Professional Documents
Culture Documents
Pmp-07-Cost Management
Pmp-07-Cost Management
Jayaraj Peter
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 1
Agenda
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 2
Project Cost Management
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 3
Project Cost Management
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 4
Processes
INITIATE CLOSE
Knowledge Process
Area Initiating Planning Executing M&C Closing
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 5
Processes
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 6
7.1
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 7
Plan Cost Management
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 8
Plan Cost Management
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 9
Plan Cost Management
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 10
Plan Cost Management
INPUTS
1. Project Charter
✓ Scope management plan - provides processes and controls that will impact cost estimation
and management.
✓ Risk management plan - approach for identifying, analyzing, and monitoring risks.
3. EEF
4. OPA
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 11
Plan Cost Management
1. Expert Judgement
2. Data Analysis
3. Meetings
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 12
Plan Cost Management
Outputs
• Units of measure - defined for each of the resources (staff hours, staff days, or weeks for
time measures; meters, liters, tons, kilometers, or cubic yards for quantity measures).
• Level of precision - degree to which cost estimates will be rounded up or down
• Level of accuracy - Acceptable range used in determining realistic cost estimates
• Organizational procedures links - unique code or account number(s) that links directly to
the performing organization’s accounting system
• Control thresholds - indicate an agreed-upon amount of variation
• Rules of performance measurement - Earned value management (EVM) rules
• Reporting formats - formats and frequency for the various cost reports
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 13
7.2
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 14
Estimate Costs
✓ In addition to estimating the cost of the resources, this process also perform costing
alternatives as well as cost trade-offs and risk analysis.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 15
Estimate Costs
✓ The accuracy of a project estimate will increase as the project progresses through the
project life cycle.
• For example, a project in the initiation phase may have a rough order of magnitude
(ROM) estimate in the range of −25% to +75%.
• Later in the project, as more information is known, definitive estimates could narrow
the range of accuracy to −5% to +10%.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 16
Estimate Costs
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 17
Estimate Costs
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 18
Estimate Costs
INPUTS
✓ Cost management plan – describes estimating methods that can be used and the level of
precision and accuracy required for the cost estimate.
✓ Scope baseline - includes the project scope statement, WBS, and WBS dictionary.
✓ Quality management plan – activities and resources necessary for the project
management team to achieve the quality objectives set for the project.
2. Project Documents
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 19
Estimate Costs
INPUTS
3. EEF
✓ Market conditions – Regional and/or global supply and demand conditions greatly
influence resource costs.
✓ Published commercial information - Resource cost rate information that track skills
and human resource costs, and provide standard costs for material and equipment.
4. OPA
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 20
Estimate Costs
1. Expert Judgment
2. Analogous Estimating
✓ Example: We spent USD 500 for the similar activity in the previous project , so in this project
also it will cost the same.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 21
Estimate Costs
3. Parametric Estimating
4. Bottom-Up Estimating
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 22
Estimate Costs
5. Three-Point Estimating
• Most likely (cM) - The cost of the activity, based on realistic effort assessment for the
required work and any predicted expenses.
• Optimistic (cO) - The cost based on analysis of the best-case scenario for the activity.
• Pessimistic (cP) - The cost based on analysis of the worst-case scenario for the activity.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 23
Estimate Costs
6. Data Analysis
✓ Reserve analysis - Cost estimates may include contingency reserves to account for
cost uncertainty.
• Contingency reserves are the budget within the cost baseline that is allocated for
identified risks, which are accepted and for which contingent or mitigating
responses are developed.
• Contingency reserves are often viewed as the part of the budget intended to
address the “known-unknowns” that can affect a project.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 24
Estimate Costs
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 25
Estimate Costs
• Prevention and appraisal costs (cost of conformance) include costs for quality
planning, quality control (QC), and quality assurance to ensure compliance to
requirements (i.e., training, QC systems, etc.).
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 26
Estimate Costs
✓ Include spreadsheets, simulation software, and statistical analysis tools to assist with
cost estimating.
8. Decision Making
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 27
Estimate Costs
OUTPUTS
1. Cost Estimates
2. Basis of Estimates
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 28
Estimate Costs
OUTPUTS
✓ Lessons learned register - updated with techniques that were efficient and effective
in developing cost estimates.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 29
7.3
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 30
Determine Budget
The key benefit of this process is that it determines the cost baseline
against which project performance can be monitored and controlled.
✓ A project budget includes all the funds authorized to execute the project.
✓ The cost baseline is the approved version of the time-phased project budget that
includes contingency reserves, but excludes management reserves.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 31
Determine Budget
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 32
Determine Budget
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 33
Determine Budget
INPUTS
✓ Cost management plan – describes how the project costs will be structured into the
project budget.
✓ Resource management plan – provides information on costs that are necessary to
estimate the overall project budget.
✓ Scope baseline.
2. Project Documents
✓ Cost estimates
✓ Basis of estimates
✓ Project schedule
✓ Risk register
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 34
Determine Budget
INPUTS
3. Business Documents
✓ Business case – identifies the critical success factors for the project, including
financial success factors.
✓ Benefits management plan – target benefits, such as net present value calculations,
timeframe for realizing benefits, and the metrics associated with the benefits.
4. Agreements
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 35
Determine Budget
1. Expert Judgement
2. Cost Aggregation
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 36
Determine Budget
3. Data Analysis
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 37
Determine Budget
6. Financing
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 38
Determine Budget
OUTPUTS
1. Cost Baseline
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 39
Determine Budget
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 40
Determine Budget
OUTPUTS
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 41
7.4
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 42
Control Costs
The key benefit of this process is that the cost baseline is maintained
throughout the project.
✓ Any increase to the authorized budget can only be approved through the Perform
Integrated Change Control process.
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 43
Control Costs
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 44
Control Costs
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 45
Control Costs
INPUTS
✓ Cost management plan – how the project costs will be managed and controlled.
✓ Cost baseline – compared with actual results to determine if a change, corrective
action, or preventive action is necessary.
2. Project Documents
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 46
Control Costs
INPUTS
✓ Data on project status such as which costs have been authorized, incurred,
invoiced, and paid.
5. OPA
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 47
Control Costs
1. Expert Judgement
2. Data Analysis
✓ Reserve Analysis
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 49
Control Costs
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 50
Control Costs
OUTPUTS
✓ The calculated CV, SV, CPI, SPI, TCPI, and VAC values for WBS components, in
particular the work packages and control accounts, are documented and
communicated to stakeholders.
2. Cost Forecasts
3. Change Requests
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 51
Control Costs
OUTPUTS
4. PMP updates
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 52
RECAP
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 53
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 54
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 55
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 56
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 57
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 58
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 59
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 60
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 61
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 62
Q&A
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 63
Jayaraj Peter