Download as pdf or txt
Download as pdf or txt
You are on page 1of 64

Project Management Professional (PMP)®

Jayaraj Peter

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 1
Agenda

✓ Project Cost Management

EARNED VALUE METHOD

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 2
Project Cost Management

Project Cost Management includes the processes involved in planning,


estimating, budgeting, financing, funding, managing, and controlling
costs so that the project can be completed within the approved budget.

✓ It is primarily concerned with the cost of the


resources needed to complete project activities.

✓ Project Cost Management, trends include the


expansion of earned value management (EVM).

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 3
Project Cost Management

Fixed Cost - A cost that does not change with an increase


or decrease in the amount of goods or services produced.

Variable Cost - Costs that vary depending on a company's


production volume; they rise as production increases and
fall as production decreases.

Direct Cost - A price that can be completely attributed to


the production of specific goods or services.

Indirect cost - Costs that are not directly accountable to


a cost object (such as a particular project, facility, function or
product).

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 4
Processes

MONITOR & CONTROL

INITIATE CLOSE

Knowledge Process
Area Initiating Planning Executing M&C Closing

7.1 Plan Cost Management


7. Project Cost
7.2 Estimate Costs 7.4 Control Costs
Management
7.3 Determine Budget

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 5
Processes

Plan Cost Control Costs


Estimate Costs Determine Budget
Management

Defining how the Developing an Aggregating the Monitoring the status


project costs will be approximation of estimated costs of of the project to update
estimated, budgeted, the monetary individual activities the project costs and
managed, monitored, resources needed to or work packages to manage changes to the
and controlled. complete project establish an cost baseline.
work. authorized cost
baseline.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 6
7.1

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 7
Plan Cost Management

The process of defining how the project costs will be estimated,


budgeted, managed, monitored, and controlled.

The key benefits of this process is that it provides guidance and


direction on how the project costs will be managed throughout the
project.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 8
Plan Cost Management

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 9
Plan Cost Management

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 10
Plan Cost Management

INPUTS

1. Project Charter

2. Project Management Plan

✓ Scope management plan - provides processes and controls that will impact cost estimation
and management.
✓ Risk management plan - approach for identifying, analyzing, and monitoring risks.

3. EEF

✓ Currency exchange rates for project costs


✓ Published commercial information such as resource cost rate information

4. OPA

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 11
Plan Cost Management

TOOLS AND TECHNIQUES

1. Expert Judgement

✓ Cost estimating and budgeting


✓ Earned value management

2. Data Analysis

✓ Alternatives analysis - consideration of ways to acquire project resources such as


making, purchasing, renting, or leasing.

3. Meetings

✓ Planning meetings to develop the cost management plan.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 12
Plan Cost Management

Outputs

1. Cost Management Plan

Describes how the project costs will be planned, structured, and


controlled.

• Units of measure - defined for each of the resources (staff hours, staff days, or weeks for
time measures; meters, liters, tons, kilometers, or cubic yards for quantity measures).
• Level of precision - degree to which cost estimates will be rounded up or down
• Level of accuracy - Acceptable range used in determining realistic cost estimates
• Organizational procedures links - unique code or account number(s) that links directly to
the performing organization’s accounting system
• Control thresholds - indicate an agreed-upon amount of variation
• Rules of performance measurement - Earned value management (EVM) rules
• Reporting formats - formats and frequency for the various cost reports

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 13
7.2

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 14
Estimate Costs

The process of developing an approximation of the cost of resources


needed to complete project work.

The key benefit of this process is that it determines the monetary


resources required for the project.

✓ In addition to estimating the cost of the resources, this process also perform costing
alternatives as well as cost trade-offs and risk analysis.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 15
Estimate Costs

✓ It is a prediction that is based on the information known at a given point in time.

✓ The accuracy of a project estimate will increase as the project progresses through the
project life cycle.

• For example, a project in the initiation phase may have a rough order of magnitude
(ROM) estimate in the range of −25% to +75%.

• Later in the project, as more information is known, definitive estimates could narrow
the range of accuracy to −5% to +10%.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 16
Estimate Costs

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 17
Estimate Costs

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 18
Estimate Costs

INPUTS

1. Project Management Plan

✓ Cost management plan – describes estimating methods that can be used and the level of
precision and accuracy required for the cost estimate.

✓ Scope baseline - includes the project scope statement, WBS, and WBS dictionary.

✓ Quality management plan – activities and resources necessary for the project
management team to achieve the quality objectives set for the project.

2. Project Documents

✓ Project schedule, Resource requirements


✓ Risk register, Lessons learned register.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 19
Estimate Costs

INPUTS

3. EEF

✓ Market conditions – Regional and/or global supply and demand conditions greatly
influence resource costs.

✓ Published commercial information - Resource cost rate information that track skills
and human resource costs, and provide standard costs for material and equipment.

✓ Exchange rates and inflation – fluctuations of currencies and inflation.

