Professional Documents
Culture Documents
Figure 4-1 PDF
Figure 4-1 PDF
This Update of the Jubail Industrial City Master Plan was completed in October, 2010 and the documents
have been in use by the Royal Commission and external stakeholders since that time. This volume is one
(1) of eleven (11) volumes comprising the Master Plan Update for the Jubail Industrial City (JIC). Volume
XI – Development Plan constitutes the integrated Development Plan for JIC for the planning period 2010
to 2030. Volume XI synthesizes and inter-relates the key findings from the preceding volumes (I to X)
into the Development Plan. The detailed technical analyses supporting the 2030 Development Plan are
contained in those other volumes. The volumes have been revised to reflect new conditions or
directions up until a freeze date of October, 2010.
The chronology for the development of the 2010 Master Plan Update is as follows:
• January, 2008 – Notice to Proceed and project inception/commencement of the Master Plan
Update for Jubail Industrial City.
• December, 2009 – Substantial completion and issuance of the volumes for use by the Royal
Commission.
• October, 2010 – Freeze date for any further revisions to the volumes. Formal adoption of the
Master Plan Update by the Royal Commission was deferred pending the completion of a study
of the fuel and feedstock allocation, which formally did not commence until April, 2010.
• April, 2012 – Royal Commission acceptance of the Updated Fuel and Feedstock Study.
• September, 2012 – Issuance of the Final Revised 2010 Master Plan Update volumes.
It is intended that the Master Plan be a“living” document that incorporates the ongoing changes in
Jubail Industrial City, which is one of the most dynamic cities in the world. Since October, 2010 a number
of significant activities have been initiated in Jubail Industrial City, as recommended in Volume XI of the
2010 Master Plan Update. Although elements of these activities have been recognized in the Final
Revised 2010 Master Plan Update dated September 2012, the detailed outcomes will only be captured
in the supplements to the 2010 Master Plan Update and in the next Master Plan Update. These activities
are at various stages of planning and development, i.e. feasibility study, planning and/ or detailed
engineering design. Examples of these activities include: the detailed planning of the new City Center;
the development of the city-wide Microsimulation Modeling Program; and the initiation of District Plans
for Reggah and the Northern Corridor Buffer Zone as well as Master Plans for area-specific locations
such as the Jubail 2 Stage 4 Light and Support Industrial Area. Of equal significance will be the potential
influence and relationship between Jubail Industrial City and the new minerals and metals city of Ras Al
Khair Industrial City (RIC) to the immediate north. As noted, upon their completion and acceptance by
the Royal Commission, these plans should be attached as supplementary documents to the 2010 Master
Plan. They will be formally incorporated into the Master Plan as part of the next Master Plan Update
program which is recommended to commence in 2017.
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
FOREWORD
In 1975, the Kingdom of Saudi Arabia completed its Second Development
Plan for economic diversification and industrialization. The central focus of
the Plan was the development of hydrocarbon-based and energy-intensive
industries, including the production, refining and manufacturing of fuels,
petrochemicals, steel and aluminium. Two cities were established to
implement the Kingdom’s industrialization aspirations, including one in Jubail
in the Eastern Province and one in Yanbu in the Western Province.
The Royal Commission for Jubail and Yanbu (RCJY) was established in 1975
by Royal Decree No. M/75 to develop the infrastructure required to transform
Jubail and Yanbu into planned industrial cities. Today, the Royal Commission
in Jubail (RCJ) continues to be responsible for planning and implementing
infrastructure plans and well integrated public services for the development
of Jubail.
JIC covers an area of approximately 763 square kilometres land area (1016
square kilometres including water), with approximately 260 square
kilometres designated for initial development. It is comprised of extensive
hydrocarbon based and energy intensive industries including primary,
secondary and support industries. Infrastructure consists of power,
telecommunication, gas, water and wastewater treatment systems, a
seawater cooling distribution system, a bulk materials handling system and
transportation facilities, including an industrial and commercial port complex
and extensive road network. At June 2010, 30 primary industries and 39
secondary industries were in operation or under design/construction in J1,
and four primary industries and 5 secondary industries were under
design/construction in J2. Over 274 light manufacturing and support
industries are also in operation or under design/construction in J1.
JIC is also home to over 105,000 residents, who live in the Community Area.
The Community Area boasts a diversity of neighbourhoods and retail areas, a
burgeoning city center and a number of high quality community services and
facilities.
