Abstract of Cost of Medical Block

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

Project : Estimate of Medical Block

Location : Sainamaina, Butwal


Owner: Sainamaina Municipality
Preapared By:ECoCoDE Nepal
Jwagal-10, Kupondole,Lalitpur

Abstract of Cost of Medical Block


S.N. Description of item Unit Quantity Rate Amount Remarks
1 Site clearance job 1 100,000.00 100,000.00

Earthwork excavation in foundation and


trenches in all type of soil excluding rock in
both dry and wet condition including
shoring and strutting when ever necessary.
2 Also Also pumping out water as when Cum 661.170 452.81 299,386.04
necessary from the trenches etc. having
lead of 30 m as per drawings, specifications
and instructions of site Engineers all
complete.

Dry brick soling in foundation and floor


3 including sand filling in joints, leveling, Sqm 1570.680 977.92 1,535,993.54
watering etc. all complete.
Plain cement Concrete (PCC) in 1:3:6 ratio
for foundations, flooring and walls with
approved quality of cement and sand and
4 Cum 117.801 13,332.50 1,570,581.40
crushed stone aggregate including mixing,
laying, curing etc all complete in approval
of site engineer.
5 Dwraf wall Cum 86.873 5,832.44 506,683.73

Providing and laying machine mixed /


machine vibrated Plain Cement Concrete (
PCC ) of grade M20/20 ( Design Mixed ) / in
nominal mix on volumetric proportion of
1:1.5:3(1 cement: 1.5coarse sand :3coarse
graded aggregate 20 mm down) for RCC
6 Cum 651.208 16,213.75 10,558,530.24
works, on Basement Ramp, Shear Walls,
Columns, Beams, Slabs, Staircase, etc
including necessary compaction, levelling,
curing, testing etc, as per drawings,
specifications and instructions of site
Engineer'sall complete.

Tor steel reinforcement bar of Fe 415/500


grade including straightening, cleaning,
7 cutting, binding & fixing in position with MT 79.881 114,703.65 9,162,633.47
annealed tying binding wire as per drawing,
design & instruction all complete.
Formwork, shuttering, centering with
approved materials for all works necessary
propping, scaffolding, staging, supporting
8 Sqm 4054.048 831.93 3,372,685.48
inclusive of wedging and cutting holes for
utilization till the support if fully unyielding
nett.
9 Backfilling cum 528.936 325.22 172,020.57
11 super structure wall Cum 338.859 12,942.72 4,385,751.92
12 Almunium Door and windows Sqm 367.562 -
13 False Ceiling Sqm 1799.990 861.35 1,550,421.39
14 Plaster Sqm 7239.374 445.05 3,221,854.33
15 Wall puty Sqm 7239.374 22.75 164,707.34
16 Distemper Painting Sqm 6372.562 222.85 1,420,106.29
17 Weather Coat Sqm 866.812 229.95 199,326.92
18 stainless Railing Rm 134.656 1,619.20 218,035.00
Sub total 38,438,717.64
Electrical 1,921,935.88
Sanitary 1,921,935.88
TOTAL AMOUNT 42,282,589.41
Calculation of Cost of Medical Block
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
1 Site clearance 1.000
Total 1.000 job

Earthwork excavation in foundation


and trenches in all type of soil
excluding rock in both dry and wet
condition including shoring and
strutting when ever necessary. Also
1
Also pumping out water as when
necessary from the trenches etc.
having lead of 30 m as per
drawings, specifications and
instructions of site Engineers all
complete.
Big block
Column Foundation
Along A -D 20 1.800 1.800 1.500 97.200
Along E-G 18 1.800 1.800 1.500 87.480
For Toe wall
Along A -D 4 15.850 1.000 1.500 95.100
Along E-G 3 17.500 1.000 1.500 78.750
Along 1 1 6.900 1.000 1.500 10.350
Along 2-6 5 18.830 1.000 1.500 141.225
Pool 1 5.500 5.000 1.800 49.500
Small block
Column Foundation
Along A-C 9 1.800 1.800 1.500 43.740
For Toe wall
Along A -C 3 5.950 1.000 1.500 26.775
Along 1-3 3 6.900 1.000 1.500 31.050
Total 661.170 Cum

Dry brick soling in foundation and


floor including sand filling in joints,
2 leveling, watering etc. all complete.
Big block
Column Foundation
Along A -D 20 1.800 1.800 64.800
Along E-G 18 1.800 1.800 58.320
For Toe wall
Along A -D 4 15.850 0.600 38.040
Along E-G 3 17.500 0.600 31.500
Along 1 1 6.900 0.600 4.140
Along 2-6 5 18.830 0.600 56.490
Pool 1 5.500 5.000 27.500
Small block
Column Foundation
Along A-C 9 1.800 1.800 29.160
For Toe wall 0.000
Along A -C 3 5.950 0.600 10.710
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
Along 1-3 3 6.900 0.600 12.420
Flooring 1 1237.600
Total 1570.680 Sqm
Plain cement Concrete (PCC) in
1:3:6 ratio for foundations,
flooring and walls with approved
quality of cement and sand and
crushed stone aggregate including
mixing, laying, curing etc all
complete in approval of site
3 engineer.
Big block
Column Foundation
Along A -D 20 1.800 1.800 0.075 4.860
Along E-G 18 1.800 1.800 0.075 4.374
For Toe wall
Along A -D 4 15.850 0.600 0.075 2.853
Along E-G 3 17.500 0.600 0.075 2.363
Along 1 1 6.900 0.600 0.075 0.311
Along 2-6 5 18.830 0.600 0.075 4.237
Pool 1 5.500 5.000 0.075 2.063
Small block
Column Foundation
Along A-C 9 1.800 1.800 0.075 2.187
For Toe wall
Along A -C 3 5.950 0.600 0.075 0.803
Along 1-3 3 6.900 0.600 0.075 0.932
Flooring 1 1237.600 0.075 92.820
Total 117.801 Cum
4 Dwarf wall
Tie Beam
Big block
Along A -D 4 21.050 0.230 1.070 20.722
Along E-G 3 24.000 0.230 1.070 17.719
Along 1 1 9.500 0.230 1.070 2.338
Along 2-6 5 26.630 0.230 1.070 32.768
Small block
For Toe wall
Along A -C 3 8.550 0.230 1.070 6.312
Along 1-3 3 9.500 0.230 1.070 7.014
86.873 Cum
S.N Description of work No. Length Breadth Height Quantity Unit Remarks

