Monthly Progress Report For The Month of June-2020

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

Four laning/Two Laning with paved shoulder from Km 0.000 to Km 83.

453 of Dausa-Lalsot-Kauthun
section of NH-11A Extn. in the State of Rajasthan under
NHDP Phase IV on Hybrid Annuity Mode
CLIENT : NATIONAL HIGHWAYS AUTHORITY OF INDIA
NAME OF CONSULTANT : SAI CONSULTING ENGINEERS PVT.LTD.
NAME OF CONCESSIONARE : M/s PNC Rajasthan Highways Pvt. Ltd
NAME OF EPC CONTRACTOR : PNC INFRATECH LIMITED
MONTHLY PROGRESS REPORT FOR THE MONTH OF JUNE- 2020
Qty. previous
Specification Unit month
Qty. This month Qty. up to date Previous Months This Month Till Date
Sl. No. Name of Test Testing Method Frequency of Test
Requirement
Passed Failed Passed Failed Passed Failed
1) Soil/O.G.L Material
1 Atterberg's Limit IS:2720 Part 5 As Required LL=50 max, PI=25 max 397 0 0 0 397 0
2 Sieve Analysis IS:2720 Part 4 As Required 397 0 0 0 397 0
15.2 kN/m3 min. for emb upto 3m ht. and
3 Proctor Test IS:2720 Part 8 As Required
16.0 kN/m3 for emb more than 3m
0 397 0 0 0 397 0

