FOR APPROVAL

A 19.09.2019 P.T.ANH L.C.HAI Y.H.LEE FOR APPROVAL


Rev Date Prepared Checked Approved Details of Revision
Owner

Owner’s Engineer

Contractor

DOOSAN HEAVY INDUSTRIES VIETNAM

Sub-Supplier
BAC MIEN TRUNG CONSULTANCY INVESTMENT
CONSTRUCTION AND TRADING JOINT STOCK
COMPANY
Project

NGHI SON 2 BOT THERMAL POWER PLANT PROJECT


(2 X 600 MW)
Title

[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work

Document No. Rev. Page No.

NS2-DD09-P0UYK-770011 A 10 Pages
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

RECORD OF REVISIONS

Rev. Date Page Affected Description of Revision

A 19.09.2019 All First Issue

Page 1 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

Contents
1. PURPOSE ............................................................................................................. 3

2. MACHINERY & EQUIPMENT ............................................................................ 3

3. RESPONSIBILITIES ............................................................................................ 3

4. MATERIAL .......................................................................................................... 3

5. PROCEDURE AND SEQUENCE .......................................................................... 4

6. WORKING METHOD/PROCEDURES ................................................................. 4

7. QUALITY CONTROL .......................................................................................... 5

8. PRESSURE TEST (For water supply pipe) ............................................................. 5

9. LEAKAGE TEST (For drainage pipe) .................................................................... 6

10. ENVIRONMENT, HEALTH AND SAFETY (EHS) ................................................ 6


10.1 RESPONSIBILITIES AND INSTRUCTIONS ............................................... 6
10.2 SAFETY (PPE) ................................................................................................ 7
10.3 ENVIRONMENTAL ....................................................................................... 7
10.4 JOB SAFETY ANALYSIS .............................................................................. 8

Page 2 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

1. PURPOSE
The purpose of this Method Statement is to describe the methodology involved on the
installation of uPVC; HDPE; PPR piping, the steps to be taken in meeting the technical
standards and EHS requirements of Nghi Son 2 BOT Thermal Power Plant
+ Plant Project :Nghi Son 2 BOT Thermal Power Plant
+ Company/Owner :Nghi Son 2 Power Limited Liability Company
+ Main Contractor : Doosan Heavy Industries VietNam
+ Subcontractor : Bac Mien Trung Consultancy investment construction and trading JSC
Reference document:
+ Inspection and Test Plan
+ Health & Safety Management Plan
+ Material Approval Request for UPVC,HDPE,PPR Pipe Tien Phong, Dekko
+ TCVN 4519:1988 Indoor water supply and drainage systems-
Codes for construction, check and acceptance
+ Project technical requirement.
+ Approval civil construction drawing

2. MACHINERY & EQUIPMENT


No. Description Remark

1 Hand Tools : glue roller, knives, scissors

Required Machine for Joint: Cutting machine, Sander


2
(if required as per manufacture recommend)

3 Consumables : Pipes and fittings, duct tape

3. RESPONSIBILITIES
- It is overall responsibility of Project Manager to organize resources prior to perform
construction activities as per project specification in compliance with the quality,
schedule & safety requirements.
- EHS Manager will ensure in coordination with Site Engineer that all
measure/construction taken shall be maintained till completion of job.
- It is the responsibility of Construction Manager/Site Engineer that construction
activities are executed according to the relevant project specification in compliance with the
quality, schedule & safety requirements.
- BMT will ensure that all works are performed safely.
- The relevant BMT Supervisor will ensure that the work is carried out in
accordance with this method statement and project specification.
- The QC Inspector will ensure that the work is executed according to the
requirements of quality dossier are fulfilled.

4. MATERIAL
- All materials required shall be approved by the Owner.
- All materials required shall be true to size, without cracks, chips, splits, or other
defects which may impair their strength or durability.