Strategic Objectives:
Growth – Expand the industrial base through growth in a number of
cities and industrial output (tonnage);
Tenant Portfolio – Optimize tenant portfolio by attracting additional
investments;
Cities of Excellence – to be recognized as one of the top industrial
cities globally;
Best People – to be recognized as the employer of choice in the
Kingdom; and
Financial – to gradually develop financial sustainability and increased
efficiency.
Volume VI – Transportation
Volume VI updates the Transportation Plan (Volume IV) of the 1999 MPU.
This volume summarizes the existing and planned passenger and materials
handlings transportation systems in JIC and identifies future capital projects
required to meet 2030 demands. Volume VI also identifies transportation
programs and policies to support system objectives related to safety, public
transit, and urban design. The evacuation plan for JIC is also updated.
Volume IX – Community
Volume IX updates portions of the 1999 Volume III, Community Plan. It
outlines existing (and approved) community facilities, long term development
constraints and opportunities and recommendations for community planning
standards. This volume addresses housing, education, religion, commercial,
health care, public administration, emergency and security, cultural, social
and recreational facilities, and parks and open space.
TABLE OF CONTENTS
SECTION PAGE
1.0 INTRODUCTION ........................................................................ 1
1.1 GOALS AND OBJECTIVES ........................................................... 1
1.2 REPORT STRUCTURE ................................................................ 1
1.3 METHODOLOGY ...................................................................... 2
1.4 SIGNIFICANT CHANGES SINCE THE 1999 MPU ................................. 3
2.0 MANAGEMENT AND OPERATIONS FRAMEWORK ........................ 10
2.1 OVERVIEW OF EXISTING FRAMEWORK .......................................... 10
2.1.1 Water Based Utilities............................................... 13
2.1.2 Power and Telecom ................................................ 18
2.1.3 Solid and Hazardous Waste Management ................... 22
2.2 RECOMMENDATIONS FOR COORDINATION AND MANAGEMENT ............... 23
2.2.1 RCJ and Utility Company Inter-Relationships and
Responsibilities ................................................................. 23
2.2.2 Asset Management System ...................................... 24
2.2.3 Utility Rights-of-Way............................................... 27
3.0 SEAWATER COOLING ............................................................... 28
3.1 EXISTING SYSTEM ................................................................ 28
3.1.1 Seawater Cooling Supply (Generation)....................... 28
3.1.2 Seawater Cooling Distribution................................... 33
3.2 CURRENT EXPANSION AND REHABILITATION PLANS .......................... 36
3.2.1 Seawater Cooling Supply (Generation)....................... 36
3.2.2 Seawater Cooling Distribution................................... 37
3.3 PLANNING AND DESIGN CRITERIA .............................................. 40
3.3.1 Commentary on Existing Design Guidelines ................ 40
3.3.2 Planning Criteria Adopted for this MPU ....................... 44
3.4 SUPPLY AND DEMAND ASSESSMENT ............................................ 45
3.5 OPPORTUNITIES AND ISSUES .................................................... 51
3.5.1 Demand Management ............................................. 51
3.5.2 Supply.................................................................. 53
3.6 RECOMMENDATIONS .............................................................. 54
4.0 POTABLE WATER ..................................................................... 56
4.1 EXISTING SYSTEM ................................................................ 56
4.1.1 Potable Water Supply (Generation) ........................... 56
4.1.2 Potable Water Distribution ....................................... 61
4.2 CURRENT EXPANSION AND REHABILITATION PLANS .......................... 64
4.2.1 Potable Water Supply (Generation) ........................... 64
4.2.2 Potable Water Distribution ....................................... 65
4.3 PLANNING AND DESIGN CRITERIA .............................................. 67
4.3.1 Commentary on Existing Design Guidelines ................ 67
4.3.2 Planning Criteria Adopted for this MPU ....................... 75
LIST OF APPENDICES
Appendix A Energy Conservation, Sustainability and Alternatives
Alternative Energy Resources
Energy Conservation
Power Sustainability – International Examples
The GCC Power Grid
LIST OF TABLES
Table 2-1 JIC Management and O&M of Utilities & Infrastructure
Table 2-2 Potable Water Tariffs for Industry (2010)
Table 2-3 Potable Water Tariffs for Residential (2010)
Table 2-4 Sanitary Wastewater Tariffs for Al-Jubail Tankers (2010)
Table 2-5 Non-Industrial Customer Electricity Tariffs (2010)
Table 2-6 Small Industrial Customer Time of Use Electricity Tariffs (2010)
Table 2-7 Large Industrial Customer Time of Use Electricity Tariffs (2010)
Table 2-8 Responsibility for Telecommunications Service
Table 8-1 Summary of Pertinent Design Guidelines for Stormwater and MPU
Assessment
Table 8-2 Surface Water Recommendations
Table 9-4 Average Power Consumption Per Capita World Map (2005)
Table 9-5 Power Supply and MPU Composite Demand Forecast to 2030
Table 9-6 Consolidated Network Capacity Shortfalls
Table 9-7 Power Recommendations
LIST OF FIGURES
Figure 1-1 Jubail Regional Context
Figure 1-2 Jubail Industrial City Existing Conditions
Figure 1-3 Current Planned Land Use
Figure 9-1 Key Power Dispatching Diagram (SEC Eastern Operating Area)