4 Free Swell Index IS:2720 Part 40 As Required 50% max 397 0 0 0 397 0
5 CBR IS:2720 Part 16 As Required 68 0 0 0 68 0
6 Field Density (OGL/Emb )Set IS:2720 Part 28 1 set/3000 m2 95% Sqm. 1627494 0 1627494 9439 95 0 0 9439 95
2) Soil/Embankment
1 Field Density (Emb)Set IS:2720 Part 28 1 set/3000 m2 95% Sqm. 1698257 0 1698257 56189 619 0 0 56189 619
3) Soil/ Borrow Area/Subgarde Material
LL=50 max, PI=25
1 Atterberg's Limit IS:2720 Part 5 1 test/1500 m3
max 1844 0 0 0 1844 0
2 Sieve Analysis IS:2720 Part 4 1 test/1500 m 3
1844 0 0 0 1844 0
3 Proctor Test IS:2720 Part 8 1 test/1500 m3 17.5 kN/m3 min. Cum. 2354659 0 2354659 1844 0 0 0 1844 0
4 Free Swell Index IS:2720 Part 40 As Required 50% max 1844 0 0 0 1844 0
5 CBR IS:2720 Part 16 1 test/3000 m3 10% minimum 350 0 0 0 350 0
6 Field Density (Test)Set IS:2720 Part 28 1 Set/2000 m2 97% Sqm. 6563611 10505 6574116 31788 630 66 0 31854 630
7 Shoulder Field Density (Test)Set IS:2720 Part 28 1 Set/2000 m2 97% Sqm. 322487 2594 325081 1912 16 21 0 1933 16
4) GSB Materials
LL=25 max, PI=6
1 Atterberg's Limit IS:2720 Part 5 1 test/400 m3
max 1284 0 14 0 1298 0
MORTH Table 400-1
2 Sieve Analysis IS:2720 Part 1 1 test/400 m3
G-V 1284 0 14 0 1298 0
3 Proctor Test IS:2720 Part 8 1test/Source Cum. 342982 1619 344601 3 0 0 0 3 0
4 CBR IS:2720 Part 16 As Required 30% minimum 2 0 0 0 2 0
5 10% Fines Value BS:812 Part III As Required 50 kN Min.(Soaked Condition) 1 0 0 0 1 0
6 Water Absorption IS:2386 Part 3 As Required 2% max,if>2% do soundness 2 0 0 0 2 0
7 Field Density (Test) Set IS:2720 Part 28 1 test/1000 m2 98% Sqm. 1874758 12144 1886902 7155 152 66 0 7221 152
MONTHLY PROGRESS REPORT FOR THE MONTH OF JUNE- 2020
Qty. previous
Specification Unit month
Qty. This month Qty. up to date Previous Months This Month Till Date
Sl. No. Name of Test Testing Method Frequency of Test
Requirement
Passed Failed Passed Failed Passed Failed
5) WMM Materials
1 Atterberg's Limit IS:2720 Part 5 1 test/200 m3 PI=6 max 1094 0 9 0 1103 0
2 Sieve Analysis IS:2386 Part 1 1 test/200 m3 MORTH Table400-11 1094 0 9 0 1103 0
3 Proctor Test IS:2720 Part 8 1test/Source 2 0 0 0 2 0
4 Aggregate Impact Value IS:2386 Part 4 1 test/1000 m3 30% maximum Cum. 160366 718 161084 586 0 9 0 595 0
Combined Flakiness &
5
Elongation Index
IS:2386 Part 1 1 test/500 m3 30% maximum
670 0 9 0 679 0
6 Water Absorption IS:2386 Part 3 As Required 2% max,if>2% do soundness 2 0 0 0 2 0
7 Field Density (Test)Set IS:2720 Part 28 1Set/1000 m2 98% Sqm. 914388 3439 917827 3388 30 24 0 3412 30
6) Bitumen (VG-40)
1 Penetration IS:1203 1 test/Vehicle Min. 35 425 0 7 0 432 0
2 Softening Point IS:1205 1 test/Vehicle Minimum 50 425 0 7 0 432 0
Tanker 425 7 432
3 Kinematic Viscosity IS:1206 1 test/Vehicle Minimum 400 Cst 142 0 0 0 142 0
4 Absolute Viscosity IS:1206 1 test/Vehicle 3200 - 4800 Poise 425 0 7 0 432 0
7) Emulsion (SS-1)
1 Viscosity IS:8887 1test/Vehicle 20 - 100 Second 15 0 0 0 15 0
Lot 13 0 13
2 Residue IS:8887 1test/Vehicle Max. 0.1 % 15 0 0 0 15 0
3 Prime Coat One Test Per 500m2 and Two Test Per Day 7 - 10 Kg Per 10m2
Sqm. 615675 11533 627208 2340 0 39 0 2379 0
7 A) Emulsion (RS-1)
1 Viscosity IS:8887 1test/Vehicle 20 - 100 Second 24 0 1 0 25 0
Lot 23 1 24
2 Residue IS:8887 1test/Vehicle Max. 0.05 % 24 0 1 0 25 0
Tack Coat One Set Per 1000m2 and Two Test Per Day 2.5 - 3.0 Kg Per 10m2 Sqm. 1362096 39442 1401538 3531 0 111 0 3642 0
8) Dense Bituminous Macadam
1 Sieve Analysis of Dry Mix IS: 2386, Part 1 2 tests per day MORTH Table 500-4 630 0 18 0 648 0
2 Extraction Test of Bitumen ASTM D-2192 2 tests per day + 0.30% by weight of total mix 630 0 18 0 648 0
3 Aggregate Impact Value IS: 2386, Part 4 1 test per 350 m3 27% maximum 348 0 13 0 361 0
Cum. 54501 750 55251
4 Comb. Flakiness & Elongation IS: 2386, Part 1 1 test per 350 m3 35% maximum 361 0
348 0 13 0
5 Marshall Stability (In Set) ASTM D-1559 Set of 3 Marshall moulds – 2 tests per day/plant At 60 C - 9 kN min.
o
612 0 18 0 630 0
6 Core Density 1 test per 700 m2 92% of GMM Sqm. 687429 32386 719815 1074 0 65 0 1139 0
9) Bituminous Concrete
1 Sieve Analysis of Dry Mix IS: 2386, Part 1 2 tests per day MORTH Table 500-15 517 0 33 0 550 0
2 Extraction Test of Bitumen ASTM D-2192 2 tests per day At 60oC - 9 kN min. 512 0 33 0 545 0
3 Aggregate Impact Value IS: 2386, Part 4 1 test per 350 m3 24% maximum Cum. 77364 837 78201 289 0 25 0 314 0
4 Comb. Flakiness & Elongation IS: 2386, Part 1 1 test per 350 m3 35% maximum 314 0
289 0 25 0
5 Marshall Stability (In Set) ASTM D-1559 Set of 3 Marshall moulds – 2 tests per day/plant At 60 C - 9 kN min.
o
497 0 33 0 530 0
6 Core Density 1 test per 700m2 92% of GMM Sqm. 682079 103683 785762 987 0 186 0 1173 0
MONTHLY PROGRESS REPORT FOR THE MONTH OF JUNE- 2020
Qty. previous
Specification Unit month
Qty. This month Qty. up to date Previous Months This Month Till Date
Sl. No. Name of Test Testing Method Frequency of Test
Requirement
Passed Failed Passed Failed Passed Failed
10) Water for Embankment, Sub-Grade, GSB, WMM and Concrete Mixes
1 pH Value 1 Test/Source or as directed by engineer 6 minimum 25 0 0 0 25 0
2 Suspended Matter IS:3025 1 Test/Source or as directed by engineer 2000mg/liter(maximum) 25 0 0 0 25 0
3 Chloride(Cl) IS:3025 1 Test/Source or as directed by engineer 500mg/liter(maximum) 25 0 0 0 25 0
4 Sulphates(SO3) IS:3025 1 Test/Source or as directed by engineer 400mg/liter(maximum) 25 0 0 0 25 0
5 Voume of 0.02 N NaOH IS:3025 1 Test/Source or as directed by engineer 3000mg/liter(Maximum) 25 0 0 0 25 0
25 0 25
6 Voume of 0.02 N H2SO IS:3025 1 Test/Source or as directed by engineer 3000mg/liter(Maximum) 25 0 0 0 25 0

