Professional Documents
Culture Documents
Technical Specifications For The Installation of Telecoms Mast and Towers
Technical Specifications For The Installation of Telecoms Mast and Towers
Technical Specifications For The Installation of Telecoms Mast and Towers
FOR THE
INSTALLATION OF
1
Table of Contents
Page
1.1 Preamble 4
1.2 Types of Structures 5
1.3 General Guidelines 5
1.4 Certification - Company and Employees 7
1.5 Siting 8
1.6 Environmental Requirements 9
1.7 Structural Certification 14
1.8 The Terrain 14
1.9 Basic Wind Speed 16
2
3.8 Screw Down Clamps 92
3.9 Earth Bars and Disconnecting Clamps 93
3.10 Lightning Arrestor 95
3.11 Copper Tapes 96
3.12 Connectors 97
3.13 Bi-metallic Connectors 98
3.14 Guy System Materials 99
3.15 Antenna Mounting Frames 101
Glossary 121
Index 124
3
CHAPTER ONE
4
1.1 Preamble
We have also provided comprehensive data on wind speeds for the entire country
that will form an easy reference material for engineers that are in the business of
designing masts and towers.
5
1.2 Types of Structures
Monopoles that consist of tapered steel tubes that fit over each other to form
a stable pole,
Guyed towers that are stabilized by tethered wires
Self-supporting towers that are free-standing lattice structures.
Guyed Self-supporting
Monopole
.
(a) It is assumed that the predominant load on these structures is wind load.
(b) Each structure shall be made of hot dip galvanized steel sections.
6
(c) Masts could be guyed or free standing
(d) Free standing masts should not exceed 150 meters in height.
(e) Masts and towers may be installed on a property with the written
permission of the property owner and the approval of the Nigerian
Communications Commission.
(f) Structures above 30 meters in height may only be installed with a
clearance certificate issued by the Nigeria Airspace Management
Authority (NAMA).
(g) No masts or towers (irrespective of the height) may be installed within
15 kilometers of any airport without prior approval and a permit from the
Nigeria Airspace Management Authority (NAMA). This requirement
also applies to such structures within the proximity of helicopter pads and
their approaches.
(h) The armed forces are exempted from this regulation in times of war
only. At the cessation of hostilities any structures erected under this
waiver must be submitted for reassessment and approval.
(i) The open space available at the site of a proposed mast or tower
installation must be at least three times the space required by the base of
the structure.
(j) A permit must be obtained from the Nigerian Communications
Commission for the erection of any Masts or Towers whose height
exceeds 20 meters and such structures shall be registered with the NCC
on completion.
The following documents will be submitted to the NCC as part of the application
for a permit.
7
II. Evidence of ownership of the property on which the structure is to be installed
or a written consent of the landlord.
III. Geographical coordinates of the proposed location of the structure and that of
the nearest airport, heliport or helipad. In the alternative, a permit issued by
the Nigeria Airspace Management Authority (NAMA) for the erection of the
structure in the proposed location.
IV. Design of the structure showing its effective height, foundation, guys (where
used), members, ladders, rest and work platforms, earthing, lightning
protection and aviation lighting.
V. Detailed information on the software package used in the design to enable easy
verification of the fidelity of the design of the structure.
Each completed mast or tower must have a name plate bolted to each of its legs on
which the following particulars of the fabricator, operator and installer are detailed
Name of owner
address of owner
telephone numbers of owner
Permit Number issued by the NCC for erection of the Mast at the location
and in addition the following particulars pertaining to the antenna.
date of erection
height
number of antenna
Operating Frequencies
Location address
Geographical coordinates
a log book showing inspection dates and types of inspections performed
8
A tower or mast erecting crew must have a current Workmen’s Compensation
policy from a 1st Class insurance company to a minimum value of five million
naira or any such amount as may from time to time be specified by the Nigerian
Communications Commission, for any one claim for third party claims.
Responsibility for accidents during the installation period shall be that of the
installer and it shall revert to the owner of the masts or towers on completion and
handover.
All masts and towers must be insured by their owners against third party claims in
the event of collapse.
A tower fabricating company shall be licensed by the NCC upon satisfaction that
She has acquired enough capital equipment to enable her deliver safe and
quality installation.
She has in her employ, qualified and licensed fabricators.
She has a good Workmen’s compensation insurance policy from a reputable
insurance company
She also has a good third party accident insurance policy
She has a viable Health, Safety and Environment policy
9
1.5 Siting
This Section establishes siting the location of telecommunication towers and masts
with the objective of minimizing their number, protecting and promoting public
safety, and mitigating the adverse visual impacts on the community whilst
promoting the provision of telecommunications service to the public.
Cities may not refuse the placement, construction and modification of tower
facilities on the basis of environmental or radio frequency emissions as long as
such facilities comply with the Nigerian Communications Commission’s
regulations concerning such emissions.
Height
(1) Will not be detrimental to the public health, safety or general welfare.
(2) Will not have a substantial negative effect upon neighbourhood.
(3) Is in conformity with the intent and purpose of the planning of the area
and the general plan of the community.
(4) Will not impair the obligation to comply with any other applicable laws or
regulations.
b. Any tower site lying 50 meters or less from a paved road shall be paved
10
c. If the site is more than 50 meters from a paved road, hard-surfacing of
parking / loading spaces and driveways shall not be required for those
portions of the site lying more than 50 meters from any paved road.
1.6.2 Screening
An opaque screen at least 2.5 meters in height must surround the base of a
telecommunication tower. The screening shall also include landscaping provisions
for any portions of the development visible from adjacent residential or used
property or right-of-way. The use of barbed wire or other security fencing material
shall be allowed. Screening requirements may be waived if the design of the tower
is found to be compatible with the adjacent land uses.
A tower that has not been maintained for a continuous period of three years shall
be considered abandoned. The NCC will determine the date of abandonment and
may request documentation from the owner/operator regarding the issue of usage.
Upon the determination of abandonment, the NCC will issue a removal notice to
the owner.
The owner shall dismantle and remove the tower from the property within 90 days
of receipt of notice from the Nigerian Communications Commission. An
abandoned tower that is not removed within the 90 day period shall be removed by
the NCC and removal costs plus a penalty shall be paid by the owner.
1.6.4 Inspections
1.6.5 Authorization
11
All telecommunications towers and masts shall be erected and operated in
compliance with Nigerian Communications Commission and Nigeria Airspace
Management Authority regulations.
1.6.6 Structure
Towers and masts shall be designed and located such that should any structure fall,
it will avoid habitable structures and public streets. This shall be the major
determinant factor in the issue of setbacks from adjacent existing structures.
1.6.7 Co-location
1.6.8 Fencing
Security fencing, if installed, shall be by a wrought iron, barbed wire, steel chain
link fence with evergreen hedge or a masonry wall not less than 1.8 meters in
height. The exterior of equipment buildings and/or metal equipment cabinets
visible from residential areas or public rights-of-way shall be painted to reflect the
color and character of adjoining structures or blend with adjacent landscaping and
other surroundings.
1.6.9 Setbacks
All telecommunication towers as well as guys and guy anchors shall be located
within the buildable area of the property and not within the front, rear, or side
building setbacks. Telecommunication towers in excess of 150 meters in height
shall be set back a minimum of 50 meters from the right-of-way of all controlled
access, federal and state roadways designated as freeways, to provide unobstructed
flight paths for helicopters.
12
(c) The distance specified as a potential hazard area by the designer of
the structure.
Guy wire anchors and accessory structures shall not encroach into the mandatory
setbacks listed above.
1.6.10Signage
1.6.11Lighting
13
should be designed to have minimal serviceable components so as to reduce the
problems of regular ascent of towers to service lamps.
1.6.12Residential Areas
14
1.6.14Nearness to Power Lines
1.6.16Antenna Mounts
15
property by a minimum 1.8 meter high screening fence.
b. Building and roof mounted dish antennas of one (1) meter or less in
diameter, are permitted in all areas. No permits are required for this
category
The terrain for purposes of this specification is Nigeria and includes its territorial
waters and the continental shelf. In making designs for masts and tower structures,
this terrain is classified into three broad geographical zones based on measured
worst case wind speeds measured over a period of 30 years.
