construction Industry Arbitration Commission (CIAC) a
SUPREME COURT case for arbitration against Macrogen Realty  seeking payment by the latter of its unpaid
Manila billings and project costs. Petitioner, through counsel, then conveyed to respondent his
THIRD DIVISION purported willingness to amicably settle the arbitration case. On 17 April 2000, before the
G.R. No. 173526             August 28, 2008 arbitration case could be set for trial, respondent and Macrogen Realty entered into a
BENJAMIN BITANGA, petitioner, Compromise Agreement,5 with petitioner acting as signatory for and in behalf of
vs. Macrogen Realty. Under the Compromise Agreement, Macrogen Realty agreed to pay
PYRAMID CONSTRUCTION ENGINEERING CORPORATION, respondent. respondent the total amount of P6,000,000.00 in six equal monthly installments, with
each installment to be delivered on the 15 th day of the month, beginning 15 June 2000.
DECISION Macrogen Realty also agreed that if it would default in the payment of two successive
CHICO-NAZARIO, J.: monthly installments, immediate execution could issue against it for the unpaid balance,
Assailed in this Petition for Review under Rule 45 1 of the Revised Rules of Court are: (1) without need of judgment or decree from any court or tribunal. Petitioner guaranteed the
the Decision2 dated 11 April 2006 of the Court of Appeals in CA-G.R. CV No. 78007 which obligations of Macrogen Realty under the Compromise Agreement by executing a
affirmed with modification the partial Decision 3 dated 29 November 2002 of the Regional Contract of Guaranty6 in favor of respondent, by virtue of which he irrevocably and
Trial Court (RTC), Branch 96, of Quezon City, in Civil Case No. Q-01-45041, granting the unconditionally guaranteed the full and complete payment of the principal amount of
motion for summary judgment filed by respondent Pyramid Construction and Engineering liability of Macrogen Realty in the sum of P6,000,000.00. Upon joint motion of respondent
Corporation and declaring petitioner Benjamin Bitanga and his wife, Marilyn Bitanga and Macrogen Realty, the CIAC approved the Compromise Agreement on 25 April 2000. 7
(Marilyn), solidarily liable to pay P6,000,000.000 to respondent; and (2) the
Resolution4 dated 5 July 2006 of the appellate court in the same case denying petitioner’s However, contrary to petitioner’s assurances, Macrogen Realty failed and refused to pay
Motion for Reconsideration. all the monthly installments agreed upon in the Compromise Agreement. Hence, on 7
September 2000, respondent moved for the issuance of a writ of execution 8 against
The generative facts are: Macrogen Realty, which CIAC granted.

On 6 September 2001, respondent filed with the RTC a Complaint for specific performance On 29 November 2000, the sheriff 9 filed a return stating that he was unable to locate any
and damages with application for the issuance of a writ of preliminary attachment against property of Macrogen Realty, except its bank deposit of P20,242.33, with the Planters
the petitioner and Marilyn. The Complaint was docketed as Civil Case No. Q-01-45041. Bank, Buendia Branch.
Respondent then made, on 3 January 2001, a written demand 10 on petitioner, as The Motion To Dismiss Complaint Against Defendant Marilyn Andal Bitanga filed on
guarantor of Macrogen Realty, to pay the P6,000,000.00, or to point out available November 12, 2001 is denied for lack of merit considering that Sec. 4, Rule 3, of the Rules
properties of the Macrogen Realty within the Philippines sufficient to cover the obligation of Court (1997) specifically provides, as follows:
guaranteed. It also made verbal demands on petitioner. Yet, respondent’s demands were
left unheeded. "SEC. 4. Spouses as parties. – Husband and wife shall sue or be sued jointly, except as
provided by law."
Thus, according to respondent, petitioner’s obligation as guarantor was already due and
demandable. As to Marilyn’s liability, respondent contended that Macrogen Realty was and that this case does not come within the exception. 12
owned and controlled by petitioner and Marilyn and/or by corporations owned and
controlled by them. Macrogen Realty is 99% owned by the Asian Appraisal Holdings, Inc.
(AAHI), which in turn is 99% owned by Marilyn. Since the completion of the construction Petitioner filed with the RTC on 12 November 2001, his Answer 13 to respondent’s
project would have redounded to the benefit of both petitioner and Marilyn and/or their Complaint averring therein that he never made representations to respondent that
corporations; and considering, moreover, Marilyn’s enormous interest in AAHI, the Macrogen Realty would faithfully comply with its obligations under the Compromise
corporation which controls Macrogen Realty, Marilyn cannot be unaware of the Agreement. He did not offer to guarantee the obligations of Macrogen Realty to entice
obligations incurred by Macrogen Realty and/or petitioner in the course of the business respondent to enter into the Compromise Agreement but that, on the contrary, it was
operations of the said corporation. respondent that required Macrogen Realty to offer some form of security for its
obligations before agreeing to the compromise. Petitioner further alleged that his wife
Marilyn was not aware of the obligations that he assumed under both the Compromise
Respondent prayed in its Complaint that the RTC, after hearing, render a judgment Agreement and the Contract of Guaranty as he did not inform her about said contracts,
ordering petitioner and Marilyn to comply with their obligation under the Contract of nor did he secure her consent thereto at the time of their execution.
Guaranty by paying respondent the amount of P6,000,000.000 (less the bank deposit of
Macrogen Realty with Planter’s Bank in the amount of P20,242.23) and P400,000.000 for
attorneys fees and expenses of litigation. Respondent also sought the issuance of a writ of As a special and affirmative defense, petitioner argued that the benefit of excussion was
preliminary attachment as security for the satisfaction of any judgment that may be still available to him as a guarantor since he had set it up prior to any judgment against
recovered in the case in its favor. him. According to petitioner, respondent failed to exhaust all legal remedies to collect
from Macrogen Realty the amount due under the Compromise Agreement, considering
that Macrogen Realty still had uncollected credits which were more than enough to pay
Marilyn filed a Motion to Dismiss, 11 asserting that respondent had no cause of action for the same. Given these premise, petitioner could not be held liable as guarantor.
against her, since she did not co-sign the Contract of Guaranty with her husband; nor was Consequently, petitioner presented his counterclaim for damages.
she a party to the Compromise Agreement between respondent and Macrogen Realty.
She had no part at all in the execution of the said contracts. Mere ownership by a single
stockholder or by another corporation of all or nearly all of the capital stock of another At the pre-trial held on 5 September 2002, the parties submitted the following issues for
corporation is not by itself a sufficient ground for disregarding the separate personality of the resolution of the RTC:
the latter corporation. Respondent misread Section 4, Rule 3 of the Revised Rules of
Court. (1) whether the defendants were liable under the contract of guarantee dated April 17,
2000 entered into between Benjamin Bitanga and the plaintiff;
The RTC denied Marilyn’s Motion to Dismiss for lack of merit, and in its Order dated 24 (2) whether defendant wife Marilyn Bitanga is liable in this action;
January 2002 decreed that: (3) whether the defendants are entitled to the benefit of excussion, the plaintiff on the
one hand claiming that it gave due notice to the guarantor, Benjamin Bitanga, and the
defendants contending that no proper notice was received by Benjamin Bitanga;
(4) if damages are due, which party is liable; and
(5) whether the benefit of excussion can still be invoked by the defendant guarantor even
after the notice has been allegedly sent by the plaintiff although proper receipt is On 29 November 2002, the RTC rendered a partial Decision, the dispositive portion of
denied.14 which provides:

On 20 September 2002, prior to the trial proper, respondent filed a Motion for Summary WHEREFORE, summary judgment is rendered ordering defendants SPOUSES BENJAMIN
Judgment.15 Respondent alleged therein that it was entitled to a summary judgment on BITANGA and MARILYN ANDAL BITANGA to pay the [herein respondent], jointly and
account of petitioner’s admission during the pre-trial of the genuineness and due severally, the amount of P6,000,000.00, less P20,242.23 (representing the amount
execution of the Contract of Guaranty. The contention of petitioner and Marilyn that they garnished bank deposit of MACROGEN in the Planters Bank, Buendia Branch); and the
were entitled to the benefit of excussion was not a genuine issue. Respondent had already costs of suit.
exhausted all legal remedies to collect from Macrogen Realty, but its efforts proved
unsuccessful. Given that the inability of Macrogen Realty as debtor to pay the amount of Within 10 days from receipt of this partial decision, the [respondent] shall inform the
its debt was already proven by the return of the writ of execution to CIAC unsatisfied, the Court whether it shall still pursue the rest of the claims against the defendants. Otherwise,
liability of petitioner as guarantor already arose. 16 In any event, petitioner and Marilyn such claims shall be considered waived.20
were deemed to have forfeited their right to avail themselves of the benefit of excussion
because they failed to comply with Article 2060 17 of the Civil Code when petitioner
ignored respondent’s demand letter dated 3 January 2001 for payment of the amount he Petitioner and Marilyn filed a Motion for Reconsideration of the afore-quoted Decision,
guaranteed.18 The duty to collect the supposed receivables of Macrogen Realty from its which the RTC denied in an Order dated 26 January 2003.21
creditors could not be imposed on respondent, since petitioner and Marilyn never
informed respondent about such uncollected credits even after receipt of the demand In time, petitioner and Marilyn filed an appeal with the Court of Appeals, docketed as CA-
letter for payment. The allegation of petitioner and Marilyn that they could not respond to G.R. CV 78007. In its Decision dated 11 April 2006, the appellate court held:
respondent’s demand letter since they did not receive the same was unsubstantiated and
insufficient to raise a genuine issue of fact which could defeat respondent’s Motion for UPON THE VIEW WE TAKE OF THIS CASE, THUS, the judgment appealed from must be, as
Summary Judgment. The claim that Marilyn never participated in the transactions that it hereby is, MODIFIED to the effect that defendant-appellant Marilyn Bitanga is adjudged
culminated in petitioner’s execution of the Contract of Guaranty was nothing more than a not liable, whether solidarily or otherwise, with her husband the defendant-appellant
sham. Benjamin Bitanga, under the compromise agreement or the contract of guaranty. No costs
in this instance.22
In opposing respondent’s foregoing Motion for Summary Judgment, petitioner and
Marilyn countered that there were genuinely disputed facts that would require trial on In holding that Marilyn Bitanga was not liable, the Court of Appeals cited Ramos v. Court
the merits. They appended thereto an affidavit executed by petitioner, in which he of Appeals,23 in which it was declared that a contract cannot be enforced against one who
declared that his spouse Marilyn could not be held personally liable under the Contract of is not a party to it. The Court of Appeals stated further that the substantial ownership of
Guaranty or the Compromise Agreement, nor should her share in the conjugal partnership shares in Macrogen Realty by Marilyn Bitanga was not enough basis to hold her liable.
be made answerable for the guaranty petitioner assumed, because his undertaking of the
guaranty did not in any way redound to the benefit of their family. As guarantor,
petitioner was entitled to the benefit of excussion, and he did not waive his right thereto. The Court of Appeals, in its Resolution dated 5 July 2006, denied petitioner’s Motion for
He never received the respondent’s demand letter dated 3 January 2001, as Ms. Dette Reconsideration24 of its earlier Decision.
Ramos, the person who received it, was not an employee of Macrogen Realty nor was she
authorized to receive the letter on his behalf. As a guarantor, petitioner could resort to Petitioner is now before us via  the present Petition with the following assignment of
the benefit of excussion at any time before judgment was rendered against errors:
him.19 Petitioner reiterated that Macrogen Realty had uncollected credits which were
more than sufficient to satisfy the claim of respondent.
I
THE COURT OF APPEALS GRAVELY ERRED IN AFFIRMING THE VALIDITY OF THE PARTIAL
SUMMARY JUDGMENT BY THE REGIONAL TRIAL COURT OF QUEZON CITY, BRANCH 96, First off, we rule that the issue regarding the propriety of the service of a copy of the
DESPITE THE CLEAR EXISTENCE OF DISPUTED GENUINE AND MATERIAL FACTS OF THE demand letter on the petitioner in his office is a sham issue. It is not a bar to the issuance
CASE THAT SHOULD HAVE REQUIRED A TRIAL ON THE MERITS. of a summary judgment in respondent’s favor.
II
THE COURT OF APPEALS GRAVELY ERRED IN NOT UPHOLDING THE RIGHT OF PETITIONER A genuine issue is an issue of fact which requires the presentation of evidence as
BENJAMIN M. BITANGA AS A MERE GUARANTOR TO THE BENEFIT OF EXCUSSION UNDER distinguished from an issue which is a sham, fictitious, contrived or false claim. To forestall
ARTICLES 2058, 2059, 2060, 2061, AND 2062 OF THE CIVIL CODE OF THE PHILIPPINES.25 summary judgment, it is essential for the non-moving party to confirm the existence of
genuine issues, as to which he has substantial, plausible and fairly arguable
As in the two courts below, it is petitioner’s position that summary judgment is improper defense, i.e.,29 issues of fact calling for the presentation of evidence upon which
in Civil Case No. Q-01-45041 because there are genuine issues of fact which have to be reasonable findings of fact could return a verdict for the non-moving party, although a
threshed out during trial, to wit: mere scintilla of evidence in support of the party opposing summary judgment will be
insufficient to preclude entry thereof.
(A) Whether or not there was proper service of notice to petitioner considering the said
letter of demand was allegedly received by one Dette Ramos at Macrogen office and not Significantly, petitioner does not deny the receipt of the demand letter from the
by him at his residence. respondent. He merely raises a howl on the impropriety of service thereof, stating that
(B) Whether or not petitioner is entitled to the benefit of excussion?26 "the address to which the said letter was sent was not his residence but the office of
Macrogen Realty, thus it cannot be considered as the correct manner of conveying a letter
We are not persuaded by petitioner’s arguments. of demand upon him in his personal capacity." 30

Rule 35 of the Revised Rules of Civil Procedure provides: Section 6, Rule 13 of the Rules of Court states:

Section 1. Summary judgment for claimant. – A party seeking to recover upon a claim, SEC. 6. Personal service. – Service of the papers may be made by delivering personally a
counterclaim, or cross-claim or to obtain a declaratory relief may, at any time after the copy to the party or his counsel, or by leaving it in his office with his clerk or with a
pleading in answer thereto has been served, move with supporting affidavits, depositions person having charge thereof. If no person is found in his office, or his office is not known,
or admissions for a summary judgment in his favor upon all or any part thereof. or he has no office, then by leaving the copy, between the hours of eight in the morning
and six in the evening, at the party’s or counsel’s residence, if known, with a person of
sufficient age and discretion then residing therein.
For a summary judgment to be proper, the movant must establish two requisites: (a)
there must be no genuine issue as to any material fact, except for the amount of
damages; and (b) the party presenting the motion for summary judgment must be entitled The affidavit of Mr. Robert O. Pagdilao, messenger of respondent’s counsel states in part:
to a judgment as a matter of law. Where, on the basis of the pleadings of a moving party,
including documents appended thereto, no genuine issue as to a material fact exists, the 2. On 4 January 2001, Atty. Jose Vicente B. Salazar, then one of the Associates of the
burden to produce a genuine issue shifts to the opposing party. If the opposing party fails, ACCRA Law Offices, instructed me to deliver to the office of Mr. Benjamin Bitanga a letter
the moving party is entitled to a summary judgment. 27 dated 3 January 2001, pertaining to Construction Industry Arbitration Commission
(hereafter, "CIAC") Case No. 99-56, entitled "Pyramid Construction Engineering
In a summary judgment, the crucial question is: are the issues raised by the opposing Corporation vs. Macrogen Realty Corporation."
party not genuine so as to justify a summary judgment? 28
3. As instructed, I immediately proceeded to the office of Mr. Bitanga located at the
12th Floor, Planters Development Bank Building, 314 Senator Gil Puyat Avenue, Makati
City. I delivered the said letter to Ms. Dette Ramos, a person of sufficient age and petitioner] Mr. Benjamin Bitanga and/or of the latter’s companies, said [petitioner] merely
discretion, who introduced herself as one of the employees of Mr. Bitanga and/or of the offered a bare denial. But bare denials, unsubstantiated by facts, which would be
latter’s companies.31 (Emphasis supplied.) admissible in evidence at a hearing,  are not sufficient to raise a genuine issue of fact
sufficient to defeat a motion for summary judgment. 36
We emphasize that when petitioner signed the Contract of Guaranty and assumed
obligation as guarantor, his address in the said contract was the same address where the We further affirm the findings of both the RTC and the Court of Appeals that, given the
demand letter was served.32 He does not deny that the said place of service, which is the settled facts of this case, petitioner cannot avail himself of the benefit of excussion.
office of Macrogen, was also the address that he used when he signed as guarantor in the
Contract of Guaranty. Nor does he deny that this is his office address; instead, he merely Under a contract of guarantee, the guarantor binds himself to the creditor to fulfill the
insists that the person who received the letter and signed the receiving copy is not an obligation of the principal debtor in case the latter should fail to do so. The guarantor who
employee of his company. Petitioner could have easily substantiated his allegation by a pays for a debtor, in turn, must be indemnified by the latter. However, the guarantor
submission of an affidavit of the personnel manager of his office that no such person is cannot be compelled to pay the creditor unless the latter has exhausted all the property
indeed employed by petitioner in his office, but that evidence was not submitted. 33 All of the debtor and resorted to all the legal remedies against the debtor. This is what is
things are presumed to have been done correctly and with due formality until the otherwise known as the benefit of excussion. 37
contrary is proved. This juris tantum presumption stands even against the most well-
reasoned allegation pointing to some possible irregularity or anomaly. 34 It is petitioner’s
burden to overcome the presumption by sufficient evidence, and so far we have not seen Article 2060 of the Civil Code reads:
anything in the record to support petitioner’s charges of anomaly beyond his bare
allegation. Petitioner cannot now be heard to complain that there was an irregular service Art. 2060. In order that the guarantor may make use of the benefit of excussion, he must
of the demand letter, as it does not escape our attention that petitioner himself indicated set it up against the creditor upon the latter’s demand for payment from him, and point
"314 Sen. Gil Puyat Avenue, Makati City" as his office address in the Contract of Guaranty. out to the creditor available property of the debtor within Philippine territory, sufficient to
cover the amount of the debt.38
Moreover, under Section 6, Rule 13 of the Rules of Court, there is sufficiency of service
when the papers, or in this case, when the demand letter is personally delivered to the The afore-quoted provision imposes a condition for the invocation of the defense of
party or his counsel, or by leaving it in his office with his clerk or with a person having excussion. Article 2060 of the Civil Code clearly requires that in order for the guarantor to
charge thereof, such as what was done in this case. make use of the benefit of excussion, he must set it up against the creditor upon the
latter’s demand for payment and point out to the creditor available property of the debtor
We have consistently expostulated that in summary judgments, the trial court can within the Philippines sufficient to cover the amount of the debt. 39
determine a genuine issue on the basis of the pleadings, admissions, documents, affidavits
or counter affidavits submitted by the parties. When the facts as pleaded appear It must be stressed that despite having been served a demand letter at his office,
uncontested or undisputed, then there is no real or genuine issue or question as to any petitioner still failed to point out to the respondent properties of Macrogen Realty
fact, and summary judgment is called for.35 sufficient to cover its debt as required under Article 2060 of the Civil Code. Such failure on
petitioner’s part forecloses his right to set up the defense of excussion.
The Court of Appeals was correct in holding that:
Worthy of note as well is the Sheriff’s return stating that the only property of Macrogen
Here, the issue of non-receipt of the letter of demand is a sham or pretended issue, not a Realty which he found was its deposit of P20,242.23 with the Planters Bank.
genuine and substantial issue. Indeed, against the positive assertion of Mr. Roberto O.
Pagdilao (the private courier) in his affidavit that he delivered the subject letter to a Article 2059(5) of the Civil Code thus finds application and precludes petitioner from
certain Ms. Dette Ramos who introduced herself as one of the employees of [herein interposing the defense of excussion. We quote:
Art. 2059. This excussion shall not take place:

xxxx

(5) If it may be presumed that an execution on the property of the principal debtor would
not result in the satisfaction of the obligation.

As the Court of Appeals correctly ruled:

We find untenable the claim that the [herein petitioner] Benjamin Bitanga cannot be
compelled to pay Pyramid because the Macrogen Realty has allegedly sufficient assets.
Reason: The said [petitioner] had not genuinely controverted the return made by Sheriff
Joseph F. Bisnar, who affirmed that, after exerting diligent efforts, he was not able to
locate any property belonging to the Macrogen Realty, except for a bank deposit with the
Planter’s Bank at Buendia, in the amount of P20,242.23. It is axiomatic that the liability of
the guarantor arises when the insolvency or inability of the debtor to pay the amount of
debt is proven by the return of the writ of execution that had not been unsatisfied. 40

WHEREFORE, premises considered, the instant petition is DENIED for lack of merit. The
Decision of the Court of Appeals dated 11 April 2006 and its Resolution dated 5 July 2006
are AFFIRMED. Costs against petitioner.

SO ORDERED.
properties, or upon BMC’s insolvency, or if it is declared to be in a state of suspension of
payments. Respondent bank granted BMC’s loan applications.