Figure 9-2 Existing 230/115/34.5/13.8 KV Power Distribution
Figure 9-3 Existing115/34.5/13.8 KV Duct Bank System
Figure 9-4 Existing and Current Planned Power Distribution and Main
Substation Layout
Figure 9-5 Power Supply and MPU Composite Demand Forecast to 2030
1.0 INTRODUCTION
This volume is Volume V, Utilities and Infrastructure, of the 11-Volume JIC
2010 Master Plan Update (MPU). It was prepared as part of Contract No.
101-T14R.
1.3 Methodology
Volume V considers the original 1978 Master Plan, the 1984 MPU, the 1999
MPU, as well as reports prepared since the 1999 MPU. This Volume
summarizes and updates Volume II Industrial and Utilities Plan of the 1999
MPU and incorporates the findings of various studies that have been prepared
since the 1999 MPU. Where appropriate, the findings of these various
reports have been adapted in an effort to update and include the latest
information available. The main reference documents that were used to
update the 1999 MPU include:
Alternative Feedstock Basis for Jubail 2 – Jubail Master Plan Update by
Purvin & Gertz Inc. (PGI) and CMAI (May 2011),
Environmental Impact Study for Jubail Industrial Area by Rashid
Geotechnical & Material Engineers & Converse Consultants (August
2004),
Utilities and Services for JIC Supply and Demand information prepared
by RCJ Planning and Budget Department and RCJ Strategic Planning,
MARAFIQ 2009-2013 Supply Plan and 2011-2015 Supply Plan,
Other MARAFIQ supply and demand projections,
Reports prepared for MARAFIQ regarding SWC, IWW, SWW and TWW,
and
This was supplemented with information obtained through interviews
with RCJ staff as well as interviews with utility providers from
December 2008 through November 2011.
The utility forecasts include both industrial and community demands to give
an estimate of total utility needs in JIC. Industrial demand has generally
been split between Jubail 1 Industrial Area (J1) and Jubail 2 Industrial Area
(J2) for the following reasons:
J1 and J2 are physically separate areas;
J1 is built and mostly occupied while J2 is rapidly being constructed for
some utilities and a number of industrial sites; and
J1 and J2 are based on different planning principles regarding uses and
how utility services will be provided.
Specific assumptions used to determine demand for each utility are outlined
in each Chapter under Subsection 3.2 titled “Planning Criteria Adopted for
this MPU”.
Volume II provides detail related to the overall proposed development for JIC
identified in the 2010 MPU including buffer zone, eastern corridor, city
centre, islands, etc. The proposed land use identified in this Volume was
used in determining servicing requirements.
These are briefly described below, and a fuller description can be found in
Volumes I, II, III/IV and VIII.
For reference, Figure 1-1 illustrates the JIC regional context, Figure 1-2
illustrates the existing (build) city layout and Figure 1-3 illustrates the
current planned city land use.
The 1999 MPU, projected that the population of JIC would be around 142,000
people by 2013. The 2010 MPU population projection for 2013 is 157,500,
which is an increase of 15,500 compared to the 1999 MPU. The population
projection for 2030 is 347,000.
As described in Volume II, there are some land use changes proposed in this
MPU. The primary changes are related to development of the City Centre
and University, development of the buffer zone, and modifications to the
Eastern Corridor.
Ras Al Khair Industrial City (RIC), the new “mineral city” is located
approximately 75 km north of JIC. It is proposed to include energy intensive
developments related to aluminum and phosphate production. Similar to JIC,
RIC will be a new city that will include both industrial and community
components. The 7,980 hectare industrial component will focus on primary,
secondary and downstream industries. The planned phasing for the built out
of RIC is expected to occur between 2010 and 2040, with the first phase
between 2010 and 2020.