4. OPA

✓ Cost estimating policies, templates


✓ Historical information and lessons learned repository

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 20
Estimate Costs

TOOLS AND TECHNIQUES

1. Expert Judgment

2. Analogous Estimating

✓ A technique for estimating the duration or cost of an activity or a project using


historical data from a similar activity or project.

✓ Example: We spent USD 500 for the similar activity in the previous project , so in this project
also it will cost the same.

✓ It is generally less expensive and less time consuming comparing to other


techniques. It is also generally less accurate comparing to others.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 21
Estimate Costs

TOOLS AND TECHNIQUES

3. Parametric Estimating

✓ Uses a statistical relationship between


relevant historical data and other variables.

4. Bottom-Up Estimating

✓ A method of estimating project duration or


cost by aggregating the estimates of the
lower-level components of the work
breakdown structure (WBS).

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 22
Estimate Costs

TOOLS AND TECHNIQUES

5. Three-Point Estimating

✓ A technique used to estimate cost or duration by applying an average of optimistic,


pessimistic, and most likely estimates when there is uncertainty with the individual
activity estimates.

• Most likely (cM) - The cost of the activity, based on realistic effort assessment for the
required work and any predicted expenses.
• Optimistic (cO) - The cost based on analysis of the best-case scenario for the activity.
• Pessimistic (cP) - The cost based on analysis of the worst-case scenario for the activity.

The expected cost, cE, can be calculated using formula,


Triangular distribution. cE = (cO + cM + cP) / 3
Beta distribution. cE = (cO + 4cM + cP) / 6

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 23
Estimate Costs

TOOLS AND TECHNIQUES

6. Data Analysis

✓ Alternatives analysis - technique used to evaluate identified options in order to


select which options or approaches to perform the project work.

✓ Reserve analysis - Cost estimates may include contingency reserves to account for
cost uncertainty.

• Contingency reserves are the budget within the cost baseline that is allocated for
identified risks, which are accepted and for which contingent or mitigating
responses are developed.

• Contingency reserves are often viewed as the part of the budget intended to
address the “known-unknowns” that can affect a project.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 24
Estimate Costs

TOOLS AND TECHNIQUES

• Management reserves are an amount of the project


budget withheld for management control purposes
and are reserved for unforeseen work that is within
scope of the project.

• Management reserves are intended to address the


“unknown unknowns” that can affect a project.

• The management reserve is not included in the cost


baseline but is part of the overall project budget and
funding requirements.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 25
Estimate Costs

TOOLS AND TECHNIQUES

✓ Cost of quality - A method of determining the costs incurred to ensure quality.

• Prevention and appraisal costs (cost of conformance) include costs for quality
planning, quality control (QC), and quality assurance to ensure compliance to
requirements (i.e., training, QC systems, etc.).

• Failure costs (cost of non-conformance) include costs to rework products,


components, or processes that are non-compliant, costs of warranty work and waste,
and loss of reputation

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 26
Estimate Costs

TOOLS AND TECHNIQUES

7. Project Management Information System (PMIS)

✓ Include spreadsheets, simulation software, and statistical analysis tools to assist with
cost estimating.

8. Decision Making

✓ Voting - engaging team members to improve estimate accuracy and commitment to


the emerging estimates.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 27
Estimate Costs

OUTPUTS

1. Cost Estimates

✓ Include quantitative assessments of the probable costs required to complete


project work, as well as contingency amounts to account for identified risks, and
management reserve to cover unplanned work.

• Includes labor, materials, equipment, services, facilities.

2. Basis of Estimates

✓ Supporting documentation outlining the details used in establishing project


estimates such as assumptions, constraints, level of detail, ranges, and confidence
levels.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 28
Estimate Costs

OUTPUTS

3. Project Document updates

✓ Risk register - updated when appropriate risk responses are chosen.

✓ Assumption log - new assumptions or constraints may be made, and existing


assumptions or constraints may be revisited.

✓ Lessons learned register - updated with techniques that were efficient and effective
in developing cost estimates.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 29
7.3

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 30
Determine Budget

The process of aggregating the estimated costs of individual activities


or work packages to establish an authorized cost baseline.

The key benefit of this process is that it determines the cost baseline
against which project performance can be monitored and controlled.

✓ A project budget includes all the funds authorized to execute the project.

✓ The cost baseline is the approved version of the time-phased project budget that
includes contingency reserves, but excludes management reserves.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 31
Determine Budget

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 32
Determine Budget

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 33
Determine Budget

INPUTS

1. Project Management Plan

✓ Cost management plan – describes how the project costs will be structured into the
project budget.
✓ Resource management plan – provides information on costs that are necessary to
estimate the overall project budget.
✓ Scope baseline.

2. Project Documents

✓ Cost estimates
✓ Basis of estimates
✓ Project schedule
✓ Risk register

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 34
Determine Budget

INPUTS

3. Business Documents

✓ Business case – identifies the critical success factors for the project, including
financial success factors.
✓ Benefits management plan – target benefits, such as net present value calculations,
timeframe for realizing benefits, and the metrics associated with the benefits.