On November 22, 1991, BMC filed a petition for rehabilitation and suspension of
payments with the Securities and Exchange Commission (SEC) after its properties were
attached by creditors. Respondent bank considered debtor BMC in default of its
obligations and sought to collect payment thereof from petitioners-spouses as sureties. In
due time, petitioners-spouses filed their Answer.1awphi1.nét

On October 13, 1992, a Memorandum of Agreement (MOA) 2 was executed by debtor


BMC, the petitioners-spouses as President and Treasurer of BMC, and the consortium of
SECOND DIVISION creditor banks of BMC (of which respondent bank is included). The MOA took effect upon
G.R. No. 160466             January 17, 2005 its approval by the SEC on November 27, 1992.3
SPOUSES ALFREDO and SUSANA ONG, petitioners,
vs. Thereafter, petitioners-spouses moved to dismiss 4 the complaint. They argued that as
PHILIPPINE COMMERCIAL INTERNATIONAL BANK, respondent. the SEC declared the principal debtor BMC in a state of suspension of payments and,
under the MOA, the creditor banks, including respondent bank, agreed to temporarily
DECISION suspend any pending civil action against the debtor BMC, the benefits of the MOA should
PUNO, J.: be extended to petitioners-spouses who acted as BMC’s sureties in their contracts of loan
This is a petition for review on certiorari under Rule 45 of the Rules of Court to set aside with respondent bank. Petitioners-spouses averred that respondent bank is barred from
the Decision of the Court of Appeals in CA-G.R. SP No. 39255, dated February 17, 2003, pursuing its collection case filed against them.
affirming the decision of the trial court denying petitioners’ motion to dismiss.

The trial court denied the motion to dismiss. Petitioners-spouses appealed to the Court
The facts: Baliwag Mahogany Corporation (BMC) is a domestic corporation engaged in the of Appeals which affirmed the trial court’s ruling that a creditor can proceed against
manufacture and export of finished wood products. Petitioners-spouses Alfredo and petitioners-spouses as surety independently of its right to proceed against the principal
Susana Ong are its President and Treasurer, respectively. debtor BMC.

On April 20, 1992, respondent Philippine Commercial International Bank (now Equitable- Hence this appeal.
Philippine Commercial International Bank or E-PCIB) filed a case for collection of a sum of
money1 against petitioners-spouses. Respondent bank sought to hold petitioners-spouses
liable as sureties on the three (3) promissory notes they issued to secure some of BMC’s Petitioners-spouses claim that the collection case filed against them by respondent bank
loans, totalling five million pesos (₱5,000,000.00). should be dismissed for three (3) reasons: First, the MOA provided that during its
effectivity, there shall be a suspension of filing or pursuing of collection cases against the
BMC and this provision should benefit petitioners as sureties. Second, principal debtor
The complaint alleged that in 1991, BMC needed additional capital for its business and BMC has been placed under suspension of payment of debts by the SEC; petitioners
applied for various loans, amounting to a total of five million pesos, with the respondent contend that it would prejudice them if the principal debtor BMC would enjoy the
bank. Petitioners-spouses acted as sureties for these loans and issued three (3) suspension of payment of its debts while petitioners, who acted only as sureties for some
promissory notes for the purpose. Under the terms of the notes, it was stipulated that of BMC’s debts, would be compelled to make the payment; petitioners add that
respondent bank may consider debtor BMC in default and demand payment of the compelling them to pay is contrary to Article 2063 of the Civil Code which provides that a
remaining balance of the loan upon the levy, attachment or garnishment of any of its compromise between the creditor and principal debtor benefits the guarantor and should
not prejudice the latter. Lastly, petitioners rely on Article 2081 of the Civil Code which The provisions of the MOA regarding the suspension of payments by BMC and the non-
provides that: "the guarantor may set up against the creditor all the defenses which filing of collection suits by the creditor banks pertain only to the property of the
pertain to the principal debtor and are inherent in the debt; but not those which are principal debtor BMC. Firstly, in the rehabilitation receivership filed by BMC, only the
purely personal to the debtor." Petitioners aver that if the principal debtor BMC can set properties of BMC were mentioned in the petition with the SEC. 8 Secondly, there is
up the defense of suspension of payment of debts and filing of collection suits against nothing in the MOA that involves the liabilities of the sureties whose properties are
respondent bank, petitioners as sureties should likewise be allowed to avail of these separate and distinct from that of the debtor BMC. Lastly, it bears to stress that the MOA
defenses. executed by BMC and signed by the creditor-banks was approved by the SEC whose
jurisdiction is limited only to corporations and corporate assets. It has no jurisdiction over
We find no merit in petitioners’ contentions. the properties of BMC’s officers or sureties.1awphi1.nét

Reliance of petitioners-spouses on Articles 2063 and 2081 of the Civil Code is misplaced Clearly, the collection suit filed by respondent bank against petitioners-spouses as sureties
as these provisions refer to contracts of guaranty. They do not apply to suretyship can prosper. The trial court’s denial of petitioners’ motion to dismiss was proper.
contracts. Petitioners-spouses are not guarantors but sureties of BMC’s debts. There is a
sea of difference in the rights and liabilities of a guarantor and a surety. A guarantor IN VIEW WHEREOF, the petition is DISMISSED for lack of merit. No pronouncement as to
insures the solvency of the debtor while a surety is an insurer of the debt itself. A costs.
contract of guaranty gives rise to a subsidiary obligation on the part of the guarantor. It is
only after the creditor has proceeded against the properties of the principal debtor and SO ORDERED.
the debt remains unsatisfied that a guarantor can be held liable to answer for any unpaid
amount. This is the principle of excussion. In a suretyship contract, however, the benefit
of excussion is not available to the surety as he is principally liable for the payment of
the debt. As the surety insures the debt itself, he obligates himself to pay the debt if the
principal debtor will not pay, regardless of whether or not the latter is financially capable
to fulfill his obligation. Thus, a creditor can go directly against the surety although the
principal debtor is solvent and is able to pay or no prior demand is made on the principal
debtor. A surety is directly, equally and absolutely bound with the principal debtor for
the payment of the debt and is deemed as an original promissor and debtor from the
beginning.5

Under the suretyship contract entered into by petitioners-spouses with respondent bank,
the former obligated themselves to be solidarily bound with the principal debtor BMC for
the payment of its debts to respondent bank amounting to five million pesos
(₱5,000,000.00). Under Article 1216 of the Civil Code,6 respondent bank as creditor may
proceed against petitioners-spouses as sureties despite the execution of the MOA which
provided for the suspension of payment and filing of collection suits against BMC.
Respondent bank’s right to collect payment from the surety exists independently of its
right to proceed directly against the principal debtor. In fact, the creditor bank may go
against the surety alone without prior demand for payment on the principal debtor. 7
SO ORDERED.

The case arose when petitioner refused to pay the demurrage being collected by
respondent.

The facts are as follows:

In a contract dated 26 April 1983, respondent was appointed as the exclusive Philippine
indent representative of Richco Rotterdam B.V. (Richco), a foreign corporation, in the sale
of the latter’s commodities. Under one of the terms of the contract, respondent was to
assume the liabilities of all the Philippine buyers, should they fail to honor the
commitments on the discharging operations of each vessel, including the payment of
demurrage and other penalties. In such instances, Richco shall have the option to debit
Republic of the Philippines the account of respondent corresponding to the liabilities of the buyers, and respondent
SUPREME COURT shall then be deemed to be subrogated to all the rights of Richco against these defaulting
Manila buyers.3
SECOND DIVISION
G.R. No. 152313               October 19, 2011 Sometime in 1987, petitioner purchased Canadian barley and soybean meal from Richco.
REPUBLIC FLOUR MILLS CORPORATION, Petitioner, The latter thereafter chartered four (4) vessels to transport the products to the
vs. Philippines. Each of the carrier bulk cargoes was covered by a Contract of Sale executed
FORBES FACTORS, INC. Respondent. between respondent as the seller and duly authorized representative of Richco and
petitioner as the buyer. The four contracts specifically referred to the charter party in
DECISION determining demurrage or dispatch rate. The contract further provided that petitioner
SERENO, J.: guarantees to settle any demurrage due within one (1) month from respondent’s
Petitioner filed this present Petition for Review 1 under Rule 45 of the Rules of Court, presentation of the statement.
seeking a reversal of the Court of Appeals Decision, 2 the dispositive portion of which
states:
Upon delivery of the barley and soybean meal, petitioner failed to discharge the cargoes
from the four (4) vessels at the computed allowable period to do so. Thus, it incurred a
WHEREFORE, premises considered, the Decision dated April 15, 1996 rendered by the demurrage amounting to a total of US$193,937.41.
Regional Trial Court of Makati City, Branch 60, is hereby AFFIRMED, with MODIFICATIONS,
as follows:
On numerous occasions, on behalf of Richco, respondent demanded from petitioner the
payment of the demurrage, to no avail. Consequently, on 20 October 1991, Richco sent a
1) The legal interest rate of six percent (6%) per annum should be computed from the communication to respondent, informing it that the demurrage due from petitioner had
date of the filing of the complaint which shall become twelve percent (12%) per annum been debited from the respondent’s account.
from the time the judgment becomes final and executory until its satisfaction.
2) The award of ₱300,000.00 as exemplary damages is reduced to ₱50,000.00;
3) The award of ₱400,00.00 as attorney’s fees is likewise reduced to ₱75,000.00; Thereafter, on 12 February 1992, respondent filed with the Regional Trial Court (RTC),
4) The Decision is hereby affirmed in all other respects. National Capital Judicial Region, Makati City, a Complaint for demurrage and damages
against petitioner. Meanwhile, the latter raised the defense that the delay was due to Subsequently, petitioner appealed to the Court of Appeals (CA), alleging that respondent
respondent’s inefficiency in unloading the cargo. was not a real party-in-interest to bring the collection suit. Petitioner insisted that the
payment of demurrage should be made to the owner of the vessels that transported the
On 15 April 1996, after trial on the merits, the RTC rendered a Decision 4 holding petitioner goods, and not to respondent who was merely the indent representative of Richco, the
liable to pay demurrage and damages to respondent, to wit: charterer of the vessel. In addition, petitioner claimed that it was denied due process
when the RTC refused to reset the hearing for the presentation of Reynaldo Santos,
petitioner’s witness and export manager. Finally, petitioner contested the RTC’s award of
34. WHEREFORE, the Court hereby renders judgment as follows: exemplary damages and attorney’s fees.

34.1 The defendant REPUBLIC FLOUR MILLS CORPORATION is ordered to pay the plaintiff On 18 February 2002, the CA promulgated the assailed Decision. It upheld the validity of
FORBES FACTORS, INC. the following: the Contracts of Sale and held that these had the force of law between the contracting
parties and must be complied with in good faith. However, the appellate court modified
34.1.1. US$193,937.41 or its Philippine PESO equivalent at the rate of exchange at the the trial court’s award of damages. It held that exemplary damages are not intended to
time of payment – As demurrage. enrich anyone, thus, reducing the amount from ₱300,000 to ₱50,000. It also found the
award of attorney’s fees to be excessive, and consequently reduced it from ₱400,000 to
34.1.2 Six (6) percent of the amount in the preceding paragraph 34.1.1 – Per annum from ₱75,000.
October 29, 1991 until the said amount is fully paid – As damages.
Hence this Petition.
34.1.3. ₱300,000.00 – As exemplary damages.
Three issues are raised for the resolution by this Court. First, petitioner assails the right of
34.1.4. ₱ 400,000.00 – As attorney’s fees. respondent to demand payment of demurrage. Petitioner asserts that, by definition,
demurrage is the sum fixed by the contract of carriage as remuneration to the ship owner
for the detention of the vessel beyond the number of days allowed by the charter
34.2. The COUNTERCLAIM is DISMISSED; and party.5 Thus, since respondent is not the ship owner, it has no right to demand the
payment of demurrage and has no personality to bring the claim against petitioner.
34.3. Cost is taxed against the defendant. Second, petitioner questions the propriety of the award of damages in favor of
respondent. And third, the former insists that it was denied due process when the RTC
denied its Motion to reset the hearing to present its witness.
The RTC found that the delay in discharging the cargoes within the allowable period was
due to petitioner’s failure to provide enough barges on which to load the goods. It
likewise found that petitioner in fact acknowledged that the latter had incurred We find the petition without merit.
demurrage when it alleged that the computation was bloated. Petitioner was thus liable
to pay demurrage based on the sales contracts executed with respondent and on the The facts are undisputed. The delay incurred by petitioner in discharging the cargoes from
contract executed between respondent and Richco. the vessels was due to its own fault. Its obligation to demurrage is established by the
Contracts of Sale it executed, wherein it agreed to the conditions to provide all
Finally, the court ruled that respondent was entitled to damages from petitioner’s discharging facilities at its expense in order to effect the immediate discharge of cargo;
"wanton, fraudulent, reckless, oppressive or malevolent" refusal to pay the latter’s and to place for its account all discharging costs, fees, taxes, duties and all other charges
liabilities despite repeated demands. incurred due to the nature of the importation. 6
Meanwhile, respondent unequivocally established that Richco charged to it the (1) When a creditor pays another creditor who is preferred, even without the debtor’s
demurrage due from petitioner. Thus, at the moment that Richco debited the account of knowledge;
respondent, the latter is deemed to have subrogated to the rights of the former, who in
turn, paid demurrage to the ship owner. It is therefore immaterial that respondent is not (2) When a third person, not interested in the obligation, pays with the express or tacit
the ship owner, since it has been able to prove that it has stepped into the shoes of the approval of the debtor;
creditor.

(3) When, even without the knowledge of the debtor, a person interested in the
Subrogation is either "legal" or "conventional." Legal subrogation is an equitable doctrine fulfillment of the obligation pays, without prejudice to the effects of confusion as to the
and arises by operation of the law, without any agreement to that effect executed latter’s share."
between the parties; conventional subrogation rests on a contract, arising where "an
agreement is made that the person paying the debt shall be subrogated to the rights and
remedies of the original creditor." 7 The case at bar is an example of legal subrogation, the "Art. 2067. The guarantor who pays is subrogated by virtue thereof to all the rights which
petitioner and respondent having no express agreement on the right of subrogation. Thus, the creditor had against the debtor.
it is of no moment that the Contracts of Sale did not expressly state that demurrage shall
be paid to respondent. By operation of law, respondent has become the real party-in- If the guarantor has compromised with the creditor, he cannot demand of the debtor
interest to pursue the payment of demurrage. As aptly stated by the RTC: more than what he has really paid."

19. True it is that demurrage is, as a rule, an amount payable to a shipowner by a As we held in Fireman’s Fund Insurance Company v. Jamila & Company, Inc.:
charterer for the detention of the vessel beyond the period allowed for the loading or
unloading or sailing. This however, does not mean that a party cannot stipulate with …Subrogation has been referred to as the doctrine of substitution. It "is an arm of equity
another who is not a shipowner, on demurrage. In this case, FORBES stipulated under the that may guide or even force one to pay a debt for which an obligation was incurred but
charter parties on demurrage with the shipowners. This stipulation could be the basis of which was in whole or in part paid by another" (83 C.J.S. 576, 678, note 16, citing
the provisions on demurrage in the four (4) Contracts of Sale (Exhs. B, N, X, and CC) and Fireman's Fund Indemnity Co. vs. State Compensation Insurance Fund, 209 Pac. 2d 55).
contract between FORBES and RICHCO (Exh. A).

"Subrogation is founded on principles of justice and equity, and its operation is governed
x x x           x x x          x x x by principles of equity. It rests on the principle that substantial justice should be attained
regardless of form, that is, its basis is the doing of complete, essential, and perfect justice
20. RICHCO debited the US$193,937.41 from the accounts of FORBES as evidenced by Exh. between all the parties without regard to form"(83 C.J.S. 579- 80)81avvphi1
OO. Hence, FORBES was subrogated to the right of RICHCO to collect the said amount
from RFM pursuant to the contract between RICHCO and FORBES (Exh. A). Anent the second issue, we have previously held in Pepsi Cola Products Phil., Inc. v. Court
of Appeals,9 that a motion for continuance of postponement is not a matter of right.
21. Under Exh. A, FORBES guaranteed its "…buyers (sic) payment schedule…" Rather, the motion is addressed to the sound discretion of the court, whose action
Consequently, it was subrogated to the rights of RICHCO arising from the failure of RFM to thereon will not be disturbed by appellate courts in the absence of clear and manifest
pay its demurrage and FORBES paid for it. The subrogation was pursuant to Articles 1302 abuse of discretion, resulting in a denial of substantial justice.
and 2067, New Civil Code, which read:
On the last issue, we find that the award of exemplary damages proper. Petitioner refused
"Art. 1302. It is presumed that there is legal subrogation: to honor the contract despite respondent’s repeated demands and its proof of payment
to Richco; and despite its repeated promise to settle its outstanding obligations in the
span of almost five years. Petitioner indeed acted in a wanton, fraudulent, reckless,
oppressive or malevolent manner. Because respondent was also forced to initiate the 2001 of the appellate court in CA-G.R. SP No. 58763 which denied herein petitioner’s
present Complaint, it was only proper that it was awarded attorney’s fees. Lastly, the CA motion for reconsideration.
was correct in reducing the award of exemplary damages or attorney’s fees, since neither
is meant to enrich anyone. The facts of this case are not disputed.

WHEREFORE, in view of the foregoing, the assailed Decision of the Court of Appeals is The private respondents are the complainants in a case for illegal dismissal, docketed as
hereby AFFIRMED. The present Petition is DENIED. NLRC NCR Case No. 02-00672-90, filed against Radon Security & Allied Services Agency
and/or Raquel Aquias and Ever Emporium, Inc. In his Decision dated August 20, 1996, the
SO ORDERED. Labor Arbiter ruled that the private respondents were illegally dismissed and ordered
Radon Security to pay them separation pay, backwages, and other monetary claims.

Radon Security appealed the Labor Arbiter’s decision to public respondent NLRC and
posted a supersedeas bond, issued by herein petitioner AFPGIC as surety. The appeal was
docketed as NLRC NCR CA-011705-96.

On April 6, 1998, the NLRC affirmed with modification the decision of the Labor Arbiter.
Republic of the Philippines The NLRC found the herein private respondents constructively dismissed and ordered
SUPREME COURT Radon Security to pay them their separation pay, in lieu of reinstatement with backwages,
Manila as well as their monetary benefits limited to three years, plus attorney’s fees equivalent to
SECOND DIVISION 10% of the entire amount, with Radon Security and Ever Emporium, Inc. adjudged jointly
G.R. No. 151133             June 30, 2008 and severally liable.
AFP GENERAL INSURANCE CORPORATION, petitioner,
vs. Radon Security duly moved for reconsideration, but this was denied by the NLRC in its
NOEL MOLINA, JUANITO ARQUEZA, LEODY VENANCIO, JOSE OLAT, ANGEL CORTEZ, Resolution dated June 22, 1998.
PANCRASIO SIMPAO, CONRADO CALAPON AND NATIONAL LABOR RELATIONS
COMMISSION (FIRST DIVISION), respondents. Radon Security then filed a Petition for Certiorari docketed as G.R. No. 134891 with this
Court, but we dismissed this petition in our Resolution of August 31, 1998.
DECISION
QUISUMBING, J.:
This is a petition for review on certiorari of the Decision 1 dated August 20, 2001 of the When the Decision dated April 6, 1998 of the NLRC became final and executory, private
Court of Appeals in CA-G.R. SP No. 58763 which dismissed herein petitioner’s special civil respondents filed an Urgent Motion for Execution. As a result, the NLRC Research and
action for certiorari. Before the appellate court, petitioner AFP General Insurance Information Unit submitted a Computation of the Monetary Awards in accordance with
Corporation (AFPGIC) sought to reverse the Resolution 2 dated October 5, 1999 of the the NLRC decision. Radon Security opposed said computation in its Motion for
National Labor Relations Commission (NLRC) in NLRC NCR CA-011705-96 for having been Recomputation.
issued with grave abuse of discretion. The NLRC affirmed the Order 3 dated March 30, 1999
of Labor Arbiter Edgardo Madriaga in NLRC NCR Case No. 02-00672-90 which had denied On February 5, 1999, the Labor Arbiter issued a Writ of Execution 5 incorporating the
AFPGIC’s Omnibus Motion to Quash Notice/Writ of Garnishment and Discharge AFPGIC’s computation of the NLRC Research and Information Unit. That same date, the Labor
appeal bond for failure of Radon Security & Allied Services Agency (Radon Security) to pay Arbiter dismissed the Motion for Recomputation filed by Radon Security. By virtue of the
the premiums on said bond. Equally challenged is the Resolution 4 dated December 14,
writ of execution, the NLRC Sheriff issued a Notice of Garnishment 6 against AFPGIC then moved for reconsideration, but the NLRC denied the motion in its
the supersedeas bond. Resolution12 dated February 29, 2000.