7 Total Organic Matter IS:3025 1 Test/Source or as directed by engineer 200 max(as total volatile solid) 25 0 0 0 25 0
8 Acidity IS:3025 1 Test/Source or as directed by engineer 5ml Max. 0 0 0 0 0 0
9 Alkalinity IS:3025 1 Test/Source or as directed by engineer 25ml Max. 0 0 0 0 0 0
11) Cement ( OPC-43 Grade)
1 Fineness(Dry sieve) IS 4031, Part-1 1test/lot 10% max 167 0 5 0 172 0
2 Normal Consistency IS 4031, Part-4 1test/lot 167 0 5 0 172 0
30 minute min(initial) and 600
3 Setting Time IS 4031, Part-5 1test/lot 172 0
minute max(Final) 167 0 5 0
Lot 167 5 172
Compressive Strength
3 Day's 23MPa min at 3days, 33MPa min 342 0
338 0 4 0
4 IS 4031, Part-6 1test/lot at 7days and 43 Mpa min at 28
7 Day's days(Set) 334 0 5 0 339 0
28 Day's 314 0 5 0 319 0
12) Concrete Works
1 Sieve Analysis of CA IS:2386, Part 1 1 test/operation IS:383 2192 30 2222 2192 0 30 0 2222 0
2 Sieve Analysis of FA IS:2386, Part 1 1 test/operation IS:383 1339 30 1369 1339 0 30 0 1369 0
Days
3 Flakiness Index IS:2386, Part 1 1 test/weekly 35% Maximum 244 5 249 244 0 5 0 249 0
4 Aggregate Impact Value IS:2386, Part 4 1 test/weekly 45% max 244 5 249 244 0 5 0 249 0
MONTHLY PROGRESS REPORT FOR THE MONTH OF JUNE- 2020
Qty. previous
Specification Unit month
Qty. This month Qty. up to date Previous Months This Month Till Date
Sl. No. Name of Test Testing Method Frequency of Test
Requirement
Passed Failed Passed Failed Passed Failed
13) Concrete Compressive Strength(in set)
M-15(7 days) IS:516 4087 0 39 0 4126 0
I See * below MORTH Section 1700 16392.37 1545.50 17937.87
M-15(28 days) Cum. 6728 0 16 0 6744 0
M-20(7 days) IS:516 251 0 6 0 257 0
II See * below MORTH Section 1700 799.75 71.85 871.60
M-20(28 days) Cum. 418 0 2 0 420 0
M-25(7 days) IS:516 7299 0 49 0 7348 0
III See * below MORTH Section 1700 18262.22 436.71 18698.93
M-25(28 days) Cum. 9584 0 48 0 9632 0
M-30(7 days) IS:516 2037 0 0 0 2037 0
IV See * below MORTH Section 1700 Cum. 12884.61 0.00 12884.61
M-30(28 days) 4086 0 0 0 4086 0
M-35(S)(7 days) IS:516 5163 0 1 0 5164 0
V See * below MORTH Section 1700 Cum. 48140.80 2.00 48142.80
M-35(S)(28 days) 14679 0 0 0 14679 0
M-35(P)(7 days) IS:516 170 0 0 0 170 0
VI See * below MORTH Section 1700 820.20 0.00 820.20
M-35(P)(28 days) Cum. 315 0 0 0 315 0
M-40(7 days) IS:516 1353 0 0 0 1353 0
VII See * below MORTH Section 1700 Cum. 134437.04 0.00 134437.04
M-40(28 days) 2895 0 0 0 2895 0
M-50(7 days) IS:516 295 0 0 0 295 0
VIII See * below MORTH Section 1700 Cum. 2921.14 0.00 2921.14
M-50(28 days) 679 0 0 0 679 0
DLC(7 days) IS:516 3 Samples/ 1000Sqm. Cum 114696.25 121.00 114817.25 3419 0 18 0 3437 0
VIII MORTH Section -600
Field Density (Test)Set IS:2720 Part 28 1 Set/2000 m2 Sqm 728993.00 6020.00 735013.00 2007 0 45 0 2052 0
I M-40 PQC(7 days) 1074 0 10 0 1084 0
IS:516 6 Samples Everyday MORTH Section -600 Cum 201586.47 6.00 201592.47
II M-40 PQC(28 days) 2107 0 25 0 2132 0
I M-20 KERB(7 days) IS;516 645 0 26 0 671 0
See * below MORTH Section -400 Cum 8414.45 285.50 8699.95
II M-20 KERB(28 days) 1558 0 57 0 1615 0
I Cement Grouting( 7 Days) MORTH Section 1700 & 136 0 0 0 136 0
II Cement Grouting( 28 Days) Appendices 245 0 0 0 245 0
14) BRICK TEST
I Water Absorption IS:3495 Part-2 6 0 0 0 6 0
II Compressive Strength IS:3495 Part-1 MORTH Section -1000 Lot 8 1 0 0 8 1
III Dimention 6 0 0 0 6 0
15) INTERLOCKING BLOCK
(7 days) IS-15658 104 0 0 0 104 0
(28 days) IS-15658 199 0 0 0 199 0
16) MORTOR CUBE
(7 days) IS-2250 144 0 0 0 144 0
(28 days) IS-2250 123 0 0 0 123 0
*Frequency
Quantity of Concrete in work,m3 Nos. of Samples(Set) Cum.
1-5 1
6-15 2
16-30 3
31-50 4
51 and above 4 plus one additional sample for each additional 50m 3 or part thereof
Camp 1
WEATHER REPORT FOR THE MONTH OF MARCH.-2020 (From 01.06.2020 to 30.06.2020)
Temperature (0c) Humidity (%)
Weather Rain Fall (mm)
Date (Sunny/Cloudy/Rainy) (mm)
Min. Max. Min. Max.

