Information Leaflet - BWMC - August 2009

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Ballast Water Management

Convention
General information – status August 2009

DNV Maritime
The Convention specifies two standards to satisfy its require- exchange of ballast water will be phased out and no longer
ments, Ballast Water Exchange (Standard D-1) and Ballast Water acceptable. Ballast water treatment will then be the only accept-
Treatment (Standard D-2). able method.

1. BALLAST WATER EXCHANGE 2. BALLAST WATER TREATMENT

In order to meet the requirements of the Ballast Water Ballast water treatment systems used to treat ballast water to meet
Management Convention Regulation B-4 (see footnote 2 in the the standard specified in Regulation D-2 of the Convention, must
Table above), there are three approved exchange methods that be type approved in accordance with the G8 guidelines and/or
can be used: G9 procedures of the Convention (ref. resolutions
MEPC.174(58) and MEPC.126(53) respectively).
Sequential method: a process by which a ballast tank or hold
intended for the carriage of ballast water is first emptied of at The G8 is a set of guidelines for approval of ballast water man-
least 95% of its volume and then refilled with replacement bal- agement systems.
last water.
The G9 is a set of procedures for approval of Active Substances
Flow through method: a process by which replacement ballast used in the treatment system.
water is pumped into a ballast tank or hold allowing water to
overflow through openings on open deck. At least 3 times the A treatment system using active substances must receive Basic
tank or hold volume shall be pumped through the tank or and Final Approval from GESAMP-BWWG – following the G9
Figure 1 States with restrictions on ballast water hold. procedures – before a Type Approval Certificate may be issued by
the Administration. Such systems are then approved following
Dilution method: a process by which replacement ballast water is both the G8 guidelines and the G9 procedures.
filled through the top of the ballast tank or hold with simulta-
The status of the Ballast Water Management Convention Until the Convention enters into force, a number of States have neous discharge from the bottom at the same flow rate and A treatment system not using active substances does not need to
(Convention) per August 2009 is that 18 States representing introduced, or plan to introduce, restrictions on ballast water for maintaining a constant level in the tank or hold. At least 3 follow the G9 procedures and may thus receive a Type Approval
15.36% of the gross tonnage of the world’s merchant fleet have ships entering their territorial waters. These States are per times the tank or hold volume shall be pumped through the Certificate directly from the Administration. Such systems are
ratified the Convention. Those states are: August 2009: tank or hold. approved following the G8 guidelines.

I Antigua & Barbuda I Argentina As the Convention starts entering into force for the different Per August 2009, the status of approval of the different treatment
I Albania I Australia types of ships, as given in Figure 2 below, these methods of systems is as follows:
I Barbados I Bahrain
I Egypt I Brazil
I France I Canada
Treatment system Approving Administration Following G8 or G8&G9
I Kenya I Chile
I Kiribati I Egypt PureBallast – Alfa Laval DNV on behalf of Norway G8 & G9
I Liberia I Georgia
I Maldives I Iran OceanSaver® – OceanSaver DNV on behalf of Norway G8 & G9
I Mexico I Iraq Sedna® – Hamann AG Germany G8 & G9
I Nigeria I Israel
Electro-Cleen™ - Techcross Republic of Korea G8 & G9
I Norway I Kuwait
I St. Kitts & Nevis I Lithuania NEI Treatment Systems Liberia and Marshall Islands G8
I Sierra Leone I New Zealand Hyde Marine BWTS LR on behalf of the UK G8
I South Africa I Norway
I Spain I Oman
I Syria I Panama Channel
I Tuvalu I Peru
I Qatar 3. BALLAST WATER MANAGEMENT PLAN Brazil and Norway require that the plans are approved; Brazil has
The Convention will enter into force 12 months after the date on I Russia delegated the approval of the plans to class. Norway, although a
which not less than 30 States representing not less than 35% of I Saudi Arabia Guidelines on how a Ballast Water Management Plan must be set formal delegation is not yet given, will probably delegate the
the gross tonnage of the world’s merchant fleet have ratified the I Turkey up have been developed within IMO. The Guidelines are given approval of the ballast water management plans to class.
Convention. I Ukraine in Resolution MEPC.127(53).
I United Arab Emirates DNV approves Ballast Water Management Plans found to be in
When the Convention enters into force, ballast management I USA compliance with the aforementioned guidelines, as mentioned in 4. BALLAST WATER RECORD BOOK
becomes an international requirement and the entire world fleet I UK (Orkney Island) footnote 4 in the Table below.
(with some exemptions) will have to comply with the standards A Ballast Water Management Plan for ships using exchange The Ballast Water Record book should contain at least the infor-
in the Convention. methods is different than a Ballast Water Management Plan for mation contained in Appendix II of the Convention.
ships using treatment methods. However, the Guidelines given in
Resolution MEPC.127(53) are valid for both methods.