Page 3 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

- Material should be take receiving inspection with all their certificate from factory
approved

5. PROCEDURE AND SEQUENCE


- The Contractor shall furnish all labor, tools and materials necessary for the
complete installation of the plumbing system which includes pipe lines
inside(including under) Buildings
- Underground Soil, Waste, Drain and Vent Pipe and Fittings - Underground soil, waste,
drain and vent pipe and fittings shall be uPVC; HDPE; PPR pipe.
- Underslab sanitary sewer pipes from fixtures to the building main shall be uPVC pipe.
Fittings shall be uPVC and solvent weld shall comply ASTM solvent cement.
- All excavation shall be restored to its required level. The bottom of trench shall be dry
prior to installation. After installation, all pipe ends shall be capped to prevent egress of
unsuitable materials.
- The trench bottom shall be continuous, smooth, free of rocks and in accordance to the
line and grade shown in the drawing.

6. WORKING METHOD/PROCEDURES

- Remove foreign matter from inside of pipe before installation.


- Adequately support vertical lines at their bases or by a suitable hanger place in
horizontal line near riser or by a base fitting set on pedestal.
- Run piping in straight lines and square with the building. Riser lines to be plumb. Provide
dielectric fittings for connecting dissimilar metals
- Do not route piping over any electrical equipment where the possibility of damage
exists. Provide flanges and unions throughout piping system to facilitate the installation
and removal of piping and equipment.
- Sewer lines shall not cross over water line. In case inevitable, suitable measures at the
crossing shall be taken.
- Valves shall be installed in horizontal lines with stems either horizontal or vertical.
Isolation valves shall be installed at any other points indicated or required for draining,
isolation, or sectionalizing purposes as per Drawings. Valves shall be installed such that
maintenance access is maintained for all parts requiring service. Control valves shall be
provided in water pipes to provide complete regulation of plumbing fixtures and
equipment
- Provisions must be included for servicing and removal of equipment without dismantling
piping works. Place water supply pipes, storm drainage pipes, sanitary sewer pipes,
waste pipes and drain pipes at elevation and slopes as per drawing.
- Preparation for the first fix shall commenced immediately upon completion of civil
works
Page 4 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

- Marking for the pipe route considering the other agencies shall be done with due
consideration for slopes and tapping points as per the drawings.
- After the chasing works, the concealed pipes shall be concealed
- The process of installing pipelines shall be inspected by the stakeholders and ensured to
follow the required procedures. (There will be no leak if the installation process follows
the right procedures). Visual leak check shall be carried-out after the installation.
- Pipes shall be joint when the length of a pipe has been put into use, and in case in case
that there are changes on the elevation and direction of the pipeline in accordance with
the design, joint fittings shall be needed.
- Checking the slope of pipes following the design: Before installing pipes in the concrete
structure or associated with other structures, the elevation (pipe bottom) shall be
determined by the theodolite. For the pipelines on the ground, the elevation shall be
determined by the theodolite and the land area is prepared following the design
elevation, then pipes shall be directly installed on the prepared ground. After the pipe
installation, checking the slope again by the theodolite and tape measure. Tolerance of
elevation and location of pipe ≤ 5mm.
- The bottom of pipe and back fill material shall not have any sharp edged material
which may damage the pipes. Hence generally, the bottom 100mm shall be filled
with sand and also back filling shall be done with sand till 100mm above the pipe
to ensure no damage to pipe and to consolidate properly without applying
excessive loading.

7. QUALITY CONTROL
- The Site Inspection and Test Plan (ITP) for this work summarize various
characteristics to be checked. The concerned Site Engineer/Foreman will be responsible
to ensure stage wise compliance for these operations and the Site QA/QC
Engineer/Inspector will carry-out quality control checks and report the inspection
results.

