Topic 5 Maintenance Schemes For Private Buildings in Hong Kong (Part 2)
Topic 5 Maintenance Schemes For Private Buildings in Hong Kong (Part 2)
Buildings aged 30 years or above are required to appoint an RI to carry out the
prescribed inspection and supervise the necessary repair works of the common parts,
external walls and projections or signboards of the buildings once every 10 years
Owners of buildings aged 10 years or above are required to appoint a QP to carry out
prescribed inspection and supervise necessary repair works of all windows of the
buildings once every 5 years
2,000 buildings will be selected for both MBIS and MWIS to be carried out concurrently
each year
Extra 3,800 buildings selected for MWIS only
Target buildings would represent a mix of buildings in different conditions and age
profiles in various districts
A selection panel comprising representatives from professional institutions, relevant
non-government organizations, property management professionals, District Councils
and relevant Govn’t departments is established to render advice to BD for the selection
Standard of Works
1
CIVL6060
External elements
Structural elements
Fire safety elements
Drainage system
Identification of UBWs in common parts of building; on exterior parts such as external
wall, roof or podium; and on street on which building fronts or abuts. (BD will deal
with such UBWs in accordance with prevailing policy.)
2
CIVL6060
Structures in common parts and on roof top, flat roof, yard, lane or street
Projections and signboards erected on exterior of building
Alterations or additions affecting fire safety
Alterations and additions of structural elements
Alterations and additions of drainage system
Alterations of external walls or parapets
Removal or alterations of provisions for barrier free access for people with disability
3
CIVL6060
Pre-notification Letter
Not less than 6 months advance notice to owners before issuance of MBIS Notice
MBIS Notice ( 3* + 3 + 6 )
3 months for appointment of RI
3 months for completion of prescribed inspection
6 months for completion of prescribed repair
(* extra 3 months allowed for building without OC)
Pre-notification Letter
Not less than 2 months advance notice to owners before issuance of MWIS Notice
MWIS Notice ( 3* + 2 + 1 )
3 months for appointment of QP
2 months for completion of prescribed inspection
1 month for completion of prescribed repair
(* extra 3 months allowed for building without OC)
4
CIVL6060
Where RI considers that prescribed repair is required, owners must appoint RGBC or
RMWC to carry out prescribed repair under supervision of RI (who may be the same as
or different from RI who has carried out prescribed inspection)
Upon completion of prescribed inspection and prescribed repair, RI must submit an
inspection report and a completion report respectively, with a certificate in specified
form, to BD for record and audit check
5
CIVL6060
Document Submission by RI
Notification of Appointment of RI
Submission with 7 days after date of appointment
Specified Form
External Finishes
Loose or missing tiles and rendering
Cracks
Bulging, bowing, separation, delamination
Corrosion of metallic parts embedded in external finishes
Spalling
Cladding
Displacement of cladding panels
Cracked or loose cladding panels
Defective sealing joints
6
CIVL6060
Stains
Corrosion of fixing anchors or metal frames
Fins, Grilles and Metal Louvers
Dilapidation
Corrosion of metallic parts
Loose or defective fixings
Protective Barriers, Railings, Parapets and Balustrades
Cracked, loose, broken or missing glass panels
Corroded or loose fixings
Loose or defective railings
Defective sealants
Fencing and Associated Fixings
Dilapidation
Corrosion
Loose or defective fixings
Curtain Wall and Associated Openable Windows
Cracked, loose, broken or missing glass panes
Corroded or loose fixings
Defective sealants
Defective fire stop
Defective locking devices and bar hinges
Signs of water leakage behind curtain wall
Appendages
Dilapidation
Corrosion
Loose or defective fixings
Manually or Electrically Operated Metal Gates
Defective or missing hinges
Defective track, guide rail, stopper and safety device to prevent gate from sliding
off the rail
Corrosion of supporting structural steel posts and fixings
Defects to be identified
Dampness
Rust stains or corrosion of reinforcement
Cracks or signs of distress
Spalling
Delamination
Exposed reinforcement
Voids and honeycombing
Deformation or displacement
Abnormal separation of building from adjoining buildings
For cantilevered slab canopy, apart from general structural elements above, RI must look
out for any water ponding, defective drains, signs of water seepage, existence of UBW
erected on and/or attached to soffit of canopy
7
CIVL6060
RI must conduct the following investigation and conduct assessment to ascertain safety
level of canopy projecting over street
Opening up concrete cover at suitable locations at roof of canopy immediately
adjoining parent structure must be conducted to assess degree of corrosion of
existing main reinforcement;
Coring at appropriate locations must be carried out to measure actual slab thickness,
compressive strength and carbonation of concrete;
At open-up locations, layout of existing reinforcement, including bar diameter, bar
spacing, thickness of concrete cover, and thickness of screeding and waterproofing
on canopy must be measured; and
Span length of cantilevered slab canopy, dimensions of any parapet wall, downturn
and/or architectural features, etc. must be measured.