Both Ever Emporium, Inc. and Radon Security moved to quash the writ of execution. AFPGIC then filed a special civil action for certiorari, docketed as CA-G.R. SP No. 58763,
with the Court of Appeals, on the ground that the NLRC committed a grave abuse of
On March 30, 1999, the Labor Arbiter denied both motions, and Radon Security appealed discretion in affirming the Order dated March 30, 1999 of the Labor Arbiter.
to the NLRC.
On August 20, 2001, the appellate court dismissed CA-G.R. SP No. 58763, disposing as
On April 14, 1999, AFPGIC entered the fray by filing before the Labor Arbiter an Omnibus follows:
Motion to Quash Notice/Writ of Garnishment and to Discharge AFPGIC’s Appeal Bond on
the ground that said bond "has been cancelled and thus non-existent in view of the failure WHEREFORE, the foregoing considered, the petition is denied due course and
of Radon Security to pay the yearly premiums."7 accordingly DISMISSED. SO ORDERED.13

On April 30, 1999, the Labor Arbiter denied AFPGIC’s Omnibus Motion for lack of AFPGIC seasonably moved for reconsideration, but this was denied by the appellate court
merit.8 The Labor Arbiter pointed out that the question of non-payment of premiums is a in its Resolution14 of December 14, 2001.
dispute between the party who posted the bond and the insurer; to allow the bond to be
cancelled because of the non-payment of premiums would result in a factual and legal Hence, the instant case anchored on the lone assignment of error that:
absurdity wherein a surety will be rendered nugatory by the simple expedient of non-
payment of premiums.
THE COURT OF APPEALS SERIOUSLY ERRED IN SUSTAINING THE PUBLIC RESPONDENT
NLRC ALTHOUGH THE LATTER GRAVELY ABUSED ITS DISCRETION WHEN IT ARBITRARILY
The petitioner then appealed the Labor Arbiter’s order to the NLRC. The appeals of Radon IGNORED THE FACT THAT SUBJECT APPEAL BOND WAS ALREADY CANCELLED FOR NON-
Security and AFPGIC were jointly heard as NLRC NCR CA-011705-96. PAYMENT OF PREMIUM AND THUS IT COULD NOT BE SUBJECT OF EXECUTION OR
GARNISHMENT.15
On October 5, 1999, the NLRC disposed of NLRC NCR CA-011705-96 in this wise:
The petitioner contends that under Section 64 16 of the Insurance Code, which is deemed
WHEREFORE, premises considered, the appeals under consideration are hereby written into every insurance contract or contract of surety, an insurer may cancel a policy
DISMISSED for lack of merit. upon non-payment of the premium. Said cancellation is binding upon the beneficiary as
the right of a beneficiary is subordinate to that of the insured. Petitioner points out that
SO ORDERED.9 in South Sea Surety & Insurance Co., Inc. v. CA, 17 this Court held that payment of premium
is a condition precedent to and essential for the efficaciousness of a contract of
insurance.18 Hence, following UCPB General Ins. Co., Inc. v. Masagana Telamart, Inc., 19 no
In dismissing the appeal of AFPGIC, the NLRC pointed out that AFPGIC’s theory that the insurance policy, other than life, issued originally or on renewal is valid and binding until
bond cannot anymore be proceeded against for failure of Radon Security to pay the actual payment of the premium. 20 The petitioner also points to Malayan Insurance Co.,
premium is untenable, considering that the bond is effective until the finality of the Inc. v. Cruz Arnaldo,21 which reiterated that an insurer may cancel an insurance policy for
decision.10 The NLRC stressed that a contrary ruling would allow respondents to simply non-payment of premium.22 Hence, according to petitioner, the Court of Appeals
stop paying the premium to frustrate satisfaction of the money judgment. 11 committed a reversible error in not holding that under Section 77 23 of the Insurance Code,
the surety bond between it and Radon Security was not valid and binding for non-
payment of premiums, even as against a third person who was intended to benefit forego paying premiums on their surety bond in order to evade payment of the monetary
therefrom. judgment. The Court cannot be a party to any such iniquity.

The private respondents adopted in toto the ratiocinations of the Court of Appeals that Moreover, the Insurance Code supports the private respondents’ arguments. The
inasmuch as a supersedeas bond was posted for the benefit of a third person to guarantee petitioner’s reliance on Sections 64 and 77 of the Insurance Code is misplaced. The said
that the money judgment will be satisfied in case it is affirmed on appeal, the third person provisions refer to insurance contracts in general. The instant case pertains to a surety
who stands to benefit from said bond is entitled to notice of its cancellation for any bond; thus, the applicable provision of the Insurance Code is Section 177, 31 which
reason. Likewise, the NLRC should have been notified to enable it to take the proper specifically governs suretyship. It provides that a surety bond, once accepted by the
action under the circumstances. The respondents submit that from its very nature, obligee becomes valid and enforceable, irrespective of whether or not the premium has
a supersedeas bond remains effective and the surety liable thereon until formally been paid by the obligor. The private respondents, the obligees here, accepted the bond
discharged from said liability. To hold otherwise would enable a losing party to frustrate a posted by Radon Security and issued by the petitioner. Hence, the bond is both valid and
money judgment by the simple expedient of ceasing to pay premiums. enforceable. A verbis legis non est recedendum (from the language of the law there must
be no departure).32
We find merit in the submissions of the private respondents.
When petitioner surety company cancelled the surety bond because Radon Security failed
The controversy before the Court involves more than just the mere application of the to pay the premiums, it gave due notice to the latter but not to the NLRC. By its failure to
provisions of the Insurance Code to the factual circumstances. This instant case, after all, give notice to the NLRC, AFPGIC failed to acknowledge that the NLRC had jurisdiction not
traces its roots to a labor controversy involving illegally dismissed workers. It thus entails only over the appealed case, but also over the appeal bond. This oversight amounts to
the application of labor laws and regulations. Recall that the heart of the dispute is not an disrespect and contempt for a quasi-judicial agency tasked by law with resolving labor
ordinary contract of property or life insurance, but an appeal bond required by both disputes. Until the surety is formally discharged, it remains subject to the jurisdiction of
substantive and adjective law in appeals in labor disputes, specifically Article 223 24 of the the NLRC.
Labor Code, as amended by Republic Act No. 6715, 25 and Rule VI, Section 626 of the
Revised NLRC Rules of Procedure. Said provisions mandate that in labor cases where the Our ruling, anchored on concern for the employee, however, does not in any way seek to
judgment appealed from involves a monetary award, the appeal may be perfected only derogate the rights and interests of the petitioner as against Radon Security. The former is
upon the posting of a cash or surety bond issued by a reputable bonding company not devoid of remedies against the latter. Under Section 176 33 of the Insurance Code, the
accredited by the NLRC.27 The perfection of an appeal by an employer "only" upon the liability of petitioner and Radon Security is solidary in nature. There is solidary liability only
posting of a cash or surety bond clearly and categorically shows the intent of the when the obligation expressly so states, or when the law so provides, or when the nature
lawmakers to make the posting of a cash or surety bond by the employer to be the of the obligation so requires. 34 Since the law provides that the liability of the surety
exclusive means by which an employer’s appeal may be perfected. 28 Additionally, the filing company and the obligor or principal is joint and several, then either or both of them may
of a cash or surety bond is a jurisdictional requirement in an appeal involving a money be proceeded against for the money award.
judgment to the NLRC.29 In addition, Rule VI, Section 6 of the Revised NLRC Rules of
Procedure is a contemporaneous construction of Article 223 by the NLRC. As an The Labor Arbiter directed the NLRC Sheriff to garnish the surety bond issued by the
interpretation of a law by the implementing administrative agency, it is accorded great petitioner. The latter, as surety, is mandated to comply with the writ of garnishment, for
respect by this Court.30 Note that Rule VI, Section 6 categorically states that the cash or as earlier pointed out, the bond remains enforceable and under the jurisdiction of the
surety bond posted in appeals involving monetary awards in labor disputes "shall be in NLRC until it is discharged. In turn, the petitioner may proceed to collect the amount it
effect until final disposition of the case." This could only be construed to mean that the paid on the bond, plus the premiums due and demandable, plus any interest owing from
surety bond shall remain valid and in force until finality and execution of judgment, with Radon Security. This is pursuant to the principle of subrogation enunciated in Article
the resultant discharge of the surety company only thereafter, if we are to give teeth to 206735 of the Civil Code which we apply to the suretyship agreement between AFPGIC and
the labor protection clause of the Constitution. To construe the provision any other way Radon Security, in accordance with Section 178 36 of the Insurance Code. Finding no
would open the floodgates to unscrupulous and heartless employers who would simply
reversible error committed by the Court of Appeals in CA-G.R. SP No. 58763, we sustain The documents essential for the credit facility and submitted for this purpose were the (a)
the challenged decision. Board Resolution or excerpts of the Board of Directors Meeting, duly ratified by a Notary
Public, authorizing the loan and security arrangement as well as designating the officers to
WHEREFORE, the instant petition is DENIED for lack of merit. The assailed Decision dated negotiate and sign for FBPC specifically stating authority to mortgage, pledge and/or
August 20, 2001 of the Court of Appeals in CA-G.R. SP No. 58763 and the Resolution dated assign the properties of the corporation; (b) agreement to purchase Domestic Bills; and,
December 14, 2001, of the appellate court denying the herein petitioner’s motion for (c) Continuing Guaranty for any and all amounts signed by petitioner-spouses Luis Toh and
reconsideration are AFFIRMED. Costs against the petitioner. Vicky Tan Toh, and respondent-spouses Kenneth and Ma. Victoria Ng Li. 4 The spouses Luis
Toh and Vicky Tan Toh were then Chairman of the Board and Vice-President, respectively,
of FBPC, while respondent-spouses Kenneth Ng Li and Ma. Victoria Ng Li were President
SO ORDERED. and General Manager, respectively, of the same corporation. 5

It is not disputed that the credit facility as well as its terms and conditions was not
cancelled or terminated, and that there was no prior notice of such fact as required in the
"letter-advise," if any was done.

On 10 May 1993, more than thirty (30) days from date of the "letter-advise," petitioner-
spouses Luis Toh and Vicky Tan Toh and respondent-spouses Kenneth Ng Li and Ma.
Victoria Ng Li signed the required Continuing Guaranty, which was embodied in a public
document prepared solely by respondent Bank. 6 The terms of the instrument defined the
contract arising therefrom as a surety agreement and provided for the solidary liability of
the signatories thereto for and in consideration of "loans or advances" and "credit in any
other manner to, or at the request or for the account" of FBPC.

The Continuing Guaranty set forth no maximum limit on the indebtedness that
SECOND DIVISION respondent FBPC may incur and for which the sureties may be liable, stating that the
G.R. No. 154183            August 7, 2003 credit facility "covers any and all existing indebtedness of, and such other loans and credit
SPOUSES VICKY TAN TOH and LUIS TOH, petitioners, facilities which may hereafter be granted to FIRST BUSINESS PAPER CORPORATION." The
vs. surety also contained a de facto acceleration clause if "default be made in the payment of
SOLID BANK CORPORATION, FIRST BUSINESS PAPER CORPORATION, KENNETH NG LI and any of the instruments, indebtedness, or other obligation" guaranteed by petitioners and
MA. VICTORIA NG LI, respondents. respondents. So as to strengthen this security, the Continuing Guaranty waived rights of
BELLOSILLO, J.: the sureties against delay or absence of notice or demand on the part of respondent Bank,
and gave future consent to the Bank's action to "extend or change the time payment,
and/or the manner, place or terms of payment," including renewal, of the credit facility or
RESPONDENT SOLID BANK CORPORATION AGREED TO EXTEND an "omnibus line" credit
any part thereof in such manner and upon such terms as the Bank may deem proper
facility worth P10 million in favor of respondent First Business Paper Corporation (FBPC).
without notice to or further assent from the sureties.
The terms and conditions of the agreement as well as the checklist of documents
necessary to open the credit line were stipulated in a "letter-advise" of the Bank dated 16
May 1993 addressed to FBPC and to its President, respondent Kenneth Ng Li. 1 The "letter- The effectivity of the Continuing Guaranty was not contingent upon any event or cause
advise"2 was effective upon "compliance with the documentary requirements." 3 other than the written revocation thereof with notice to the Bank that may be executed
by the sureties.
On 16 June 1993 respondent FBPC started to avail of the credit facility and procure letters Petitioner-spouses however could not be certain whether to deny or admit the due
of credit.7 On 17 November 1993 FBPC opened thirteen (13) letters of credit and obtained execution and authenticity of the Continuing Guaranty. 21 They could only allege that they
loans totaling P15,227,510.00.8 As the letters of credit were secured, FBPC through its were made to sign papers in blank and the Continuing Guaranty could have been one of
officers Kenneth Ng Li, Ma. Victoria Ng Li and Redentor Padilla as signatories executed a them.
series of trust receipts over the goods allegedly purchased from the proceeds of the
loans.9 Still, as petitioners asserted, it was impossible and absurd for them to have freely and
consciously executed the surety on 10 May 1993, the date appearing on its face 22 since
On 13 January 1994 respondent Bank received information that respondent-spouses beginning March of that year they had already divested their shares in FBPC and assigned
Kenneth Ng Li and Ma. Victoria Ng Li had fraudulently departed from their conjugal them in favor of respondent Kenneth Ng Li although the deeds of assignment were
home.10 On 14 January 1994 the Bank served a demand letter upon FBPC and petitioner notarized only on 14 June 1993. 23 Petitioners also contended that through FBPC Board
Luis Toh invoking the acceleration clause 11 in the trust receipts of FBPC and claimed Resolution dated 12 May 1993 petitioner Luis Toh was removed as an authorized
payment for P10,539,758.68 as unpaid overdue accounts on the letters of credit plus signatory for FBPC and replaced by respondent-spouses Kenneth Ng Li and Ma. Victoria Ng
interests and penalties within twenty-four (24) hours from receipt thereof. 12 The Bank also Li and Redentor Padilla for all the transactions of FBPC with respondent Bank. 24 They even
invoked the Continuing Guaranty executed by petitioner-spouses Luis Toh and Vicky Tan resigned from their respective positions in FBPC as reflected in the 12 June 1993
Toh who were the only parties known to be within national jurisdiction to answer as Secretary's Certificate submitted to the Securities and Exchange Commission 25 as
sureties for the credit facility of FBPC.13 petitioner Luis Toh was succeeded as Chairman by respondent Ma. Victoria Ng Li, while
one Mylene C. Padilla took the place of petitioner Vicky Tan Toh as Vice-President. 26
On 17 January 1994 respondent Bank filed a complaint for sum of money with ex parte
application for a writ of preliminary attachment against FBPC, spouses Kenneth Ng Li and Finally, petitioners averred that sometime in June 1993 they obtained from respondent
Ma. Victoria Ng Li, and spouses Luis Toh and Vicky Tan Toh, docketed as Civil Case No. Kenneth Ng Li their exclusion from the several surety agreements they had entered into
64047 of RTC-Br. 161, Pasig City. 14 Alias summonses were served upon FBPC and spouses with different banks, i.e., Hongkong and Shanghai Bank, China Banking Corporation, Far
Luis Toh and Vicky Tan Toh but not upon Kenneth Ng Li and Ma. Victoria Ng Li who had East Bank and Trust Company, and herein respondent Bank. 27 As a matter of record, these
apparently absconded.15 other banks executed written surety agreements that showed respondent Kenneth Ng Li
as the only surety of FBPC's indebtedness.28
Meanwhile, with the implementation of the writ of preliminary attachment resulting in
the impounding of purported properties of FBPC, the trial court was deluged with third- On 16 May 1996 the trial court promulgated its Decision in Civil Case No. 64047 finding
party claims contesting the propriety of the attachment. 16 In the end, the Bank respondent FBPC liable to pay respondent Solid Bank Corporation the principal of
relinquished possession of all the attached properties to the third-party claimants except P10,539,758.68 plus twelve percent (12%) interest per annum from finality of
for two (2) insignificant items as it allegedly could barely cope with the yearly premiums the Decision until fully paid, but absolving petitioner-spouses Luis Toh and Vicky Tan Toh
on the attachment bonds.17 of any liability to respondent Bank. 29 The court a quo found that petitioners "voluntarily
affixed their signature[s]" on the Continuing Guaranty and were thus "at some given point
Petitioner-spouses Luis Toh and Vicky Tan Toh filed a joint answer to the complaint where in time willing to be liable under those forms," 30 although it held that petitioners were not
they admitted being part of FBPC from its incorporation on 29 August 1991, which was bound by the surety contract since the letters of credit it was supposed to secure were
then known as "MNL Paper, Inc.," until its corporate name was changed to "First Business opened long after petitioners had ceased to be part of FBPC. 31
Paper Corporation."18 They also acknowledged that on 6 March 1992 Luis Toh was
designated as one of the authorized corporate signatories for transactions in relation to The trial court described the Continuing Guaranty as effective only while petitioner-
FBPC's checking account with respondent Bank. 19 Meanwhile, for failing to file an answer, spouses were stockholders and officers of FBPC since respondent Bank compelled
respondent FBPC was declared in default.20 petitioners to underwrite FBPC's indebtedness as sureties without the requisite
investigation of their personal solvency and capability to undertake such risk. 32 The lower
court also believed that the Bank knew of petitioners' divestment of their shares in FBPC Petitioner-spouses moved for reconsideration of the Decision, and after respondent
and their subsequent resignation as officers thereof as these facts were obvious from the Bank's comment, filed a lengthy Reply with Motion for Oral Argument.43 On 2 July 2002
numerous public documents that detailed the changes and substitutions in the list of reconsideration of the Decision was denied on the ground that no new matter was raised
authorized signatories for transactions between FBPC and the Bank, including the many to warrant the reversal or modification thereof. 44 Hence, this Petition for Review.
trust receipts being signed by persons other than petitioners, 33 as well as the designation
of new FBPC officers which came to the notice of the Bank's Vice-President Jose Chan Jr. Petitioner-spouses Luis Toh and Vicky Tan Toh argue that the Court of Appeals denied
and other officers.34 them due process when it did not grant their motion for reconsideration and without
"bother[ing] to consider [their] Reply with Motion for Oral Argument." They maintain that
On 26 September 1996 the RTC-Br. 161 of Pasig City denied reconsideration of its the Continuing Guaranty is not legally valid and binding against them for having been
Decision.35 executed long after they had withdrawn from FBPC. Lastly, they claim that the surety
agreement has been extinguished by the material alterations thereof and of the "letter-
On 9 October 1996 respondent Bank appealed the Decision to the Court of Appeals, advise" which were allegedly brought about by (a) the provision of an acceleration clause
docketed as CA-G.R. CV No. 55957.36 Petitioner-spouses did not move for reconsideration in the trust receipts; (b) the flight of their co-sureties, respondent-spouses Kenneth Ng Li
nor appeal the finding of the trial court that they voluntarily executed the Continuing and Ma. Victoria Ng Li; (c) the grant of credit facility despite the non-payment of marginal
Guaranty. deposits in an amount beyond the credit limit of P10 million pesos; (d) the inordinate
delay of the Bank in demanding the payment of the indebtedness; (e) the presence of
ghost deliveries and fictitious purchases using the Bank's letters of credit and trust
The appellate court modified the Decision of the trial court and held that by signing the receipts; (f) the extension of the due dates of the letters of credit without the required
Continuing Guaranty, petitioner-spouses became solidarily liable with FBPC to pay 25% partial payment per extension; (g) the approval of another letter of credit, L/C 93-
respondent Bank the amount of P10,539,758.68 as principal with twelve percent (12%) 0042, even after respondent-spouses Kenneth Ng Li and Ma. Victoria Ng Li had defaulted
interest per annum from finality of the judgment until completely paid. 37 The Court of on their previous obligations; and, (h) the unmistakable pattern of fraud.
Appeals ratiocinated that the provisions of the surety agreement did not "indicate that
Spouses Luis and Vicky Toh x x x signed the instrument in their capacities as Chairman of
the Board and Vice-President, respectively, of FBPC only." 38 Hence, the court a quo Respondent Solid Bank maintains on the other hand that the appellate court is presumed
deduced, "[a]bsent any such indication, it was error for the trial court to have presumed to have passed upon all points raised by petitioners' Reply with Motion for Oral
that the appellees indeed signed the same not in their personal capacities." 39 The Argument as this pleading formed part of the records of the appellate court. It also
appellate court also ruled that as petitioners failed to execute any written revocation of debunks the claim of petitioners that they were inexperienced and ignorant parties who
the Continuing Guaranty with notice to respondent Bank, the instrument remained in full were taken advantage of in the Continuing Guaranty since petitioners are astute
force and effect when the letters of credit were availed of by respondent FBPC. 40 businessmen who are very familiar with the "ins" and "outs" of banking practice. The Bank
further argues that the notarization of the Continuing Guaranty discredits the
uncorroborated assertions against the authenticity and due execution thereof, and that
Finally, the Court of Appeals rejected petitioners' argument that there were "material the Decision of the trial court in the civil case finding the surety agreement to be valid and
alterations" in the provisions of the "letter-advise," i.e., that only domestic letters of credit binding is now res judicata for failure of petitioners to appeal therefrom. As a final point,
were opened when the credit facility was for importation of papers and other materials, the Bank refers to the various waivers made by petitioner-spouses in the Continuing
and that marginal deposits were not paid, contrary to the requirements stated in the Guaranty to justify the extension of the due dates of the letters of credit.
"letter-advise." 41 The simple response of the appellate court to this challenge was, first,
the "letter-advise" itself authorized the issuance of domestic letters of credit, and second,
the several waivers extended by petitioners in the Continuing Guaranty, which included To begin with, we find no merit in petitioners' claim that the Court of Appeals deprived
changing the time and manner of payment of the indebtedness, justified the action of them of their right to due process when the court a quo did not address specifically and
respondent Bank not to charge marginal deposits. 42 explicitly their Reply with Motion for Oral Argument. While the Resolution of the appellate
court of 2 July 2002 made no mention thereof in disposing of their arguments on
reconsideration, it is presumed that "all matters within an issue raised in a case were laid
before the court and passed upon it." 45 In the absence of evidence to the contrary, we But as we bind the spouses Luis Toh and Vicky Tan Toh to the surety agreement they
must rule that the court a quo discharged its task properly. Moreover, a reading of the signed so must we also hold respondent Bank to its representations in the "letter-advise"
assailed Resolution clearly makes reference to a "careful review of the records," which of 16 May 1993. Particularly, as to the extension of the due dates of the letters of credit,
undeniably includes the Reply with Motion for Oral Argument, hence there is no reason we cannot exclude from the Continuing Guaranty the preconditions of the Bank that were
for petitioners to asseverate otherwise. plainly stipulated in the "letter-advise." Fairness and justice dictate our doing so, for the
Bank itself liberally applies the provisions of cognate agreements whenever convenient to
This Court holds that the Continuing Guaranty is a valid and binding contract of petitioner- enforce its contractual rights, such as, when it harnessed a provision in the trust receipts
spouses as it is a public document that enjoys the presumption of authenticity and due executed by respondent FBPC to declare its entire indebtedness as due and demandable
execution. Although petitioners as appellees may raise issues that have not been assigned and thereafter to exact payment thereof from petitioners as sureties. 49 In the same
as errors by respondent Bank as party-appellant, i.e., unenforceability of the surety manner, we cannot disregard the provisions of the "letter-advise" in sizing up the panoply
contract, we are bound by the consistent finding of the courts a quo that petitioner- of commercial obligations between the parties herein.
spouses Luis Toh and Vicky Tan Toh "voluntarily affixed their signature[s]" on the surety
agreement and were thus "at some given point in time willing to be liable under those Insofar as petitioners stipulate in the Continuing Guaranty that respondent Bank "may at
forms."46 In the absence of clear, convincing and more than preponderant evidence to the any time, or from time to time, in [its] discretion x x x extend or change the time
contrary, our ruling cannot be otherwise. payment," this provision even if understood as a waiver is confined per se to the grant of
an extension and does not surrender the prerequisites therefor as mandated in the
Similarly, there is no basis for petitioners to limit their responsibility thereon so long as "letter-advise." In other words, the authority of the Bank to defer collection contemplates
they were corporate officers and stockholders of FBPC. Nothing in the Continuing only authorized extensions, that is, those that meet the terms of the "letter-advise."
Guaranty restricts their contractual undertaking to such condition or eventuality. In fact
the obligations assumed by them therein subsist "upon the undersigned, the heirs, Certainly, while the Bank may extend the due date at its discretion pursuant to the
executors, administrators, successors and assigns of the undersigned, and shall inure to Continuing Guaranty, it should nonetheless comply with the requirements that domestic
the benefit of, and be enforceable by you, your successors, transferees and assigns," and letters of credit be supported by fifteen percent (15%) marginal deposit extendible three
that their commitment "shall remain in full force and effect until written notice shall have (3) times for a period of thirty (30) days for each extension, subject to twenty-five percent
been received by [the Bank] that it has been revoked by the undersigned." Verily, if (25%) partial payment per extension. This reading of the Continuing Guaranty is consistent
petitioners intended not to be charged as sureties after their withdrawal from FBPC, they with Philippine National Bank v. Court of Appeals 50 that any doubt on the terms and
could have simply terminated the agreement by serving the required notice of revocation conditions of the surety agreement should be resolved in favor of the surety.
upon the Bank as expressly allowed therein.47 In Garcia v. Court of Appeals[48] we ruled –
Furthermore, the assurance of the sureties in the Continuing Guaranty that "[n]o act or
Regarding the petitioner's claim that he is liable only as a corporate officer of WMC, the omission of any kind on [the Bank's] part in the premises shall in any event affect or impair
surety agreement shows that he signed the same not in representation of WMC or as its this guaranty" 51 must also be read "strictissimi juris" for the reason that petitioners are
president but in his personal capacity. He is therefore personally bound. There is no law only accommodation sureties, i.e., they received nothing out of the security contract they
that prohibits a corporate officer from binding himself personally to answer for a signed.52 Thus said, the acts or omissions of the Bank conceded by petitioners as not
corporate debt. While the limited liability doctrine is intended to protect the stockholder affecting nor impairing the surety contract refer only to those occurring "in the premises,"
by immunizing him from personal liability for the corporate debts, he may nevertheless or those that have been the subject of the waiver in the Continuing Guaranty, and stretch
divest himself of this protection by voluntarily binding himself to the payment of the to no other. Stated otherwise, an extension of the period for enforcing the indebtedness
corporate debts. The petitioner cannot therefore take refuge in this doctrine that he has does not by itself bring about the discharge of the sureties unless the extra time is not
by his own acts effectively waived. permitted within the terms of the waiver, i.e., where there is no payment or there is
deficient settlement of the marginal deposit and the twenty-five percent (25%)
consideration, in which case the illicit extension releases the sureties. Under Art. 2055 of
the Civil Code, the liability of a surety is measured by the terms of his contract, and while
he is liable to the full extent thereof, his accountability is strictly limited to that assumed A:         Whenever this obligation becomes due and demandable except when you roll it
by its terms. over so there is novation there on the original obligations55  (underscoring supplied).