8. PRESSURE TEST (For water supply pipe)


- Pressure test is not made to discover premature failure of components, but to find
installation errors or fabrication defects of piping.
- Preparation: Piping network shall be prepared for carrying out a pressure test. For this, dead
plugs shall be installed at the outlets (in case of hydrostatic pressure testing, a venting point
shall be made at the highest outlet). Pressure gauge having the proper range and that has a
valid calibration shall be installed and connected to the piping network.
- Hydrostatic Pressure Testing:

Page 5 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

+ The purpose of the Hydrostatic Pressure Testing is to discover the premature failure of
components and to improve the reliability and safety of the tested system. Hydro testing will
be applied to all water-based system. The items below describe the steps to be taken to
complete the hydrostatic pressure testing.
+ Isolate piping from the existing main network (if applicable) closing by blind flange or
plug. Confirm that a drain at lowest point & vent valves at highest point have been installed
in the piping network. Fill water in the piping network to be tested for the hydrostatic test.
+ Testing pressure shall be equal to working pressure plus 5 daN/cm2, but not exceed 10
daN/cm2 and keep during time 10 minutes. Allowed reducing pressure in testing time < 0.5
daN/cm2 (TCVN 4519:1988 Indoor water supply and drainage system – Codes for
construction, check and acceptance)

9. LEAKAGE TEST (For drainage pipe)


- Leakage test shall be controlled by Piping Engineer and performed under witness of QA/QC
Inspector and Owner's Representative.
- The water used for the testing operation shall be of clean water.
- Keeping the time of leak test up to 2 hours and/or according to the requirements.
- The test record, updated line and drawing number, showing the boundaries of test.
- QA/QC Inspector shall review all documents within test boundary and notify the Owner of
test schedule with related documents.
- It is required to prevent movement of pipe, the pipe trench between joints may be temporary
fixed before testing.
- Vent shall be provided at high points of test boundary and filling and drain line shall be
installed for testing.
- Before filling of water, Piping Engineer shall verify that all preparation for test is
completed.
- The system shall be visual checked for leaks.
- After leakage test is completed low point drain valve shall be opened and the system
through
drained.

10. ENVIRONMENT, HEALTH AND SAFETY (EHS)

10.1 RESPONSIBILITIES AND INSTRUCTIONS


PM/EHSS Officer shall ensure that all work is undertaken in accordance with the specified
work scope.
- Safety training should be conducted to all personnel assigned at site prior to commence any
work.

Page 6 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

- All personnel should know the locations of fire extinguishers, communications, manual
alarms.
- ESD points.
- All personnel should be aware of assembly points, escape routes, emergency contact
numbers.
- Personal Protective Equipment (PPE) shall be worn at all times.
- Good housekeeping shall be observed in work areas.
- Construction wastes shall be segregated and disposed to an approved dump yard area.
- Adequate lighting equipment when working night time.
- Ensure all workers and equipments working overtime are properly accounted and obtained
permit/approval from Doosan EHS Manager prior to carry-on works.
- Periodic refresher trainings, tool box talk and audit shall be conducted.

10.2 SAFETY (PPE)


- Personal Protective Equipment (PPE) will be issued to all workers such as safety shoes, hard
hat, working gloves, earplug, safety goggles, reflective vest and safety harness for workers who
will be assigned.
- Wearing of the basic PPE will be enforced fully.
- All new recruits will undergo proper orientation and safety induction before they could
deployed at site for work.
- As pipes are subjected to various pressures, there is always a possibility of damage to pipe and
sudden outburst. The personnel working during testing shall be very vigilant and take proper
precautions.

10.3 ENVIRONMENTAL
- The work will be carried with full protection to environment.
- Working area shall be clean, not slippery and free from any debris.

Page 7 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

10.4 JOB SAFETY ANALYSIS


List of All Job
Steps List of All Known Hazards How to Eliminate Hazards

A.1a Be operated only by workers who have been


authorized and given appropriate training

A.1b Safe operating procedure should be established


and used for all tools and equipment

A.1c Daily checklist of equipment must be provided


Prior to stat any work.

A.1 Injury by using hand tools and


both manual and power driven. A.1d Every power driven tools should be provided
with adequate means, immediately accessible and
readily identifiable by operator, of stopping it quickly
and preventing it from being started again
inadvertently.