2) Open terrain with widely spaced obstructions (100m apart) having heights
and plan dimensions generally between 1.5m and 10m. This category
includes large airfields, open parklands or farmlands and undeveloped
outskirts of towns and suburbs with few trees.
16
seasonally variable loads are non-existent. Wind load rating is based on the height
of the tower and where it is located.
17
Figure 1.1
Figure 1.1 above is a map of Nigeria showing the average wind speeds as
measured by the Nigerian Meteorological Agency. Wind loading for a structure is
to be considered over the full length of the structure and is to be measured in
Newtons per square meter (N/m2). The basic wind speeds depicted in this map are
measured at 10 meters above the ground. These values increase with height and
need to be so corrected when making computations.
18
Engineers are encouraged to consider and design for specific conditions that might
exceed these given standard values. Design philosophy shall be based on two
limiting states - strength and serviceability. The strength limit considers the
loading of a tower under extreme conditions; the serviceability limit ensures the
tower will provide the proper service under normal conditions.
Towers shall be analyzed under three specific types of loading:
(a) wind
(b) environmental
(c) seismic
The superstructure is really being designed to resist various pressures, wind load,
being the major one for Nigeria. Wind velocities constitute the measured data
generally available. A conversion has to be made from wind velocity to wind
pressure. Various existing standards define and measure wind velocity in different
ways and therefore the formulas used to convert these velocities to pressure
produce results that can vary as much as 25%. That translates into a 25%
difference in design loads that will produce different foundation sizes all of which
mean a totally different installed cost.
For example, for a 90 meter tower with a basic wind speed design of 115
km hr-1, the wind load design at the top of the tower is 160 km hr -1.
Structures shall be designed to withstand forceful wind speeds that occur on the
average of once every 30 to 50 years. This wind speed is then escalated, with
height, to a much higher wind speed at the top of the structure. A gust factor to
19
account for the varying nature of wind shall also be incorporated into the design of
the structure.
The wind speeds shown in figure 1.1 above were measured from the stations listed
in Table 1.1. Engineers who desire greater accuracy in their wind speed
calculations are encouraged to use figure 1 in conjunction with Table 1.1.
Table 1.1
20
15 09.06’ 06.01’ NIGER 144.3
BIDA N E
16 09.37’ 06.32’ NIGER 256.4
MINNA N E
17 09.15’ 07.00’ 343.1
ABUJA N E FCT
18 09.52’ 08.54’ PLATEAU 1780.0
JOS N E
19 08.11’ 09.45’ TARABA 110.7
IBI N E
20 09.14’ 12.28’ ADAMAWA 186.1
YOLA N E
21 07.58’ 03.36’ OYO 330.0
ISEYIN N E
22 06.35’ 03.20’ LAGOS 39.4
IKEJA N E
23 06.30’ 03.23’ LAGOS 19.0
OSHODI N E
MET.AGRO
24 06.27’ 03.24’ LAGOS 14.0
LAGOS (HQ) N E
ROOF
25 LAGOS (MARINE) 06.26’ 03.25’ LAGOS 2.0
N E
26 07.26’ 03.54’ OYO 227.2
IBADAN N E
27 06.50’ 03.56’ OGUN 77.0
IJEBU-ODE N E
28 07.10’ 03.20’ OGUN 104.0
ABEOKUTA N E
29 07.47’ 04.29’ OSUN 302.0
OSHOGBO N E
30 07.06’ 04.50’ ONDO 287.3
ONDO N E
31 06.19’ 05.06’ EDO 77.8
BENIN N E
32 07.17’ 05.18’ ONDO 375.0
AKURE N E
33 05.31’ 05.44’ DELTA 6.1
WARRI N E
34 07.47’ 06.44’ KOGI 62.5
LOKOJA N E
21
35 06.09’ 06.47’ ANAMBRA 67.0
ONITSHA N E
36 04.51’ 07.01’ RIVERS 19.5
PORT- N E
HARCOURT
37 05.29’ 07.00’ IMO 91.0
OWERRI N E
38 06.28’ 07.33’ ENUGU 141.8
ENUGU N E
39 05.30’ 07.55’ AKWA IBOM 38.0
UYO N E
40 04.58’ 08.21’ CROSS RIVER 61.9
CALABAR N E
41 07.44’ 08.32’ BENUE 112.9
MAKURDI N E
42 05.58’ 08.42’ CROSS RIVER 119.0
IKOM N E
43 06.40’ 08.48’ CROSS RIVER 117.0
OGOJA N E
The above data obtained from the National Meteorological Services indicate that
the highest recorded wind speed over a period of 20 years is 7 ms-1, which
translates to a mere 420 mhr-1. However, wind gusts of the order of 55 km hr-1
have been recorded infrequently. Since these data form our worst case scenario,
masts and towers in Nigeria shall be designed to withstand a minimum ground
wind speed of 70 km hr-1.
22
CHAPTER TWO
23
2.1 SERVICE LIFE
The expected service life of a tower shall be 25 years. The design, choice of
fabrication materials, fabrication methods, installation accessories, all safety
factors and tower loadings shall all be made to conform to standards for this to be
achieved.
Qualified professional engineers shall design and specify materials that meet the
requirements to give a minimum service life of 25 years in the working
environment. Qualified welders and skilled welding supervision shall be deployed
to give positive effect on the finished product. The highest quality of welding must
be built in. Poor quality welding will be apparent shortly after installation by which
time repairs will be very expensive and time consuming. Proper welding means
good quality finishes and thus minimizes long term maintenance costs.
2.2 SUPERSTUCTURE
2.2.1 Finishes
All steel materials that are to be used in the superstructure shall as a standard be
hot-dip galvanized and later painted according to NAMA paint schedule for
obstructions. All aluminum materials shall have aluminum finish and will be
equally painted according to NAMA paint schedule for obstructions.
Self support design is often the solution of choice when land availability is limited.
The tower uses tapered sections, and face widths will vary according to height and
load capacity required.
1) Lattice structure
24
Work platforms provided at all height where antennas are to
be installed
Fitted with climbing ladder
a) Lattice Leg
cost-efficient, high-capacity design
ideally suited for multi-carrier applications
fast and easy assembly
Bracings shall be of angle steel
b) Angle Leg
bolt-up construction
constructed from steel angle steel
Bracings shall be of angle steel
25
Towers legs shall be constructed from schedule 80 pipes or angle steel. Hollow
aluminum pipes shall be used for short towers. Bracings shall be of angle steel
construction or aluminum in case of aluminum towers.
Mast sections, when made from steel pipes, shall be
joined to each other through joint plates welded to the
base of each section. The width of the mast section joint
plates should be double the width of the wall of the pipe
they are supporting.
When a tower is made from angle steel, sections shall be joined to each other
through appropriately sized flanges, bolts, washers and lock nuts.
Bracing inhibits torque on a tower and its non adequate application exposes towers
to torque. This in turn results in loss of signal during strong winds speeds.
Monopole or Post Masts are to be made from galvanised hollow steel pipes or
high strength steel. They shall be designed for a variety of multi-user
configurations and finishes to meet local aesthetic requirements.
The pipes are to be constructed tapered so that one pipe base fits into the top of
another until the desired height is achieved. A joint in the arrangement has an
overlay between the two adjacent pipes. The depth of the overlay, the base
width and the number of pipes in a particular monopole shall be determined by
height desired of the tower, the thickness of the pipe walls, the base diameter
and whether the tower shall be guyed or not.
For a monopole,
26
Sections shall be made from hollow, heavy duty, thick steel tubes, flanged
steel tubes or low-alloy, high-strength steel.
Each shaft section shall be a constant-tapered hollow steel section
Slip joints are designed with a minimum of 11/2 times the pole diameter at
the splice.
Sections shall fit into each other with overlap
Pipe diameter shall decrease from bottom to top
Shall be guyed or self supported
Shall be fitted with climbing rugs
Usually not very tall structure in the self support design
Tapered steel and flanged steel poles feature designs that blend well into
the environment and require minimum space for installation.
