Professional Documents
Culture Documents
For Approval: Bac Mien Trung Consultancy Investment Construction and Trading Joint Stock Company
For Approval: Bac Mien Trung Consultancy Investment Construction and Trading Joint Stock Company
Owner’s Engineer
Contractor
Sub-Supplier
BAC MIEN TRUNG CONSULTANCY INVESTMENT
CONSTRUCTION AND TRADING JOINT STOCK
COMPANY
Project
NS2-DD09-P0UYK-770011 A 10 Pages
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
RECORD OF REVISIONS
Page 1 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
Contents
1. PURPOSE ............................................................................................................. 3
3. RESPONSIBILITIES ............................................................................................ 3
4. MATERIAL .......................................................................................................... 3
Page 2 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
1. PURPOSE
The purpose of this Method Statement is to describe the methodology involved on the
installation of uPVC; HDPE; PPR piping, the steps to be taken in meeting the technical
standards and EHS requirements of Nghi Son 2 BOT Thermal Power Plant
+ Plant Project :Nghi Son 2 BOT Thermal Power Plant
+ Company/Owner :Nghi Son 2 Power Limited Liability Company
+ Main Contractor : Doosan Heavy Industries VietNam
+ Subcontractor : Bac Mien Trung Consultancy investment construction and trading JSC
Reference document:
+ Inspection and Test Plan
+ Health & Safety Management Plan
+ Material Approval Request for UPVC,HDPE,PPR Pipe Tien Phong, Dekko
+ TCVN 4519:1988 Indoor water supply and drainage systems-
Codes for construction, check and acceptance
+ Project technical requirement.
+ Approval civil construction drawing
3. RESPONSIBILITIES
- It is overall responsibility of Project Manager to organize resources prior to perform
construction activities as per project specification in compliance with the quality,
schedule & safety requirements.
- EHS Manager will ensure in coordination with Site Engineer that all
measure/construction taken shall be maintained till completion of job.
- It is the responsibility of Construction Manager/Site Engineer that construction
activities are executed according to the relevant project specification in compliance with the
quality, schedule & safety requirements.
- BMT will ensure that all works are performed safely.
- The relevant BMT Supervisor will ensure that the work is carried out in
accordance with this method statement and project specification.
- The QC Inspector will ensure that the work is executed according to the
requirements of quality dossier are fulfilled.
4. MATERIAL
- All materials required shall be approved by the Owner.
- All materials required shall be true to size, without cracks, chips, splits, or other
defects which may impair their strength or durability.
Page 3 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
- Material should be take receiving inspection with all their certificate from factory
approved
6. WORKING METHOD/PROCEDURES
- Marking for the pipe route considering the other agencies shall be done with due
consideration for slopes and tapping points as per the drawings.
- After the chasing works, the concealed pipes shall be concealed
- The process of installing pipelines shall be inspected by the stakeholders and ensured to
follow the required procedures. (There will be no leak if the installation process follows
the right procedures). Visual leak check shall be carried-out after the installation.
- Pipes shall be joint when the length of a pipe has been put into use, and in case in case
that there are changes on the elevation and direction of the pipeline in accordance with
the design, joint fittings shall be needed.
- Checking the slope of pipes following the design: Before installing pipes in the concrete
structure or associated with other structures, the elevation (pipe bottom) shall be
determined by the theodolite. For the pipelines on the ground, the elevation shall be
determined by the theodolite and the land area is prepared following the design
elevation, then pipes shall be directly installed on the prepared ground. After the pipe
installation, checking the slope again by the theodolite and tape measure. Tolerance of
elevation and location of pipe ≤ 5mm.
- The bottom of pipe and back fill material shall not have any sharp edged material
which may damage the pipes. Hence generally, the bottom 100mm shall be filled
with sand and also back filling shall be done with sand till 100mm above the pipe
to ensure no damage to pipe and to consolidate properly without applying
excessive loading.
7. QUALITY CONTROL
- The Site Inspection and Test Plan (ITP) for this work summarize various
characteristics to be checked. The concerned Site Engineer/Foreman will be responsible
to ensure stage wise compliance for these operations and the Site QA/QC
Engineer/Inspector will carry-out quality control checks and report the inspection
results.
Page 5 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
+ The purpose of the Hydrostatic Pressure Testing is to discover the premature failure of
components and to improve the reliability and safety of the tested system. Hydro testing will
be applied to all water-based system. The items below describe the steps to be taken to
complete the hydrostatic pressure testing.
+ Isolate piping from the existing main network (if applicable) closing by blind flange or
plug. Confirm that a drain at lowest point & vent valves at highest point have been installed
in the piping network. Fill water in the piping network to be tested for the hydrostatic test.
+ Testing pressure shall be equal to working pressure plus 5 daN/cm2, but not exceed 10
daN/cm2 and keep during time 10 minutes. Allowed reducing pressure in testing time < 0.5
daN/cm2 (TCVN 4519:1988 Indoor water supply and drainage system – Codes for
construction, check and acceptance)
Page 6 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
- All personnel should know the locations of fire extinguishers, communications, manual
alarms.
- ESD points.
- All personnel should be aware of assembly points, escape routes, emergency contact
numbers.
- Personal Protective Equipment (PPE) shall be worn at all times.
- Good housekeeping shall be observed in work areas.
- Construction wastes shall be segregated and disposed to an approved dump yard area.
- Adequate lighting equipment when working night time.
- Ensure all workers and equipments working overtime are properly accounted and obtained
permit/approval from Doosan EHS Manager prior to carry-on works.
- Periodic refresher trainings, tool box talk and audit shall be conducted.
10.3 ENVIRONMENTAL
- The work will be carried with full protection to environment.
- Working area shall be clean, not slippery and free from any debris.
Page 7 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
A.Equipment/Tools
and Material A.1e Every hand tools must be inspected every month
Preparation and attached inspection tag
Page 8 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex]Method Statement for uPVC, HDPE, PPR Piping Work
NS2-DD09-P0UYK-770011
B.4 Fire
B.4d All extinguishers shall be readily accessible, free
from construction and their locations clearly marked by
Adequate signs.
Page 9 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works
[Housing Complex](Building Technicians And Operators 2)Calculation Water Supply And Drainage
NS2-VS00-P0UYK-750002
List of All Job List of All Known
Steps Hazards How to Eliminate Hazards
C.3 While application at higher C.3a Use safe working platform with toe boards
elevations
C.3b No person will be allowed to work directly under
whist this activity is on progress
D.1 Working operation may cause D.1a Must provide sufficient lightings on the entire
injury to personnel due to poor working area
visibility of the area
D.1b All equipments/tools must be fitted with
appropriate safety device and ensure all lights are
operational not obscured by dirt & mud
Page 10 of 10
Project: Nghi Son 2 BOT Thermal Power Plant(2x600 MW)
Work Item: Calculation Works