1.0 E S A. P - A: Issue Date Description Originated by Reviewed by Approved by

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

Good afternoon!

We acknowledge the receipt of your purchase order PO#27997.


Thank you again for your order and business.

ISSUE DATE DESCRIPTION ORIGINATED BY REVIEWED BY APPROVED BY

1.0 EXECUTIVE SUMMARY


A. PRE-PRODUCTION ACTIVITIES
EVENT ORIGINAL PLAN ACTUAL REMARKS
LOA – Award Date 5 Sep 11 Received
PO - Receipt Date Received
Mill Cert, 12” – Review & Approval Received
WPS/PQR - Review & Approval Received
Receipt of PO and approval
ITP - Review & Approval Received
of documents
Drawing 12” - Review & Approval Received
NDT Procedures - Review &
Received
Approval
Pipe Materials 12” – Arrival 29 Sep 11 Received

B. INSPECTION & PREPARATION


EVENT ORIGINAL PLAN ACTUAL REMARKS
Visual and Dimensional 14 Oct 11 16 of 16
Allocation of Trace Number 14 Oct 11 32 of 32
Cutting of Pipes 20 Oct 11 32 of 32
Grit Blasting – Batch No.1 11 Nov 11 4 of 4
Batch No.2 21 Nov 11 4 of 4
Pipe, Seamless, 12” x 9.5mm
Batch No.3 - 4 of 4
WT x 6m, API 5L X65 PLS2
Batch No.4 - 4 of 4
Batch No.5 - 4 of 4
Batch No.6 - 4 of 4
Batch No.7 - 4 of 4
Batch No.8 - 4 of 4

C. PRODUCTION ACTIVITIES
EVENT ORIGINAL PLAN ACTUAL REMARKS
Cladding Operations 24 Nov 11 4 of 4
NDT - PT & UT 29 Nov 11 4 of 4
Batch No. 1
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 0 of 4
NDT – PT - 0 of 4
Cladding Operations 2 Dec 11 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 2
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Batch No. 3 Cladding Operations - 4 of 4
Pipe,12” NPS x 6m NDT (PT & UT) - 4 of 4
Visual / Dimension Inspection - 4 of 4
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 4
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 5
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 6
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 7
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 8
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4

D. ADDITIONAL TEST
EVENT ORIGINAL PLAN ACTUAL REMARKS

SUPPLEMENTARY TEST Sulfide Stress Cracking Test - - Included in


12” NPS Pipe Pitting Corrosion Test – G48 - - Package 5013

E. PROGRESSIVE DELIVERY
EVENT ORIGINAL PLAN ACTUAL REMARKS
Batch No.1 15 Dec 11 19 Dec 11 Ex-works
Batch No.2 15 Dec 11 19 Dec 11 Ex-works
Batch No.3 15 Dec 11 19 Dec 11 Ex-works
Batch No.4 15 Dec 11 19 Dec 11 Ex-works
Pipe,12” NPS x 6m
Batch No.5 15 Dec 11 27 Dec 11 Ex-works
Batch No.6 15 Dec 11 27 Dec 11 Ex-works
Batch No.7 15 Dec 11 27 Dec 11 Ex-works
Batch No.8 15 Dec 11 27 Dec 11 Ex-works

2.0 PROGRESS SUMMARY


BATCH CLADDED PIPE
Marking
Dimensio
Batc Machining &
Blaste Cladd NDT nal NDT
h DESCRIPTION of Bevel- Packagin
d% ed % % Inspection %
No. End % g
%
%
1 Pipe, Seamless, 12” x 100% 100 100 100% 100% 10 0%
9.5mm WT, API 5L X65 % % 0
%
PLS2
Pipe, Seamless, 12” x 10
100 100
2 9.5mm WT, API 5L X65 100% 100% 100% 0 0%
% %
PLS2 %
Pipe, Seamless, 12” x 10
100 100
3 9.5mm WT, API 5L X65 100% 100% 100% 0 100%
% %
PLS2 %
Pipe, Seamless, 12” x
100 100 10
4 9.5mm WT, API 5L X65 100% 100% 100%% 100%
% % 0%
PLS2
Pipe, Seamless, 12” x
100 100 10
5 9.5mm WT, API 5L X65 100% 100% 100% 100%
% % 0%
PLS2
Pipe, Seamless, 12” x
100 100 10
6 9.5mm WT, API 5L X65 100% 100% 100% 100%
% % 0%
PLS2
Pipe, Seamless, 12” x
100 100 10
7 9.5mm WT, API 5L X65 100% 100% 100% 100%
% % 0%
PLS2
Pipe, Seamless, 12” x
100 100 10
8 9.5mm WT, API 5L X65 100% 100% 100% 100%
% % 0%
PLS2

3.0 PROJECT HIGHLIGHTS


THIS WEEK ACTIVITIES NEXT WEEK ACTIVITIES
Pre Production Activities: Pre Production Activities:
Inspection & Preparation: Inspection & Preparation:
Production Activities: Production Activities:
Post-Production Activities: Post-Production Activities:
1. Received for IRN for Batch No. No. 5, 6, 7 & 8 (16
lengths).
2. Batch No.5, 6, 7 & 8 (16 lengths of 12” Clad Pipe) –
Ex-works Delivery thru SASB/PTL
3. Handover of manufacturing documents of Batch No.
5, 6, 7 & 8 (16 lengths) to SASB/PTL and witness by
Velosi (Intecsea Rep.)

4.0 AREAS OF CONCERN:


ACTION
NO DESCRIPTION DATE RAISED CLOSED DATE
PARTY

1.

5.0 ADDITIONAL MATERIALS REQUIRED


QTY DATE DATE
NO DESCRIPTION REMARKS ACTION BY
REQ’RED RAISED REC’VED
1

6.0 TECHNICAL QUERY


TQ DATE
W.O DESCRIPTIONS TQ STATUS WORK STATUS
NO RAISED

7.0 REASONS FOR SLOW PROGRESS / DELAY IN COMPLETION


DATE DATE ACTION
NO DESCRIPTION REMARKS
RAISED CLOSED BY
1.

8.0 ANY OTHER BUSINESS (AOB)


DATE DATE ACTION
NO DESCRIPTION REMARKS
RAISED CLOSED BY
1

This progress report is base on submitted project schedule XX.XX.2011 and actual activities.