Flanged steel poles are easy to handle and install. Connections shall be precision
fitted to allow quick assembly of modular sections and the top platform, side arms
or mounting frame. Pole sections shall be made with identical base flange plates to
permit simplified modifications of mounting heights and antenna reconfigurations.
Tapered steel poles have comparatively smaller base diameters and so demand
minimal land space. Tapered poles can be installed quickly do offer extremely
efficient strength-to-cost ratio.
All sections must be straight square sections and eliminate any potential problems
with twisting or the need to shim the legs. Typical tower sections shall have a
brace configuration with horizontals (z, x or k) and pivot base sections. These
tower-structures are wholly of steel, modular and hot-dip galvanized. Sections can
be of the same face width but should the tapered type be contemplated, it shall be
27
designed with junction flanges. Tube or solid legs with solid bracing increases the
tower rigidity to allow for the twist and sway.
In the guyed mode all the forces on a tower are supported by the guy wires.
Everything about the guy wire has to be engineered with precision and a minimum
safety factor of 2.0 applied to the design. The design, based on the load
calculations shall determine working load and the break strength required of the
guy wire and subsequently the choice of the size and grade of the wire.
The choice of each guy earth screw anchor shall be dependent on its holding power
in the soil, which is a function of its diameter and length. This is used to compute
the minimum number of guys required.
As a general rule guys are planted in three directions at 120 o apart from each other.
The distance from the base of the tower to the guy anchor base shall be one quarter
of the height of the tower.
Panel Height
Type X1 X2 X3 X4 X5 X6
2.3 Structural types for Self Support Lattice
K - Bracing
Panel Height
Type K1 K2 K3 K4 K5 K6
28
Figure 2.1 – Bracing Types
29
Diagonal Spacing
Double K2 Down
Double K3, K3A, K4 Double K 1 Down
Figure 2.2
Horizontal
30
Secondary Horizontal
Diamond Double K
Z bracing M - Bracing
Figure 2.3
Members shall be made from solid rod, pipe or angles.
Engineer must specify wall thickness if design is of pipes and
sizes and thickness of legs if of angles.
31
K-Brace End Panel
Face A
Double Slope-Bracing
Figure 2.4
Horizontal
32
X-Brace
CX-Brace TX-Brace
Secondary Horizontal
Horizontal
Redundant Vertical
Redundant Sub-Horizontal
K1 Down K2 Down
K1 Up (Opposite) K 2 Up (Opposite)
Figure 2.5
Members shall be made from solid rod, pipe or angles.
Engineer must specify wall thickness if design is of pipes and sizes and
thickness of legs if of angles.
33
Redundant Sub Horizontal
K 3 Down K 3A Down
K 3 Up (opposite) K 4 Up
(Opposite)
Redundant Sub-Horizontal
Redundant Diagonal
Redundant Sub-Diagonal
K 1B Down
Figure 2.6
Members shall be made from solid rod, pipe or angles.
Engineer must specify wall thickness if design is of pipes and sizes and
thickness of legs if of angles.
Sub Diagonal
Working Point
Sub Diagonal
Redundant Sub Horizontal
Optional Vertical
34
Red Diagonal 3
Horizontal 3
Diagonal 2
Horizontal 2
Diagonal 1
Horizontal 1
Diagonal
Figure 2.7
35
Sub Diagonal
Redundant Sub Horizontal
Optional Vertical
Diagonal 3
Horizontal 3
Diagonal 2
Horizontal 2
Diagonal
1
Horizont
al 1
Diagonal
36
Face width
Section height
Slope change
Height
Face width
Fig. 2.9
37
Face width
0.16
Section 15
Section 14
Section 13
Section 12
Section 11
Section 10
This represents a generalized design
Section 9 of a 15 section, 6m length per
section tower.
Section 8
300'
Loading considerations to be taken
Section 7 into account in the specification of
275.6'
Section 1
Face width
34'
Figure 2.10
38
Face width
4
Section 13
Section 12
Section 11
Section 10
Section 9
Section 1
Face width
Figure 2.11
39
1.6m
section 13 section 16
section 12 section 15
section 11 section 14
section 10 section 13
section 9 section 12
section 8 section 11
section 7 section 10
section 6 section 9
section 5 section 8
section 4 section 7
section 3 section 6
section 2 section 5
section 1 section 4
Face Width
8.4metres
section 3
section 2
Two towers of different heights illustrating the
general relationships between lattice tower heights,
number of sections and the face widths at the top
and bottom. Both towers are of identical design but
have different heights. section 1
Face width
10.4 meters
Top Frame
7 13 19 25 31 37 43
8 X
14 20 26 32 38 44
9 Lower Frame 15 21 27 33 39 45
LEG # 4
LEG # 3
LEG # 7
LEG # 2
LEG # 5
LEG # 6
e 10 H 16 22 28 34 40 46
g
#1 6"
11 17 23 29 41 47
35
24"
12 18 24 30 36 42 48
49 55 61 67 73
25 1-/X''
50 56 62 68 74
51 57 63 69 75
LEG # 8
LEG # 11
X'
LEG # 12
LEG # 9
H
LEG # 10
52 58 64 70 76
53 59 65 71 77
24"
54 60 66 72 78
Figure 2.13
A 12-section, single braced, lattice tower. Each section is tapered to produce an overall
tapered structure. Additional sections, if the tower has to be higher shall be of greater
face width than section 12 until the tower reaches required height.
41
Design Data of a Ten Section Light Duty Self-Supporting Tower
TOWER SCHEDULE
Section Spread Dimension Tower Legs** Tower Braces Bolts
Number Upper Lower 36 KSI Yield STR 36 KSI YIELD STR A 325 GRADE
1 (Top) 30 cm 30 cm 5.0 cm2 2.5cm x 2.5cm x 0.32cm 8mm
2 30 cm 30 cm 5.0 cm2 2.5cm x 2.5cm x 0.32cm 8mm
3 30 cm 50 cm 5.0 cm2 2.5cm x 2.5cm x 0.32cm 8mm
4 50 cm 72 cm 5.0 cm2 3.2cm x 3.2cm x 0.5cm 10mm
5 72 cm 94 cm 5.0 cm2 3.2cm x 3.2cm x 0.5cm 10mm
6 94 cm 114 cm 5.0 cm2 3.2cm x 3.2cm x 0.5cm 10mm
7 114 cm 135 cm 5.75 cm2 3.2cm x 3.2cm x 0.5cm 10mm
8 135 cm 156 cm 5.75 cm2 3.2cm x 3.2cm x 0.5cm 10mm
9 156 cm 176 cm 5.75 cm2 3.2cm x 3.2cm x 0.5cm 10mm
10(Grnd) 176 cm 198 cm 5.75 cm2 3.2cm x 3.2cm x 0.5cm 10mm
**Cross-sectional area
Table 2.1
Table 2.2
42
Table 2.3
43
Below 145 ms-1 wind speed; shear, vertical and uplift forces are negligible.
All foundation designs shall be in accordance with maximum reaction loads indicated
above. Modification of loading locations and equipment can be made provided reaction
loads do not exceed indicated values.
Design Data of a Fifteen Section Medium Duty Self-Supporting Tower
Table 2.5
Table 2.6
44
12 3.0 m 76 Kg 145 Kg 8.0 Kg 246 Kg
13 3.0 m 111 Kg 148 Kg 12.7 Kg 288 Kg
14 3.0 m 111 Kg 156 Kg 12.7 Kg 296 Kg
15 3.0 m 111 Kg 166 Kg 12.7 Kg 306 Kg
Table 2.7
45
46
Table 2.8 TOWER FOUNDATION DESIGN & LOADING
25 m 145 17.29 14.02 1.79 2.65 2.53
20 m 145 15.94 12.9 1.73 2.6 2.14
Below 145 ms-1 wind speed; shear, vertical and uplift forces are negligible.
All foundation designs shall be in accordance with maximum reaction loads indicated
above. Modification of loading locations and equipment can be made provided reaction
loads do not exceed indicated values.