It is admitted in the Complaint of respondent Bank before the trial court that several As a result of these illicit extensions, petitioner-spouses Luis Toh and Vicky Tan Toh are
letters of credit were irrevocably extended for ninety (90) days with alarmingly flawed and relieved of their obligations as sureties of respondent FBPC under Art. 2079 of the Civil
inadequate consideration - the indispensable marginal deposit of fifteen percent (15%) Code.
and the twenty-five percent (25%) prerequisite for each extension of thirty (30) days. It
bears stressing that the requisite marginal deposit and security for every thirty (30) - day Further, we note several suspicious circumstances that militate against the enforcement
extension specified in the "letter-advise" were not set aside or abrogated nor was there of the Continuing Guaranty against the accommodation sureties. Firstly, the guaranty was
any prior notice of such fact, if any was done. executed more than thirty (30) days from the original acceptance period as required in the
"letter-advise." Thereafter, barely two (2) days after the Continuing Guaranty was signed,
Moreover, these irregular extensions were candidly admitted by Victor Ruben L. Tuazon, corporate agents of FBPC were replaced on 12 May 1993 and other adjustments in the
an account officer and manager of respondent Bank and its lone witness in the civil case – corporate structure of FBPC ensued in the month of June 1993, which the Bank did not
investigate although such were made known to it.
Q:         You extended it even if there was no marginal deposit?
A:         Yes. By the same token, there is no explanation on record for the utter worthlessness of the
Q:         And even if partial payment is less than 25%? trust receipts in favor of the Bank when these documents ought to have added more
A:         Yes x x x x security to the indebtedness of FBPC. The Bank has in fact no information whether the
Q:         You have repeatedly extended despite the insufficiency partial payment trust receipts were indeed used for the purpose for which they were obtained. 56 To be
requirement? sure, the goods subject of the trust receipts were not entirely lost since the security officer
A:         I would say yes.53 of respondent Bank who conducted surveillance of FBPC even had the chance to intercept
the surreptitious transfer of the items under trust: "We saw two (2) delivery vans with
The foregoing extensions of the letters of credit made by respondent Bank without Plates Nos. TGH 257 and PAZ 928 coming out of the compound x x x [which were] taking
observing the rigid restrictions for exercising the privilege are not covered by the waiver out the last supplies stored in the compound." 57 In addition, the attached properties of
stipulated in the Continuing Guaranty. Evidently, they constitute illicit extensions FBPC, except for two (2) of them, were perfunctorily abandoned by respondent Bank
prohibited under Art. 2079 of the Civil Code, "[a]n extension granted to the debtor by the although the bonds therefor were considerably reduced by the trial court. 58
creditor without the consent of the guarantor extinguishes the guaranty." This act of the
Bank is not mere failure or delay on its part to demand payment after the debt has The consequence of these omissions is to discharge the surety, petitioners herein, under
become due, as was the case in unpaid five (5) letters of credit which the Bank did not Art. 2080 of the Civil Code,59 or at the very least, mitigate the liability of the surety up to
extend, defer or put off, 54 but comprises conscious, separate and binding agreements to the value of the property or lien released –
extend the due date, as was admitted by the Bank itself –
If the creditor x x x has acquired a lien upon the property of a principal, the creditor at
Q:         How much was supposed to be paid on 14 September 1993, the original LC of once becomes charged with the duty of retaining such security, or maintaining such lien in
P1,655,675.13? the interest of the surety, and any release or impairment of this security as a primary
A:         Under LC 93-0017 first matured on 14 September 1993. We rolled it over, resource for the payment of a debt, will discharge the surety to the extent of the value of
extended it to December 13, 1993 but they made partial payment that is why we the property or lien released x x x x [for] there immediately arises a trust relation between
extended it. the parties, and the creditor as trustee is bound to account to the surety for the value of
Q:         The question to you now is how much was paid? How much is supposed to be paid the security in his hands.60
on September 14, 1993 on the basis of the original amount of P1,655,675.13?
For the same reason, the grace period granted by respondent Bank represents SO ORDERED.
unceremonious abandonment and forfeiture of the fifteen percent (15%) marginal deposit
and the twenty-five percent (25%) partial payment as fixed in the "letter-advise." These
payments are unmistakably additional securities intended to protect both respondent
Bank and the sureties in the event that the principal debtor FBPC becomes insolvent
during the extension period. Compliance with these requisites was not waived by
petitioners in the Continuing Guaranty. For this unwarranted exercise of discretion,
respondent Bank bears the loss; due to its unauthorized extensions to pay granted to
FBPC, petitioner-spouses Luis Toh and Vicky Tan Toh are discharged as sureties under the
Continuing Guaranty.

Finally, the foregoing omission or negligence of respondent Bank in failing to safe-keep


the security provided by the marginal deposit and the twenty-five percent (25%)
requirement results in the material alteration of the principal contract, i.e., the "letter-
advise," and consequently releases the surety. 61 This inference was admitted by the Bank
through the testimony of its lone witness that "[w]henever this obligation becomes due
and demandable, except when you roll it over, (so) there is novation there on the original
obligations." As has been said, "if the suretyship contract was made upon the condition
that the principal shall furnish the creditor additional security, and the security being
furnished under these conditions is afterwards released by the creditor, the surety is
wholly discharged, without regard to the value of the securities released, for such a
transaction amounts to an alteration of the main contract." 62

WHEREFORE, the instant Petition for Review is GRANTED. The Decision of the Court of
Appeals dated 12 December 2001 in CA-G.R. CV No. 55957, Solid Bank Corporation v. First
Business Paper Corporation, Kenneth Ng Li, Ma. Victoria Ng Li, Luis Toh and Vicky Tan Toh,
holding petitioner-spouses Luis Toh and Vicky Tan Toh solidarily liable with First Business
Paper Corporation to pay Solid Bank Corporation the amount of P10,539,758.68 as
principal with twelve percent (12%) interest per annum until fully paid, and its Resolution
of 2 July 2002 denying reconsideration thereof are REVERSED and SET ASIDE.

The Decision dated 16 May 1996 of RTC-Br. 161 of Pasig City in Civil Case No. 64047, Solid
Bank Corporation v. First Business Paper Corporation, Kenneth Ng Li, Ma. Victoria Ng Li,
Luis Toh and Vicky Tan Toh, finding First Business Paper Corporation liable to pay
respondent Solid Bank Corporation the principal of P10,539,758.68 plus twelve percent
(12%) interest per annum until fully paid, but absolving petitioner-spouses Luis Toh and
Vicky Tan Toh of any liability to respondent Solid Bank Corporation is REINSTATED and
AFFIRMED. No costs.
PHILIPPINE EXPORT and FOREIGN LOAN GUARANTEE CORPORATION, Respondent.

DECISION
TINGA, J.:

Before us are consolidated petitions questioning the Decision1 of the Court of Appeals


(CA) in CA-G.R. CV No. 61318, entitled Philippine Export and Foreign Loan Guarantee
Corporation v. JN Development Corporation, et al.,  which reversed the Decision of the
Regional Trial Court (RTC) of Makati, Branch 60.

On 13 December 1979, petitioner JN Development Corporation ("JN") and Traders Royal


Bank (TRB) entered into an agreement whereby TRB would extend to JN an Export Packing
Credit Line for Two Million Pesos (₱2,000,000.00). The loan was covered by several
securities, including a real estate mortgage 2 and a letter of guarantee from respondent
Philippine Export and Foreign Loan Guarantee Corporation ("PhilGuarantee"), now Trade
and Investment Development Corporation of the Philippines, covering seventy percent
(70%) of the credit line.3 With PhilGuarantee issuing a guarantee in favor of TRB, 4 JN,
petitioner spouses Rodrigo and Leonor Sta. Ana 5 and petitioner Narciso Cruz 6 executed
a Deed of Undertaking7 (Undertaking) to assure repayment to PhilGuarantee.

It appears that JN failed to pay the loan to TRB upon its maturity; thus, on 8 October 1980
TRB requested PhilGuarantee to make good its guarantee. 8 PhilGuarantee informed JN
about the call made by TRB, and inquired about the action of JN to settle the loan. 9 Having
received no response from JN, on 10 March 1981 PhilGuarantee paid TRB Nine Hundred
Thirty Four Thousand Eight Hundred Twenty Four Pesos and Thirty Four Centavos
(₱934,824.34).10 Subsequently, PhilGuarantee made several demands on JN, but the latter
failed to pay. On 30 May 1983, JN, through Rodrigo Sta. Ana, proposed to settle the
obligation "by way of development and sale" of the mortgaged property. 11 PhilGuarantee,
however, rejected the proposal.
Republic of the Philippines
SUPREME COURT PhilGuarantee thus filed a Complaint12 for collection of money and damages against
SECOND DIVISION herein petitioners.
G.R. No. 151060. August 31, 2005
JN DEVELOPMENT CORPORATION, and SPS. RODRIGO and LEONOR STA.
ANA, Petitioners, In its Decision dated 20 August 1998, the RTC dismissed PhilGuarantee’s Complaint as well
vs. as the counterclaim of petitioners. It ruled that petitioners are not liable to reimburse
PHILIPPINE EXPORT AND FOREIGN LOAN GUARANTEE CORPORATION, respondent. PhilGuarantee what it had paid to TRB. Crucial to this holding was the court’s finding that
G.R. No. 151311. August 31, 2005 TRB was able to foreclose the real estate mortgage executed by JN, thus extinguishing
NARCISO V. CRUZ, Petitioners, petitioners’ obligation.13 Moreover, there was no showing that after the said foreclosure,
vs. TRB had demanded from JN any deficiency or the payment of the difference between the
proceeds of the foreclosure sale and the actual loan. 14 In addition, the RTC held that since Petitioners sought reconsideration of the Decision  and prayed for the  admission of
PhilGuarantee’s guarantee was good for only one year from 17 December 1979, or until documents evidencing the foreclosure of the real estate mortgage, but the motion for
17 December 1980, and since it was not renewed after the expiry of said period, reconsideration was denied by the CA for lack of merit. The CA ruled that the
PhilGuarantee had no more legal duty to pay TRB on 10 March 1981. 15 The RTC likewise documentary evidence presented by petitioners cannot be considered as newly
ruled that Cruz cannot be held liable under the Undertaking since he was not the one who discovered evidence, it being already in existence while the case was pending before the
signed the document, in line with its finding that his signature found in the records is trial court, the very forum before which it should have been presented. Besides, a
totally different from the signature on the Undertaking. 16 foreclosure sale per se is not proof of petitioners’ payment of the loan to PhilGuarantee,
the CA added.27
According to the RTC, the failure of TRB to sue JN for the recovery of the loan precludes
PhilGuarantee from seeking recoupment from the spouses Sta. Ana and Cruz what it paid So now before the Court are the separate petitions for review of the CA Decision. JN and
to TRB. Thus, PhilGuarantee’s payment to TRB amounts to a waiver of its right under Art. the spouses Sta. Ana, petitioners in G.R. No. 151060, posit that the CA erred in
2058 of the Civil Code.17 interpreting Articles 2079, 2058, and 2059 of the Civil Code in its Decision.28 Meanwhile,
petitioner Narciso Cruz in G.R. No. 151311 claims that the CA erred when it held that
Aggrieved by the RTC Decision, PhilGuarantee appealed to the CA. The appellate court petitioners are liable to PhilGuarantee despite its payment after the expiration of its
reversed the RTC and ordered petitioners to pay PhilGuarantee Nine Hundred Thirty Four contract of guarantee and the lack of PhilGuarantee’s consent to the extensions granted
Thousand Six Hundred Twenty Four Pesos and Thirty Four Centavos (₱934,624.34), plus by TRB to JN. Moreover, Cruz questions the reversal of the ruling of the trial court anent
service charge and interest.18 his liability as a signatory to the Undertaking.29

In reaching its denouement, the CA held that the RTC’s finding that the loan was On the other hand, PhilGuarantee maintains that the date of default, not the actual date
extinguished by virtue of the foreclosure sale of the mortgaged property had no factual of payment, determines the liability of the guarantor and that having paid TRB when the
support,19 and that such finding is negated by Rodrigo Sta. Ana’s testimony that JN did not loan became due, it should be indemnified by petitioners. 30 It argues that, contrary to
receive any notice of foreclosure from PhilGuarantee or from TRB. 20 Moreover, Sta. Ana petitioners’ claim, there could be no waiver of its right to excussion more explicit than its
even offered the same mortgaged property to PhilGuarantee to settle its obligations with act of payment to TRB very directly.31 Besides, the right to excussion is for the benefit of
the latter.21 the guarantor and is not a defense for the debtor to raise and use to evade liability. 32 
Finally, PhilGuarantee maintains that there is no sufficient evidence proving the alleged
forgery of Cruz’s signature on the Undertaking, which is a notarized document and as such
The CA also ruled that JN’s obligation had become due and demandable within the one- must be accorded the presumption of regularity. 33
year period of effectivity of the guarantee; thus, PhilGuarantee’s payment to TRB
conformed with its guarantee, although the payment itself was effected one year after the
maturity date of the loan.22 Contrary to the trial court’s finding, the CA ruled that the The Court finds for PhilGuarantee.
contract of guarantee was not extinguished by the alleged lack of evidence on
PhilGuarantee’s consent to the extensions granted by TRB to JN. 23 Interpreting Art. 2058 Under a contract of guarantee, the guarantor binds himself to the creditor to fulfill the
of the Civil Code,24 the appellate court explained that while the provision states that the obligation of the principal debtor in case the latter should fail to do so. 34 The guarantor
guarantor cannot be compelled to pay unless the properties of the debtor are exhausted, who pays for a debtor, in turn, must be indemnified by the latter. 35 However, the
the guarantor is not precluded from waiving the benefit of excussion and paying the guarantor cannot be compelled to pay the creditor unless the latter has exhausted all the
obligation altogether.25 property of the debtor and resorted to all the legal remedies against the debtor. 36 This is
what is otherwise known as the benefit of excussion.
Finally, the CA found that Narciso Cruz was unable to prove the alleged forgery of his
signature in the Undertaking, the evidence presented not being sufficient to overcome the It is clear that excussion may only be invoked after legal remedies against the principal
presumption of regularity of the Undertaking which is a notarized document. 26 debtor have been expanded. Thus, it was held that the creditor must first obtain a
judgment against the principal debtor before assuming to run after the alleged guarantor, it is likewise waivable by the guarantor. Thus, even assuming that extensions were indeed
"for obviously the ‘exhaustion of the principal’s property’ cannot even begin to take place granted by TRB to JN, PhilGuarantee could have opted to waive the need for consent to
before judgment has been obtained."37 The law imposes conditions precedent for the such extensions. Indeed, a guarantor is not precluded from waiving his right to be notified
invocation of the defense. Thus, in order that the guarantor may make use of the benefit of or to give his consent to extensions obtained by the debtor. Such waiver is not contrary
of excussion, he must set it up against the creditor upon the latter’s demand for payment to public policy as it is purely personal and does not affect public interest. 41 In the instant
and point out to the creditor available property of the debtor within the Philippines case, PhilGuarantee’s waiver can be inferred from its actual payment to TRB after the
sufficient to cover the amount of the debt. 38 latter’s demand, despite JN’s failure to pay the renewal/guarantee fee as indicated in the
guarantee.42
While a guarantor enjoys the benefit of excussion, nothing prevents him from paying the
obligation once demand is made on him. Excussion, after all, is a right granted to him by For the above reasons, there is no basis for petitioner’s claim that PhilGuarantee was a
law and as such he may opt to make use of it or waive it. PhilGuarantee’s waiver of the mere volunteer payor and had no legal obligation to pay TRB. The law does not prohibit
right of excussion cannot prevent it from demanding reimbursement from petitioners. The the payment by a guarantor on his own volition, heedless of the benefit of excussion. In
law clearly requires the debtor to indemnify the guarantor what the latter has paid. 39 fact, it recognizes the right of a guarantor to recover what it has paid, even if payment
was made before the debt becomes due, 43 or if made without notice to the debtor, 44 
Petitioners’ claim that PhilGuarantee had no more obligation to pay TRB because of the subject of course to some conditions.
alleged expiration of the contract of guarantee is untenable. The guarantee, dated17
December 1979, states: Petitioners’ invocation of our ruling in Willex Plastic Industries, Corp. v. Court of Appeals 45 
is misplaced, if not irrelevant. In the said case, the guarantor claimed that it could not be
In the event of default by JNDC and as a consequence thereof, PHILGUARANTEE is made proceeded against without first exhausting all of the properties of the debtor. The Court,
to pay its obligation arising under the aforesaid guarantee PHILGUARANTEE shall pay the finding that there was an express renunciation of the benefit of excussion in the contract
BANK the amount of ₱1.4 million or 70% of the total obligation unpaid… of guarantee, ruled against the guarantor.

