Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

MAY 2003 AMM

The giant PT Freeport underground operation in Indonesia


has received a boost from Orica’s digital blasting
technology. By Richard Roberts

O ne of
underground
the world’s
mines
largest
has
demonstrated the benefits of using
(DOZ) underground operation in mid-
2001 after worldwide studies showed it
would deliver advantages over the post
timing range of conventional non-electric
detonators meant drawbells previously
had to be taken with two 17m inclined
advanced detonating technology to undercut method employed previously. In raises. Where required, drawbells were
efficiently and safely clear drawbells at particular, it was determined that the blasted twice, with the first blast
the base of its block cave. At a time of advanced undercut method would deliver incorporating the two raises and nine
increasing interest in block caving as an improved long-term mine pillar stability. rings. Once sufficient muck was drawn to
underground mining method around the The DOZ currently contributes about create a void two final rings were blasted.
world, PT Freeport’s successful 38,000 tonnes per day of underground Apart from limiting the flexibility of the
application of the i-kon digital blasting production from the PT Freeport process, the two blasts often produced
technology could set a standard for operations, with the mature IOZ delays in drawing down cave sections
drawbell construction for other sites to (Intermediate Ore Zone) yielding about and created safety concerns.
follow. 11,000tpd. Freeport is currently Twenty working man-shifts of 12 hours
Developed and supplied by Australian considering ramping up the DOZ per shift were required to drill and
company Orica, which also provides PT production to 50,000tpd. develop each 17m raise and a further 12-
Freeport’s surface and underground The operator needs to open up 4-6 hour shift was needed to hook and fire up
copper-gold operations in West Papua, drawbells a month to maintain a steady the first stage. Arlaud said firing the first
Indonesia, with other blasting products production flow from caving zones. stage often damaged EXEL tubes and
and services, the i-kon detonators were Blasting of 14m-high central raises in pre-charged blastholes, which could lead
first used in underground trials at PT each drawbell connects the production to misfires and poor second-stage blasts.
Freeport early last year. This progressed level with cave sections, opening up Connecting up second-stage blasts also
to full production use soon after. draw-down points for columns of ore up created risks to personnel as the activity
PT Freeport switched to the advanced to 400m high. occurred adjacent to and under ground
undercut method of accessing the area PT Freeport senior planning engineer affected by the first blast.
beneath the cave at this Deep Ore Zone Tracy Arlaud said the limited detonation

ORICA developed the i-kon digital energy control


system as a means of achieving better rock
fragmentation with bigger blasts and a simpler and
safer detonation process.
The result of years of research and development,
i-kon comprises programmable digital detonators –
each one replacing many delay detonators used
previously, as well as control equipment, loggers and a
blaster for firing the detonators. Orica has also
developed blast design and simulation software
(SHOTPlus-i) specifically for use with i-kon detonators.
Two-way communication between the detonators
and loggers facilitates programming and function
verification prior to firing. Loggers cannot set off
detonators, a highly important safety feature for an
electronic initiation device. Only the specifically
designed i-kon blaster has sufficient energy, and the
properly coded and sequenced signal, to initiate the
detonators, which further enhances system safety.
The i-kon system can fire 3200 detonators, with
each detonator fully programmable- from 0-15,000
milliseconds - in 1ms increments.
Blast designs from the SHOTPlus-i software can be
downloaded into loggers to enable automatic
programming of delay times when each detonator is
connected to a surface harness wire.
MAY 2003 AMM 31

“We weren’t able to achieve better than “We’re saving $US26,000 per Monthly from the company’s Jakarta
four drawbells a month,” Arlaud said. drawbell in measurable costs which, office that the site was the first in the
“Since the introduction of the i-kon based on four drawbells a month, is region at which the i-kon system had
detonators we have varied production to $US1.248 million per year. At a been formally handed over to a customer.
the undercut level between 4-6 drawbells production rate of six drawbells per “We have engineers here who can
a month. Getting the drawbells on line as month, we’re saving $US1.872 million assist with blasts as required, but there
efficiently as possible gives us fast per year. are fully trained Freeport operators and
access to the ore to draw it down, and it “Other savings which aren’t as easy engineers who can fire i-kon on their
also removes the possibility of material to measure as reducing to single shorter own,” he said.
recompacting above the drawbell, which cental development, include brought Orica, together with local alliances
creates separate issues. forward revenue from production, partner PT Multi Nitrotama Kimia (MNK),
“When we blasted in two stages we improved fragmentation and the continues to have more than 20
would blast the first section of the reduced vibration damage. Then there employees involved in its product supply
drawbell and then have to draw the muck are the reduced risks to personnel.” and blast design and engineering
to create enough void to blast the second Since their commercial release in operations at PT Freeport’s underground
stage. It could mean having to draw for August 2000, the i-kon detonators and and surface mines. The company has
up to a month to get a void. Sometimes it other components of the i-kon system been supplying explosives and blasting
was never actually safe enough to get have become significant product lines accessories to the mine operator since
back in to set up the second blast, which for Orica during a growth phase for the 1997 and has had a full service contract
usually meant that drawbell wouldn’t draw company’s mining business. The since mid-2001.
as much ore as anticipated. technology has now been used in a “What has been critical to the success
“We’re now getting drawbells on line wide range of mining applications. we’ve had at Freeport is that they have
up to 30 days earlier.” Orica assigned experienced i-kon adopted an attitude of working together
The use of i-kon detonators also project manager Mike Lovitt to liaise with suppliers and service providers,”
reduced blast vibration damage to with PT Freeport and other Orica Labriola said. “ Our people are really part
surrounding panels and drawpoints, while personnel, in particular Bonifacio Degay of their team.
reducing mine personnel exposure to Jr, at the remote mine during the “Together we have achieved a world-
hazards and the cost of panel implementation phase. Lovitt previously first with I-kon in that application and it
rehabilitation. Fully programmed worked with Arlaud at the Bronzewing has not just been about the technology.
detonation sequences were producing gold mine in Western Australia when Freeport did a phenomenal amount of
more predictable, lower-cost drawbell that site started blasting large pillar work in other areas such as drilling and
outcomes, Arlaud said. sections with i-kon detonators in the surveying, to ensure drawbells were set
“I believe we are the only block cave second half of 2000. Bonifacio came up properly.
operation in the world to blast a drawbell with a strong block caving background “MNK and Orica also had to work
in a single blast, successfully, and the from the Philex block cave operation in closely together to get approvals from
only block cave operation doing drawbell the Philippines. officials to bring i-kon into the
blasting with i-kon,” she said. Orica technical services country.”
superintendent, South Asia, Angelo
[ENVIRONMENT] Labriola told Australia’s Mining

You might also like