RI must exercise his professional judgment to select sufficient opening up and coring
locations with at least 2 numbers for each discrete canopy of a building under inspection,
or 1 number for every 6 m along length of canopy, whichever is the greater.
Means of Escape
Defective or missing exit signs
Inadequate lighting
Defective balustrades and handrails in staircases and escape routes
Door swing obstructing means of escape
Blocked or obstructed means of escape
Defective treads
Means of Access for Fire Fighting and Rescue
Blocked means of access to building, particularly along rear lane
Blocked or obstructed means of access within building such as access to fireman’s
lift lobby on G/F
Dilapidated emergency vehicular access
Defects in integrity of fireman’s lift lobby
Fire Resisting Construction
Defective or dilapidated materials resulting in inadequate FRC
Ventilation ducts or other building services passing through compartment walls or
floors breaching the requirements of FRC
Broken hinges or glass panels in fire doors
Defective or non-provision of self-closing mechanism in fire doors
Broken or dilapidated fire doors or fire resisting glazing
Inadequate fire resistance of fire door or glazing
Non-emergency services such as electric wires, cables and meters in escape
staircases and lobbies, without adequate fire protection
Damaged staircase enclosure such as walls, windows and doors including those for
protected lobby
Obstruction to fire dampers or fire shutters for compartmentation
Defective or blocked staircase top vents
Unauthorized Alterations and Additions
Doors, gates or roller shutters obstructing escape route
Unprotected openings at enclosure walls or exit routes or compartment walls, floors
and ceilings
Structures on refuge floors
8
CIVL6060
General
Corrosion, leakage, deformation, displacement, damage and blockage of drain pipes
and traps including underground drains
Corrosion, loosening or breaking of metal brackets
Damage or blockage of manhole/septic tank
Broken and blockage of surface channel, gullies and catch pits
Missing drain pipes or grating at top of ventilating pipes
Deterioration or missing of mica flap in fresh air inlet
Unauthorized Alterations and Additions
Misconnection of foul or waste water to surface water drainage system or discharge
of foul or waste water to external parts of building or open areas
Drainage alteration and addition resulting in discharge of untreated trade effluent,
including hot water, into drainage system or to external parts of building or open
areas
Mis-connection of surface water to foul water system
Inspection Report
Cover Page
Building name, address and lot no.
9
CIVL6060
Detailed Investigation
Conduct detailed investigation where there are serious defects constituting structural
instability or serious health hazard, or where extent or cause of defects cannot be
ascertained in inspection
RI to determine whether a DI is required to be conducted
10
CIVL6060
Structural Assessment
Where RI is not certain about the material properties, he may use the approach of Worst
Credible Strength under the following circumstances:
An initial assessment using characteristic values has shown that a structural element
may be incapable of carrying the full assessment loading;
A structure suffers from damage or deterioration resulting in the actual strength
being less than the characteristic values; or
Information in respect of the characteristic values adopted in the design cannot be
retrieved.
For determining factored load effects on rc and steel structures based on the Concrete
Code and Steel Code, modified partial safety factors for loads shall be used.
Where the concrete strength is based on the WCS from cores, the partial safety factors
for material strength (m) for concrete in flexure or axial load may be taken as 1.25 (not
1.5).
11
CIVL6060
Where the reinforcement strength is based on a WCS from test results, the value of m
for reinforcement may be taken as 1.05 (not 1.15).
12
CIVL6060
Spalling
Patch Repair
Suitable for localized and non-critical defects with repair depth < 75 mm
Materials
Repair mortar – cementitious mortar or polymer modified cementitious mortar
Primer for reinforcement – rust inhibitor, cement-based reinforcement primer
or epoxy-based reinforcement primer
Bond coat – cement-based, epoxy-based or acrylic-based
New reinforcement – Construction Standard CS2
Hacking – All spalled concrete to be thoroughly removed
Treatment to Reinforcement – exposed reinforcement to be wire-brushed to remove
loose mill scale and rust. Where reinforcement is corroded seriously (i.e. loss of
sectional are > 15%), it shall be replaced by new reinforcement with adequate
lapped length to remained existing reinforcement
Application of Repair Mortar – apply bond coat to concrete substrate; place each
layer of repair mortar to thickness not < 10 mm
Proof Tests – RI to conduct or direct proof tests such as hammer-tapping or other
feasible means to ascertain integrity of repair works
Recasting
Adopt recasting where there is extensive spalling, significant deterioration or high
chloride content in concrete substrate, or significant corrosion of reinforcement
Materials
New cast concrete – compressive strength of new cast concrete not inferior to
that of parent concrete
Conduct sampling of concrete and compressive test of concrete test cubes to
CS1
New reinforcement – Construction Standard CS2
Hacking – All spalled concrete to be thoroughly removed
Treatment to Reinforcement – exposed reinforcement to be wire-brushed to remove
loose mill scale and rust. Where reinforcement is corroded seriously (i.e. loss of
sectional are > 15%), it shall be replaced by new reinforcement with adequate
lapped length to remained existing reinforcement
Concreting – Ensure that concrete has been compacted adequately by using
vibrator or other suitable methods
Proof Tests – RI to conduct or direct rebound hammer test or other suitable proof
tests to ascertain quality of recast concrete
Cracks
RI may select the following methods
Brushing cement grout
Opening up of larger cracks and conducting patch repair
Pouring low viscosity polymer resin
Pressurized injection of epoxy resin
RI must ensure that repair is carried out in accordance with repair proposal.