.... The cited case finds no application in the case a quo. PhilGuarantee is not invoking the
benefit of excussion. It cannot be overemphasized that excussion is a right granted to the
guarantor and, therefore, only he may invoke it at his discretion.
This guarantee shall be valid for a period of one (1) year from date hereof but may be
renewed upon payment by JNDC of the guarantee fee at the same rate of 1.5% per
annum.40 The benefit of excussion, as well as the requirement of consent to extensions of payment,
is a protective device pertaining to and conferred on the guarantor. These may be invoked
by the guarantor against the creditor as defenses to bar the unwarranted enforcement of
The guarantee was only up to 17 December 1980. JN’s obligation with TRB fell due on 30 the guarantee. However, PhilGuarantee did not avail of these defenses when it paid its
June 1980, and demand on PhilGuarantee was made by TRB on 08 October 1980. That obligation according to the tenor of the guarantee once demand was made on it. What is
payment was actually made only on 10 March 1981 does not take it out of the terms of peculiar in the instant case is that petitioners, the principal debtors themselves, are
the guarantee. What is controlling is that default and demand on PhilGuarantee had taken muddling the issues and raising the same defenses against the guarantor, which only the
place while the guarantee was still in force. guarantor may invoke against the creditor, to avoid payment of their own obligation to
the guarantor. The Court cannot countenance their self-seeking desire to be exonerated
There is likewise no merit in petitioners’ claim that PhilGuarantee’s failure to give its from the duty to reimburse PhilGuarantee after it had paid TRB on their behalf and to
express consent to the alleged extensions granted by TRB to JN had extinguished the unjustly enrich themselves at the expense of PhilGuarantee.
guarantee. The requirement that the guarantor should consent to any extension granted
by the creditor to the debtor under Art. 2079 is for the benefit of the guarantor. As such,
Petitioners assert that TRB’s alleged foreclosure of the real estate mortgage over the land The Court notes the letter 51 of Rodrigo Sta. Ana offering, by way of settlement of JN’s
executed as security for the loan agreement had extinguished PhilGuarantee’s obligation; obligations to PhilGuarantee, the very same parcel of land mortgaged as security for the
thus, PhilGuarantee’s recourse should be directed against TRB, as per the pari- loan agreement. This further weakens the position of petitioners, since it becomes
passu provision46 in the contract of guarantee. 47 We disagree. obvious that they acknowledged the payment made by PhilGuarantee on their behalf and
that they were in fact willing to negotiate with PhilGuarantee for the settlement of the
The foreclosure was made on 27 August 1993, "after the case was submitted for decision said obligation before the filing of the complaint a quo.
in 1992 and before the issuance of the decision of the court a quo in 1998". 48 Thus,
foreclosure was resorted to by TRB against JN when they both had become aware that Anent the issue of forgery, the CA is correct in reversing the decision of the trial court.
PhilGuarantee had already paid TRB and that there was a pending case filed by Save for the denial of Narciso Cruz that it was not his signature in the Undertaking and the
PhilGuarantee against petitioners. This matter was not raised and proved in the trial court, perfunctory comparison of the signatures, nothing in the records would support the claim
nor in the appeal before the CA, but raised for the first time in petitioners’ motion for of forgery. Forgery cannot be presumed and must be proved by clear, positive and
reconsideration in the CA. In their appellants’ Brief, petitioners claimed that "there was no convincing evidence and the burden of proof lies on the party alleging forgery. 52 Mere
need for the defendant-appellee JNDC to present any evidence before the lower court to denial will not suffice to overcome the positive value of the Undertaking, which is a
show that indeed foreclosure of the REM took place." 49 As properly held by the CA, notarized document, has in its favor the presumption of regularity, and carries the
evidentiary weight conferred upon it with respect to its due execution. 53 Even in cases
… Firstly, the documents evidencing foreclosure of mortgage cannot be considered as where the alleged forged signature was compared to samples of genuine signatures to
newly discovered evidence. The said documents were already subsisting and should have show its variance therefrom, this Court still found such evidence insufficient. 54 Mere
been presented during the trial of the case. The alleged foreclosure sale was made on variance of the signatures cannot be considered as conclusive proof that the same were
August 23, 1993 … while the decision was rendered by the trial court on August 20, 1998 forged.55
about five (5) years thereafter. These documents were likewise not submitted by the
defendants-appellees when they submitted their appellees’ Brief to this Court. Thus, these WHEREFORE, the consolidated petitions are DENIED. The Decision  of the Court of Appeals
cannot be considered as newly discovered evidence but are more correctly ascribed as in CA-G.R. CV No. 61318 is AFFIRMED.
suppressed forgotten evidence… Secondly, the alleged foreclosure sale is not proof of
payment of the loan by defendant-appellees to the plaintiffs-appellants. 50 No pronouncement as to costs.

Besides, the complaint a quo was filed by PhilGuarantee as guarantor for JN, and its cause SO ORDERED.
of action was premised on its payment of JN’s obligation after the latter’s default.
PhilGuarantee was well within its rights to demand reimbursement for such payment
made, regardless of whether the creditor, TRB, was subsequently able to obtain payment
from JN. If double payment was indeed made, then it is JN which should go after TRB, and
not PhilGuarantee. Petitioners have no one to blame but themselves, having allowed the
foreclosure of the property for the full value of the loan despite knowledge of
PhilGuarantee’s payment to TRB. Having been aware of such payment, they should have
opposed the foreclosure, or at the very least, filed a supplemental pleading with the trial
court informing the same of the foreclosure sale.

Likewise, petitioners cannot invoke the pari-passu  clause in the guarantee, not being
parties to the said agreement. The clause is clearly for the benefit of the guarantor and no
other.
CORPORATION), PHILIPPINE PHOENIX SURETY AND INSURANCE, INC., PARAMOUNT
INSURANCE CORPORATION,* AND FORTUNE LIFE AND GENERAL INSURANCE
COMPANY, Respondents.

DECISION
PERLAS-BERNABE, J.:
Assailed in this petition for review on certiorari 1 are the Decision2 dated April 30, 2008 and
Resolution3 dated March 27, 2009 of the Court of Appeals (CA) in CA-G.R. CV No. 86558
which affirmed the Decision4 dated April 29, 2005 of the Regional Trial Court of Makati,
Branch 132 (RTC) in Civil Case No. 95-1812. The CA upheld the RTC’s finding that the
liabilities of Paramount Insurance Corporation (Paramount), and respondents Philippine
Phoenix Surety and Insurance, Inc. (Phoenix), Mega Pacific Insurance Corporation 5 (Mega
Pacific), and Fortune Life and General Insurance Company (Fortune) on their respective
counter-surety bonds have been extinguished due to the extension of the principal
obligations these bonds covered, to which said respondents did not give their consent.

The Facts

On January 19, 1981, respondents Asia Paces Corporation (ASPAC) and Paces Industrial
Corporation (PICO) entered into a sub-contracting agreement, denominated as "200 KV
Transmission Lines Contract No. 20-/80-II Civil Works & Electrical Erection," with the
Electrical Projects Company of Libya (ELPCO), as main contractor, for the construction and
erection of a double circuit bundle phase conductor transmission line in the country of
Libya. To finance its working capital requirements, ASPAC obtained loans from foreign
banks Banque Indosuez and PCI Capital (Hong Kong) Limited (PCI Capital) which, upon the
latter’s request, were secured by several Letters of Guarantee issued by petitioner Trade
and Investment Development Corporation of the Philippines (TIDCORP), 6 then Philippine
Export and Foreign Loan Guarantee Corp., a government owned and controlled
corporation created for the primary purpose of, among others, "guarantee[ing], with the
prior concurrence of the Monetary Board, subject to the rules and regulations that the
Republic of the Philippines Monetary Board may prescribe, approved foreign loans, in whole or in part, granted to
SUPREME COURT any entity, enterprise or corporation organized or licensed to engage in business in the
Manila Philippines."7 Under the Letters of Guarantee, TIDCORP irrevocably and unconditionally
SECOND DIVISION guaranteed full payment of ASPAC’s loan obligations to Banque Indosuez and PCI Capital
G.R. No. 187403               February 12, 2014 in the event of default by the latter. 8 The denominations of these letters, including the
TRADE AND INVESTMENT DEVELOPMENT CORPORATION OF THE PHILIPPINES (Formerly loan agreements secured by each, are detailed as follows: 9
PHILIPPINE EXPORT AND FOREIGN LOAN GUARANTEE CORPORATION.), Petitioner,
vs.
ASIA PACES CORPORATION, PACES INDUSTRIAL CORPORATION, NICOLAS C. LETTER OF GUARANTEE LOAN AGREEMENT SECURED CREDITOR
BALDERRAMA, SIDDCOR INSURANCE CORPORATION (now MEGA PACIFIC INSURANCE
Letter of Guarantee No. 82-446 F Loan Agreement dated March 9, 1982 G(16)0190319
Banque
dated March 11, 1982 (with an extension dated March 25,
Indosuez 548 F
(LG No. 82-446 F) 1983), in the amount of US$250,000.00 Surety Bond No. Mega
₱5,030,000.00 September 28, 198522
G(16)0149721 Pacific
Letter of Guarantee No. 82-498 F
Loan Agreement dated June 10, 1982, in PCI
dated June 10, 1982
the amount of US$250,000.00 Capital ASPAC eventually defaulted on its loan obligations to Banque Indosuez and PCI Capital,
(LG No. 82-498 F)
prompting them to demand payment from TIDCORP under the Letters of Guarantee. The
Letter of Guarantee No. 82-548 F demand letter of Banque Indosuez was sent to TIDCORP on March 5, 1984, 23 while that of
Loan Agreement dated October 5, 1982, PCI
dated October 5, 1982 PCI Capital was sent on February 21, 1985. 24 In turn, TIDCORP demanded payment from
in the amount of US$2,000,000.00 Capital
(LG No. 82-548 F) Paramount,25 Phoenix,26 Mega Pacific,27 and Fortune28 under the Surety Bonds. TIDCORP’s
demand letters to the bonding companies were sent on May 28, 1985, or before the final
expiration dates of all the Surety Bonds, but to no avail. 29
As a condition precedent to the issuance by TIDCORP of the Letters of Guarantee, ASPAC,
PICO, and ASPAC’s President, respondent Nicolas C. Balderrama (Balderrama) had to
Taking into account the moratorium request 30 issued by the Minister of Finance of the
execute several Deeds of Undertaking,10 binding themselves to jointly and severally pay
Republic of the Philippines (whereby members of the international banking community
TIDCORP for whatever damages or liabilities it may incur under the aforementioned
were requested to grant government financial institutions, 31 such as TIDCORP, among
letters. In the same light, ASPAC, as principal debtor, entered into surety agreements
others, a 90-day roll over from their foreign debts beginning October 17, 1983), TIDCORP
(Surety Bonds) with Paramount, Phoenix, Mega Pacific and Fortune (bonding companies),
and its various creditor banks, such as Banque Indosuez and PCI Capital, forged a
as sureties, also holding themselves solidarily liable to TIDCORP, as creditor, for whatever
Restructuring Agreement32 on April 16, 1986, extending the maturity dates of the Letters
damages or liabilities the latter may incur under the Letters of Guarantee. 11 The details of
of Guarantee.33 The bonding companies were not privy to the Restructuring Agreement
said bonds, including their respective coverage amounts and expiration dates, among
and, hence, did not give their consent to the payment extensions granted by Banque
others, are as follows:
Indosuez and PCI Capital, among others, in favor of TIDCORP. Nevertheless, following new
payment schedules,34 TIDCORP fully settled its obligations under the Letters of Guarantee
to both Banque Indosuez and PCI Capital on December 1, 1992, and April 19 and June 4,
1991, respectively.35 Seeking payment for the damages and liabilities it had incurred under
the Letters of Guarantee and with its previous demands therefor left unheeded, TIIDCORP
LETTER OF BONDING FINAL filed a collection case36 against: (a) ASPAC, PICO, and Balderrama on account of their
COVERAGE
SURETY BOND GUARANTE COMPANY/ EXPIRATION obligations under the deeds of undertaking; and (b) the bonding companies on account of
AMOUNT12
E COVERED SURETY DATE their obligations under the Surety Bonds.
Surety Bond No. LG No. 82-
₱2,752,000.00 Paramount March 5, 198614 The RTC Ruling
G(16)0194313 446 F

Surety Bond No. In a Decision37 dated April 29, 2005, the RTC partially granted TIDCORP’s complaint and
₱1,845,000.00 Paramount June 4, 198616
G(16)0190615 thereby found ASPAC, PICO, and Balderrama jointly and severally liable to TIDCORP in the
LG No. 82-
498 F sum of ₱277,891,359.66 pursuant to the terms of the Deeds of Undertaking, but absolved
Surety Bond No. the bonding companies from liability on the ground that the moratorium request and the
₱1,849,000.00 Fortune November 21, 198518
G(16)1549517 consequent payment extensions granted by Banque Indosuez and PCI Capital in TIDCORP’s
favor without their consent extinguished their obligations under the Surety Bonds. As
Surety Bond No. LG No. 82- ₱11,970,000.00 Phoenix September 28, 198520
basis, the RTC cited Article 2079 of the Civil Code which provides that an extension
granted to the debtor by the creditor without the consent of the guarantor/surety CA-G.R. CV No. 92818, entitled "Trade & Investment Corporation of the Phils., et al. v.
extinguishes the guaranty/suretyship, and, in this relation, added that the bonding Roblet Industrial Construction Corp. and Paramount Insurance Corp., et al." 51
companies "should not be held liable as sureties for the extended period." 38
The Issue Before the Court
Dissatisfied, TIDCORP and Balderrama filed separate appeals before the CA. 39 For its part,
TIDCORP averred, among others, that Article 2079 of the Civil Code is only limited to The essential issue raised for the Court’s resolution is whether or not the CA erred in
contracts of guaranty, and, hence, should not apply to contracts of suretyship. Meanwhile, holding that the bonding companies’ liabilities to TIDCORP under the Surety Bonds have
Balderrama theorized that the main contractor’s (i.e., ELPCO) failure to pay ASPAC due to been extinguished by the payment extensions granted by Banque Indosuez and PCI Capital
the war/political upheaval in Libya which further resulted in the latter’s inability to pay to TIDCORP under the Restructuring Agreement.
Banque Indosuez and PCI Capital had the effect of releasing him from his obligations
under the Deeds of Undertaking.
The Court’s Ruling

The CA Ruling
The petition is granted.
40
In a Decision  dated April 30, 2008, the CA upheld the RTC’s ruling that the moratorium
request "had the effect of an extension granted to a debtor, which extension was without A surety is considered in law as being the same party as the debtor in relation to whatever
the consent of the guarantor, and thus released the surety companies from their is adjudged touching the obligation of the latter, and their liabilities are interwoven as to
respective liabilities under the issued surety bonds" pursuant to Article 2079 of the Civil be inseparable. Although the contract of a surety is in essence secondary only to a valid
Code.41 To this end, it noted that "the maturity of the foreign loans was extended to principal obligation, his liability to the creditor is direct, primary and absolute; he becomes
December 31, 1989 or up to December 31, 1994 as provided under Section 4.01 of the liable for the debt and duty of another although he possesses no direct or personal
Restructuring Agreement," and that "said extension is beyond the expiry date[s] of the interest over the obligations nor does he receive any benefit therefrom. 52 The
surety bonds x x x and the maturity date of the principal obligations it purportedly fundamental reason therefor is that a contract of suretyship effectively binds the surety as
secured, which extension was without [the bonding companies’] consent," 42 It further a solidary debtor. This is provided under Article 2047 of the Civil Code which states:
discredited TIDCORP’s contention that Article 2079 of the Civil Code is only limited to
contracts of guaranty by citing the Court’s pronouncement on the provision’s applicability Article 2047. By guaranty a person, called the guarantor, binds himself to the creditor to
to suretyships in the case of Security Bank and Trust Co., Inc. v. Cuenca 43 (Security Bank). fulfill the obligation of the principal debtor in case the latter should fail to do so.
As for Balderrama, the CA debunked his assignment of error, ratiocinating that "[h]is
undertaking to pay is not dependent upon the payment to be made by ELPCO to If a person binds himself solidarily with the principal debtor, the provisions of Section 4,
ASPAC."44 The CA, however, modified the RTC decision to the extent of holding ASPAC, Chapter 3, Title I of this Book shall be observed. In such case the contract is called a
PICO, and Balderrama liable to TIDCORP for attorney’s fees in the reasonable amount of suretyship. (Emphasis and underscoring supplied)
₱2,000,000.00 since the payment of attorney’s fees was stipulated by the parties in the
Deed of Undertaking dated April 2, 1982.45
Thus, since the surety is a solidary debtor, it is not necessary that the original debtor first
failed to pay before the surety could be made liable; it is enough that a demand for
Aggrieved, TIDCORP and Balderrama filed separate motions for reconsideration, 46 which payment is made by the creditor for the surety’s liability to attach. 53
were, however, denied in a Resolution 47 dated March 27, 2009. Only TIDCORP elevated
the matter to the Court on appeal. Pending resolution thereof, or on October 6, 2010,
TIDCORP filed a Motion for Partial Withdrawal 48 of its claim against Paramount in view of Article 1216 of the Civil Code provides that:
their Compromise Agreement49 dated June 24, 2010 which was approved 50 by the CA in
Article 1216. The creditor may proceed against any one of the solidary debtors or some or Applying these principles, the Court finds that the payment extensions granted by Banque
all of them simultaneously. The demand made against one of them shall not be an Indosuez and PCI Capital to TIDCORP under the Restructuring Agreement did not have the
obstacle to those which may subsequently be directed against the others, so long as the effect of extinguishing the bonding companies’ obligations to TIDCORP under the Surety
debt has not been fully collected. Bonds, notwithstanding the fact that said extensions were made without their consent.
This is because Article 2079 of the Civil Code refers to a payment extension granted by the
Comparing a surety’s obligations with that of a guarantor, the Court, in the case of creditor to the principal debtor without the consent of the guarantor or surety. In this
Palmares v. CA,54 illumined that a surety is responsible for the debt’s payment at once if case, the Surety Bonds are suretyship contracts which secure the debt of ASPAC, the
the principal debtor makes default, whereas a guarantor pays only if the principal debtor principal debtor, under the Deeds of Undertaking to pay TIDCORP, the creditor, the
is unable to pay, viz.:55 damages and liabilities it may incur under the Letters of Guarantee, within the bounds of
the bonds’ respective coverage periods and amounts. No payment extension was,
however, granted by TIDCORP in favor of ASPAC in this regard; hence, Article 2079 of the
A surety is an insurer of the debt, whereas a guarantor is an insurer of the solvency of the Civil Code should not be applied with respect to the bonding companies’ liabilities to
debtor.1âwphi1 A suretyship is an undertaking that the debt shall be paid; a guaranty, an TIDCORP under the Surety Bonds.
undertaking that the debtor shall pay. Stated differently, a surety promises to pay the
principal’s debt if the principal will not pay, while a guarantor agrees that the creditor,
after proceeding against the principal, may proceed against the guarantor if the principal The payment extensions granted by Banque Indosuez and PCI Capital pertain to TIDCORP’s
is unable to pay. A surety binds himself to perform if the principal does not, without own debt under the Letters of Guarantee wherein it (TIDCORP) irrevocably and
regard to his ability to do so. A guarantor, on the other hand, does not contract that the unconditionally guaranteed full payment of ASPAC’s loan obligations to the banks in the
principal will pay, but simply that he is able to do so. In other words, a surety undertakes event of its (ASPAC) default. In other words, the Letters of Guarantee secured ASPAC’s
directly for the payment and is so responsible at once if the principal debtor makes loan agreements to the banks. Under this arrangement, TIDCORP therefore acted 58 as a
default, while a guarantor contracts to pay if, by the use of due diligence, the debt cannot guarantor,59 with ASPAC as the principal debtor, and the banks as creditors.
be made out of the principal debtor.
Proceeding from the foregoing discussion, it is quite clear that there are two sets of
(Emphases and underscoring supplied; citations omitted) transactions that should be treated separately and distinctly from one another following
the civil law principle of relativity of contracts "which provides that contracts can only
bind the parties who entered into it, and it cannot favor or prejudice a third person, even
Despite these distinctions, the Court in Cochingyan, Jr. v. R&B Surety & Insurance Co., if he is aware of such contract and has acted with knowledge thereof." 60 Verily, as the
Inc.,56 and later in the case of Security Bank, held that Article 2079 of the Civil Code, which Surety Bonds concern ASPAC’s debt to TIDCORP and not TIDCORP’s debt to the banks, the
pertinently provides that "[a]n extension granted to the debtor by the creditor without payments extensions (which conversely concern TIDCORP’s debt to the banks and not
the consent of the guarantor extinguishes the guaranty," equally applies to both contracts ASPAC’s debt to TIDCORP) would not deprive the bonding companies of their right to pay
of guaranty and suretyship. The rationale therefor was explained by the Court as follows: 57 their creditor (TIDCORP) and to be immediately subrogated to the latter’s remedies
against the principal debtor (ASPAC) upon the maturity date. It must be stressed that
The theory behind Article 2079 is that an extension of time given to the principal debtor these payment extensions did not modify the terms of the Letters of Guarantee but only
by the creditor without the surety’s consent would deprive the surety of his right to pay provided for a new payment scheme covering TIDCORP’s liability to the banks. In fine,
the creditor and to be immediately subrogated to the creditor’s remedies against the considering the inoperability of Article 2079 of the Civil Code in this case, the bonding
principal debtor upon the maturity date. The surety is said to be entitled to protect companies’ liabilities to TIDCORP under the Surety Bonds – except those issued by
himself against the contingency of the principal debtor or the indemnitors becoming Paramount and covered by its Compromise Agreement with TIDCORP – have not been
insolvent during the extended period. (Emphasis and underscoring supplied; citations extinguished. Since these obligations arose and have been duly demanded within the
omitted) coverage periods of all the Surety Bonds, 61 TIDCORP’s claim is hereby granted and the CA’s
ruling on this score consequently reversed. Nevertheless, given that no appeal has been
filed on Balderrama’s adjudged liability or on the award of attorney's fees, the CA's
dispositions on these matters are now deemed as final and executory. DECISION
LEONARDO-DE CASTRO, J.:
WHEREFORE, the petition is GRANTED. The Decision dated April 30, 2008 and Resolution Assailed in this Petition for Review on Certiorari are: (1) the Decision 1 dated May 30, 2002
dated March 27, 2009 of the Court of Appeals in CA-G.R. CV No. 86558 are MODIFIED in of the Court of Appeals in CA-G.R. CV No. 54066, which reversed and set aside the
that respondents Philippine Phoenix Surety and Insurance, Inc., Mega Pacific Insurance Decision2 dated May 2, 1996 of the Regional Trial Court (RTC), Makati City, Branch 66, and
Corporation, Fortune Life and General Insurance Company are ORDERED to fulfill their held petitioner CCC Insurance Corporation (CCCIC) liable under its Surety and Performance
respective obligations to petitioner Trade and Investment Development Corporation of Bonds to respondent Kawasaki Steel Corporation (Kawasaki); and (2) the
the Philippines (TIDCORP) under the Surety Bonds subject of this case, discounting the Resolution3 dated November 14, 2002 of the appellate court in the same case which
obligations arising from the Surety Bonds issued by Paramount Insurance Corporation and denied the Motion for Reconsideration of CCCIC.
covered by its Compromise Agreement with TIDCORP.
The antecedents of this case are as follows:
SO ORDERED.
On August 16, 1988, Kawasaki, represented by its Manager, Yoshimitsu Hosoya, and F .F.
Mañacop Construction Company, Inc. (FFMCCI), represented by its President, Florante F.
Mañacop (Mañacop ), executed a Consortium Agreement for Pangasinan Fishing Port
Network Project (Consortium Agreement). 4 Kawasaki and FFMCCI formed a consortium
(Kawasaki-FFMCCI Consortium) for the purpose of contracting with the Philippine
Government for the construction of a fishing port network in Pangasinan (Project).
According to their Consortium Agreement, Kawasaki and FFMCIA undertook to perform
and accomplish their respective and specific portions of work in the intended contract
with the Philippine Government.5