Weight Weight x 12
(Kg/m) (Kg/m)
43 17.16
1.43 17.16
1.43 17.16
2.23 26.76
2.40 28.8
2.40 28.8
1.61 19.32
3.06 36.72
3.02 36.24
47
Table 2.10 Lap Link Weight Table
Weight Weight x 3
(Kg/m) (Kg/m)
55.63 166.89
58.01 174.03
62.63 187.89
65.55 196.65
Table 2.11
STRUCTURAL DESIGN DATA FOR A TYPICAL LATTICE TOWER
All brace connections shall be bolted and provided with locking pal nuts.
Sections are in typical 6 meter lengths
Leg strength minimum 46 KSI yield.
Max Share/Leg: 40.11 KIPS
Max Uplift: 288.26 KIPS
Max Compression: 345.76 KIPS
Design Wind Speed is 120 Km hr-1
Table 2.12
STRUCTURAL DESIGN DATA FOR A TYPICAL LATTICE TOWER
48
100 metre Configuration Lattice Tower
Section Height Leg Thickness
( m) (cm) 50 KSI Brace Redundant
Bolt Size Diag. Config. Size (mm) Size (cm)
1 6 16 (2) 20mm Double A 90 x 75 x 6 6 x 6 x 60
2 12 16 (2) 20mm Double A 90 x 75 x 6 6 x 6 x 60
3 18 16 (2) 20mm Double A 90 x 75 x 6 6 x 6 x 60
4 24 16 (2) 20mm Double A 90 x 75 x 6 6 x 6 x 60
5 30 13 22mm Single 2A 10 x 10 x 6 6 x 6 x 60
49
6 36 13 22mm Single 2A 10 x 10 x 6 6 x 6 x 60
7 42 13 22mm Single 2A 10 x 10 x 6 6 x 6 x 60
8 48 13 22mm Single 2A 75 x 75 x 8 6 x 6 x 60
9 54 10 22mm Single 2A 75 x 75 x 8 6 x 6 x 60
10 60 10 20mm Single 2A 75 x 75 x 8 6 x 6 x 60
11 66 9 20mm Single 3A 75 x 75 x 8 6 x 6 x 60
12 72 7.5 20mm Single 3A 60 x 60 x 600 6 x 6 x 60
13 78 7.5 20mm Single 3A 60 x 60 x 600 6 x 6 x 60
14 84 5 16mm Single 4X 50 x 50 x 6 -
15 90 5 16mm Single 5X 25 SOLID -
16 96 5 16mm Single 1X 25 SOLID -
BRACE
Internal
Traingle
1 6 75 x 75 x 6
2 12 75 x 75 x 6
3 18 75 x 75 x 6
4 24 75 x 75 x 6
50
Monopole Tower – Structural Form
Platform
Platform Height
Section 1
d d
Section 2
d – section overlap
d d
Section 3
Height
d d
Section 4
d d
Section 5 Section Height
Base Plate
Figure 2.14
Sections fit into each other with an overlap (d). Base diameter, section height, depth of
overlap between sections and total mast height are all structural stability issues
determined by the structural design engineer. For higher towers, additional sections are
added below section 5 until the required height is reached but there must be
corresponding increases in base width as the number of sections and consequently the
height increases.
51
Table 2.13 Design details of a four section, 45 meter Monopole (Typical)
Section 4 3 2 1
Length (m) 13.7 12 12 11.2
Number of Sides 18 18 18 18
Thickness (mm) 10 8 6.5 5.5
Lap splice / section overlap (m) 1.7 1.45 1.14
Top Dia (cm) 106 80 75 56
Bottom Dia (cm) 130 110 93 75
Grade of Steel A572-65
Weight (Kg) 8.4 5.3 3.5 2.3
Material Strength 80 ksi 80 ksi 65 ksi 65 ksi
52
Antenna carrying Monopole (Self Supporting)
Figure 2.15
Pictorial of a self-supporting monopole tower fully fitted with antenna support bracket
and carrying antennas
53
Section of a Typical Guyed three-legged Mast
(Single or Z-bracing)
Figure 2.16
54
N-section Guyed Pole Mast
1
2 H
1
4 H
Base Plate
Base Plate
Figure 2.17
A four section guyed monopole illustrating the relationship between tower height (H)
and the horizontal distance from tower base to the guy anchor
(1/4 H). Tower can be installed in many sections.
This design of masts is ideal for the installation of HF-SSB dipole antennas.
55
Tria n g u la r G u y Wire su p p o rt
Fits in to th e to p p o rtio n o f th e
Ma st
Figure 2.18
Details of parts of the guyed pole mast in figure 2.17 above
56
Figure 2.19
Shows in detail, the antenna support outrigger shown in figure 2.17 above.
57
Roof Mounts - Pictorial
Figure 2.20
58
Figure 2.21
Figure 2.22
Penetrating Roof Mounts showing acceptable craftsmanship
2.4 Painting
59
All skeleton type structures must be painted to ICAO stipulations on obstruction
painting.
In addition mast and towers shall be painted with base primer paint, one suitable under
coat of red and white or orange and white followed by two coats of non gloss (matt)
paint.
All mast and tower structures in Nigeria must conform strictly to ICAO / NAMA
regulations with respect to obstruction lighting of tall structures as follows:
For every fifty meters of height above ground level, a tower shall have installed
on it, one lamp on top and two lamps at the sides.
Obstruction lamps shall be fitted and shall be maintained in a working condition
at all times on all structures within 15 kilometers of an airport or helipad.
Light intensity and colour as follows:
Betw 45 and 150m not below 1600 candelas Red and flashing
60
NAMA / ICAO Lighting Regulation
45 - 107 m
Double
lights
0 - 45 m
Figure 2.23
Schamatic representation of the ICAO / NAMA obstruction lighting regulations.
2.6 Substructure
Foundations for the tower and mast structures shall be designed to withstand the full
expected dynamic loads - antennae, feeders, wind loading, etc. It shall take cognisance
of the complete findings of the site conditions (geotechnical investigation of soils and
wind conditions). This may call for different types of foundation which may take the
form of reinforced concrete blocks, standard pad and column, raft, preset rock anchors
or piles. Engineers must compute the weight of tower structure, weight of antenna
feeders and all associated steel work then calculate effects of wind loads on total
surface.
61
Worst case load design condition shall always constitute the initial factor of safety
against overturning for complete foundations or any part thereof.
Standard foundation designs are to be made for normal soils. They may be modified to
suit the soil conditions at the installation site. Soil investigations must be carried out at
each site to determine the bearing pressures (vertical and horizontal) and other
subsurface conditions. The final foundation design shall be made to suit the soil
conditions at the site.
Normal soils are defined as dry cohesive soils having
Three basic physical forces shall be taken into consideration whilst designing tower and
masts foundations. They are: -
Proper soil borings shall be made by competent soil testing specialists and they must go
deeper than the probable depth of the foundation to make sure of soil type consistency a
little deeper.
For guyed towers, borings are also to be taken at all guy locations and at the base pier
location. Conditions can vary widely on the site. Watch out that the concrete mix
specified by engineer is adhered to.
Standard foundations and anchors may be used for construction when actual soil
parameters equal or exceed normal soft parameters. Geotechnical investigation to verify
that actual site soil parameters equal or exceed normal soil parameters must be made
before standard foundations and anchors are utilized in final designs.
Foundations and anchors shall be designed for the maximum structure reactions
resulting from the anticipated worst loading conditions. When nonstandard foundations
and anchors are to be used for construction, the soil parameters recommended by the
geotechnical engineer should incorporate a minimum safety factor of 2.0 against
ultimate soil strength.
Rock anchors shall be of type to permit long life and shall be treated against corrosion
to last over the design life of the tower. Pre-stressed rock anchors are to have their upper
terminating steel work in such a way as to have a steel-to-steel connection between the
structure footing and the rock anchor tendon. The upper end termination of rock anchors
shall not be encased in concrete but shall be protected against corrosion so as to allow
any subsequent checking of the tension in the tendons during the life of the structure.