2 3
5. NATIONAL REQUIREMENTS FOR BALLAST WATER MANAGEMENT

State Ports Ships Exchange Treatment Ballast Water Ballast Water Entry into Additional information
Management Plan Record Book force

Argentina All All Yes Yes1 Yes Yes 1998 See www.prefecturanaval.gov.ar

Australia All All Yes2 Recommended 2001 See www.daff.gov.au/aqis

Brazil All All3 Yes2 Yes4 Yes 2006 See www.dpc.mar.mil.br

ROPME area (Bahrain, Iran, Iraq, All in ROPME All ships entering Yes5 2009-11-01 Refer to document MEPC.59/INF.3.
Kuwait, Oman, Saudi Arabia, sea area ROPME sea area
Qatar & United Arab Emirates)

Canada All All Yes2 Yes Yes 2000 See www.tc.gc.ca/marinesafety/oep/

Chile All All Yes2 Yes 1995

Egypt Alexandria All Yes

Georgia All All Yes Yes6

Israel All All Yes7

Lithuania Klaipeda & Butinge All Yes8 Advised Advised See HELCOM (Helsinki Commission)
Oil Terminal recommendations

New Zealand All All Yes2 Yes9 No10 Yes 1998 See www.biosecurity.govt.nz/enter/ships/ballast

Norway All All Yes2 Yes1 Yes4 Yes 2010-01-01 See www.regjeringen.no/en/dep/md.html?id=668

Panama Panama Canal11 All 1999 See www.pancanal.com

Peru All All Yes12 Yes13 Yes See www.dicapi.mil.pe

Russia Novorossiysk All Yes14 2006 See www.nmtp.info/en

Turkey All All Yes

Ukraine All All Yes15 Yes16 See www.kmu.gov.ua

United States of America All All17 Yes Yes18 Yes19 2004 See www.uscg.mil/hq/cg5/cg522/cg5224/bwm.asp

United Kingdom All ports in the All20 See www.orkneyharbours.com


(Orkney Islands) Scapa Flow

1 Type approved treatment system in accordance with 6 Treatment may be accepted. Owners are advised to 12 All ballast water must be exchanged at least 12nm 17 All ships entering US EEZ (Exclusive Economic Zone)
IMO guidelines consult with the port authorities first from the Peruvian coast. The requirement also except passenger ships equipped with ballast water
applies to ballast water taken up in a Peruvian port. treatment systems and crude oil tankers engaged in
2 Ballast water exchange is required to be performed 7 All ships entering the coast of Israel have to US coastwise trade
in accordance with Regulation B-4 of the Convention, exchange the ballast water beyond any continental 13 In addition to the Ballast Water Management Plan, a
meeting the standard of Regulation D-1 of the shelf or fresh water current effect Ballast Water Notification must be submitted to the 18 Approved ballast water treatment methods. Contact
Convention Maritime Authority the US Coast Guard to find out if the installed
8 All ships coming to the Baltic Sea have to exchange treatment system is approved or not
3 Exemptions are given to Offshore Supply Vessels ballast in the North Sea 14 All ballast must be exchanged in the Black Sea before
arriving to Novorossiysk 19 Ballast reports are required to be submitted to the
4 Approved by the Administration 9 Ships are required to clean the ballast water either US authorities
onboard or onshore 15 All ships arriving to a port in Ukraine must have
5 Ballast Water Exchange is required to be performed exchanged the ballast water in the Black Sea 20 See www.orkneyharbours.com for more details on
in accordance with Regulation B-4 of the Convention; 10 A ballast declaration must be submitted before ship types and requirements for exchange and
no standards are mentioned entering the port 16 Ships must apply for discharging ballast water in the delivery to reception facilities.
ports
11 No ballast water can be discharged in the Panama
Canal