The Project was awarded to the Kawasaki-FFMCCI Consortium for the contract price of
₱62,000,441.00, 33 .3 7% of which or ₱20,692,026.00 was the price of work of FFMCCI. On
October 4, 1988, the Republic of the Philippines (Republic), through the Department of
Public Works and Highways (DPWH), represented by former Secretary Romulo M. del
Rosario, as owner, and the Kawasaki-FFMCCI Consortium, represented by Shigeru Kohda,
as contractor, entered into a Contract Agreement entitled Stage I-A Construction of
Pangasinan Fishing Port Network (Construction Contract). 6
Republic of the Philippines
SUPREME COURT In accordance with Article 10 of the Consortium Agreement, 7 "Consortium Leader"
Manila Kawasaki, on behalf of the Consortium, secured from the Philippine Commercial
FIRST DIVISION International Bank (PCIB) Letter of Credit No. 38-001-183617 8 in the amount of
G.R. No. 156162               June 22, 2015 ₱6,200,044.10 in favor of DPWH, available from September 9, 1988 to November 19,
CCC INSURANCE CORPORATION, Petitioner, 1990. Said Letter of Credit guaranteed the faithful performance by Kawasaki-FFMCCI
vs. Consortium of its obligation under the Construction Contract.
KAWASAKI STEEL CORPORATION, F.F. MAÑACOP CONSTRUCTION CO., INC., and
FLORANTE F. MAÑACOP, Respondents.
The Republic made an advance payment for the Project to the Kawasaki-FFMCCI In its Answer with Counterclaims, 18 CCCIC denied any liability on its Surety and
Consortium in the amount of ₱9,300,066.15, representing 15% of the contract price of: Performance Bonds on the following grounds: (a) the rights of Kawasaki under the Surety
₱62,000,441.00. and Performance Bonds had not yet accrued since the said Bonds were mere counter-
guarantees, for which CCCIC could only be held liable upon the filing of a claim by the
For the release of its share in the advance payment made by the Republic, and also Republic against the Kawasaki-FFMCCI Consortium; (b) Kawasaki and FFMCCI, without the
pursuant to Article 10 of the Consortium Agreement, FFMCCI secured from CCCIC the consent of CCCIC, executed a new Agreement dated August 24, 1989 novating the terms
following bonds in favor of Kawasaki: (a) Surety Bond No. B-88/11191 9 in the amount of of the Consortium Agreement, which prevented CCCIC from being subrogated to the right
₱3,103,803.90 (equivalent to 15% of the price of work of FFMCCI), effective from October of Kawasaki against FFMCCI; (c) Kawasaki, in completing the Transferred Portion of Work
26, 1988 to October 26, 1989, to counter guarantee the amount of advance payment was correspondingly compensated, which negated any allegation of loss on the part of
FFMCCI would receive from Kawasaki; and (b) Performance Bond B-88/11193 10 in the Kawasaki; and (d) the obligation of CCCIC was extinguished when the Republic granted the
amount of ₱2,069,202.60 (equivalent to 10% of the price of work of FFMCCI), effective Kawasaki-FFMCCI Consortium an extension of time to complete the Project, without the
from October 27, 1988 to October 27, 1989, to guarantee completion by FFMCCI of its consent of CCCIC.
scope of work in the Project. In turn, FFMCCI and Mañacop executed two Indemnity
Agreements11 promising to compensate CCCIC for any damages the insurance company CCCIC subsequently filed on August 19, 1991 before the RTC a Third-Party
might incur from issuing the Surety and Performance Bonds. Complaint19 against FFMCCI and its President Mañacop based on the two Indemnity
Agreements which FFMCCI and Mañacop executed in favor of CCCIC. The RTC issued
In two letters dated October 27, 1998, 12 FFMCCI submitted the Surety and Performance summonses but FFMCCI and Mañacop failed to file any responsive pleading to the Third-
Bonds to Kawasaki and requested Kawasaki to release the advance payment in the Party Complaint of CCCIC. Upon motion of CCCIC, the RTC issued an Order 20 dated
amount of ₱3,103,803.90. FFMCCI eventually received the amount of advance payment it December 2, 1991 declaring FFMCCI and Mañacop in default.
requested on a staggered basis.13
After trial, the RTC rendered a Decision on May 2, 1996 dismissing the Complaint of
The Project commenced in November 1988. 14 Sometime in April 1989, FFMCCI ceased Kawasaki and the counterclaim of CCCIC. The RTC agreed with CCCIC that the Surety and
performing its work in the Project after suffering financial problems and/or business Performance Bonds issued by the insurance company were mere counter-guarantees and
reverses. After discussions, Kawasaki and FFMCCI then executed a new Agreement 15 on the cause of action of Kawasaki based on said Bonds had not yet accrued. Since the
August 24, 1989 wherein Kawasaki recognized the "Completed Portion of Work" of Republic did not exercise its right to claim against the PCIB Letter of Credit No. 38-001-
FFMCCI as of April 25, 1989, and agreed to take over the unfinished portion of work of 183617, nor compelled Kawasaki to perform the unfinished work of FFMCCI, Kawasaki
FFMCCI, referred to as "Transferred Portion of Work." Kawasaki and FFMCCI further could not claim indemnification from CCCIC. Moreover, the RTC, citing Article 2079 of the
agreed that "[a]ny profit or benefit arising from the performance by [Kawasaki] of the Civil Code, ruled that the obligations of CCCIC under the Surety and Performance Bonds
Transferred Portion of Work shall accrue to [Kawasaki]." were extinguished when the Republic granted the Kawasaki-FFMCCI Consortium a 43-day
extension to finish the Project, absent the consent of CCCIC. The RTC found no deliberate
intent on the part of Kawasaki to cause prejudice to CCCIC, so it did not grant the
In a letter dated September 14, 1989,16 Kawasaki informed CCCIC about the cessation of counterclaims for moral and exemplary damages and attorney's fees of CCCIC against
operations of FFMCCI, and the failure of FFMCCI to perform its obligations in the Project Kawasaki.
and repay the advance payment made by Kawasaki. Consequently, Kawasaki formally
demanded that CCCIC, as surety, pay Kawasaki the amounts covered by the Surety and
Performance Bonds. Because CCCIC did not act upon its demand, Kawasaki filed on Kawasaki appealed before the Court of Appeals assigning the following errors on the part
November 6, 1989 before the RTC a Complaint 17 against CCCIC to collect on Surety Bond of the RTC:
No. B-88/11191 and Performance Bond No. B-88/11193.
I. THE COURT A QUO GROSSLY ERRED IN HOLDING THAT [CCCIC] CAN BE HELD LIABLE TO
[Kawasaki] UNDER THE SUBJECT BONDS ONLY "IF THE GOVERNMENT EXERCISES ITS
RIGHTS AGAINST THE GUARANTEE-BONDS ISSUED TO IT BY [Kawasaki]" ON THE THEORY accordance with the plans and specifications of the contract" subject only to the condition
ADVANCED BY [CCCIC], WHICH THE COURT A QUO FULLY EMBRACED AND ADOPTED, that "the liability of the [herein] surety shall in no case exceed the amount of Pesos: TWO
THAT THE BONDS ARE MERE "COUNTER-GUARANTEES." MILLION SIXTY-NINE THOUSAND TWO HUNDRED TWO & 60/100 (₱2,069,202.60)
Philippine currency."
II. THE COURT A QUO GROSSLY ERRED IN HOLDING THAT THE EXTENSION GRANTED BY
THE GOVERNMENT TO THE CONSORTIUM FOR THE CONSTRUCTION OF THE PANGASINAN The right of KAW AS AKI as the obligee/creditor of the said bonds was not made subject to
FISHING PORT NETWORK PROJECT EXTINGUISHED THE LIABILITY OF [CCCIC]. any other condition expressly so provided in the Consortium Agreement, which was the
reason for the bonds posted by [FFMCCI] and CCCIC, or in the subject bonds themselves.
III. THE COURT A QUO GROSSLY ERRED IN HOLDING THAT ARTICLE 2079 OF THE CIVIL
CODE OF THE PHILIPPINES APPLIES TO THE CASE AT BAR. IN A LONG LINE OF DECISIONS, Hence, this Court finds that the court a quo did err in ruling that "[u]nder the Consortium
THE SUPREME COURT HAS HELD THAT THE RULE OF "STRICTISSIMI JURIS" DOES NOT Agreement, the bonds are counter-guarantees which only guarantee the plaintiff
APPLY TO SURETY COMPANIES SUCH AS [CCCIC] HEREIN. KAWASAKI for reimbursement to the extent of the value of the bonds in case the
employer (government) successfully exercised its rights under the bonds issued to it by
IV. THE SUBJECT BONDS ARE FIXED UNTIL OCTOBER 26 AND 27, 1989 RESPECTIVELY plaintiff KAW AS AKI;" and that "[ c]onsidering that the government did not exercise its
WHILE THE ORIGINAL PERIOD OF THE CONTRACT WITH THE GOVERNMENT, THE rights against the bond issued to it by the Consortium Leader, it follows that the
PERFORMANCE OF WHICH BY [CCCIC] ARE PRECISELY GUARANTEED BY THESE BONDS, IS Consortium Leader cannot collect from the counter-guarantees furnished by [FFMCCI]."
UNTIL DECEMBER 30, 1989. ON THE OTHER HAND, THE DEF AULT BY [FFMCCI] WHICH THE
BONDS GUARANTEED AGAINST OCCURRED ON [OR] ABOUT AUGUST 24, 1989. Time and again, the Supreme Court has stressed the rule that a contract is the law
THEREFORE, IRRESPECTIVE OF WHETHER THERE WAS AN EXTENSION OR NOT AT THE END between the parties, and courts have no choice but to enforce such contract so long as
OF THE ORIGINAL CONTRACT PERIOD AND IRRESPECTIVE OF WHETHER THIS EXTENSION IS they are not contrary to law, morals, good customs or public policy.
KNOWN OR UNKNOWN TO [CCCIC], THE LIABILITY THAT IT BOUND ITSELF UNTO UNDER
THE BONDS IS VERY CLEARLY AND UNEQUIVOCALLY FIXED UNTIL OCTOBER 26 AND 27, With respect to the second, third and fourth issues raised, suffice it to say that this Court
1989 RESPECTIVELY. THEREFORE, ARTICLE 2079 WILL NOT APPLY. HENCE, THE COURT A finds Article 2079 of the Civil Code of the Philippines not applicable. [Kawasaki] claims that
QUO GROSSLY ERRED IN HOLDING OTHERWISE.21 since the issue in this case is the liability of CCCIC to KAWASAKI, the extension of forty-
three (43) days within which to complete the Pangasinan Fishing Port Network Project
The Court of Appeals, in its Decision dated May 30, 2002, reversed the appealed RTC granted by the Philippine government, who is not a party to the two (2) bonds posted by
Decision, reasoning as follows:21 [FFMCCI] and CCCIC, to the consortium, does not absolve CCCI C's liabilities to KAWASAKI
under the subject bonds.
From the language of the aforesaid bonds, it is clear that, in the case of the surety bond,
the same was posted, jointly and severally, by [FFMCCI] and CCCIC "to fully and faithfully We agree.
guarantee the repayment of the downpayment made by the principal ([FFMCCI]) to the
obligee (KAWASAKI) in connection with the construction of the Pangasinan Fishing Port As stated earlier, the parties insofar as the surety bond and performance bond are
Network Project at Pangasin.an" subject only to the condition that "the liability of the concerned are: KAWASAKI, as obligee, [FFMCCI], as principal; and CCCIC, as surety.
[herein] surety shall in no case exceed the amount of Pesos: THREE MILLION ONE Considering therefore that the extension of time within which to complete the
HUNDRED THREE THOUSAND EIGHT HUNDRED THREE & 90/100 (₱3,103,803.90) construction of the Pangasinan Fishing Port Network Project was granted by the Philippine
Philippine currency; and in the case of the performance bond, the same was posted, government, who is not the creditor of the bonds, this Court finds that Article 2079 of the
jointly and severally by [FFMCCI] and CCCIC "to guarantee the full and faithful Civil Code of the Philippines does not apply and the extension of time granted by the
performance of the principal ([FFMCCI]) of its obligation in connection with the project for Philippine government, contrary to the ruling of the trial court, does not absolve the
the construction of the Pangasinan Fishing Port Network located at Pangasinan in surety of its liabilities to KAWASAKI under the subject bonds.
The principle of relativity of contracts provides that contracts can only bind the parties A.
who entered into it.
THE COURT OF APPEALS, CONTRARY TO LAW, FAILED TO CONSIDER
Finally, this Court finds the award of attorney's fees in favor of the appellant warranted THE TRUE NATURE OF THE TRANSACTION BETWEEN THE PARTIES
under the circumstance, pursuant to paragraph (2) of Article 2208 of the Civil Code of the AND THE TRUE NATURE OF A COUNTER-GUARANTEE.
Philippines.22
B.
In the end, the Court of Appeals decreed:
THE COURT OF APPEALS, CONTRARY TO LAW, FAILED TO APPRECIATE
WHEREFORE, the instant appeal is hereby GRANTED. Accordingly, the assailed decision of THE APPLICABILITY OF ARTICLE 2079 OF THE CIVIL CODE, WHICH
the Regional Trial Court of Makati City, Branch 66, is hereby REVERSED and SET ASIDE. CCC PROVIDES THAT AN EXTENSION GRANTED TO THE DEBTOR BY THE
Insurance Corporation is hereby ordered to pay KAWASAKI the following: CREDITOR WITHOUT THE CONSENT OF THE GUARANTOR
EXTINGUISHES THE GUARANTY.
1. The amount of ₱3,103,803.90 representing its liability to Kawasaki Steel Corporation
under Surety Bond No. B-88/11191, plus legal interest at the rate of 12% per annum C.
computed from 15 September 1989, until fully paid;
THE COURT OF APPEALS, CONTRARY TO LAW, ERRONEOUSLY FAILED
2. The amount of ₱2,069,202.80 representing its liability to Kawasaki Steel Corporation TO CONSIDER THE FACT THAT KAWASAKI AND FFMCCI HAVE
under Performance Bond No. B-88/11193, plus legal interest at the rate of 12% per NOVATED THEIR ORIGINAL AGREEMENT
annum computed from 15 September 1989, until fully paid; and
WITHOUT THE KNOWLEDGE AND CONSENT OF CCCIC, THEREBY
3. 15% of the total amount due as and for attorney's fees. 23 In its Resolution dated RELEASING THE LATTER FROM ANY OBLIGATION UNDER THE BONDS
November 14, 2002, the Court of Appeals denied the Motion for Reconsideration of IT ISSUED.
CCCIC. However, in the same Resolution, the appellate court partially granted the Third-
Party Complaint of CCCIC by holding Mañacop liable under the Indemnity Agreements he D.
executed in favor of the insurance company, while declaring the RTC was without
jurisdiction over FFMCCI due to invalid service of summons. The Court of Appeals
ultimately resolved: THE COURT OF APPEALS, CONTRARY TO LAW, ERRONEOUSLY
RENDERED CCCIC LIABLE TO PAY THE FULL AMOUNT OF THE SURETY
AND PERFORMANCE BONDS DESPITE THE FACT THAT FFMCCI WAS
WHEREFORE, judgment is hereby rendered in favor of third-party plaintiff CCC Insurance ABLE TO PARTIALLY EXECUTE ITS PORTION OF THE WORK AND THAT
Corporation and against third-party defendant Florante F. Mañacop, ordering the latter to KAWASAKI HAD BEEN FULLY COMPENSATED FOR TAKING OVER THE
indemnify the former the total amount paid by the former to Kawasaki Steel Corporation UNFINISHED PORTION.
representing CCC Insurance Corporation's liabilities under Surety Bond No. B-88/11191
and Performance Bond No. B88/11193 and to pay CCC Insurance Corporation 25% of the
total amount due, as and for attorney's fees. 24 E.

In the instant Petition for Review on Certiorari, CCCIC assails the aforementioned Decision
and Resolution of the Court of Appeals on six grounds, viz.:
THE COURT OF APPEALS, CONTRARY TO LAW, ERRONEOUSLY The Petition is partly meritorious.
AWARDED ATTORNEY'S FEES TO KAWASAKI UNDER PARAGRAPH 2 OF
ARTICLE 2208 OF THE CIVIL CODE. The liability of CCCIC under the
Surety and Performance Bonds is
F. dependent on the fulfillment and/or
non-fulfillment of the obligation of
THE COURT OF APPEALS, CONTRARY TO LAW, ERRONEOUSLY RULED FFMCCI to KAWASAKI under the
THAT THER WAS NO VALID SERVICE OF SUMMONS UPON FFMCCI. 25 Consortium Agreement.

