C. PRODUCTION ACTIVITIES
EVENT ORIGINAL PLAN ACTUAL REMARKS
Cladding Operations 24 Nov 11 4 of 4
NDT - PT & UT 29 Nov 11 4 of 4
Batch No. 1
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 0 of 4
NDT – PT - 0 of 4
Cladding Operations 2 Dec 11 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 2
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Batch No. 3 Cladding Operations - 4 of 4
Pipe,12” NPS x 6m NDT (PT & UT) - 4 of 4
Visual / Dimension Inspection - 4 of 4
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 4
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 5
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 6
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 7
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
Cladding Operations - 4 of 4
NDT (PT & UT) - 4 of 4
Batch No. 8
Visual / Dimension Inspection - 4 of 4
Pipe,12” NPS x 6m
Machining of Bevel-End - 4 of 4
NDT – PT - 4 of 4
D. ADDITIONAL TEST
EVENT ORIGINAL PLAN ACTUAL REMARKS
E. PROGRESSIVE DELIVERY
EVENT ORIGINAL PLAN ACTUAL REMARKS
Batch No.1 15 Dec 11 19 Dec 11 Ex-works
Batch No.2 15 Dec 11 19 Dec 11 Ex-works
Batch No.3 15 Dec 11 19 Dec 11 Ex-works
Batch No.4 15 Dec 11 19 Dec 11 Ex-works
Pipe,12” NPS x 6m
Batch No.5 15 Dec 11 27 Dec 11 Ex-works
Batch No.6 15 Dec 11 27 Dec 11 Ex-works
Batch No.7 15 Dec 11 27 Dec 11 Ex-works
Batch No.8 15 Dec 11 27 Dec 11 Ex-works
1.