Providing and laying machine


mixed / machine vibrated Plain
Cement Concrete ( PCC ) of grade
M20/20 ( Design Mixed ) / in
nominal mix on volumetric
proportion of 1:1.5:3(1 cement:
1.5coarse sand :3coarse graded
aggregate 20 mm down) for RCC
works, on Basement Ramp, Shear
Walls, Columns, Beams, Slabs,
Staircase, etc including necessary
compaction, levelling, curing,
testing etc, as per drawings,
specifications and instructions of
5 site Engineer'sall complete.
Big block
Column Foundation
Footing Base F1 38 1.800 1.800 0.200 24.624
1.94=((1.8
*1.8)+(0.8
Footing Slope 38 1.940 0.100 7.372 *0.8))/2
Column
up to Lower 38 0.500 0.500 1.070 10.165
upto +3.6 38 0.500 0.500 1.450 13.775
upto +7.2 24 0.500 0.500 7.200 43.200
upto +10.8 18 0.500 0.500 11.450 51.525
Lower Tie beam
Along A -D 4 21.050 0.230 0.300 5.810
Along E-G 3 24.000 0.230 0.300 4.968
Along 1 1 9.500 0.230 0.300 0.656
Along 2-6 5 26.630 0.230 0.300 9.187 171.282
Tie Beam +0 level
Along A -D 4 21.050 0.300 0.400 10.104
Along E-G 3 24.000 0.300 0.400 8.640
Along 1 1 9.500 0.300 0.400 1.140
Along 2-6 5 26.630 0.300 0.400 15.978
Beam +3.6 level
Along A -D 4 21.050 0.300 0.400 10.104
Along E-G 3 24.000 0.300 0.400 8.640
Along 1 1 9.500 0.300 0.400 1.140
Along 2-6 5 26.630 0.300 0.400 15.978
Beam +7.2 level
Along A 1 6.055 0.300 0.400 0.727
Along B-C 2 15.100 0.300 0.400 3.624
Along D- F 3 21.050 0.300 0.400 7.578
Beam +10.8 level
Along B-C 2 9.540 0.300 0.400 2.290
Along D- F 3 15.550 0.300 0.400 5.598
Small block
Column Foundation
Footing Base F1 9 1.800 1.800 0.200 5.832
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
1.94=((1.8
*1.8)+(0.8
Footing Slope 9 1.940 0.100 1.746 *0.8))/2
Column
up to Lower 9 0.500 0.500 1.070 2.408
upto +3.6 9 0.500 0.500 3.600 8.100
Lower Tie beam
Along A -C 3 8.550 0.230 0.300 1.770
Along 1-3 3 9.500 0.230 0.300 1.967 21.822
Beam +0 level
Along A -C 3 8.550 0.300 0.400 3.078
Along 1-3 3 9.500 0.300 0.400 3.420
Beam +3.6 level
Along A -C 3 8.550 0.300 0.400 3.078
Along 1-3 3 9.500 0.300 0.400 3.420
Slab
Big block
+3.6 level 1 777.900 0.125 97.238
+7.2 level 1 514.710 0.125 64.339
+10.8 level 1 336.780 0.125 42.098
Small block
+3.6 level 1 170.600 0.125 21.325
Pool
Raft 1 5.200 4.800 0.300 1.560
Shearwall 4 20.000 0.230 1.200 96.000
651.208 Cum

Tor steel reinforcement bar of Fe


415/500 grade including
straightening, cleaning, cutting,
binding & fixing in position with
annealed tying binding wire as per
drawing, design & instruction all
6 complete.
A Foundation
F1 13 1.800 1.800
main bar 16mm @ 150 c/c 13.00 2.09 1.58 556.83 kg
distribution bar 16mm @ 150 c/c 13.00 2.09 1.58 556.83 kg

F3 2 2.100 2.100
main bar 16mm @ 150 c/c 15.00 2.39 1.58 113.05 kg
distribution bar 16mm @ 150 c/c 15.00 2.39 1.58 113.05 kg

F4 5 2.400 2.400
main bar 16mm @ 150 c/c 17.00 2.69 1.58 360.54 kg
distribution bar 16mm @ 150 c/c 17.00 2.69 1.58 360.54 kg

F5 3 2.550 2.550
main bar 16mm @ 150 c/c 18.00 2.84 1.58 241.83 kg
distribution bar 16mm @ 150 c/c 18.00 2.84 1.58 241.83 kg