Templates provide proper anchor bolt orientation at the time of foundation forming.
Templates shall be precisely fabricate and used in constructing tower foundations to
design specifications. Use of templates eliminates problems associated with
misalignment. A minimum of two anchor stirrups shall be provided around each leg of a
tower. Each stripe shall have a safe working load (SWL) of 100KN.
2.6.5 Uplift
Straight shaft drilled piers for standard foundations shall have an ultimate skin friction
of 31 kPa per linear meter of depth to a maximum of 48kPa of shaft surface area for
uplift or download resistance.
The effects of the presence of water shall be taken into account in the design of
nonstandard foundations. Reduction in the weight of materials due to buoyancy and the
effect on soil properties under submerged conditions shall be considered.
2.6.6 Concreting
Loose material shall be removed from bottom of excavation and the sides of excavation
shall be rough and free of loose cuttings before concrete placement.
Concrete shall be placed in such a way that will prevent segregation of concrete material
and any occurrence that may decrease the strength or durability of the foundation.
Concrete placement shall be continuous. No construction joints shall be allowed.
Weight of concrete mixture shall be 24kNm-3.
Concrete mixture must be such as to enable the concrete develop a minimum
compressive strength of 30Nm-2 in 28 days. Reinforcement steel shall be grade 50
deformed bars and shall be covered with concrete overlay of a minimum thickness of
75mm. Spacers shall be used to achieve this minimum cover on reinforcement. Concrete
should always be thoroughly mixed prior to putting in place, and any water which, seeps
into excavation should be removed prior to placing concrete. A concrete vibration
machine must be used until all concrete is in place.
The concrete column of foundation must always be installed inside wood or steel
formwork and left in place for 24 hours before removing. When the formwork is
removed concrete must be kept wet for first seven days of drying in the south of the
country whilst a ten-day period is recommended for the north.
Aggregate size shall be 20mm.
64
Mechanical vibration shall be used in making concrete so as to eliminate honeycombs
and voids. Welding and splicing is prohibited on reinforcement steel and embodiments.
Concrete curing time should be 28 days.
The surface level of mast foundation, guy anchor and tower foundation blocks shall be
between 150mm and 300mm above the highest point of the existing ground level.
When separate blocks of foundation for each leg of tower are employed, the upper
surface of each must be at the same level. The upper surfaces of all foundations are to
be given a gentle slope to ensure water run off. They are to be painted further with
bituminous paint to avoid dampness around the foundation bolts, sole plates and guy
attachment steel works. All loose materials are to be removed from the excavation
before placement of concrete. A curing time of four weeks (28 days) is to be allowed
before erection of steel on the concrete base.
If power cables, feeders, grounding tape must pass through concrete base, appropriately
sized diameter plastic or asbestos pipe shall be imbedded in concrete works.
Where land for structure is limited, grounding tapes and rods may be placed below or to
the side of foundation.
65
2.6.7 Raft Foundation
The dimensions of the raft are to be chosen so that the pressure distribution under
maximum design loads will be such that tensile forces will not develop under a
significant part of the raft area. Raft foundations shall be designed by certified
foundation engineers using geotechnical data for the site. A name plate giving details of
the designer and the builder shall be placed in conspicuous location at the tower base.
2.6.8 Piles
In swamps and peat soils, pile foundations are recommended in order to overcome
catastrophic effects of uneven settlement in other types of foundation. Pile foundations
shall be designed by certified foundation engineers using geotechnical data for the site.
A name plate giving details of the designer and the builder shall be placed in
conspicuous location at the tower base.
For sandy soils, it is a little more tricky. The hole will usually cave in as its being
drilled. A casing can be used and pulled out as the concrete is placed so the concrete is
in contact with the sides of the hole. Or drilling slurry could be used. The hole is kept
filled with "mud". As the concrete is pumped into the bottom of the hole, the mud is
pumped out at the top. The concrete likewise makes intimate contact with the soil and
the foundation provides the support that the engineering calls for.
2.6.10 Reinforcement
Main reinforcement bars shall have a minimum concrete cover of 75mm. Sufficient
auxiliary reinforcement shall be included to minimize the occurrence of cracking whilst
the integrity of the foundation remains intact. Reinforcement in block type foundations
shall be such as to ensure that the total weight of concrete can be fully utilized to give
the specified resistance to uplift forces.
In the case of guy anchor blocks, a safety factor of 2 shall be applied to the maximum
design guy tension. In calculating the resistance to shear (for the foundation only) the
friction between the bottom face of the concrete and the soil shall be taken into account.
In the case of guy anchor blocks, the earth resistance in the direction of the horizontal
force may be assumed to be utilized, in which case the soil shall be checked against the
possibility of shear-friction failure. The soil surrounding the foundation shall not be
included in the calculation of resistance to uplift and overturning.
67
Foundation design for Self- Supporting Post Mast
Infill between base and
Base Plate
plate (concrete or epoxy)
Studding
Dimensions of X and Y
are dependent on soil
conditions, dead weight
of mast and wind loading
Figure 2.25
68
SECTION VIEWS – SHOWING SUBSTRUCTURE ARRANGEMENT
(Raft Foundation)
X1
X
A
Horizontal Ties
X4 X3
Vertical Bars
FOUNDATION PLAN
Tower Base
D2
D1 Ground Level
Horizontal Ties
Vertical Bars
D
Foundation stub leg
1"-3"
L
SECTION THROUGH FOUNDATION
Figure 2.26
This foundation type can be used for all types of towers. It is applied for individual
legs for a three or four legged structure. Type of soil and the overall dynamic
loading determine the dimensions. These shall be determined for each particular
site by the geotechnical engineer.
69
BASIC RAFT FOUNDATION DESIGN FOR TOWERS
½X
Plan View
Bar Clearance
Horizontal bars, spaced according to engineer's design
Section AA
Figure 2.27
All dimensions, reinforcement steel sizes and quantities shall be according to the
engineer’s design which will be dependent on the soil characteristics, dead loading of
mast, its height and worst case calculated wind loading
70
Traditionally reinforced concrete is the choice option for tower guy anchors. A concrete
block, in the size determined by the design engineer, is placed against undisturbed earth
to hold the guys. Construction involves digging, forming and pouring the concrete, then
backfilling and tamping. The equipment required includes backhoes, forming equipment
and concrete mixers, etc.
71
Basic Foundation Design - Four Legged Tower
Y
Z
SECTION
Stud holes
Anchor Plates
X2(All sides)
Studding Details
X1 (All sides)
Figure 2.29
Design for light weight mast in normal soil
Foundation design for one leg in a three or four legged tower configuration.
This is a galvanised steel tower socket base for installation on a concrete foundation. Each corner of
the base is provided with a clearance hole for studs that provide a leveling method. Typical values for a
lightweight tower in a normal soil are as follows:
72
Drilled Pier Foundation Design for Towers in Swamps
(Three Legged)
32' - 6"
9' - 4 9/16"
A
60o 60o 60° 60°
Tower Center
18' - 9 1/18"
120°
120o
Tower Leg Base Plate
A
Double Nut
Drilled Pier
Anchor bolt projection
Form Top. Drilled Pier with
galvanised sheet metal Non shrink grout 135
33" - 0"MINIMUM
Drain plate
BASE DETAIL
A
FOUNDATION PLAN
SECTION A - A .
Figure 2.30
Plan of a typical foundation type for unconsolidated soils.
All dimensions are to be specified by a geotechnical engineer and are strictly dependent
on the site soil characteristics, expected maximum dynamic loads, shear stress, uplift
and compression.
73
Typical Micropile in an unconsolidated Formation
Lead Section
Figure 2.31
Section of drilled Pier Foundation
Figure 2.32:
75
Figure 2.33
Typical Pier and Pad foundation construction
Tower Base
76
Basic Foundation Design for a Three legged slim lattice Mast
W Ground Level
Y Expansion fillet
A393 wire mesh to side faces
Nominal Cover to all faces
X
Section View
X
X/2 X/2
W – Lattice face width at the
base
X/2 X – Foundation dimension
(square)
X
X/2
Plan View
Figure 2.35
All dimensions are to be specified by a geotechnical engineer and are strictly dependent
on the site soil characteristics, expected maximum dynamic loads, shear stress, uplift
and compression.