CCCIC avers that its liabilities under the Surety and Performance Bonds are directly linked The statutory definition of suretyship is found in Article 204 7 of the Civil Code, thus:
with the obligation of the Kawasaki-FFMCCI Consortium to finish the Project for the
Republic, so that its liability as surety of FFMCCI will only arise if the Republic made a Art. 2047. By guaranty a person, called the guarantor, binds himself to the creditor to
claim on the PCIB Letter of Credit furnished by Kawasaki, on behalf of the Consortium. fulfill the obligation of the principal debtor in case the latter should fail to do so.
Since the Republic has not exercised its right against said Letter of Credit, Kawasaki does
not have a cause of action against CCCIC. If a person binds himself solidarily with the principal debtor, the provisions of Section 4,
Chapter 3, Title I of this Book shall be observed. In such case the contract is called a
CCCIC also maintains that its obligations under the Surety and Performance Bonds had suretyship. (Emphasis supplied.)
been extinguished when (a) the Republic extended the completion period for the Project
upon the request of Kawasaki but without the knowledge or consent of CCCIC, based on Jurisprudence also defines a contract of suretyship as "an agreement where a party called
Article 2079 of the Civil Code; and (b) when Kawasaki and FFMCCI executed the the surety guarantees the performance by another party called the principal or obligor of
Agreement dated August 24, 1989, without the consent of CCCIC, there being a novation an obligation or undertaking in favor of a third person called the obligee. Specifically,
of the Consortium Agreement. suretyship is a contractual relation resulting from an agreement whereby one person, the
surety, engages to be answerable for the debt, default or miscarriage of another, known
CCCIC further argues that when Kawasaki, under the Agreement dated August 24, 1989, as the principal." 26 The Court expounds that "a surety's liability is joint and several, limited
voluntarily took over the Transferred Portion of Work from FFMCCI, it resulted in the to the amount of the bond, and determined strictly by the terms of contract of suretyship
reduction of revenue of FFMCCI on which CCCIC relied upon as a source of in relation to the principal contract between the obligor and the obligee. It bears
indemnification. CCCIC additionally posits that Kawasaki already received compensation stressing, however, that although the contract of suretyship is secondary to the principal
for doing the Transferred Portion of Work, so the Court of Appeals had no basis for still contract, the surety's liability to the obligee is nevertheless direct, primary, and
ordering Kawasaki to pay the full value of the Surety and Performance Bonds, plus absolute."27
interest.
At the outset, the Court ascertains that there are two principal contracts in this case: (1)
Moreover, CCCIC contends that the Court of Appeals erred in awarding attorney's fees in the Consortium Agreement wherein Kawasaki and FFMCCI agreed to jointly enter into a
favor of Kawasaki based on paragraph 2 of Article 2208 of the Civil Code as it is not a contract with the Republic for the Project, each assuming the performance of specific
sound policy to place a penalty on the right to litigate. scopes of work in said Project; and (2) the Construction Contract whereby the Republic
awards the Project to the Kawasaki-FFMCCI Consortium. While there is a connection
Lastly, CCCIC insists that there was proper service of summons upon FFMCCI, through one between these two contracts, they are each distinguishable from and enforceable
of its directors, as authorized by the Rules of Court. independently of one another: the first governs the rights and obligations between
Kawasaki and FFMCCI, while the second covers contractual relations between the
Republic and the Kawasaki-FFMCCI Consortium. The Surety and Performance Bonds from
CCCIC guaranteed the performance by FFMCCI of its obligations under the Consortium THE CONDITIONS OF THIS OBLIGATION ARE AS FOLLOWS:
Agreement; whereas the Letter of Credit from PCIB warranted the completion of the
Project by the Kawasaki FFMCCI Consortium. At the crux of the instant controversy are the TO FULLY AND FAITHFULLY GUARANTEE THE REPAYMENT OF THE
Surety and Performance Bonds issued by CCCIC in relation to the Consortium Agreement. DOWNPAYMENT MADE BY THE PRINCIPAL TO THE OBLIGEE IN
CONNECTION WITH THE CONSTRUCTION OF THE PANGASINAN
FFMCCI secured the Surety and Performance Bonds from CCCIC in compliance with Article FISHING PORT NETWORK PROJECT AT PANGASINAN; AND PROVIDED
10 of the Consortium Agreement which provided: HOWEVER, THAT THE LIABILITY OF THE HEREIN SURETY SHALL IN NO
CASE EXCEED THE AMOUNT OF PESOS: THREE MILLION ONE
ARTICLE 10 - BONDS HUNDRED THREE THOUSAND EIGHT HUNDRED THREE & 90/100
ONLY (₱3,103,803.90) PHILIPPINE CURRENCY.

10.1 The CONSORTIUM LEADER [Kawasaki] shall arrange, at [its] own cost, all necessary
bonds or guarantees as required under the CONTRACT on behalf of the CONSORTIUM. xxxx
[FFMCCI] shall, at its own cost, furnish the CONSORTIUM LEADER [Kawasaki] with a
suitable counter guarantees of its advance payment under the CONTRACT and the WHEREAS, the said OBLIGEE requires said Principal to give a good
performance of its PORTION OF WORK in the amount of fifteen (15%) percent (in the case and sufficient bond in the above-stated sum to secure the full and
of the repayment guarantee for the advance) and ten (10%) percent (in the case of the faithful performance on his part of said UNDERTAKING. NOW,
performance guarantee) of the price of its PORTION OF THE WORK. THEREFORE, if the above bounden principal shall in all respects duly
and fully observe and perform all and singular the aforesaid
10.2 If the EMPLOYER [Republic] exercises its right on the bonds or guarantees furnished covenants, conditions and agreements to the true intent and
by the CONSORTIUM LEADER, the PARTIES shall decide the respective responsibilities meaning thereof, then this obligation shall be null and void,
according to the provisions of this AGREEMENT and the necessary reimbursement or otherwise to remain in full force and effect.
compensation shall be made also according to the provisions of this AGREEMENT.
Pertinent portions of Surety Bond No. B-88/11191 read: The liability of the Surety under this bond shall expire on October 26, 1989 and the Surety
does not assume responsibility for any liability incurred or created after said date. Any
SURETY BOND claims against this bond must be presented to the Surety in writing not later than ten (10)
days after said expiry date; otherwise, failure to do so shall forthwith release the Surety
from all liabilities under this bond and shall be a bar to any court action against it and
KNOW ALL MEN BY THESE PRESENTS: which right to sue is hereby waived by the Obligee after the lapse of said period often (10)
days above cited.29
That we, F.F. MANACOP CONSTRUCTION CO., INC., x xx, as principal,
and CCC Insurance Corporation, x x x, as SURETY, are held and firmly (Emphases supplied.)
bound unto KAWASAKI STEEL CORPORATION, hereinafter referred to
as the OBLIGEE: in the sum of PESOS: THREE MILLION ONE HUNDRED
THREE THOUSAND EIGHT HUNDRED THREE & 90/100 ONLY Performance Bond No. B-88111193 contains the following terms and conditions:
(₱3,103,803.90), Philippine currency, for the payment of which, well
and truly to be made, we bind ourselves, our heirs, executors, PERFORMANCE BOND
administrators, successors and assigns, jointly and severally, firmly
bound from notice of acceptance, by these presents. KNOW ALL MEN BY THESE PRESENTS:
That we, F.F. MANACOP CONSTRUCTION CO., INC., xx x, as principal, which right to sue is hereby waived by the Obligee after the lapse of said period of ten
and CCC Insurance Corporation, x x x, as SURETY, are held and firmly ( 10) days above cited. 30
bound unto KAWASAKI STEEL CORPORATION, hereinafter referred to
as the OBLIGEE: in the sum of PESOS: TWO MILLION SIXTY-NINE (Emphasis supplied.)
THOUSAND TWO HUNDRED TWO & 60/100 ONLY (₱2,069,202.60),
Philippine currency, for the payment of which, well and truly to be
made, we bind ourselves, our heirs, executors, administrators, The Court reiterates that a surety's liability is determined strictly by the terms of contract
successors and assigns, jointly and severally, firmly bound from of suretyship, in relation to the principal contract between the obligor and the obligee.
notice of acceptance, by these presents. Hence, the Court looks at the Surety and Performance Bonds, in relation to the
Consortium Agreement.

THE CONDITIONS OF THIS OBLIGATION ARE AS FOLLOWS:


According to the principle of relativity of contracts in Article 1311 of the Civil Code, 31 a
contract takes effect only between the parties, their assigns, and heirs; except when the
TO GUARANTEE THE FULL AND FAITHFUL PERFORMANCE OF THE contract contains a stipulation in favor of a third person, which gives said person the right
PRINCIPAL OF ITS OBLIGATION IN CONNECTION WITH THE PROJECT to demand fulfillment of said stipulation. In this case, the Surety and Performance Bonds
FOR THE CONSTRUCTION OF PANGASINAN FISHING PORT NETWORK are enforceable by and against the parties FFMCCI (the obligor) and CCCIC (the surety), as
LOCATED AT PANGASINAN IN ACCORDANCE WITH THE PLANS AND well as the third person Kawasaki (the obligee) in whose favor said bonds had been
SPECIFICATION OF THE CONTRACT, AND; PROVIDED HOWEVER, THAT explicitly constituted; while the related Consortium Agreement binds the parties Kawasaki
THE LIABILITY OF THE HEREIN SURETY SHALL IN NO CASE EXCEED THE and FFMCCI. Since the Republic is neither a party to the Surety and Performance Bonds
AMOUNT OF PESOS: TWO MILLION SIXTY-NINE THOUSAND TWO nor the Consortium Agreement, any action or omission on its part has no effect on the
HUNDRED TWO & 60/100 ONLY (₱2,069,202.60) PHILIPPINE liability of CCCIC under said bonds.
CURRENCY.

The Surety and Performance Bonds state that their purpose was "to secure the full and
xxxx faithful performance on [FFMCCI' s] part of said undertaking," particularly, the repayment
by FFMCCI of the downpayment advanced to it by Kawasaki (in the case of the Surety
WHEREAS, the said OBLIGEE requires said Principal to give a good Bond) and the full and faithful performance by FFMCCI of its portion of work in the Project
and sufficient bond in the above-stated sum to secure the full and (in the case of the Performance Bond).These are the only undertakings expressly
faithful performance on his part of said UNDERTAKING. guaranteed by the bonds, the fulfillment of which by FFMCCI would release CCCIC from its
obligations as surety; or conversely, the non-performance of which would give rise to the
NOW, THEREFORE, if the above bounden principal shall in all respects liabilities of CCCIC as a surety.
duly and fully observe and perform all and singular the aforesaid
covenants, conditions and agreements to the true intent and The Surety and Performance Bonds do not contain any condition that CCCIC would be
meaning thereof, then this obligation shall be null and void, liable only if, in addition to the default on its undertakings by FFMCCI, the Republic also
otherwise to remain in full force and effect. made a claim against the PCIB Letter of Credit furnished by Kawasaki, on behalf of the
Kawasaki-FFMCCI Consortium. The Court agrees with the observation of the Court of
The liability of the Surety under this bond shall expire on October 27, 1989 and the Surety Appeals that "it is not provided, neither in the Consortium Agreement nor in the subject
does not assume responsibility for any liability incurred or created after said date. Any bonds themselves that before KAWASAKI may proceed against the bonds posted by
claims against this bond must be presented to the Surety in writing not later than ten (10) [FFMCCI] and CCCIC, the Philippine government as employer must first exercise its rights
days after said expiry date; otherwise, failure to do so shall forthwith release the Surety against the bond issued in its favor by the consortium." 32
from all liabilities under this bond and shall be a bar to any court action against it and
The Court cannot give any additional meaning to the plain language of the undertakings in clearly establish that the parties entered into a surety agreement as defined under Article
the Surety and Performance Bonds. The extent of a surety's liability is determined by the 2047 of the New Civil Code. x x x.
language of the suretyship contract or bond itself. Article 1370 of the Civil Code provides
that "[i]f the terms of a contract are clear and leave no doubt upon the intention of the xxxx
contracting parties, the literal meaning of its stipulations shall control. " 33

As provided in Article 204 7, the surety undertakes to be bound solidarily with the
There is no basis for the interpretation by CCCIC of the word "counter-guarantee" in principal obligor. That undertaking makes a surety agreement an ancillary contract as it
Article 10 of the Consortium Agreement. The first paragraph of Article 10 of the presupposes the existence of a principal contract. Although the contract of a surety is in
Consortium Agreement provides that Kawasaki, as the Consortium Leader, shall arrange, essence secondary only to a valid principal obligation, the surety becomes liable for the
at its own cost but on behalf of the Kawasaki-FFMCCI Consortium, for all necessary bonds debt or duty of another although it possesses no direct or personal interest over the
and guarantees under the Construction Contract with the Republic. The same paragraph obligations nor does it receive any benefit therefrom. Let it be stressed that
requires, in turn, that FFMCCI, at its own cost, to furnish Kawasaki with suitable counter- notwithstanding the fact that the surety contract is secondary to the principal obligation,
guarantees for the repayment by FFMCCI for the advance payment from Kawasaki and the surety assumes liability as a regular party to the undertaking.
performance by FFMCCI of its portion of work in the Project. Clearly, the "guarantees" and
"counter-guarantees" were securities for the fulfillment of the obligations of the
Kawasaki-FFMCCI Consortium to the Republic under the Construction Contract and of Stronghold Insurance Company, Inc. v. Republic-Asahi Glass Corporation, reiterating the
FFMCCI to the Consortium Leader Kawasaki under the Consortium Agreement, ruling in Garcia v. Court of Appeals, expounds on the nature of the surety's liability:
respectively. The CCCIC Surety and Performance Bonds were not counter-guarantees to
the PCIB Letter of Credit. In fact, in the event that the Republic did make a claim on the x x x. The surety's obligation is not an original and direct one for the performance of his
PCIB Letter of Credit, the second paragraph of Article 10 of the Consortium Agreement own act, but merely accessory or collateral to the obligation contracted by the principal.
stipulates Nevertheless, although the contract of a surety is in essence secondary only to a valid
principal obligation,
that Kawasaki and FFMCCI would still have to determine their respective
his liability to the creditor or promisee of the principal is said to be direct, primary and
responsibilities, reimbursements, and/or compensations according to the provisions of absolute; in other words, he is directly and equally bound with the principal.
the Consortium Agreement, instead of simply allowing Kawasaki to recover on the
"counter-guarantees" of FFMCCI. Suretyship, in essence, contains two types of relationship - the principal relationship
between the obligee (petitioner) and the obligor (Lucky Star), and the accessory surety
It is not disputed that FFMCCI, due to financial difficulties, was unable to repay the relationship between the principal (Lucky Star) and the surety (respondent). In this
advance payment it received from Kawasaki and to finish its scope of work in the Project, arrangement, the obligee accepts the surety's solidary undertaking to pay if the obligor
thus, FFMCCI defaulted on its obligations to Kawasaki. Given the default of FFMCCI, CCCIC does not pay. Such acceptance, however, does not change in any material way the
as surety obligee's relationship with the principal obligor. Neither does it make the surety an active
party to the principal obligee-obligor relationship. Thus, the acceptance does not give the
surety the right to intervene in the principal contract. The surety's role arises only upon
became directly, primarily, and absolutely liable to Kawasaki as the obligee under the the obligor's default, at which time, it can be directly held liable by the obligee for
Surety and Performance Bonds. The following pronouncements of the Court in Asset payment as a solidary obligor.
Builders Corporation v. Stronghold Insurance Company, Inc. 34 are relevant herein:

In the case at bench, when Lucky Star failed to finish the drilling work within the agreed
Respondent, along with its principal, Lucky Star, bound itself to the petitioner when it time frame despite petitioner's demand for completion, it was already in delay. Due to
executed in its favor surety and performance bonds. The contents of the said contracts
this default, Lucky Star's liability attached and, as a necessary consequence, respondent's default, while a guarantor contracts to pay if, by the use of due diligence, the debt cannot
liability under the surety agreement arose. Undeniably, when Lucky Star reneged on its be made out of the principal debtor.
undertaking with the petitioner and further failed to return the ₱575,000.00
downpayment that was already advanced to it, respondent, as surety, became solidarily xxx.
bound with Lucky Star for the repayment of the said amount to petitioner. The clause,
"this bond is callable on demand," strongly speaks of respondent's primary and direct
responsibility to the petitioner. Despite these distinctions, the Court in Cochingyan, Jr. v. R&B Surety & Insurance Co., Inc.,
and later in the case of Security Bank, held that Article 2079 of the Civil Code, which
pertinently provides that "[a]n extension granted to the debtor by the creditor without
Accordingly, after liability has attached to the principal, the obligee or, in this case, the the consent of the guarantor extinguishes the guaranty," equally applies to both contracts
petitioner, can exercise the right to proceed against Lucky Star or respondent or both. x x of guaranty and suretyship. The rationale therefore was explained by the Court as follows:
x. (Emphases supplied, citations omitted.)

The theory behind Article 2079 is that an extension of time given to the principal debtor
Article 2079 of the New Civil Code is not applicable to the instant case. by the creditor without the surety's consent would deprive the surety of his right to pay
the creditor and to be immediately subrogated to the creditor's remedies against the
To free itself from its liabilities under the Surety and Performance Bonds, CCCIC cites principal debtor upon the maturity date. The surety is said to be entitled to protect
Article 2079 of the Civil Code, which reads: Art. 2079. An extension granted to the debtor himself against the contingency of the principal debtor or the indemnitors becoming
by the creditor without the consent of the guarantor extinguishes the guaranty. The mere insolvent during the extended period.
failure on the part of the creditor to demand payment after the debt has become due
does not of itself constitute any extension of time referred to herein. Applying these principles, the Court finds that the payment extensions granted by Banque
Indosuez and PCI Capital to TIDCORP under the Restructuring Agreement did riot have the
The aforequoted provision clearly speaks of an extension for the payment of a debt effect of extinguishing the bonding companies' obligations to TIDCORP under the Surety
granted by the creditor to a debtor without the consent of the surety. The theory behind Bonds, notwithstanding the fact that said extensions were made without their consent.
Article 2079 was further explained by the Court in Trade and Investment Development This is because Article 2079 of the Civil Code refers to a payment extension granted by the
Corporation of the Philippines (Formerly Philippine Export and Foreign Loan Guarantee creditor to the principal
Corporation) v. Asia Paces Corporation, 35 thus: Comparing a surety's obligations with that
of a guarantor, the Court, in the case of Palmares v. CA, illumined that a surety is debtor without the consent of the guarantor or surety. In this case, the Surety Bonds are
responsible for the debt's payment at once if the principal debtor makes default, whereas suretyship contracts which secure the debt of ASP AC, the principal debtor, under the
a guarantor pays only if the principal debtor is unable to pay, viz.: Deeds of Undertaking to pay TIDCORP, the creditor, the damages and liabilities it may
incur under the Letters of Guarantee, within the bounds of the bonds' respective coverage
A surety is an insurer of the debt, whereas a guarantor is an insurer of the solvency of the periods and amounts. No payment extension was, however, granted by TIDCORP in favor
debtor. A suretyship is an undertaking that the debt shall be paid; a guaranty, an of ASP AC in this regard; hence, Article 2079 of the Civil Code should not be applied with
undertaking that the debtor shall pay. Stated differently, a surety promises to pay the respect to the bonding companies' liabilities to TIDCORP under the Surety Bonds.
principal's debt if the principal will not pay, while a guarantor agrees that the creditor,
after proceeding against the principal, may proceed against the guarantor if the principal The payment extensions granted by Banque Indosuez and PCI Capital pertain to TIDCORP's
is unable to pay. A surety binds himself to perform if the principal does not, without own debt under the Letters of Guarantee wherein it (TIDCORP) irrevocably and
regard to his ability to do so. A guarantor, on the other hand, does not contract that the unconditionally guaranteed full payment of ASPAC's loan obligations to the banks in the
principal will pay, but simply that he is able to do so. In other words, a surety undertakes event of its (ASP AC) default. In other words, the Letters of Guarantee secured ASPAC's
directly for the payment and is so responsible at once if the principal debtor makes loan agreements to the banks. Under this arrangement, TIDCORP therefore acted as a
guarantor, with ASP AC as the principal debtor, and the banks as creditors.
Proceeding from the foregoing discussion, it is quite clear that there are two sets of subsequent Agreement dated August 24, 1989 executed between Kawasaki and FFMCCI,
transactions that should be treated separately and distinctly from one another following without the consent of CCCIC.
the civil law principle of relativity of contracts "which provides that contracts can only
bind the parties who entered into it, and it cannot favor or prejudice a third person, even The Court first notes that the default of FFMCCI preceded the execution of the Agreement
if he is aware of such contract and has acted with knowledge thereof." Verily, as the on August 24, 1989 which purportedly novated the Consortium Agreement and, in effect,
Surety Bonds concern ASPAC's debt to TIDCORP and not TIDCORP's debt to the banks, the extinguished the Surety and Performance Bonds. As early as his letter dated July 20, 1989,
payments extensions (which conversely concern TIDCORP's debt to the banks and not ASP Mañacop, FFMCCI President, already admitted the inability of FFMCCI to continue with its
A C's debt to TIDCORP) would not deprive the bonding companies of their right to pay portion of work in the Project and authorized Kawasaki to continue the same. It was
their creditor (TIDCORP) and to be immediately subrogated to the latter's remedies precisely because FFMCCI defaulted on its obligations under the Consortium Agreement
against the principal debtor (ASP AC) upon the maturity date. It must be stressed that that necessitated the execution of the Agreement dated August 24, 1989 between
these payment extensions did not modify the terms of the Letters of Guarantee but only Kawasaki and FFMCCI, and this is evident from one of the "whereas" clauses in the said
provided for a new payment scheme covering TIDCORP's liability to the banks. In fine, Agreement which says that "due to some financial reverses[, FFMCCI] can no longer do its
considering the inoperability of Article 2079 of the Civil Code in this case, the bonding portion of the work under the Contract." The liabilities of CCCIC as surety to Kawasaki
companies' liabilities to TIDCORP under the Surety Bonds - except those issued by under the Surety and Performance Bonds had already attached upon the default of
Paramount and covered by its Compromise Agreement with TIDCORP - have not been FFMCCI while the said bonds were still in effect and prior to the alleged novation of the
extinguished. Since these obligations arose and have been duly demanded within the Consortium Agreement by the Agreement dated August 24, 1989 which resulted in the
coverage periods of all the Surety Bonds, TIDCORP's claim is hereby granted. extinguishment of the bonds.

