Generator House
Generator House
DETAILED ESTIMATE
1. Labor
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 2 days 500 1,000.00
2 Unskilled Laborers 2 days 300 1,200.00
Total 2,200.00
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 35 bags Portland Cement 250 8,750.00
2 5 Cu.m. Course Agrregates (G-1) 800 4,000.00
3 3 Cu.m. Fine Aggregates 800 2,400.00
4 10 Kg. No. 16 Tie Wire 75 750.00
Total 15,900.00
2. Labor
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 3 days 500 1,500.00
1 Skilled Labor 3 days 400 1,200.00
2 Unskilled Laborers 3 days 300 1,800.00
Total 4,500.00
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 16 Kg. 16mm x 6m RSB 365 5,840.00
2 28 Kg. 12mm x 6m RSB 214 5,992.00
3 24 Kg. 10mm x 6m RSB 142 3,408.00
4 10 Kg. No. 16 Tie Wire 75 750.00
Total 15,990.00
2. Labor : Duration: 391/100 3.91 days
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 4 days 500 2,000.00
1 Skilled Labor 4 days 400 1,600.00
1 Unskilled Laborers 4 days 300 1,200.00
Total 4,800.00
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 310 pcs 100mm CHB 13 4,030.00
2 11 pcs 10mm x 6m RSB 142 1,562.00
3 3 Cu.m. Washed Sand 800 2,400.00
4 15 bags Portland Cement 250 3,750.00
5 7 Kg. No. 16 Tie Wire 75 525.00
Total 12,267.00
2. Labor :
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 4 days 500 2,000.00
1 Skilled Labor 4 days 400 1,600.00
1 Unskilled Laborers 4 days 300 1,200.00
Total 4,800.00
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 5 pcs 50mmx100mmx 6m x 0.50mm thick C-Purlins 375 1,875.00
2 3 pcs 50mmx150mmx 6m x 0.50mm thick C-Purlins 425 1,275.00
3 6 pcs 10mmx300mm hardisenepa 370 2,220.00
4 2 Kgs Rivets 90 180.00
5 1 pc Hand-riveter 365 365.00
Total 5,915.00
2. Labor :
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 2 days 500 1,000.00
1 Skilled Labor 2 days 400 800.00
1 Unskilled Laborers 2 days 300 600.00
Total 2,400.00
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 5 pcs ¼" x 4' x 8' Hardiflex 520 2,600.00
2 7 pcs 2" x 2" x 12' ceiling studs @45/bf 180 1,260.00
3 7 Kg. Assorted CWN 75 525.00
Total 4,385.00
2. Labor :
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 1 days 500 500.00
1 Skilled Labor 1 days 400 400.00
1 Unskilled Laborers 1 days 300 300.00
Total 1,200.00
VII. FORM WORKS ( includes fabrication, installation, dismantling of forms and depositing to the DENR office)
Quantity: 1 Lot
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 7 pcs ¼" x 4' x 8' ordinary plywood 375 2,625.00
2 7 pcs 2" x 2" x 12' ceiling studs @45/bf 180 1,260.00
3 10 Kg. Assorted CWN 75 750.00
Total 4,635.00
2. Labor :
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 1 days 500 500.00
1 Skilled Labor 1 days 400 400.00
1 Unskilled Laborers 1 days 300 300.00
Total 1,200.00
VIII. TINSMITHTRY
Quantity: 1 Lot
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 4 LM 0.5mm Long Span (ribb-type) x 4.0m long 295 4,720.00
2 3 pcs 0.50mm GI Flashing 105 315.00
3 2 Kg. TEKSCREW (drilled type) 95 190.00
Total 5,225.00
2. Labor :