77
C
L
Tower axis and centre pad
C L
A A
Square
(W)
PLAN VIEW
Tower section
Grade
d1 d
#7 Steel bars
Drainage bed of compacted gravel and sand
ELEVATION VIEW - section AA
Figure 2.36
All dimensions are to be specified by a geotechnical engineer and are strictly dependent
on the site soil characteristics, expected maximum dynamic loads, shear stress, uplift
and compression. Typical values in normal soil for a 45 meter light weight steel tower
are:
This design does not give room for leveling after concrete has been poured
78
Foundation Design for a Self –Support Monopole Tower
Section
Plan
Figure 2.37
Dimensions given above vary with the peculiarities of the monopole and the soil
79
2.6.13 Foundation in Swamps
Guyed tower erection in swamps can be performed more quickly, more efficiently and
less expensively with modified construction techniques and an alternative method for
anchoring.
One alternative method is the ‘simple marsh anchor’ method. This technology uses
square rods with screw helices at one meter intervals on the initial three to six meter
length. These rods are then screwed into the ground with one, two, or three meter
extensions being added until the proper depth and torque are reached. This method is
analogous to driving in earth rods into the earth except that here, hydraulic screwing is
used. The torque and final depth are determined by the soil and by the pulling strength
required. Each anchor is then topped with an eye to attach one guy wire.
Using screw anchors requires only the availability of an auger machine to screw the
anchors into the ground. No digging of holes, forming, and pouring concrete for the guy
anchor is required.
With this method, just one anchor per guy wire would do. The anchors are simply
screwed into the ground until a layer of earth is encountered that is resistant enough to
achieve the required installation torque. Anchors could be screwed into the ground for a
few hundred meters. The depth could be shortened considerably by using multiple
anchors with load-distributing linkages.
This method has unique advantage of ease of adding extensions or additional anchors at
a later date, should guy wire capacity need to be increased for additional load
requirements or for the addition of torque arms.
The only concrete needed is for the tower base foundation.
All masts shall be grounded. The earth resistance measured at the earth terminal block
shall be less than 2 ohms. A lightning air terminal (Faraday Rod) shall be mounted on
mast top and a vertical copper earth wire or tape run down the side of one mast leg to
ground and connected to the earth at the terminal box.
The most important in getting a good earth is the use of right and good quality materials
for installation.
80
Tapered Base, Guyed Tower - Grounding Guyed Tower Leg Grounding
Figure 2.38
81
Earthing and lightning protection methods
Earth Bar
1 Antenna Cable Bulkhead separately
earthed to Tower Earth Tape - Copper
2 Buried Earth Rods
Other Equipment Earth bonded to
Tower
Figure 2.39
82
2.7.1 Earthing
Earthing and Lightning protection shall be provided in all completed towers sites to
protect equipment from damage and personnel from harm which may result from
excessive voltages during a lighting strike. The arrangement shall be such that lightning
discharge current must be prevented from entering equipment rooms. Equipotential
conditions shall be maintained throughout the site by bonding.
Resistivity at any depth is related to the diameter of the earth rod, the target resistance
and the depth to which the earth electrode is driven into the soil by:
An accurate assessment of the soil resistivity should be made around the tower base
using a direct reading resistance meter to determine the appropriate depth to drive in the
copper earth rods, the number of rods, the need for an earth mat, etc.
Table 2.1 gives typical values which can be used for computation but shall not serve as
a substitute for actual measured values.
83
Table 2.14 – Resistivity Values for different Soil Types
Lightning rod is clamped to the highest point on the mast. Ground wire is connected to
the lightning rod and shall, most desirably, be one continuous piece all the way to the
earth ground rod. Sometimes, the antenna type may not permit the use of a lightning
rod point. In such cases, the ground wire shall be taped or wire-tied to the mast as far up
as practical. Ground wire shall run from the tip of the mast, be connected to the tower,
and then run all the way to the ground.
Copper bond earth rods made up of copper electrolytically bonded onto a high tensile
steel core shall be driven into the ground at varying depths dictated by earth resistivity
measurements. Several lengths of the rod may have to be so driven in. Each length is
coupled to the next through coupling threads. The rod is driven in by hammering on the
driving high tensile steel head. Each leg of a mast or tower shall have at least one earth
rod driven into the ground beside it. The leg of the mast is tied to the earth rod through a
flat copper tape.
The number of earth rods to be driven into the ground at the optimum depth shall be
such that is necessary to achieve a suitably low resistance.
Where a good grounding cannot be obtained at a reasonable depth, a three meter pit
should be dug and partly filled with layers of carbon, salt and manure and backfilled
firmly.
84
2.7.3 Protective Grounding
A similar ground rod shall be installed at each guy anchor and connected to each guy at
the anchor in case of guyed towers.
Self-supporting towers exceeding 1.5 m in base width shall have one ground rod per
tower leg. All the earth rods shall be tied together to maintain an equipotential all over
the structure. Top ground strap are to be bonded at both ends. Bottom ground strap are
also to be bonded at both ends. All equipment on a structure (antennas, antenna
supports, warning safety lights, etc) shall be connected by a secondary ground.
The earth of the tower shall be bonded to the general earth of any adjoining equipment
room and all shall form a single earth. The maximum permissible resistance to earth is 2
ohms.
Figure 2.41
A complete fall arrest system consists of the rail and the trolley.
2.7.1 Trolley
86
Locking brake pawl attaches to climber’s harness
Moves freely along the Safety Rail with climber in normal climbing position
In case of a slip trolley brakes remain locked until the force is removed
Falls are instantly arrested when a sudden downward motion is applied to the Trolley.
Trolley remains stationary once disconnected from the harness.
Safety Rail
87
2.7.3 Climbing Facilities
The lowest point on the ladder shall be at a height of 3m to 4.5m above ground level and
it shall run all through to the top of the structure. The ladder shall be so located that a
clearance of at least 150mm at the rear of the ladders exists between the ladder and the
structure.
Anti climbing devices shall be provided on the structure to prevent access except from
the climbing ladder.
The vertical separation between rest platforms shall be 20m. Work and test platforms
shall be located at those points where antennas are to be installed.
Guard-rails
These shall be of height between 0.9m and 1.1m and shall be provided on all platforms,
stairways and horizontal members used as walkways. They shall have an intermediate
rail at half this height and a toe board not less than 150mm high. The distance between
any toe-board and the lowest guard – rail above it shall not exceed 750mm. Widths of
88
walk-ways and platforms should not be less than 650mm. Walk-ways and surface used
as working platforms or traversed to gain access to platforms or traversed to gain access
to working positions are to be provided with anti-slip surface.
Guard rails and toe boards shall be attached at each vertical stanchion. They shall be
secured to prevent rotation.
Step Bolt
Safety Enhancement
Safety in the installation and use in service of masts and towers are enhance by the
following practices which shall be mandatory on all tower owners and installers
(1) Tower assembly parts shall be standardized e.g. fasteners for the main
structure should ideally be of only one size, length and material.
(2) Manually handing over of parts or tools between installers during tower
erection is totally forbidden.
3) All parts must be fully labeled especially where the method of assembling
is not obvious.
(4) Towers must be structurally designed for simple assembly - ease of fit,
elimination of small loose parts, etc.
(5) On-site welding and riveting is prohibited. All site connections shall be by
bolt and nut with a means provided for locking the nut against loosening by
vibration. All nuts bolts and washers shall be galvanized. Such galvanizing
shall be done so as to permit the ready assembly of nuts and bolts after
galvanizing. Taper washers shall be used whenever the steel section shape
requires their use. Bolt lengths shall be such that with the locking device in
place a minimum of one complete thread shall protrude beyond the nut.
Bolt threads shall protrude inside the structure only.