13
CIVL6060
Table 1 -- Minimum Qualifications and Experience for RI’s Level 1 and Level 2 Rep
14
CIVL6060
15
CIVL6060
Note:
Level 1 supervision – may be performed by RI’s Level 1 representative, RI’s Level 2
representative or RI
Level 2 supervision - may be performed by RI’s Level 2 representative or RI. The RI
however must carry out the first inspection to rectification/repair works and proof tests
that are specified for Level 2 supervision.
Completion Report
Cover Page
Building name, address and lot no.
MBIS notice no.
Name, certificate of registration no. and date of expiry of registration of RI
Name, certificate of registration no. and date of expiry of registration of RC
Date of report
16
CIVL6060
NB Internal glass partitions and shopfront show windows on G/F are not windows under
MWIS, and curtain walls are subject to MBIS and not MWIS
17
CIVL6060
Service Providers
RI for MBIS – AP, RSE or registered building professionals possessing relevant work
experience in field of building construction, repair and maintenance whose name is on
the inspectors’ register kept by BD
QP for MWIS – AP, RSE, RI, RGBC or RMWC
18
CIVL6060
Duties of RI
Inspection Stage
Carry out prescribed inspection personally
Comply with BO
Notify BA of any case of emergency
Record and notify BA any unauthorized building works in the common parts and
external walls of building
The RI must
Notify BA in writing
Submit to BA proposal of DI for endorsement
Arrange for DI in accordance with endorsed proposal
(NB: RI must engage and supervise a specialist to carry out a DI)
Repair Stage
Provide proper supervision for carrying out of prescribed repair
Ensure repair materials to be used:
Are not defective and comply with BO; and
Have been mixed, prepared, applied, used, erected, constructed, placed or fixed in
manner required for such materials under BO
Ensure building is safe or has been rendered safe
Comply with BO
Notify the BA of any case of emergency
Duties of QP
Inspection Stage
Carry out prescribed inspection personally*
Comply with BO
Notify BA of any case of emergency
Repair Stage
Provide proper supervision for carrying out of prescribed repair
Ensure repair materials to be used:
Are not defective and comply with BO; and
Have been mixed, prepared, applied, used, erected, constructed, placed or fixed in
manner required for such materials under BO
Ensure windows are safe or have been rendered safe
Comply with BO
Notify the BA of any case of emergency
19
CIVL6060
NB QP who is RGBC or RMWC may also act as contractor for prescribed repair
Organization Stage
Briefing sessions arranged for owners concerned to assist them to comply with statutory
notices (BD/HAD/HKHS/URA/ICAC)
Technical advice in respect of appointment of RI, QP and RC (HKHS/URA/ICAC)
Assistance to building owners to form OC (HAD/HKHS/URA)
Subsidy of up to $3,000 per OC to be formed and technical assistance for OC formation
(HKHS/URA)
Inspection/Repair Stage
Subsidy on cost of appointment of RI for first prescribed building inspection to eligible
owners, subject to a cap (HKHS/URA)
Technical advisory services in respect of matters relating to building and window
inspection and maintenance and, where necessary, referral to relevant professional bodies
for free professional advice (HKHS/URA)
One-stop Integrated Building Maintenance Assistance Scheme (IMBAS) providing
financial assistance and technical support to building owners (HKHS/URA)
After Repair
For successful application with completion of repair works under the Common Area
Repair Works Subsidy or Common Area Repair Works Interest-free loan of the IBMAS,
a subsidy of 50% of the insurance premium for the public liability insurance / third party
risks insurance for the common parts of the building of up to $6,000 per annum for 3
consecutive years will be provided to the OC (HKHS/URA)
Building Safety Loan Scheme – Loans to owners up to $1 million for each unit of
accommodation (BD)
Common Area Repair Works Subsidy – A subsidy of up to 20-30% of the approved costs
of up to $3,000 per unit capped at $1.2 million per OC (HKHS/URA)
Common Area Repair Works Interest-free Loan – Up to $100,000 per domestic unit for
repair works in common areas provided to eligible owners (HKHS/URA)
Home Renovation Interest-free Loan – Up to $50,000 per domestic unit for interior
repair works (HKHS/URA)
Building Maintenance Grant Scheme for Elderly Owners – Up to $40,000 per unit to
eligible elderly owners (HKHS)
20