LARSEN & TOUBRO LIMITED

TRANSPORTATION INFRASTRUCTURE INDEPENDENT COMPANY

Ref: IM-08-C Rev 00

Date: 14.09.2015
SAFE WORK METHOD FOR SOLID SLAB ACTIVITY
Document No : 15
Rev : 01
Name of the Project : Garden Reach Flyover Project.

Sl. No List of Control Measures Action by


1 Screening & Safety induction to all employees, Issuances of Site Engineer,
PPE (i.e. Hard hat, Safety goggles, safety shoes & required EHSO & Time
PPE for the job). office.
2 Ensure a tool box meeting conducted prior to any work, Site Engineer
Ensure a briefing about the WMS related to the job.
3 Flagman to be provided, Equipment to be fitted with Site Engineer,
reverse horn and lights, Follow the site speed limits (20 P&M & EHSO.
km/h), Install road signage, Only authorized personnel
within the working area.
4 Practice of providing metal halide lamps in the main Jib to Site Engineer.
ensure sufficient illumination. 
5 Crane with load at Slope is strictly prohibited. Site Engineer,
Trained Operator is deployed. EHSO.

6 Not allowed to work for more than a shift. During Extreme Site Engineer.
Heat Wave work will be suspended.
7 Ensure all equipment, lifting gear is 3rd party certified, Site Engineer.
Material lifted must have both side tag line
8 Competent and authorized operator is allowed to operate Site Engineer.
the equipment; No personal is standing under the load.
9 All connection to be checked. Plug top to be provided for all Site Engineer.
connection. ELCB to be provided for all DB. Open joint is not
allowed for any connection. Earthling to all DB.
10 Wear rubber gloves and keep skin covered where possible, Site Engineer.
Wear eye protection- pull down visor / goggles.
11 Proper working platform with hand railing, Proper access, Site Engineer.
Protection for any opening, Ensure Safety harness properly
anchored when working at height.
12 Proper maintenance and inspection of the concrete pump, Site Engineer.
Pre-task briefing to the pump operator and workmen
13 Monthly inspection for all tools, All defective tools to be P&M, EHSO
tagged out of services
14 No smoking / Open flame within the working area, Site Engineer &
Flammable safety signage. EHSO.
15 Usage of double mess safety net is being provided at Site Engineer.
surrounding the platform.
16 Usage of double lanyard safety harness & life line is being Site Engineer.
insisted.
17 Top rail & mid rail to be provided at the top of the platform. Site Engineer.
18 Loose material from heights will be removed immediately Site Engineer.
19 Provide shuttering oil after bracket fixing to avoid slip Site Engineer.
hazard.
20 Improve Coordination between 8nos of workman engaged Site Engineer.
at bracket fixing job.
21 Arrange on job training on particular bracket fixing job. Site Engineer,
EHSO.

Residual Risk / Impact (if any): Medium

___________________
PM/ CM / Section In charge EHSO