89
90
CHAPTER THREE
MATERIALS SPECIFICATIONS
91
3.1 The Superstructure
The sizes of members in compression shall be such that the maximum slenderness ratios
are:
Ladder 120
Bracing members 150
Subsiding members 180
Where a gusset plate connects bracings that cross, at least one of the bracings shall be
continuous between the main members to which it connects.
1. Legs - Tubular
- Angular
- Solid Round Leg
2. Members - Tubular pipes
- Angles
3. Bracing - Angles
- Tubular pipes
- Steel rods
3.1.5 Guys
Both lattice and monopole structures shall be made from steel for tall, heavy load
bearing towers or aluminum for lightweight light duty towers. Tower components shall
be of the following classification: -
All steel members shall be fabricated from Grade 50 or 42, A36 or A 572-50.
All steel tubes shall be fabricated from Grade 43C.
All structural pipes shall be fabricated from Grade 42 or Grade C steel.
Anchor rods shall be fabricated from Grade B7 steel.
Rebar shall be fabricated from Grade 400 steel.
Diagonals shall be fabricated from Grade 43A steel.
Structural Bolts fabricated from Grade A325 steel.
Steel angles shall have a minimum strength of 56ksi for tower legs and 36ksi for
tower members.
Round legs shall be fabricated from schedule 40 pipes.
Braces shall be fabricated from Grade A36 or A 572-50 steel
3.2 Concrete
Ordinary cement shall be used. Cement of different types may not be mixed. High
Alumina (HA) cement may not be used for concrete mixing. Additives that hasten the
setting of cement or give a denser concrete shall not be used.
All sand shall be clean, sharp, gritty, and free from loam earth, salt and other impurities
like humic acids. Sand shall not contain more than 15% clay or silt. The sand shall
contain grains from the finest sizes up to 4.75 mm. Grains smaller than 0.25 mm in size
shall not constitute more than 15% of the total weight of the sand to be used.
Aggregate shall be clean screened river ballast gravel, graded in size and free from dirt,
floury stone dust, loam or earth or any other impurities. The maximum size of aggregate
to be used shall be 19 mm.
93
Water to be used for concrete mixing shall be free from oil, salt, and organic substances.
It shall be clear. Cement shall have a mixture of 1:2:4.
The concrete shall be thoroughly mixed by machine.
The following metals and alloys shall be used in tower fabrication, construction and for
foundation reinforcement: -
Magnesium
Zinc
Aluminum
Lead / Tin
Silver
Graphite
94
95
3.5 Earthing Clamps
Figure 3.1
Typical clamps for installation of earth tapes
3.6 U-Bolts
96
Multi-Point Air terminal Elevation Rods Mounting Brackets
Figure 3.2
Earth and lightning protection materials
Rod to Tape Coupling Building in Rod Holdfasts
97
3.7 Connector Clamps
Figure 3.2
Installation Materials – Earthing and lightning protection
98
3.8 Screw down Clamp
Figure 3.3
Installation Materials – Earthing and lightning protection
Inspection Housing
Figure 3.4
These materials are used for earthing installation to make testing easy
100
Figure 3.5
These materials are used for earthing installation to make testing easy
Conductor inspection housing shall be installed at test points to protect the earth rod and
earth connections and make them available for testing. It shall be made from high grade,
heavy duty polypropylene and ultra violet stabilized to prevent degradation by sunlight.
It shall be non-brittle.
101
3.10 Lightning Arrestor Installation Materials
Figure 3.6
Pointed Air rod and installation saddle
102
3.11 Copper Tapes – Can be Tin or lead covered
Copper Tape
Figure 3.7
Flat Copper Tape and Flexible Copper Braid
103
3.12 Connectors
Figure 3.8
Cable connectors
104
3.13 Bi-Metallic Connectors
Non-Metallic Clips
Figure 3.9
Cable and Tape clips
Figure 3.10
Guy materials
Guying materials shall conform to the sizes, mechanical strengths and capacities shown
below in Tables 3.1 (1-4)
12.5mm Link from earth anchor to turnbuckle. Hot dip galvanized finish.
108
3.2 Antenna Mounting Frames
Frames for mounting antennas on towers or masts shall be designed in sympathy with
the type of tower structure, the type and weight and size of the antenna.
They shall be made from galvanised steel, stainless steel or aluminum. There shall be no
welded parts. All joints shall be implemented with bolts and nuts.
Some basic designs exist for certain tower structural forms. A few are shown below.
Tower
structure
DETAIL B
A A
Plan View
Section View
109
Side Antenna Mount
SADDLE- BRACKET
110
Side Mount
Plan View
Section View
111
112
Antenna Mount on Self-Support Tower
Plan View
Section View
113
metal clip
114
metal clip
115
CHAPTER FOUR
116
4.0 First Line Maintenance
In tower design, it is assumed that the worst case scenario is a total mechanical failure.
This can be caused by stress, extreme overload, use of defective and poor quality
materials, fatigue, corrosion, poor workmanship, insufficient maintenance, sabotage, as
well as any combination of these factors. Every design must attempt to foresee all
possible combinations of these that can occur in the installation environment and
incorporate protective answers to them in the design. This is the first line of
maintenance.
Unprotected steel can be seriously damaged due to environmental factors as rain, salty
humid air and extremes of temperature. Corrosion transforms steel back to its natural
state of iron, which is very fragile and can prove to be deadly in structures like towers
which support heavy pressures. The best way to avoid this phenomenon is through a
process called "hot dip galvanization".
This process consists of dipping steel in melted zinc at 450°C. At this temperature iron
and zinc share great affinity, and allow an alloy to form where pure zinc prevails to the
outside. The final product is a steel surface protected with a zinc coating.
Due to the difference of electrochemical potential between zinc and steel (cathodic
protection), a zinc coating protects steel in such a way that slightly exposed surfaces due
to cutting, scratching or piercing are equally protected against corrosion.
What considerably affects the appearance and gauge of galvanization is the contents of
alloy elements that are present in steel: carbon, magnesium, and silicon. The greatest
effect is produced by silicon in concentrations higher than 0.12%.
Most steels can be galvanized: high-strength steel, low-carbon steel, low-alloy steel, and
steels with as much as 0.20% copper content; the most appropriate being low-carbon
steels.
Major inspections shall be performed, at a minimum, every 3 years for guyed towers
and every 5 years for self-supporting towers.
Ground and aerial procedures should be performed only by authorized personnel,
experienced in climbing and tower adjustments.
All structures shall be inspected after severe winds or other extreme loading conditions.
Shorter inspection intervals of 2 years for guyed towers and three years for self
supporting towers shall be obligatory for structures in coastal salt water
environments, in corrosive atmospheres, and in areas subject to frequent vandalisation.
At every tower site, the owner shall keep a maintenance log book in a thick cellophane
folder. This folder shall be readily accessible to the regulators inspectors. It shall have
the following information: -
Installation Date
Inspection due dates
Painting due dates
Minor Maintenance due dates
Major Maintenance due dates
Name and address of Inspector
For each of the due dates, the log must show whether the inspection or the maintenance
was carried out and by whom.
4.3 Maintenance Philosophy
The external condition of Towers and Masts must be regularly inspected with intent to
detect deterioration. Necessary maintenance works must be carried out timely.
Periodic checks and inspection of the structure must be carried out:
At regular intervals of time during the service life of the structure
After the installation of an additional load like antennas on the structure
After each serious climatic event like tempest, hurricane, tornado
The first thorough check of the structure should be carried out 6 months after its
installation and erection.
Maintenance checks should be carried out yearly henceforth
4.4 Routine Checks
118
4.4.1 Main structure
Check that each cable that is part of the guy wire is neither broken nor warped
Measure the tension of each guy wire using a strand dynamometer and compare result
with the installer's stated values.
4.4.5 Verticality
Check with the appropriate devices such as theodolite that the structure stands vertical.
There shall be no tilts. Take two measurements in two different planes with a 90' angle
difference.
For a fall arrestor system with cable, check that the cable has not been over tightened.
Check that all lightning and Earthing components are existing and complete including
lightning arrestor, copper strip, connection plate,
Check the Earthing connection of coaxial cables,
Measure the resistivity of the Earth and confirm conformity to expected values.