1-Jun-20 24.90 46.30 13.00 57.00 Partly sunny/Cloudy with 4.00


Rain
2-Jun-20 25.10 46.10 16.00 58.00 sunny

3-Jun-20 24.40 45.80 13.00 61.00 Partly sunny/Cloudy with 2.00


Rain
4-Jun-20 24.90 44.70 11.00 56.00 Partly sunny

5-Jun-20 25.10 45.10 13.00 60.00 Partly sunny

6-Jun-20 27.30 38.40 39.00 54.00 Partly sunny

7-Jun-20 26.50 40.80 39.00 64.00 Cloudy with Rain 7.50

8-Jun-20 27.10 43.60 34.00 67.00 sunny

9-Jun-20 27.90 43.90 38.00 69.00 sunny

10-Jun-20 27.30 42.90 35.00 65.00 Partly sunny

11-Jun-20 27.70 43.90 35.00 67.00 sunny

12-Jun-20 27.90 44.30 36.00 65.00 sunny

13-Jun-20 31.00 43.80 39.00 53.00 sunny

14-Jun-20 29.50 43.10 39.00 56.00 sunny

15-Jun-20 30.10 43.30 36.00 61.00 sunny

16-Jun-20 29.60 43.80 25.00 56.00 sunny

17-Jun-20 30.10 44.10 25.00 61.00 sunny

18-Jun-20 29.80 44.80 25.00 57.00 Partly sunny

19-Jun-20 29.50 44.30 27.00 56.00 sunny

20-Jun-20 29.40 44.30 25.00 56.00 Partly sunny/Cloudy with 9.00


Rain
21-Jun-20 29.10 44.10 25.00 71.00 Partly sunny

22-Jun-20 29.50 41.00 46.00 60.00 Partly sunny & Cloudy

23-Jun-20 29.30 40.30 46.00 69.00 Cloudy with Rain 1.00

24-Jun-20 27.70 40.20 47.00 75.00 Cloudy

25-Jun-20 27.70 40.60 46.00 75.00 Partly Sunny

26-Jun-20 27.40 40.30 48.00 72.00 Cloudy with Rain 2.00

27-Jun-20 28.10 40.80 44.00 75.00 sunny

28-Jun-20 27.70 41.70 37.00 75.00 sunny

29-Jun-20 28.30 44.40 36.00 76.00 sunny

30-Jun-20 27.70 44.20 36.00 75.00 sunny

MONTHLY MIN. MAX This month Rainfall (mm) 25.50

TEMP. 24.40 46.30

HUMIDITY 11.00 76.00