F6 6 2.700 2.700
main bar 16mm @ 150 c/c 19.00 2.99 1.58 537.52 kg
distribution bar 16mm @ 150 c/c 19.00 2.99 1.58 537.52 kg
S.N Description of work No. Length Breadth Height Quantity Unit Remarks

F7 2 2.850 2.850
main bar 16mm @ 150 c/c 20.00 3.14 1.58 198.07 kg
distribution bar 16mm @ 150 c/c 20.00 3.14 1.58 198.07 kg

F8 3 3.000 3.000
main bar 16mm @ 150 c/c 21.00 3.29 1.58 326.87 kg
distribution bar 16mm @ 150 c/c 21.00 3.29 1.58 326.87 kg

F9 2 3.300 3.300
main bar 16mm @ 150 c/c 24.00 3.59 1.58 271.77 kg
distribution bar 16mm @ 150 c/c 24.00 3.59 1.58 271.77 kg

CF 2 3.900 2.400
main bar 16mm @ 150 c/c 17.00 4.19 1.58 224.69 kg
distribution bar 16mm @ 150 c/c 27.00 2.69 1.58 229.05 kg
sub total 5666.71 kg

B Beam
B-1 lower tie beam 1 336.340
main bar 16mm 6.00 338.23 1.58 3202.34 kg
stirrups 8mm 100 c/c 1682.00 1.54 0.40 1038.80 kg
stirrups 8mm 150 c/c 1122.00 1.54 0.40 692.95 kg

B-2 Along D-D


at lvl 0.0 m 22.997
main bar 20mm 4.00 25.36 2.47 250.53 kg
main bar 16mm 4.00 25.36 2.47 250.12 kg
stirrups 10mm @ 100 c/c 115.00 1.98 0.62 140.26 kg
stirrups 10mm @ 150 c/c 77.00 1.98 0.62 93.92 kg

at lvl 3.6 m 24.008


main bar 20mm 8.00 26.37 2.47 520.19 kg
extra bar 20mm 4.00 19.14 2.47 188.80 kg
stirrups 10mm @ 100 c/c 121.00 1.98 0.62 147.58 kg
stirrups 10mm @ 150 c/c 81.00 1.98 0.62 98.79 kg

at lvl 7.2 m 24.008


main bar 20mm 8.00 26.37 2.47 520.19 kg
extra bar 20mm 4.00 19.14 2.47 188.80 kg
stirrups 10mm @ 100 c/c 121.00 1.98 0.62 147.58 kg
stirrups 10mm @ 150 c/c 81.00 1.98 0.62 98.79 kg

at lvl 10.8 m 24.008


main bar 20mm 4.00 26.37 2.47 260.09 kg
main bar 16mm 4.00 26.37 2.47 260.09 kg
stirrups 10mm @ 100 c/c 121.00 1.98 0.62 147.58 kg
stirrups 10mm @ 150 c/c 81.00 1.98 0.62 98.79 kg

B-3 Along B-B,C-C 2


at lvl 0.0 m 23.01
main bar 20mm 4.00 25.37 2.47 501.31 kg
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
main bar 16mm 4.00 25.37 2.47 500.50 kg
stirrups 10mm @ 100 c/c 116.00 1.98 0.62 282.97 kg
stirrups 10mm @ 150 c/c 77.00 1.98 0.62 187.83 kg

at lvl 3.6 m 23.5


main bar 20mm 8.00 25.86 2.47 1020.33 kg
extra bar 20mm 4.00 27.34 2.47 539.36 kg
stirrups 10mm @ 100 c/c 118.00 1.98 0.62 287.84 kg
stirrups 10mm @ 150 c/c 79.00 1.98 0.62 192.71 kg

at lvl 7.2 m 17.519


main bar 20mm 8.00 19.88 2.47 784.35 kg
extra bar 20mm 4.00 21.36 2.47 421.37 kg
stirrups 10mm @ 100 c/c 88.00 1.98 0.62 214.66 kg
stirrups 10mm @ 150 c/c 59.00 1.98 0.62 143.92 kg

at lvl 10.8 m 11.036


main bar 20mm 4.00 13.40 2.47 264.28 kg
main bar 16mm 4.00 13.40 2.47 264.28 kg
stirrups 10mm @ 100 c/c 56.00 1.98 0.62 136.60 kg
stirrups 10mm @ 150 c/c 37.00 1.98 0.62 90.26 kg

B-4 Along A-A


at lvl 0.0 m 23
main bar 20mm 4.00 25.36 2.47 250.56 kg
main bar 16mm 4.00 25.36 2.47 250.15 kg
stirrups 10mm @ 100 c/c 116.00 1.98 0.62 141.48 kg
stirrups 10mm @ 150 c/c 78.00 1.98 0.62 95.14 kg

at lvl 3.6 m 23.51


main bar 20mm 8.00 25.87 2.47 510.36 kg
extra bar 20mm 4.00 27.35 2.47 269.78 kg
stirrups 10mm @ 100 c/c 118.00 1.98 0.62 143.92 kg
stirrups 10mm @ 150 c/c 79.00 1.98 0.62 96.35 kg

at lvl 7.2 m 6.019


main bar 20mm 8.00 8.38 2.47 165.30 kg
extra bar 20mm 4.00 9.86 2.47 97.25 kg
stirrups 10mm @ 100 c/c 31.00 1.98 0.62 37.81 kg
stirrups 10mm @ 150 c/c 21.00 1.98 0.62 25.61 kg