4. Agreements

✓ Includes information and cost purchases when determining the budget.

5. EEF - exchange rates, fluctuations of currencies.

6. OPA - historical information and lessons learned repository.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 35
Determine Budget

TOOLS AND TECHNIQUES

1. Expert Judgement

2. Cost Aggregation

✓ Cost estimates are aggregated by work


packages in accordance with the WBS. The
work package cost estimates are then
aggregated for the higher component levels of
the WBS (such as control accounts) and,
ultimately, for the entire project.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 36
Determine Budget

TOOLS AND TECHNIQUES

3. Data Analysis

✓ Reserve Analysis - An analytical


technique to determine reserve for the
schedule duration, budget, estimated
cost, or funds for a project.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 37
Determine Budget

TOOLS AND TECHNIQUES

4. Historical Information Review

✓ Reviewing historical information assist in developing parametric estimates or


analogous estimates Analysis.
5. Funding Limit Reconciliation

✓ The expenditure of funds should be reconciled


with any funding limits on the commitment of
funds for the project.

6. Financing

✓ Financing entails acquiring funding for projects.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 38
Determine Budget

OUTPUTS

1. Cost Baseline

✓ The cost baseline is the approved version of the time-phased project


budget, excluding any management reserves, which can only be
changed through formal change control procedures and is used as a
basis for comparison to actual results.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 39
Determine Budget

Time-phased view of the cost baseline displayed in the form of an S-curve

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 40
Determine Budget

OUTPUTS

2. Project Funding Requirements

✓ Total funding requirements and periodic funding requirements (e.g., quarterly,


annually) are derived from the cost baseline.

3. Project Document updates

✓ Cost estimates - updated to record any additional information.


✓ Project schedule - Estimated costs for each activity recorded.
✓ Risk register - New risks identified during this process.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 41
7.4

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 42
Control Costs

The process of monitoring the status of the project to update the


project costs and managing changes to the cost baseline.

The key benefit of this process is that the cost baseline is maintained
throughout the project.

✓ Any increase to the authorized budget can only be approved through the Perform
Integrated Change Control process.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 43
Control Costs

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 44
Control Costs

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 45
Control Costs

INPUTS

1. Project Management Plan

✓ Cost management plan – how the project costs will be managed and controlled.
✓ Cost baseline – compared with actual results to determine if a change, corrective
action, or preventive action is necessary.

2. Project Documents

✓ Lessons learned register.

3. Project Funding Requirements

✓ Include projected expenditures plus anticipated liabilities.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 46
Control Costs

INPUTS

4. Work Performance Data

✓ Data on project status such as which costs have been authorized, incurred,
invoiced, and paid.

5. OPA

✓ Existing formal and informal cost control-related policies, procedures, and


guidelines.
✓ Monitoring and reporting methods.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 47
Control Costs

TOOLS AND TECHNIQUES

1. Expert Judgement

2. Data Analysis

✓ Earned value analysis (EVA).


Refer Slide : PMP-07-EARNED VALUE MANAGEMENT

❖ Planned Value Forecasting


❖ Earned Value ❖ EAC
❖ Actual Cost ❖ ETC
❖ Schedule Variance ❖ VAC
❖ Cost Variance
❖ Schedule Performance Index Trend Analysis
❖ Cost Performance Index ❖ S Curve
Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 48
Control Costs

TOOLS AND TECHNIQUES

✓ Reserve Analysis

• used to monitor the status of contingency


and management reserves for the project.

• If the identified risks do not occur, the unused


contingency reserves may be removed from
the project budget to free up resources for
other projects or operations.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 49
Control Costs

TOOLS AND TECHNIQUES

3. To-complete Performance Index

✓ The to-complete performance


index (TCPI) is a measure of the
cost performance that is required
to be achieved with the remaining
resources in order to meet a
specified management goal.

✓ It is expressed as the ratio of the


cost to finish the outstanding work
to the remaining budget.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 50
Control Costs

OUTPUTS

1. Work Performance Information

✓ The calculated CV, SV, CPI, SPI, TCPI, and VAC values for WBS components, in
particular the work packages and control accounts, are documented and
communicated to stakeholders.

2. Cost Forecasts

✓ Either a calculated EAC value or a bottom-up EAC value is documented and


communicated to stakeholders.

3. Change Requests

✓ Analysis of project performance may result in a change request.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 51
Control Costs

OUTPUTS

4. PMP updates

✓ Cost management plan – changes to control thresholds or specified levels of


accuracy.

✓ Cost baseline - are incorporated in response to approved changes in scope,


resources, or cost estimates.

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 52
RECAP

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 53
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 54
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 55
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 56
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 57
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 58
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 59
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 60
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 61
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 62
Q&A

Jayaraj Peter ✓ These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth Edition 63
Jayaraj Peter

You might also like