Subject : SERENE HOUSE MODEL CONSTRUCTION MONITORING

FA = 50.00sqm, CIP Wall System, 3BR, 2TB, LA = 80.00sqm


Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : JBT CONSTRUCTION NTP NO: 05 NO OF UNIT: 4 NO OF UNIT: 4
Date: : August 3, 2020

AT 100% AT 100%
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1301 B1303 B1305 B1307 B1309 B1310 B1311 B1312
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX CORNER DUPLEX CORNER DUPLEX
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 9.80% 9.80% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 9.47% 9.47% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.83% 6.83% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.83% 6.83% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 10.73% 0.00% 10.73% 10.73% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.86% 0.86% 0.86% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 9.87% 9.87% 9.87% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 12.46% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 0.00% 5.19% 4.99% 5.19%
Module VII CARPENTRY 12.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 78.28% 51.50% 51.50% 42.92% 42.02% 31.29% 36.83% 42.02% 100.00% 100.00%

1.00 % Weight TOTAL ACCOMPLISHMENT 78.28% 51.50% 51.50% 42.92% 42.02% 31.29% 36.83% 42.02%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 78.28% 51.50% 51.50% 42.92% 42.02% 31.29% 26.10% 31.29%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.73% 10.73%
4.00 % Weight BALANCE AFTER THIS PERIOD 21.72% 48.50% 48.50% 57.08% 57.98% 68.71% 63.17% 57.98%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20
No of days remaining/ delays -29.00 -29.00 -29.00 -29.00 -29.00 -29.00 -29.00 -29.00

Prepared by: Verified by: Checked by: Noted by:

__________________ ___________________ _____________________ ________________


ROBERTO NOLLORA JR. JOHN RICKY CALARA AR JASON HERNANDEZ JOHN PAUL T. DY
OPR-SE A&E - Engineer A&E -Architect President