B-5 Along F-F


at lvl 0.0 m 26.422
main bar 20mm 4.00 28.78 2.47 284.37 kg
main bar 16mm 4.00 28.78 2.47 283.91 kg
stirrups 10mm @ 100 c/c 133.00 1.98 0.62 162.22 kg
stirrups 10mm @ 150 c/c 89.00 1.98 0.62 108.55 kg

at lvl 3.6 m 26.422


main bar 20mm 8.00 28.78 2.47 567.81 kg
extra bar 20mm 4.00 30.26 2.47 298.50 kg
stirrups 10mm @ 100 c/c 133.00 1.98 0.62 162.22 kg
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
stirrups 10mm @ 150 c/c 89.00 1.98 0.62 108.55 kg

at lvl 7.2 m 23
main bar 20mm 8.00 25.36 2.47 500.30 kg
extra bar 20mm 4.00 26.84 2.47 264.75 kg
stirrups 10mm @ 100 c/c 116.00 1.98 0.62 141.48 kg
stirrups 10mm @ 150 c/c 77.00 1.98 0.62 93.92 kg

at lvl 10.8 m 23
main bar 20mm 4.00 25.36 2.47 250.15 kg
main bar 16mm 4.00 25.36 2.47 250.15 kg
stirrups 10mm @ 100 c/c 116.00 1.98 0.62 141.48 kg
stirrups 10mm @ 150 c/c 77.00 1.98 0.62 93.92 kg

B-6 Along E-E


at lvl 0.0 m 26.422
main bar 20mm 4.00 28.78 2.47 284.37 kg
main bar 16mm 4.00 28.78 2.47 283.91 kg
stirrups 10mm @ 100 c/c 133.00 1.98 0.62 162.22 kg
stirrups 10mm @ 150 c/c 89.00 1.98 0.62 108.55 kg

at lvl 3.6 m 26.422


main bar 20mm 8.00 28.78 2.47 567.81 kg
extra bar 20mm 4.00 30.26 2.47 298.50 kg
stirrups 10mm @ 100 c/c 133.00 1.98 0.62 162.22 kg
stirrups 10mm @ 150 c/c 89.00 1.98 0.62 108.55 kg

at lvl 7.2 m 23
main bar 20mm 8.00 25.36 2.47 500.30 kg
extra bar 20mm 4.00 26.84 2.47 264.75 kg
stirrups 10mm @ 100 c/c 116.00 1.98 0.62 141.48 kg
stirrups 10mm @ 150 c/c 77.00 1.98 0.62 93.92 kg

at lvl 10.8 m 23
main bar 20mm 4.00 25.36 2.47 250.15 kg
main bar 16mm 4.00 25.36 2.47 250.15 kg
stirrups 10mm @ 100 c/c 116.00 1.98 0.62 141.48 kg
stirrups 10mm @ 150 c/c 77.00 1.98 0.62 93.92 kg

B-7 Along G-G


at lvl 0.0 m 22.997
main bar 20mm 4.00 25.36 2.47 250.53 kg
main bar 16mm 4.00 25.36 2.47 250.12 kg
stirrups 10mm @ 100 c/c 115.00 1.98 0.62 140.26 kg
stirrups 10mm @ 150 c/c 77.00 1.98 0.62 93.92 kg

at lvl 3.6 m 24.008


main bar 20mm 8.00 26.37 2.47 520.19 kg
extra bar 20mm 4.00 19.14 2.47 188.80 kg
stirrups 10mm @ 100 c/c 121.00 1.98 0.62 147.58 kg
stirrups 10mm @ 150 c/c 81.00 1.98 0.62 98.79 kg
sub total 25377.23 kg
S.N Description of work No. Length Breadth Height Quantity Unit Remarks

C Column
C-1 upto Plinth
C1 12.00 2.10
main bar 16mm 20.00 3.06 1.58 1158.88 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 357.89 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 223.68 kg

C2 4.00 2.10
main bar 16mm 20.00 3.60 1.58 454.46 kg
main bar 20mm 54.00 3.30 2.46 1753.49 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 119.30 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 74.56 kg

C3 1.00 2.10
main bar 16mm 16.00 3.60 1.58 90.89 kg
main bar 20mm 4.00 3.30 2.46 32.47 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 29.82 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 18.64 kg

C4 18.00 2.10
main bar 16mm 16.00 3.60 1.58 1636.07 kg
main bar 20mm 4.00 3.30 2.46 584.50 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 536.83 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 335.52 kg

C5 4 2.100
main bar 16mm 16.00 3.60 1.58 363.57 kg
main bar 20mm 8.00 3.30 2.46 259.78 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 119.30 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 74.56 kg

C-2 upto lower ground floor


C1 12.00 3.60
main bar 16mm 20.00 4.56 1.58 1726.96 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 357.89 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 223.68 kg

C2 4.00 3.60
main bar 16mm 20.00 5.10 1.58 643.82 kg
main bar 20mm 54.00 4.80 2.46 2550.53 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 119.30 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 74.56 kg

C3 1.00 3.60
main bar 16mm 16.00 5.10 1.58 128.76 kg
main bar 20mm 4.00 4.80 2.46 47.23 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 29.82 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 18.64 kg

C4 18.00 3.60
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
main bar 16mm 16.00 5.10 1.58 2317.77 kg
main bar 20mm 4.00 4.80 2.46 850.18 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 536.83 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 335.52 kg

C5 4 3.600
main bar 16mm 16.00 5.10 1.58 515.06 kg
main bar 20mm 8.00 4.80 2.46 377.86 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 119.30 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 74.56 kg