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 1 days 500 500.00
1 Skilled Labor 1 days 400 400.00
1 Unskilled Laborers 1 days 300 300.00
Total 1,200.00
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 1 pc Double Trhough Panel Box 1500 1,500.00
2 1 LM 5.5mm THHN electrical Wire 95 95.00
3 1 pc HD female socket/plug 120 120.00
4 1 pc LED bulb and electrical tape 250 250.00
5 1 LM 3.5mm THHN electrical wire 45 45.00
Total 2,010.00
2. Labor :
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 1 days 500 500.00
1 Skilled Labor 1 days 400 400.00
Total 900.00
Direct Cost 2,910.00
OCM (10%) 291.00
Contractor's Profit (10%) 291.00
Sub-total 3,492.00
VAT (5%) 174.60
Total Cost 3,666.60
Unit Cost 3,666.60
ITEM COST 3,666.60
X. DOORS AND WINDOWS
Quantity: 1 Lot
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 1 set0.9mx2.10m panel door w/jambs & complete accessories8500 8,500.00
1. Materials
Item No. Quantity Unit Particulars Unit Cost Amount
1 2 gal Flatwall latex paint (boysen white) 560 1,120.00
2 1 gal Hi-Gloss latex paint (boysen white) 620 620.00
3 1 gal Concrete nuetralizers 320 320.00
4 1 pc Roller paint brush with pan 100 100.00
5 1 pc 4" paint brush 75 75.00
Total 2,235.00
2. Labor :
Number Particulars Duration Unit Daily Rate Amount
1 Foreman 1 days 500 500.00
1 Skilled Labor 1 days 400 400.00
Total 900.00
PROGRAM OF WORK
Name of Project REPAIR AND REHABILITATION OF CENRO GENERATOR HOUSE
Location JUNCTION, PINUKPUK, KALINGA
Appropriation
Source of Fund
Length
Starting Date 7 DAYS UPON RECEIPT OF NOTICE TO PROCEED
No. of Working Days CALENDAR DAYS
Project Description
Approved:
NOEL M. BARRIENTOS
OIC-PENR Officer
Republic of the Philippines
Department of Environment and Natural Resources
Cordillera Admnistrative Region
PROVINCIAL ENVIRONMENT AND NATURAL RESOURCES OFFICE
Province of Kalinga
PROGRAM OF WORK
Name of Project CONSTRUCTION OF GENERATOR HOUSE
Location DAGUPAN, TABUK CITY, KALINGA
Appropriation
Source of Fund
Length
Starting Date 7 DAYS UPON RECEIPT OF NOTICE TO PROCEED
No. of Working Days CALENDAR DAYS
Project Description
PROGRAM OF WORK
Name of Project CONSTRUCTION OF GENERATOR HOUSE
Location BULANAO, TABUK CITY, KALINGA
Appropriation
Source of Fund
Length
Starting Date 7 DAYS UPON RECEIPT OF NOTICE TO PROCEED
No. of Working Days CALENDAR DAYS
Project Description
1 2 3 4 5 6 7 8
SPL CONSTRUCTION OCCUPATIONAL SAFETY ABD HEALTH PROGRAM
I EARTHWORKS 13.72 CU.M. 2,200.00 220 220 20%
II CONCRETE WORKS 4.6 CU.M. 20,400.00 2040 2040 20%
II REINFORCING STEEL WORKS 391.24 KGS 20,790.00 2079 2079 20%
IV MASONRY WORKS 24.58 SQ.M. 17,067.00 1706.7 1706.7 20%
V ROOF FRAMING WORKS 1 LOT 8,315.00 831.5 831.5 20%
VI CEILING WORKS 1 LOT 5,585.00 558.5 558.5 20%
VII FORM WORKS 1 LOT 5,835.00 583.5 583.5 20%
VIII TINSMITHTRY 1 LOT 6,425.00 642.5 642.5 20%
IX ELECTRICAL WORKS 1 LOT 2,910.00 291 291 20%
X DOORS AND WINDOWS 1 LOT 12,900.00 1290 1290 20%
XI PAINTING WORKS 1 LOT 3,135.00 313.5 313.5 20%
XII TARPUALIN/SIGNAGE 0
TOTAL 105,562.00 10,556.20 10,556.20
Approved:
NOEL M. BARRIENTOS
OIC-PENR Officer