Similarly, there are two sets of transactions in the present case covered by two different The Court expounded on the concept of novation in Reyes v. BPI Family Savings Bank,
contracts: the Consortium Agreement between Kawasaki and FFMCCI and the Inc.36
Construction Contract between the Republic and the Kawasaki-FFMCCI Consortium. The
Surety and Performance Bonds guaranteed the performance of the obligations of FFMCCI
to Kawasaki under the Consortium Agreement. The Republic was not a party in either the Novation is defined as the extinguishment of an obligation by the substitution or change
Surety and Performance Bonds or the Consortium Agreement. Under these of the obligation by a subsequent one which terminates the first, either by changing the
circumstances, there was no creditor-debtor relationship between the Republic and object or principal conditions, or by substituting the person of the debtor, or subrogating a
FFMCCI and Article 2079 of the Civil Code did not apply. The extension granted by the third person in the rights of the creditor.
Republic to Kawasaki modified the deadline for the completion of the Project under the
Construction Contract, but had no effect on the obligations of FFMCCI to Kawasaki under Article 1292 of the Civil Code on novation further provides:
the Consortium Agreement, much less, on the liabilities of CCCIC under the
Article 1292. In order that an obligation may be extinguished by another which substitute
Surety and Performance Bonds. the same, it is imperative that it be so declared in unequivocal terms, or that the old and
CCCIC failed to discharge the the new obligations be on every point incompatible with each other.
burden of proving the novation of
the Consortium Agreement which The cancellation of the old obligation by the new one is a necessary element of novation
would have extinguished its which may be effected either expressly or impliedly. While there is really no hard and fast
obligations under the Surety and rule to determine what might constitute sufficient change resulting in novation, the
Performance Bonds. touchstone, however, is irreconcilable incompatibility between the old and the new
obligations.
CCCIC argues that it was released from its obligations as surety under the Surety and
Performance Bonds because of the novation of the Consortium Agreement by the
In Garcia, Jr. v. Court of Appeals, we held that: CCCIC failed to discharge the burden of proving novation of the Consortium Agreement by
the Agreement dated August 24, 1989. The Court failed to see the presence of the
In every novation there are four essential requisites: (1) a previous valid obligation; (2) the essential requisites for a novation of contract, specifically, the irreconcilable
agreement of all the parties to the new contract; (3) the extinguishment of the old incompatibility between the old and new contracts. Indeed, Kawasaki and FFMCCI
contract; and (4) validity of the new one. There must be consent of all the parties to the executed the Agreement dated August 24, 1989 pursuant to Article 8.3 of the Consortium
substitution, resulting in the extinction of the old obligation and the creation of a valid Agreement:
new one .xx x. (Citations omitted.)
8.3 If, for any reason, any PARTY should fail in the performance of its PORTION OF WORK
It is well-settled that novation is never presumed - novatio non praesumitur. As the party or contractual obligations and if such defaulting PAR TY refuses to cure or makes no
alleging novation, the onus of showing clearly and unequivocally that novation had indeed remedial action, without presenting any valid cause, within fifteen (15) days following
taken place rests on CCCIC.The Court laid down guidelines in establishing novation, viz.: demand of rectification by registered letter sent by the other PARTY, the defaulting
PARTY's PORTION OF WORK may be performed at the account and responsibility of the
defaulting PARTY, by the non-defaulting PARTY or by any other contractor selected by the
Novation is never presumed, and the animus novandi, whether totally or partially, must non-defaulting PARTY and approved by the EMPLOYER. In such event, the defaulting
appear by express agreement of the parties, or by their acts that are too clear and PARTY or its representative shall, in no way, interfere with the performance of the
unequivocal to be mistaken. CONTRACT or impede the progress thereof, on any ground, and shall allow such
performing PARTY or the said contractor to use the materials and equipment of such
The extinguishment of the old obligation by the new one is a necessary element of defaulting PARTY, for the purpose of remedial action.
novation which may be effected either expressly or impliedly. The term "expressly" means
that the contracting parties incontrovertibly disclose that their object in executing the FFMCCI was unable to finish its portion of work in the Project because of business
new contract is to extinguish the old one. Upon the other hand, no specific form is reverses, and by the Agreement dated August 24, 1989, Kawasaki assumed the
required for an implied novation, and all that is prescribed by law would be an Transferred Portion of Work from FFMCCI and was accorded the right to receive the
incompatibility between the two contracts. While there is really no hard and fast rule to profits and benefits corresponding to said portion. Although the Agreement dated August
determine what might constitute to be a sufficient change that can bring about novation, 24, 1989 resulted in the reallocation of the respective portions of work of Kawasaki and
the touchstone for contrariety, FFMCCI, as well as their corresponding shares in the profits and benefits under the
Consortium Agreement, such changes were not incompatible with the object, cause, and
however, would be an irreconcilable incompatibility between the old and the new principal conditions of the Consortium Agreement. Consequently, the changes under the
obligations. Agreement dated August 24, 1989 were only modificatory and did not extinguish the
original obligations under the Consortium Agreement.
There are two ways which could indicate, in fine, the presence of novation and thereby
produce the effect of extinguishing an obligation by another which substitutes the same. Even granting that there is novation, the Court in Stronghold Insurance Company,
The first is when novation has been explicitly stated and declared in unequivocal terms. Incorporated v. Tokyu Construction Company, Ltd., 39 held that to release the surety, the
The second is when the old and the new obligations are incompatible on every point. The material change in the principal contract must make the obligation of the surety more
test of incompatibility is whether or not the two obligations can stand together, each one onerous. The Court ratiocinated in Stronghold as follows:
having its independent existence. If they cannot, they are incompatible and the latter
obligation novates the first. Corollarily, changes that breed incompatibility must be Petitioner's liability was not affected by the revision of the contract price, scope of work,
essential in nature and not merely accidental. The incompatibility must take place in any and contract schedule. Neither was it extinguished because of the issuance of new bonds
of the essential elements of the obligation, such as its object, cause or principal conditions procured from Tico.
thereof; otherwise, the change would be merely modificatory in nature and insufficient to
extinguish the original obligation.38 (Citations omitted.)
As early as February 10, 1997, respondent already sent a letter to Gabriel informing the Indeed, a surety is released from its obligation when there is a material alteration of the
latter of the delay incurred in the performance of the work, and of the former's intention principal contract in connection with which the bond is given, such as a change which
to terminate the subcontract agreement to prevent further losses. Apparently, Gabriel imposes a new obligation on the promising party, or which takes away some obligation
had already been in default even prior to the aforesaid letter; and demands had been already imposed, or one which changes the legal effect of the original contract and not
previously made but to no avail. By reason of said default, Gabriel's liability had arisen; as merely its form. However, a surety is not released by a change in the contract, which does
a consequence, so also did the liability of petitioner as a surety arise. not have the effect of making its obligation more onerous.

xxxx In the instant case, the revision of the subcontract agreement did not in any way make the
obligations of both the principal and the surety more onerous. To be sure, petitioner
By the language of the bonds issued by petitioner, it guaranteed the full and faithful never assumed added obligations, nor were there any additional obligations imposed, due
compliance by Gabriel of its obligations in the construction of the SDS and STP specifically to the modification of the terms of the contract. Failure to receive any notice of such
set forth in the subcontract agreement, and the repayment of the 15% advance payment change did
given by respondent. These guarantees made by petitioner gave respondent the right to
proceed against the former following Gabriel's non-compliance with her obligation. not, therefore, exonerate petitioner from its liabilities as surety. (Emphasis supplied,
citations omitted.)
Confusion, however, transpired when Gabriel and respondent agreed, on February 26,
1997, to reduce the scope of work and, consequently, the contract price. Petitioner There is no showing herein that the obligations of CCCIC as surety had become more
viewed such revision as novation of the original subcontract agreement; and since no onerous with the execution of the Agreement dated August 24, 1989 between Kawasaki
notice was given to it as a surety, it resulted in the extinguishment of its obligation. and FFMCCI. The Agreement dated August 24, 1989 did not alter in any way the original
coverage and the terms and conditions of the Surety and Performance Bonds of CCCIC. If
We wish to stress herein the nature of suretyship, which actually involves two types of truth be told, the Agreement dated August 24, 1989 made it more onerous for Kawasaki
relationship --the underlying principal relationship between the creditor (respondent) and which had to take over the Transferred Portion of Work from FFMCCI.
the debtor (Gabriel), and the accessory surety relationship between the principal (Gabriel)
and the surety (petitioner). The creditor accepts the surety's solidary undertaking to pay if That Kawasaki was to receive the profits and benefits corresponding to the Transferred
the debtor does not pay. Such acceptance, however, does not change in any material way Portion of Work would not extinguish the liabilities of CCCIC under the Surety and
the creditor's relationship with the principal debtor nor does it make the surety an active Performance Bonds. The right of Kawasaki to the profits and benefits corresponding to the
party to the principal creditor-debtor relationship. In other words, the acceptance does Transferred Portion of Work was granted under the Agreement dated August 24, 1989
not give the surety the right to intervene in the principal contract. The surety's role arises because Kawasaki was the one that would actually perform the remaining portion of work
only upon the debtor's default, at which time, it can be directly held liable by the creditor and complete the Project and should be duly compensated for the same. It is separate and
for payment as a solidary obliger. distinct from the right of Kawasaki to demand payment of the amounts guaranteed by
CCCIC as surety upon the default of FFMCCI on its undertakings under the Surety and
The surety is considered in law as possessed of the identity of the debtor in relation to Performance Bonds. CCCIC cannot standby passively and be benefitted by payments made
whatever is adjudged touching upon the obligation of the latter. Their liabilities are so by the Republic, as owner of the Project, to Kawasaki, as contractor, for the Transferred
interwoven as to be inseparable. Although the contract of a surety is, in essence, Portion of Work. The only way CCCIC can extinguish its liabilities as surety, which
secondary only to a valid principal
already attached upon the default of FFMCCI, is to make its own payments to Kawasaki of
obligation, the surety's liability to the creditor is direct, primary, and absolute; he the amounts guaranteed under the Surety and Performance Bonds.
becomes liable for the debt and duty of another although he possesses no direct or
personal interest over the obligations nor does he receive any benefit therefrom.
Equally without merit is the averment of CCCIC that by executing the Agreement dated (4) Damages, if they are due. Art. 2067. The guarantor who pays is subrogated by virtue
August 24, 1989, which gave Kawasaki the right to the profits and benefits corresponding thereof to all the rights which the creditor had against the debtor.
to the Transferred Portion of Work, Kawasaki and FFMCCI colluded or connived to deprive
CCCIC of its source of indemnification. Other than its allegation, CCCIC failed to present If the guarantor has compromised with the creditor, he cannot demand of the debtor
any evidence of collusion or connivance between Kawasaki and FFMCCI to intentionally more than what he has really paid.
prejudice CCCIC. The Court reiterates that the execution of the Agreement dated August
24, 1989 was actually authorized under Article 8.3 of the Consortium Agreement.
Kawasaki was given the right to the profits and benefits corresponding to the Transferred Although the foregoing provisions only speak of a guarantor, they also apply to a surety,
Portion of Work because it would be the one to perform the same. It would be the height as the Court held in Escano v. Ortigas, Jr. 40
of inequity to allow FFMCCI to continue collecting payments for work it was not able to
do. Besides, there is utter lack of basis for the claim of CCCIC that without the What is the source of this right to full reimbursement by the surety? We find the right
compensation for the Transferred Portion of Work, FFMCCI would have no means to under Article 2066 of the Civil Code, which assures that "[t]he guarantor who pays for a
indemnify CCCIC for any payments the latter would have to make to Kawasaki under the debtor must be indemnified by the latter," such indemnity comprising of, among others,
Surety and Performance Bonds. As the succeeding discussion will show, it is premature for "the total amount of the debt." Further, Article 2067 of the Civil Code likewise establishes
CCCIC to question the capacity of FFMCCI to indemnify it. that "[t]he guarantor who pays is subrogated by virtue thereof to all the rights which the
creditor had against the debtor."
CCCIC must first pay its liabilities to
Kawasaki under the Surety and Articles 2066 and 2067 explicitly pertain to guarantors, and one might argue that the
Performance Bonds before it could provisions should not extend to sureties, especially in light of the qualifier in Article 2047
be indemnified and subrogated to the that the provisions on joint and several obligations should apply to sureties. We reject
rights of Kawasaki against FFMCCI. that argument, and instead adopt Dr. Tolentino's observation that "[t]he reference in the
second paragraph of [Article 2047] to the provisions of Section 4, Chapter 3, Title I, Book
The rights of a guarantor who pays for the debt of the debtor are governed by the IV, on solidary or several obligations, however, does not mean that suretyship is
following provisions of the Civil Code: withdrawn from the applicable provisions governing guaranty." For if that were not the
implication, there would be no material difference between the surety as defined under
Article 204 7 and the joint and several debtors, for both classes of obligors would be
Art. 2066. The guarantor who pays for a debtor must be indemnified by the latter.

governed by exactly the same rules and limitations.


The indemnity comprises:

Accordingly, the rights to indemnification and subrogation as established and granted to


(1) The total amount of the debt; the guarantor by Articles 2066 and 2067 extend as well to sureties as defined under
Article 2047. x x x. (Citations omitted.)
(2) The legal interests thereon from the time the payment was made known to the debtor,
even though it did not earn interest for the creditor; Pursuant to Articles 2066 and 2067, the rights of CCCIC as surety to indemnification and
subrogation will arise only after it has paid its obligations to Kawasaki as the debtor-
(3) The expenses incurred by the guarantor after having notified the debtor that payment obligee. In Autocorp Group v. Intra Strata Assurance Corporation, 41 the Court ruled that:
had been demanded of him;
The benefit of subrogation, an extinctive subjective novation by a change of creditor,
which "transfers to the person subrogated, the credit and all the rights thereto
appertaining, either against the debtor or against third persons," is granted by the Article "The regular mode, in other words, of serving summons upon a private Philippine
2067 of the Civil Code only to the "guarantor (or surety) who pays." (Emphases supplied, Corporation is by personal service upon one of the officers of such corporation identified
citations omitted.) in Section 13. Ordinarily, such personal service may be expected to be made at the
principal office of the corporation. Section 13, does not, however, impose such
In the present case, CCCIC has yet to pay Kawasaki. requirement, and so personal service upon the corporation may be effected through
service upon, for instance, the president of the corporation at his office or residential
address." xx x.
While summons was validly served
upon FFMCCI, the Third-Party
Complaint of CCCJC against In fine, the service of summons upon respondent Baliwag Transit is proper. Consequently,
FFMCCI is dismissed on the ground the trial court validly acquired jurisdiction over respondent Baliwag. (Citation omitted.)
of lack of cause of action.
Hence, the personal service of the Alias Summons on an FFMCCI director was sufficient for
The Court disagrees with the ruling of the Court of Appeals that there was no proper the RTC to acquire jurisdiction over FFMCCI itself.
service of summons upon FFMCCI. The appellate court overlooked the fact that the
service of summons on FFMCCI at its principal address at #86 West A venue, Quezon City Nevertheless, the Third-Party Complaint filed by CCCIC against FFMCCI and Mañacop must
failed because FFMCCI had already vacated said premises without notifying anyone as to be dismissed on the ground of lack of cause of action.
where it transferred. For this reason, the RTC, upon the motion of CCCIC, issued an
Order42 dated September 4, 1991, directing the issuance and service of Alias Summons to A cause of action is defined as the act or omission by which a party violates a right of
the individual directors of FFMCCI. Eventually, the Alias Summons was personally served another. The essential elements of a cause of action are: (a) the existence of a legal right
upon FFMCCI director Vicente Concepcion on September 25, 1991.43 in favor of the plaintiff; (b) a correlative legal duty of the defendant to respect such right;
and ( c) an act or omission by such defendant in violation of the right of the plaintiff with a
Rule 14, Section 13 of the 1964 Rules of Court, which was then in force, allowed the resulting injury or damage to the plaintiff for which the latter may maintain an action for
service of summons upon a director of a private domestic corporation: the recovery of relief from the defendant. 46

Sec. 13. Service upon private domestic corporation or partnership. - If the defendant is a As discussed earlier, the rights to indemnification and subrogation of a surety only arise
corporation organized under the laws of the Philippines or a partnership duly registered, upon its payment of the obligation to the obligee. In the case at bar, since CCCIC up to this
service may be made on the president, manager, secretary, cashier, agent, or any of its point refuses to acknowledge and pay its obligation to Kawasaki under the Surety and
directors. Performance Bonds, it has not yet acquired the rights to seek indemnification from
FFMCCI and subrogation to Kawasaki as against FFMCCI. In the same vein, the
The aforementioned rule does not require that service on the private domestic corresponding obligation of FFMCCI to indemnify CCCIC under the Indemnity Agreements
corporation be served at its principal office in order for the court to acquire jurisdiction has yet to accrue. Thus far, there is no act or omission on the part of FFMCCI which
over the same. The Court, in Talsan Enterprises, Inc. vs. Baliwag Transit, lnc., 44 citing violated the right of CCCIC and for which CCCIC may seek relief from the courts. In the
Baltazar v. Court of Appeals,45 affirmed that: absence of these elements, CCCIC has no cause of action against FFMCCI and/or FFMCCI
President Mañacop. Resultantly, the Third-Party Complaint of CCCIC should be dismissed.

[S]ervice on respondent's bus terminal at the address stated in the summons and not in its
main office in Baliwag do not render the service of summons invalid. 1âwphi1 In Artemio There is no basis for awarding
Baltazar v. Court of Appeals, we held: attorney's fees in favor of Kawasaki.
In addition, the rate of legal interest
imposed shall conform with latest 1) The Third-Party Complaint filed by CCC Insurance Corporation against F.F. Mañacop
jurisprudence. Construction Company, Inc. and Mr. Florante F. Mañacop is DISMISSED on the ground of
lack of cause of action;
Article 2208(2) of the Civil Code allows the award of attorney's fees "[w]hen the
defendant's act or omission has compelled the plaintiff to litigate with third persons or to 2) The award of attorney's fees in favor of Kawasaki Steel Corporation is DELETED; and
incur expenses to protect his interest[.]" In Servicewide Specialists, Incorporated v. Court
of Appeals,47 the Court declared that: 3) In addition to the amounts CCC Insurance Corporation is ordered to pay Kawasaki Steel
Corporation under Surety Bond No. B-88/11191 and Performance Bond No. B-88/11193,
Article 2208 of the Civil Code allows attorney's fees to be awarded by a court when its CCC Insurance Corporation is further ORDERED to pay Kawasaki Steel Corporation legal
claimant is compelled to litigate with third persons or to incur expenses to protect his interest on said amounts at the rates of 12% per annum from September 15, 1989 to June
interest by reason of an unjustified act or omission on the part of the party from whom it 30, 2013 and 6% per annum from July 1, 2013 until full payment thereof.
is sought. To be sure, private respondents were forced to litigate to protect their rights
but as we have previously held: "where no sufficient showing of bad faith would be SO ORDERED.
reflected in a party's persistence in a case other than an erroneous conviction of the
righteousness of his cause, attorney's fee shall not be recovered as cost." (Citation
omitted.)

Bad faith has been defined as "a breach of a known duty through some motive of interest
or ill will. It must, however, be substantiated by evidence. Bad faith under the law cannot
be presumed, it must be established by clear and convincing evidence." 48 There is no
evidence in this case to show bad faith on the part of CCCIC. CCCIC, in refusing the claim of
Kawasaki, was merely acting based on its belief in the righteousness of its defense. Hence,
even though Kawasaki was compelled to litigate to enforce its claim against CCCIC, the
award of attorney's fees is not proper.

Finally, the Court, in Nacar v. Gallery Frames, 49 modified the guidelines in imposing
interests, taking into account Bangko Sentral ng Pilipinas-Monetary Board Resolution No.
796 dated May 16, 2013 and Circular No. 799, series of 2013, which fixed the legal rate at
6% per annum effective July 1, 2013. In the absence of stipulated interest in the present
case, the Court imposes upon the amounts covered by the Surety and Performance Bonds
the legal rate of 12% per annum from September 15, 1989, the date of demand, until June
30, 2013; and then the legal rate of6% per annum from July 1, 2013 until full payment of
the same.

WHEREFORE, premises considered, the instant Petition for Review on Certiorari is PARTLY
GRANTED. The Decision dated May 30, 2002 and Resolution dated November 14, 2002 of
the Court of Appeals are AFFIRMED with the following MODIFICATIONS:

You might also like