C-3 first floor


C4 18.00 3.60
main bar 16mm 16.00 5.10 1.58 2317.77 kg
main bar 20mm 4.00 4.80 2.46 850.18 kg
stirrups 8mm @ 100c/c 8.00 9.32 0.40 536.83 kg
stirrups 8mm @ 150c/c 5.00 9.32 0.40 335.52 kg
sub total 23312.770 kg

D Slab
lower ground floor
x-axis
bottom 10mm @ 150 c/c 186.00 15.10 0.62 1730.10 kg
top 10mm @ 150 c/c 186.00 6.20 0.62 710.37 kg

y axis
bottom 10mm @ 150 c/c 186.00 17.38 0.62 1991.33 kg
top 10mm @ 150 c/c 186.00 31.03 0.62 3554.83 kg

ground floor
x-axis
bottom 10mm @ 150 c/c 152.00 15.10 0.62 1413.84 kg
top 10mm @ 150 c/c 152.00 6.20 0.62 580.52 kg

y axis
bottom 10mm @ 150 c/c 152.00 17.38 0.62 1627.32 kg
top 10mm @ 150 c/c 152.00 31.03 0.62 2905.03 kg

first floor
x-axis
bottom 10mm @ 150 c/c 123.00 15.10 0.62 1144.10 kg
top 10mm @ 150 c/c 123.00 6.20 0.62 469.76 kg

y axis
bottom 10mm @ 150 c/c 123.00 17.38 0.62 1316.85 kg
top 10mm @ 150 c/c 123.00 31.03 0.62 2350.78 kg
sub total 19794.831 kg

E Staircase
F Staircase 3.00
main bottom bar 16mm @ 125 c/c 34.00 9.65 1.58 1553.23 kg
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
main top bar 16mm @ 300 c/c 14.00 13.42 1.58 889.49 kg
distribution bar 12mm @ 125 c/c 132.00 1.80 0.88 627.26 kg

nosing
main bar 10mm @ 150 c/c 364.00 2.67 0.62 1798.72 kg
distribution bar 10mm 26.00 2.00 0.62 96.10 kg
Landing
12mm Top+Bottom bar @ 125 c/c 68.00 4.26 0.88 764.58 kg
sub total 5729.376 kg
total reinforcement 79880.923 kg

Formwork, shuttering, centering


with approved materials for all
works necessary propping,
scaffolding, staging, supporting
inclusive of wedging and cutting
holes for utilization till the support
7 if fully unyielding nett.
Big block
Column Foundation
Footing Base F1 38 1.800 4.000 0.200 54.720
Column
up to Lower 38 0.500 4.000 1.070 81.320
upto +3.6 38 0.500 4.000 3.900 296.400
upto +7.2 24 0.500 4.000 3.900 187.200
upto +10.8 18 0.500 4.000 4.500 162.000
Lower Tie beam
Along A -D 4 21.050 2.000 0.300 50.520
Along E-G 3 24.000 2.000 0.300 43.200
Along 1 1 9.500 2.000 0.300 5.700
Along 2-6 5 26.630 2.000 0.300 79.890
Tie Beam +0 level
Along A -D 4 21.050 2.000 0.400 67.360
Along E-G 3 24.000 2.000 0.400 57.600
Along 1 1 9.500 2.000 0.400 7.600
Along 2-6 5 26.630 2.000 0.400 106.520
Beam +3.6 level
Along A -D 4 21.050 0.300 0.400 92.620
Along E-G 3 24.000 0.300 0.400 79.200
Along 1 1 9.500 0.300 0.400 10.450
Along 2-6 5 26.630 0.300 0.400 146.465
Beam +7.2 level
Along A 1 6.055 0.300 0.400 6.661
Along B-C 2 15.100 0.300 0.400 33.220
Along D- F 3 21.050 0.300 0.400 69.465
Beam +10.8 level
Along B-C 2 9.540 0.300 0.400 20.988
Along D- F 3 15.550 0.300 0.400 51.315
Small block
Column Foundation
Footing Base F1 9 1.800 4.000 0.200 12.960
Column
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
up to Lower 9 0.500 4.000 1.070 19.260
upto +3.6 9 0.500 4.000 4.500 81.000
Lower Tie beam
Along A -C 3 8.550 2.000 0.300 15.390
Along 1-3 3 9.500 2.000 0.300 17.100
Beam +0 level
Along A -C 3 8.550 2.000 0.400 20.520
Along 1-3 3 9.500 2.000 0.400 22.800
Beam +3.6 level
Along A -C 3 8.550 0.300 0.400 28.215
Along 1-3 3 9.500 0.300 0.400 31.350
Slab
Big block
+3.6 level 1 777.900 777.900
+7.2 level 1 514.710 514.710
+10.8 level 1 336.780 336.780
Small block
+3.6 level 1 170.600 170.600
Pool
Raft 1 20.000 1.000 0.300 6.000
Shearwall 4 20.000 1.000 1.200 96.000
4054.048 Sqm
8 Backfilling
Earthwork Excavation 1 661.17 661.17
Brick Soling -1 86.39 -86.39
75mm P.C.C (1:2:4) -1 117.80 -117.80
Dwarf wall -1 86.87 -86.87
R.C.C (1:1.5:3) -1 193.10 -193.10
Earthwork to be back fill Total 177.00 Cum
Earthwork to be fill in rooms 1 1237 0.3 371.10
Total Earthwork Needed Total 548.10
Earthwork left after excavated 80% 528.94