4 5
6. IMPLEMENTATION SCHEDULE OF THE CONVENTION d. Safety issues related to gas generation during treatment Ballast water from ballast tanks adjacent to cargo tanks in which
of the ballast water liquids with flash point not exceed 60°C is present, is not allowed
The following chart illustrates the implementation schedule of the Some ballast water treatment systems use or generate different to be led to the engine room because of risk of leakage of flam-
Convention based on the keel-laid date of the ship and its ballast toxic and flammable gases in order to achieve the required treat- mable gases. Following the same reasoning, it is not allowed to
water capacity: ment level by the Convention. take ballast water from such ballast tanks into gas safe rooms on
deck.
A guideline for the storage of chemicals onboard ships has been
developed at IMO, given in BWM.2/Circ.20 dated 21st July 2009.
8. CLASS NOTATIONS RELATED TO THE BALLAST WATER
Toxicity, explosion and flammability of the gases generated while MANAGEMENT CONVENTION IN DNV
treating the ballast water must be considered and proposals for
dealing with those gases (ventilation, fire fighting, alarms etc.) DNV has developed class notations related to the Ballast Water
will be considered and approved by DNV. Management Convention.

Typical gases are: Hydrogen (H2), Ozone (O3), Methane (CH4) The following class notations are available (ref. DNV Rules Pt.6
and Sodium Hypochlorite (NaClO). Ch.18):

e. Inerting of ballast tanks BWM-E ( ) Ballast water exchange. This notation is applicable to
Some ballast water treatment systems combine their technology ships complying with the Convention by means of ballast water
with inerting of the ballast tanks. Inerting of ballast tanks as part exchange. The exchange of the ballast water could take place
of normal operation represents an increased risk for personnel either by the sequential method, dilution method or by the
in connection with tank entry. flow through method. The applied method is indicated by the
letters in the bracket:
The governing rule with respect to piping system of the ballast d for dilution method
tanks is that it must be possible to over-pump the ballast tanks s for sequential method
within the pressure limits of the structure. Pressure drop calcula- f for flow-through method
Figure 2 Implementation chart of the Ballast Water Convention tions must be submitted for approval.
D-1 standard refers to ballast water exchange BWM-EP ( ) Ballast water enhanced exchange-performance. The
D-2 standard refers to ballast water treatment The following alternatives are accepted to DNV as means to application of this notation is the same as the BWM-E ( ) nota-
maintain the Inert Gas pressure in the ballast tank: tion; however, additional performance parameters of the
For ships keel-laid in 2009, Assembly Resolution A.1005(25) asks Administrations to postpone the implementation of the Convention I Pressure relief loop with discharge directly overboard. pumping system are required to receive this notation.
until the 2nd annual survey of the ship but not later than 31st December 2011.
I Pressure-Vacuum valves with means to release water.