4.4.11Salty environment
Wash the structure and accessories with clean water once every six months to eliminate
residue salt particles which may not be washed away by rain.
4.4.12Concrete blocks
4.4.13Tower loading
Check types, numbers and installed heights of all antennas currently on the structure and
confirm that the loading does not exceed structure design load.
4.5.1 Structure
121
Tension of Guy wires using a dynamometer.
Geometry of the structure.
Re-tighten main structure and accessories bolted parts (10%)
Geometry of the Bars.
Rigidity of Antennas and Accessories.
4.5.2 Safety
Ensure anti climb door can open and close. Clean and grease all hinges.
Ensure the work platform's trap can open and close. Clean and grease all door hinges.
Fixing of the fall arrestor system
Check tower ladder for any signs of weakness, re-tighten all bolts
Check the riggers’ safety gear, take inventory and record it
Right placing and right installation of safety components.
Test of the fall arrestor system with individual equipment.
4.5.3 Earthing
4.5.5 Coating
Discrepancies in galvanization
Paint coating. Repaint every three years
Rust and/or corrosion conditions
ICAO / NAMA Color marking conditions
Water collection in members - unplug drain holes, etc.
4.6 TESTING
There are two basic methods of measuring guy tensions in the field:
123
A dynamometer (load cell) with a come-along (length adjustment device), is attached to
the guy system by clamping onto the guy just above the turnbuckle and onto the anchor
shaft below the turnbuckle, thus making the turnbuckle redundant. The come-along is
then tightened until original turnbuckle begins to slacken. At this point the
dynamometer carries the entire guy load to the anchor, and the guy tension may be read
directly off the dynamometer dial.
This method is used to set the correct tension by adjusting the come-along until the
proper tension is read on the dynamometer.
Two control points are marked, one above the clamping point on the guy and one on the
anchor shaft, and the control length is measured. The dynamometer and come-along are
then removed, and the original turnbuckle is adjusted to maintain the control length
previously measured.
Dyanamometer Turnbuckle
Come - Along
(1) Dynamometer Method
As come-along is tightened,
dynamometer carries all
the load
124
down the guy N times back N times in p seconds
In p seconds
Figure 4.1
Measurement of Tension of Guy
There are two common techniques for the indirect measurement of guy initial tension -
the pulse or swing method (vibration) (Figure 4.2) and the tangent intercept method
(Figure 4.3).
TA
V L
H
125
Figure 4.2
One sharp jerk is applied to the guy cable near its connection to the anchor causing a
pulse or wave to travel up and down the cable. On the first return of the pulse to the
lower end of the guy cable, a stop watch is started. A number of returns of the pulse to
the anchor are then timed, and the guy tension is calculated from the following
equations:
where
TA = Guy tension at anchor
TM = Guy tension at mid-guy
W = Total weight of guy, including insulators, etc.
L = Guy chord length
N = Number of pulses or swings counted in P seconds
126
(b) The Tangent Intercept Method
I
I
α
TA
H
H
Figure 4.3
A line of sight is established which is tangential to the guy cable near the anchor end
and which intersects the tower leg a distance (tangent intercept) below the guy
attachment point on the mast. This tangent intercept distance is either measured or
estimated and the tension is calculated from the following equation:
where
C = Distance from guy attachment on tower to the center of gravity of the weight
W
127
I = The tangent intercept
If the weight is uniformly distributed along the guy cable, C will be approximately equal
to 1-I/2. If the weight is not uniformly distributed, the guy may be subdivided into n
segments and the following equation may be used:
where
Wi = Weight of segment i
Ci = Distance from the guy attachment on the tower to the center of gravity of segment i
If the intercept is difficult to establish, one may use the guy slope at the anchor end with
the following equation:
where
cz = Guy angle at the anchor
Note that
and that
and that WC in equation (7) may be replaced with S, as was done in equation (5).
128
Glossary of Terms
Plumb -- The horizontal distance between the vertical centerlines at any two elevations
shall not exceed .25 percent of the vertical distance between the two elevations.
Twist -- The twist (angular rotation in the horizontal plane) between any two elevations
shall not exceed 0.5 degrees in 3 m and the total twist in the structure shall not exceed
5".
Length -- For tubular steel pole structures with telescoping joint, butt welded or flanged
shaft connections, the overall length of the assembled structure shall be within plus 1
percent or minus 1/2 percent of the specified height.
Normal Soil -- A cohesive soil with an allowable net vertical bearing capacity of 192
kPa and an allowable net horizontal pressure of 63 kPa per linear meter of depth to a
maximum of 192 kPa.
Twist -- The angular rotation of the antenna beam path in a horizontal plane from the
no-wind load position at a specified elevation.
Sway -- The angular rotation of the antenna beam path in a vertical plane from the no-
wind load position at a specified elevation.
Primary Ground is the conducting connection between the structure and earth or some
conducting body, which serves in place of the earth.
Climbing Safety Devices -- Equipment devices other than cages, designed to minimize
accidental falls, or to limit the distance of such falls. The devices permit the person to
ascend or descend the structure without having to continually manipulate the device or
129
any part of the device. The climbing safety device usually consists of a carrier, safety
sleeves, and safety belts.
Lux is lumens/sq m
Alternative Mounting Structure - man made tree, clock tower, church steeple, bell
tower, utility pole, light standard, identification pylon, flagpole, or similar structure,
designed to support and camouflage or conceal the presence of telecommunications
antennas.
Dish Antenna - A parabolic or bowl shaped device that receives and/or transmits signals
in a specific directional pattern.
Co-location - single telecommunications tower and/or site used by more than one
telecommunications service provider.
130
Guyed Tower - Any telecommunications tower supported in whole or in part by cables
anchored to the ground.
Tower Height - The distance measured from ground level to the highest point of any and
all components of the structure, including antennas, hazard lighting, and other
appurtenances.
131
Index
Earthing 75,76, 78, 88, 89, 91, 92, 93, 94, 112, 114
Effective height 6
Elevation Rods 90
Environmental requirements 9
Excavators 8
133
G
Geographical coordinates 6, 7
Graphite 88
Ground mounted dish antennas 13
Guard-rails 81, 84
Gust factor 16, 35, 36, 126
Guy Anchor 11, 25, 50, 60, 61, 6, 66, 70, 75, 80,122
Guy materials 99
Guy wires 24,25, 111, 113
Guyed Towers 5, 24, 57, 80, 110
Guys 6, 11, 25, 66, 87
Height of Towers 8
HF-SSB dipole antennas 50
High Alumina (HA) 87
Hot Dip Galvanization 109
Humic Acid 87
K
K-bracing 26, 27, 28, 29, 30. 31
KNm-3 57, 59, 60
Kpa 57, 59, 121
134
Lap Link Weight Table 44
Lattice 5, 21, 22, 24, 26, 27, 34, 37, 38, 44, 45, 73. 86, 67, 111, 123
Saddle 86, 95
Lighting 6, 11, 12, 55, 56, 78, 123
Lightning and Earthing system 112
Lightning Arrestor 95, 112, 114
Lightning protection 6, 75, 76, 78, 80, 88, 90, 91, 92, 114
Log book 7, 110
Long Boom Arm Crane 8
Packer 8
Painting 55, 110
Panel Height 26
Permit Number 7
Photo sensor 12
Pier and Pad foundation construction 71
Piles 56, 61
Plate Type clamp 92
Platform height 45
Platforms 6, 21, 81, 111, 112, 122
Pointed Air Rod 95
Post Masts 23
Property Owner 6
Protective Grounding 80
Public Health 9
Public Safety 4, 8, 13, 82, 109
Tapered sections 21
Technical College 7
Terrain 14, 16, 128
Thimble 87, 100
Total anticipated antenna load 35, 36
Tower Base Foundation 75, 111
Tower loading 21, 113
Tower maintenance 109
Tower schedule 39, 41
137
Tower to Tower Spacing 12
Tube leg 21, 22
Turnbuckle 87, 99,100, 115
U, V
X, Y, Z
138