10 Superstructure wall (1:4)


Medical block ( big)
LGF
External wall
Along A 1 21.050 0.230 3.600 17.429
Along G 1 24.000 0.230 3.600 19.872
Along 1 1 9.500 0.230 3.600 7.866
Along 2 1 17.080 0.230 3.600 14.142
Along 6 1 27.130 0.230 3.600 22.464
Partition wall 0.000
Alcov clean 1 5.351 0.110 2.400 1.413
pump room 1 13.362 0.110 2.400 3.528
Pool chemical room and equipment storage
1 room
15.495 0.110 2.400 4.091
Toilet/shower / locker (f & M) 1 42.310 0.110 2.400 11.170
Registration / Admin 1 22.335 0.110 2.400 5.896
Mental halth/staff/disabl toilet 1 51.700 0.110 2.400 13.649
between A-C and 1-6 1 89.810 0.110 2.400 23.710
GF 0.000
External wall 0.000
Along A 1 6.055 0.230 3.600 5.014
Along F 1 24.000 0.230 3.600 19.872
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
Along 2 1 20.610 0.230 3.600 17.065
Along 6 1 10.120 0.230 3.600 8.379
Along D 1 5.550 0.230 3.600 4.595
Along 5 1 13.500 0.230 3.600 11.178
along 4 1 3.025 0.230 3.600 2.505
Along B' 1 12.770 0.230 3.600 10.574
Partition wall 0.000
X - Ray Room 1 47.475 0.230 3.600 39.309
ENT/EYE/AUDIOGRAM 1 46.859 0.110 2.400 12.371
Admin/Registration 1 17.525 0.110 2.400 4.627
between B-C and 2-6 1 65.950 0.110 2.400 17.411
FF 0.000
External wall 0.000
Along F 1 16.700 0.230 3.600 13.828
Along 2 1 20.610 0.230 3.600 17.065
Along 5 1 10.120 0.230 3.600 8.379
Along D 1 5.550 0.230 3.600 4.595
along 4 1 9.050 0.230 3.600 7.493
Along B' 1 12.000 0.230 3.600 9.936
Partition wall 0.000
between D-F 1 27.878 0.110 2.400 7.360
store 1 6.415 0.110 2.400 1.694
Along 3 1 9.050 0.110 2.400 2.389
Toilet partition (F &M) 1 36.600 0.110 2.400 9.662
physiotheraoy block ( small) 0.000
LGF 0.000
External wall 0.000
along 1 & 3 1 12.120 0.230 3.600 10.035
Along C 1 8.950 0.230 3.600 7.411
Along A' 1 10.450 0.230 3.600 8.653
Partition wall 0.000
between A-B 1 30.379 0.230 2.400 16.769
Opening deductions
Medical block ( big)
DW1 2 1.4 0.23 2.1 -1.352
DW2 1 2.2 0.23 3.05 -1.543
DW3 1 6.055 0.23 2.05 -2.855
W1 16 1.5 0.23 1.22 -6.734
W2 2 3.6 0.23 3.2 -5.299
W3 7 1.8 0.23 1.45 -4.202
W4 12 1.2 0.23 2.1 -6.955
D1 2 1.2 0.23 2.15 -1.187
D2 4 1.5 0.23 2.1 -2.898
D3 1 1.6 0.23 2.1 -0.773
D4 1 2 0.23 2.1 -0.966
D5 4 1.5 0.23 2.1 -2.898
D6 3 1 0.23 2.1 -1.449
D7 31 1 0.23 2.1 -14.973
D8 14 0.75 0.23 2.1 -5.072
D9 4 1.2 0.23 2.1 -2.318
D10 1 0.9 0.23 2.1 -0.435
D11 2 1 0.23 2.1 -0.966
V1 1 4.463 0.23 0.97 -0.996
physiotheraoy block ( small)
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
DW1 4 4.55 0.23 4.55 -19.046
D1 2 1.2 0.23 2.15 -1.187
D10 1 0.9 0.23 2.1 -0.435
Total 338.859 Cum

12 Almunium Door and windows


DW1 2 1.4 2.1 5.880
DW2 1 2.2 3.05 6.710
DW3 1 6.055 2.05 12.413
W1 16 1.5 1.22 29.280
W2 2 3.6 3.2 23.040
W3 7 1.8 1.45 18.270
W4 12 1.2 2.1 30.240
D1 2 1.2 2.15 5.160
D2 4 1.5 2.1 12.600
D3 1 1.6 2.1 3.360
D4 1 2 2.1 4.200
D5 4 1.5 2.1 12.600
D6 3 1 2.1 6.300
D7 31 1 2.1 65.100
D8 14 0.75 2.1 22.050
D9 4 1.2 2.1 10.080
D10 1 0.9 2.1 1.890
D11 2 1 2.1 4.200
V1 1 4.463 0.97 4.329
physiotheraoy block ( small)
DW1 4 4.55 4.55 82.810
D1 2 1.2 2.15 5.160
D10 1 0.9 2.1 1.890
Total 367.562 Sqm

