Testing

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Pt C, Ch 2, Sec 15

SECTION 15 TESTING

1 General The installation may be subdivided to any desired extent


and appliances may be disconnected if initial tests give
results less than that indicated above.
1.1 Rule application
1.1.1 Before a new installation, or any alteration or addi- 3.2 Internal communication circuits
tion to an existing installation, is put into service, the elec-
trical equipment is to be tested in accordance with [3], [4] 3.2.1 Circuits operating at a voltage of 50 V and above are
and [5] to the satisfaction of the Surveyor in charge. to have an insulation resistance between conductors and
between each conductor and earth of at least 1 M.
1.2 Insulation-testing instruments
3.2.2 Circuits operating at voltages below 50 V are to have
1.2.1 Insulation resistance may be measured with an instru- an insulation resistance between conductors and between
ment applying a voltage of at least 500 V. The measurement each conductor and earth of at least 0,33 M.
will be taken when the deviation of the measuring device is
stabilised. 3.2.3 If necessary, any or all appliances connected to the
Note 1: Any electronic devices present in the installation are to be
circuit may be disconnected while the test is being con-
disconnected prior to the test in order to prevent damage. ducted.

1.2.2 For high voltage installation, the measurement is to 3.3 Switchboards


be taken with an instrument applying a voltage adapted to
the rated value and agreed with the Society. 3.3.1 The insulation resistance between each busbar and
earth and between each insulated busbar and the busbar
2 Type approved components connected to the other poles (or phases) of each main
switchboard, emergency switchboard, section board, etc. is
2.1 to be not less than 1 M.

2.1.1 The following components are to be type approved or 3.3.2 The test is to be performed before the switchboard is
in accordance with [2.1.2]: put into service with all circuit-breakers and switches open,
all fuse-links for pilot lamps, earth fault-indicating lamps,
• electrical cables
voltmeters, etc. removed and voltage coils temporarily dis-
• transformers connected where otherwise damage may result.
• rotating machines
• electrical convertors for primary essential services 3.4 Generators and motors
• switching devices (circuit-breakers, contactors, discon-
nectors, etc.) and overcurrent protective devices 3.4.1 The insulation resistance of generators and motors, in
• sensors, alarm panels, electronic protective devices, normal working condition and with all parts in place, is to
automatic and remote control equipment, actuators, be measured and recorded.
safety devices for installations intended for essential
services (steering, controllable pitch propellers, propul- 3.4.2 The test is to be carried out with the machine hot
sion machinery, etc.), electronic speed regulators for immediately after running with normal load.
main or auxiliary engines
3.4.3 The insulation resistance of generator and motor con-
• computers used for tasks essential to safety. nection cables, field windings and starters is to be at least
2.1.2 Case by case approval based on submission of ade- 1 M.
quate documentation and execution of tests may also be
granted at the discretion of the Society. 4 Earth

3 Insulation resistance 4.1 Electrical constructions

3.1 Lighting and power circuits 4.1.1 Tests are to be carried out, by visual inspection or by
means of a tester, to verify that all earth-continuity conduc-
3.1.1 The insulation resistance between all insulated poles tors and earthing leads are connected to the frames of appa-
(or phases) and earth and, where practicable, between poles ratus and to the hull, and that in socket-outlets having
(or phases), is to be at least 1 M in ordinary conditions. earthing contacts, these are connected to earth.

96 Bureau Veritas April 2009


Pt C, Ch 2, Sec 15

4.2 Metal-sheathed cables, metal pipes or 5.2 Switchgear


conduits
5.2.1 All switchgear is to be loaded and, when found nec-
4.2.1 Tests are to be performed, by visual inspection or by essary by the attending Surveyor, the operation of overcur-
means of a tester, to verify that the metal coverings of cables rent protective devices is to be verified (see [5.2.1], Note 1).
and associated metal pipes, conduits, trunking and casings
Note 1: The workshop test is generally considered sufficient to
are electrically continuous and effectively earthed. ensure that such apparatus will perform as required while in opera-
tion.
5 Operational tests
5.2.2 Short-circuit tests may also be required at the discre-
tion of the Society in order to verify the selectivity charac-
5.1 Generating sets and their protective teristics of the installation.
devices

5.1.1 Generating sets are to be run at full rated load to ver- 5.3 Consuming devices
ify that the following are satisfactory:
5.3.1 Electrical equipment is to be operated under normal
• electrical characteristics
service conditions (though not necessarily at full load or
• commutation (if any) simultaneously) to verify that it is suitable and satisfactory
• lubrication for its purpose.
• ventilation
5.3.2 Motors and their starters are to be tested under nor-
• noise and vibration level. mal operating conditions to verify that the following are sat-
isfactory:
5.1.2 Suitable load variations are to be applied to verify the
satisfactory operation under steady state and transient con- • power
ditions (see Ch 2, Sec 4, [2] ) of: • operating characteristics
• voltage regulators
• commutation (if any)
• speed governors.
• speed
5.1.3 Generating sets intended to operate in parallel are to • direction of rotation
be tested over a range of loading up to full load to verify
that the following are satisfactory: • alignment.
• parallel operation
5.3.3 The remote stops foreseen are to be tested.
• sharing of the active load
• sharing of the reactive load (for a.c. generators). 5.3.4 Lighting fittings, heating appliances etc. are to be
tested under operating conditions to verify that they are suit-
Synchronising devices are also to be tested. able and satisfactory for their purposes (with particular
regard to the operation of emergency lighting).
5.1.4 The satisfactory operation of the following protective
devices is to be verified:
5.4 Communication systems
• overspeed protection
• overcurrent protection (see [5.1.4], Note 1) 5.4.1 Communication systems, order transmitters and
• load-shedding devices mechanical engine-order telegraphs are to be tested to ver-
ify their suitability.
• any other safety devices.

For sets intended to operate in parallel, the correct opera- 5.5 Installations in areas with a risk of
tion of the following is also to be verified:
explosion
• reverse-power protection for a.c. installations (or
reverse-current protection for d.c. installations) 5.5.1 Installations and the relevant safety certification are
• minimum voltage protection. to be examined to ensure that they are of a type permitted
in the various areas and that the integrity of the protection
Note 1: Simulated tests may be used to carry out this check where concept has not been impaired.
appropriate.

5.1.5 The satisfactory operation of the emergency source of 5.6 Voltage drop
power and of the transitional source of power, when
required, is to be tested. In particular, the automatic starting 5.6.1 Where it is deemed necessary by the attending Sur-
and the automatic connection to the emergency switch- veyor, the voltage drop is to be measured to verify that the
board, in case of failure of the main source of electrical permissible limits are not exceeded (see Ch 2, Sec 3,
power, are to be tested. [9.11.4]).

April 2009 Bureau Veritas 97

You might also like