A.Equipment/Tools
and Material A.1e Every hand tools must be inspected every month
Preparation and attached inspection tag

A.2a Provide adequate ground and circuit breakers

A.2b Must use 3 core codes electric wire and separate


distribution panel (must pass arrangement of ELCB)
A.2 Electric shock due to without And avoid any water affect.

ground external box and circuit


A.2c All kind of electric cable must be hang over
breakers
ground

A.2d Must use industrial socket and plug

A.2e Electric cabinet don't affect any water

B.1a Undetermined periods the workers should get


proper fresh air

B. During the B.1b Clear drinking water to be taken to clear the


Course of Piping Throat and blow nose to remove dust.
B.1 Inhalation of piping works
Works

B.1c All necessary PPE to be provided.

Page 8 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011

List of All Job


Steps List of All Known Hazards How to Eliminate Hazards

B.2a Workers should be provided with proper interval


whilst using cutting machine

B.2b All necessary PPE to be provided

B.2c Close supervision and monitoring to be done

B.2 Cutting Machine


B.2d Fire extinguisher equipment shall be sufficient to
Extinguish all types of fire likely to be encountered.

B.2e All extinguishers shall be readily accessible, free


from construction and their locations clearly marked by
Adequate signs.

B.3a Irrigate eye with plenty of water and seek


Medical attention if symptoms persist.
B.3 Eye contact
B.3b All necessary PPE to be provided

B.4a All LPG cylinders to be approved by Government


Authority.

B.4b Proper fire arrestor to be fixed with the cylinder

B.4c Fire extinguisher equipment shall be sufficient to


extinguish all types of fire likely to be encountered

B.4 Fire
B.4d All extinguishers shall be readily accessible, free
from construction and their locations clearly marked by
Adequate signs.

B.4e Chemical shall be stored in secondary


containment & MSDS requirement shall be
communicated with all concerned

C.1 Injury could be caused whilst


C.1a Material shall be properly off loaded and stacked
off loading & shifting the
at the location required
materials
C. Installation of
Pipe
C.2 Collapse of scaffolding due to
C.2a Use appropriate scaffold materials only.
overweight

Page 9 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex](Building Technicians And Operators 2)Calculation Water Supply And Drainage
NS2-VS00-P0UYK-750002
List of All Job List of All Known
Steps Hazards How to Eliminate Hazards

C.3 While application at higher C.3a Use safe working platform with toe boards
elevations
C.3b No person will be allowed to work directly under
whist this activity is on progress

C.3c All necessary PPE to be provided

C.4a Cordon off the area below.


C.4 Splashing of chemicals into the
eyes whilst application
C.4b Wear proper PPE including eye protection

C.5a Fire extinguisher equipment shall be sufficient to


C.5 Fire handling and storage of Extinguish all types of fire likely to be encountered.
materials

C.5b All extinguishers shall be readily accessible, free


from construction and their locations clearly marked by
Adequate signs.

C.5c Chemical shall be stored in secondary


containment & MSDS requirement shall be
communicated with all concerned

D.1 Working operation may cause D.1a Must provide sufficient lightings on the entire
injury to personnel due to poor working area
visibility of the area
D.1b All equipments/tools must be fitted with
appropriate safety device and ensure all lights are
operational not obscured by dirt & mud

D.1c Supervisor and safety personnel must always be


Present for the entire working operation.

D.1d All workers must be wearing reflective vest


D. Working
Operation During
Night Time
D.1e Must use and connect 3 core codes electric wires
With separate distribution panel (must pass
arrangement of ECLB).

D.2 Generator (Diesel) equipment


oil leakage during operation. D.2a Daily check of the equipments prior to start of work
D.2b Regular check &monitoring of the equipment
prior to use.
D.2c Provide secondary containment protection under
the equipment to prevent contamination of soil by oil
spillage
D.3 Oil/chemical storage
D.3a Diesel/chemical shall be stored in secondary
containment & MSDS requirement shall be
communicated with all concerned

Page 10 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works