14 False Ceiling
Medical block (Big block)
+3.6 level 1 777.900 777.900
+7.2 level 1 514.710 514.710
+10.8 level 1 336.780 336.780
Small block
+3.6 level 1 170.600 170.600
507.380 1799.990 Sqm
15 Plaster
In structure part
Big block
Column Foundation
Footing Base F1 38 1.800 4.000 0.200 54.720
Column
upto +3.6 38 0.500 4.000 3.900 296.400
upto +7.2 24 0.500 4.000 3.900 187.200
upto +10.8 18 0.500 4.000 4.500 162.000
Beam +3.6 level
Along A -D 4 21.050 0.300 0.400 92.620
Along E-G 3 24.000 0.300 0.400 79.200
Along 1 1 9.500 0.300 0.400 10.450
Along 2-6 5 26.630 0.300 0.400 146.465
Beam +7.2 level
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
Along A 1 6.055 0.300 0.400 6.661
Along B-C 2 15.100 0.300 0.400 33.220
Along D- F 3 21.050 0.300 0.400 69.465
Beam +10.8 level
Along B-C 2 9.540 0.300 0.400 20.988
Along D- F 3 15.550 0.300 0.400 51.315
Small block
Column Foundation
Footing Base F1 9 1.800 4.000 0.200 12.960
Column
upto +3.6 9 0.500 4.000 4.500 81.000
Beam +3.6 level
Along A -C 3 8.550 0.300 0.400 28.215
Along 1-3 3 9.500 0.300 0.400 31.350
Slab
Big block
+3.6 level 1 777.900 777.900
+7.2 level 1 514.710 514.710
+10.8 level 1 336.780 336.780
Small block
+3.6 level 1 170.600 170.600
In Brick Super Structure
Medical block ( big)
LGF
External wall
Along A 1 21.050 2.000 3.600 151.560
Along G 1 24.000 2.000 3.600 172.800
Along 1 1 9.500 2.000 3.600 68.400
Along 2 1 17.080 2.000 3.600 122.976
Along 6 1 27.130 2.000 3.600 195.336
Partition wall 0.000
Alcov clean 1 5.351 2.000 2.400 25.685
pump room 1 13.362 2.000 2.400 64.138
Pool chemical room and equipment storage
1 room
15.495 2.000 2.400 74.376
Toilet/shower / locker (f & M) 1 42.310 2.000 2.400 203.088
Registration / Admin 1 22.335 2.000 2.400 107.208
Mental halth/staff/disabl toilet 1 51.700 2.000 2.400 248.160
between A-C and 1-6 1 89.810 2.000 2.400 431.088
GF 0.000
External wall 0.000
Along A 1 6.055 2.000 3.600 43.596
Along F 1 24.000 2.000 3.600 172.800
Along 2 1 20.610 2.000 3.600 148.392
Along 6 1 10.120 2.000 3.600 72.864
Along D 1 5.550 2.000 3.600 39.960
Along 5 1 13.500 2.000 3.600 97.200
along 4 1 3.025 2.000 3.600 21.780
Along B' 1 12.770 2.000 3.600 91.944
Partition wall 0.000
X - Ray Room 1 47.475 2.000 3.600 341.820
ENT/EYE/AUDIOGRAM 1 46.859 2.000 2.400 224.923
Admin/Registration 1 17.525 2.000 2.400 84.120
between B-C and 2-6 1 65.950 2.000 2.400 316.560
FF 0.000
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
External wall 0.000
Along F 1 16.700 2.000 3.600 120.240
Along 2 1 20.610 2.000 3.600 148.392
Along 5 1 10.120 2.000 3.600 72.864
Along D 1 5.550 2.000 3.600 39.960
along 4 1 9.050 2.000 3.600 65.160
Along B' 1 12.000 2.000 3.600 86.400
Partition wall 0.000
between D-F 1 27.878 2.000 2.400 133.814
store 1 6.415 2.000 2.400 30.792
Along 3 1 9.050 2.000 2.400 43.440
Toilet partition (F &M) 1 36.600 2.000 2.400 175.680
physiotheraoy block ( small) 0.000
LGF 0.000
External wall 0.000
along 1 & 3 1 12.120 2.000 3.600 87.264
Along C 1 8.950 2.000 3.600 64.440
Along A' 1 10.450 2.000 3.600 75.240
Partition wall 0.000
between A-B 1 30.379 2.000 2.400 145.819
Opening deductions
Medical block ( big)
DW1 2 1.4 2 2.1 -11.760
DW2 1 2.2 2 3.05 -13.420
DW3 1 6.055 2 2.05 -24.826
W1 16 1.5 2 1.22 -58.560
W2 2 3.6 2 3.2 -46.080
W3 7 1.8 2 1.45 -36.540
W4 12 1.2 2 2.1 -60.480
D1 2 1.2 2 2.15 -10.320
D2 4 1.5 2 2.1 -25.200
D3 1 1.6 2 2.1 -6.720
D4 1 2 2 2.1 -8.400
D5 4 1.5 2 2.1 -25.200
D6 3 1 2 2.1 -12.600
D7 31 1 2 2.1 -130.200
D8 14 0.75 2 2.1 -44.100
D9 4 1.2 2 2.1 -20.160
D10 1 0.9 2 2.1 -3.780
D11 2 1 2 2.1 -8.400
V1 1 4.463 2 0.97 -8.658
physiotheraoy block ( small)
DW1 4 4.55 2 4.55 -165.620
D1 2 1.2 2 2.15 -10.320
D10 1 0.9 2 2.1 -3.780
Total 7239.374 Sqm
16 Wall puty
As per plaster quantity 7239.374
7239.374 Sqm