BWM-T Ballast water treatment. This notation is applicable to


Discharging of ballast normally ensures that there is adequate vessels complying with the Convention by means of system(s)
oxygen levels in ballast tanks, although one is frequently strug- for treatment of ballast water complying with the Guidelines
7. ITEMS FOR CONSIDERATION WHEN CHOOSING/ I New pressure drop calculations for the air pipes of the ballast gling with achieving adequate levels in the double bottom area for Approval of Ballast Water Management Systems.
INSTALLING BALLAST WATER TREATMENT SYSTEMS tanks in case the flow rate increases (portable fans with plastic hoses leading to the double bottoms
are normally required arranged prior to tank entry). BWM-TP Ballast water treatment (prototype). This notation is
a. Ballast water pump capacity vs. ballast water treatment c. Bypass operations of the treatment system applicable to vessels complying with the Convention by means
system capacity The guidelines for type approval of ballast water treatment sys- The following assessments must be considered when inerting bal- of system(s) for treatment of ballast water complying with the
The ballast water pumping capacity (1 pump) of a ship cannot tems require, in the event of an emergency, that suitable bypasses last tanks: Guidelines for Approval of Prototype Ballast Water Treatment
exceed the capacity (Treatment Rated Capacity, TRC) of the or overrides of the treatment system to protect the safety of the I Assessment of capacity of the P/V-valve during discharging Technologies.
treatment system, as given in the Type Approval Certificate of the ship and personnel should be arranged. Such bypasses should (vacuum) and ballasting (pressure relief with water).
treatment system. activate an alarm, and the bypass event should be recorded by I Arrangements for ventilating double bottom part of ballast

the Control Equipment of the treatment system. The alarms are tanks must be provided. 9. TYPE APPROVAL OF BALLAST WATER TREATMENT
In case two pumps (where capacity of both pumps exceed the audible and visual signals in all stations from which ballast water I Inerted ballast tanks to have direct access to open deck. SYSTEMS IN DNV
TRC of the installed treatment system) are connected to the operations are controlled. I Air and Sounding pipes to be led to open deck.

treatment system, instructions in the Ballast Water Management I Warning signs posted at the manholes of the ballast tanks. DNV has developed a Type Approval Programme for Ballast
Plan stating that only one pump can be run at a time must be Any additional bypass possibility of the treatment unit in a ballast I Safety procedures for tank entry for the ballast tanks to be Water Treatment Systems. This is given in Type Approval
included. system must in general be avoided or logged automatically in the included in the ship’s safety manual. Programme No.771.91.
A possible solution when the ballast pumping capacity exceeds treatment system’s control unit. This in general is applicable in I Leakage hazards from an inerted tank to a non-inerted tank

the TRC of the treatment system is to install an orifice in the cases of heeling operations or other internal movement of ballast must be considered and identified with relevant procedures in The DNV Type Approval Programme, together with the
inlet pipe to the treatment system to limit the flow. water in the ship. These operations must be identified by the the ship’s safety manuals. Guidelines G8 and Procedures G9 developed at IMO, constitute
control unit of the treatment system to avoid triggering the DNV’s reference when doing Type Approval of a Ballast Water
b. Ballast pump pressure head bypass alarm. f. Installation of treatment equipment in gas dangerous Treatment System.
Some ballast water treatment systems will need new or additional zones
ballast water pumps. Ballast water pumps with increased head Accidental filling and discharging by gravity of the ballast water For oil tankers and chemical carriers with liquid products having In total, DNV is engaged in the Type Approval of 5 ballast water
may cause some challenges to be considered: must be avoided by installing non-return valves on the ballast a flash point not exceeding 60°C, all electrical equipment must treatment systems, two of which have already received their Type
I Suitability of existing flanges to tackle the higher pressure in piping between the overboard discharge outlet and the ballast be based in a non-hazardous area, or must be certified as safe for Approval Certificate.
the system tanks. use in a hazardous area.

6 7
DNV (Det Norske Veritas)
NO-1322 Høvik, Norway
Tel: +47 67 57 99 00
Fax: +47 67 57 99 11

www.dnv.com

CONTACTS IN DNV

I Ballast Water Management Convention, Type Approval of Ballast Water Treatment Systems and
approval of Ballast Water Management Plans for systems using treatment method, DNV Rules, Surveys
Section for Piping Systems, Cargo Handling and Gas Carriers, MNBNA880

Coor Design 0909-029


MNBNA880@dnv.com

I Approval of Ballast Water Management Plans for systems using exchange methods
Section for Stability, MNBNA845
MNBNA845@dnv.com

© Det Norske Veritas AS 10-2009


I Consultancy related to Ballast Water Management Plans
Section for Stability Advisory Services, MNBNC369
MNBNC369@dnv.com

IConsultancy related to Ballast Water Treatment Systems


DNV Maritime Solutions, MNBNC311
maritimesolutions@dnv.com

You might also like