17 Distemper Painting
In structure part
Big block
Column Foundation
Footing Base F1 38 1.800 4.000 0.200 54.720
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
Column
upto +3.6 38 0.500 4.000 3.900 296.400
upto +7.2 24 0.500 4.000 3.900 187.200
upto +10.8 18 0.500 4.000 4.500 162.000
Beam +3.6 level
Along A -D 4 21.050 0.300 0.400 92.620
Along E-G 3 24.000 0.300 0.400 79.200
Along 1 1 9.500 0.300 0.400 10.450
Along 2-6 5 26.630 0.300 0.400 146.465
Beam +7.2 level
Along A 1 6.055 0.300 0.400 6.661
Along B-C 2 15.100 0.300 0.400 33.220
Along D- F 3 21.050 0.300 0.400 69.465
Beam +10.8 level
Along B-C 2 9.540 0.300 0.400 20.988
Along D- F 3 15.550 0.300 0.400 51.315
Small block
Column Foundation
Footing Base F1 9 1.800 4.000 0.200 12.960
Column
upto +3.6 9 0.500 4.000 4.500 81.000
Beam +3.6 level
Along A -C 3 8.550 0.300 0.400 28.215
Along 1-3 3 9.500 0.300 0.400 31.350
Slab
Big block
+3.6 level 1 777.900 777.900
+7.2 level 1 514.710 514.710
+10.8 level 1 336.780 336.780
Small block
+3.6 level 1 170.600 170.600
In Brick Super Structure
Medical block ( big)
LGF
External wall
Along A 1 21.050 1.000 3.600 75.780
Along G 1 24.000 1.000 3.600 86.400
Along 1 1 9.500 1.000 3.600 34.200
Along 2 1 17.080 1.000 3.600 61.488
Along 6 1 27.130 1.000 3.600 97.668
Partition wall 0.000
Alcov clean 1 5.351 2.000 2.400 25.685
pump room 1 13.362 2.000 2.400 64.138
Pool chemical room and equipment storage
1 room
15.495 2.000 2.400 74.376
Toilet/shower / locker (f & M) 1 42.310 2.000 2.400 203.088
Registration / Admin 1 22.335 2.000 2.400 107.208
Mental halth/staff/disabl toilet 1 51.700 2.000 2.400 248.160
between A-C and 1-6 1 89.810 2.000 2.400 431.088
GF 0.000
External wall 0.000
Along A 1 6.055 1.000 3.600 21.798
Along F 1 24.000 1.000 3.600 86.400
Along 2 1 20.610 1.000 3.600 74.196
Along 6 1 10.120 1.000 3.600 36.432
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
Along D 1 5.550 1.000 3.600 19.980
Along 5 1 13.500 1.000 3.600 48.600
along 4 1 3.025 1.000 3.600 10.890
Along B' 1 12.770 1.000 3.600 45.972
Partition wall 0.000
X - Ray Room 1 47.475 2.000 3.600 341.820
ENT/EYE/AUDIOGRAM 1 46.859 2.000 2.400 224.923
Admin/Registration 1 17.525 2.000 2.400 84.120
between B-C and 2-6 1 65.950 2.000 2.400 316.560
FF 0.000
External wall 0.000
Along F 1 16.700 1.000 3.600 60.120
Along 2 1 20.610 1.000 3.600 74.196
Along 5 1 10.120 1.000 3.600 36.432
Along D 1 5.550 1.000 3.600 19.980
along 4 1 9.050 1.000 3.600 32.580
Along B' 1 12.000 1.000 3.600 43.200
Partition wall 0.000
between D-F 1 27.878 2.000 2.400 133.814
store 1 6.415 2.000 2.400 30.792
Along 3 1 9.050 2.000 2.400 43.440
Toilet partition (F &M) 1 36.600 2.000 2.400 175.680
physiotheraoy block ( small) 0.000
LGF 0.000
External wall 0.000
along 1 & 3 1 12.120 1.000 3.600 43.632
Along C 1 8.950 1.000 3.600 32.220
Along A' 1 10.450 1.000 3.600 37.620
Partition wall 0.000
between A-B 1 30.379 2.000 2.400 145.819
Opening deductions
Medical block ( big)
DW1 2 1.4 1 2.1 -5.880
DW2 1 2.2 1 3.05 -6.710
DW3 1 6.055 1 2.05 -12.413
W1 16 1.5 1 1.22 -29.280
W2 2 3.6 1 3.2 -23.040
W3 7 1.8 1 1.45 -18.270
W4 12 1.2 1 2.1 -30.240
D1 2 1.2 2 2.15 -10.320
D2 4 1.5 2 2.1 -25.200
D3 1 1.6 2 2.1 -6.720
D4 1 2 2 2.1 -8.400
D5 4 1.5 2 2.1 -25.200
D6 3 1 2 2.1 -12.600
D7 31 1 2 2.1 -130.200
D8 14 0.75 2 2.1 -44.100
D9 4 1.2 2 2.1 -20.160
D10 1 0.9 2 2.1 -3.780
D11 2 1 2 2.1 -8.400
V1 1 4.463 1 0.97 -4.329
physiotheraoy block ( small)
DW1 4 4.55 1 4.55 -82.810
D1 2 1.2 2 2.15 -10.320
S.N Description of work No. Length Breadth Height Quantity Unit Remarks
D10 1 0.9 2 2.1 -3.780
Total 6372.562 Sqm
18 Weather Coat
Total 866.812 Sqm

22 Railing
Ramp
LGF
1st 2 11.758 23.516
2nd 2 9.890 19.780
3rd 2 14.680 29.360
GF
Ramp
1st 2 11.000 22.000
staircase 1 2 20.000 40.000
134.656 Rm