Within the broader context of the Regional Area, JIC will complement the
development of RIC in many areas. At the same time, the two cities will
mutually benefit from opportunities to share resources and collaborate with
each other. Over the long term, competitive elements are housing,
commercial and retail development, industrial and economic development,
talent and human resources. The synergistic elements are more complex and
include areas such as governance, the environment, industry and economic
development, regional scale health care and social services, higher
education, culture and tourism, including arts, culture and entertainment,
regional scale recreational facilities, transportation systems and
infrastructure (roads, rail, air, etc). It is currently anticipated that
approximately 47,500 will be housed in Al-Mutrafiah and as high as 75,000
ultimately in JIC.
When the 1999 MPU was prepared, J2 was addressed only in conceptual
terms. A plan was later prepared that proposed three stages for J2. In
response to changes in the market, the RCJ retained Nexant in 2007 to
prepare a Feasibility Study to evaluate the feasibility of expanding the
existing J2 by an additional 2,000 hectares (known as J2 Stage 4); prepare a
forecast of the planned industries and identify an optimal industry profile for
Changes are again proposed for J2 to reflect changes in the market. This is
primarily addressed under Volume III/IV of the MPU. Market changes have
occurred since the 1999 MPU and some of these were reflected in the 2007
Nexant Feasibility Study. Since the Nexant Study, further market changes
have occurred and these have been addressed through the Alternative
Feedstock Basis for Jubail 2 prepared by PGI/CMAI in 2011. This is primarily
addressed under Volume III/IV of the MPU and the high level servicing and
infrastructure implications are addressed in this Volume.
J2 was designed based on the assumption that there would be limited supply
of SWC (200,000 m3/hr with a possible expansion to 400,000 m3/hr). Due to
the limited quantity of SWC available for use in J2, mechanical draft cooling
towers have been suggested as the most practical and economical option for
industries to meet their cooling requirements (although there is an allowance
for limited once-through SWC). SWC canals in J1 have a constrained
capacity for expansion and thus limits were placed on the volume of SWC
available to J2, as it is fed from the J1 canals. The use of cooling towers
significantly reduces the volume of SWC required to meet industry demands
as the requirements for cooling tower make-up water rate is approximately
8.5-10%.
The RCER are being revised in 2009 and 2010 (though not yet released as of
September, 2010), providing an update to the 2004 RCER. RCER are
comparable to prevailing international environmental norms to regulate the
industrial activities. The major changes between the 1999 RCER and 2004
RCER can be summarized as follows:
The 2004 RCJ Environmental Regulation System has enhanced the
previous regulations through the introduction of the two new
requirements titled: Environmental Consent to Construct (ECC) and
Environmental Permit to Operate (EPO). The new two requirements
85 95
Ras Al-Khair
Industrial Area
85
Abu Ali
Island
Airport
King Fahd
Industrial Port
Al-
Saudi
ARAMCO Jubail
Jubail
Commercial
Port
Power and
Desalination Plant
Ras Al-Ghar
LPG
Export
Terminal
613
Ju' Aymah
ARAMC
NGL Plant
614
Safwa
King Fahd
International
Airport Najmah
40 Qatif
Tarut
Ras Tanura
Anik
Dammam
Ghunan
10
Abqaiq Dhahran
Al
h Khobar
iyad
To R Dhahran
Airport
To use
Ca
Ba wa
hra y
in
JUBAIL REGIONAL AREA FUTURE INDUSTRIAL CITY JUBAIL INDUSTRIAL CITY BOUNDARY
BASE DATA PROVIDED BY MAP PROJECTION: AIN EL ABD UTM ZONE 39N
THE ROYAL COMMISSION FOR JUBAIL AND YANBU. PROJECT #: 078523
STATUS: FINAL
0 2.5 5 10 km
FILE LOCATION: G:\GIS\078523 JUBAIL MP SAUDI ARABIA\ DATE: 12/20/11
GIS DATA\MXDS\MP FIGURES - MXD'S\
JUBAIL INDUSTRIAL CITY
Al-Batinah MASTER PLAN UPDATE
Island
FIGURE 1-2
JUBAIL INDUSTRIAL CITY
EXISTING CONDITIONS
Al-Gurmah
Island MAJOR ROADS
TS7
POST SECONDARY INSTITUTION
T2
BUFFER ZONE
NATURAL ENVIRONMENTAL MONITORING
Saudi Ele
Kharsania
TS4 AREA
Al-Fanateer
Al-Deffi District GOVERNMENT RESERVE
Railroad RO
ctric Comp
District
h Ras Tanu
PORT/AIRPORT AREA
Community Area Al-Fanateer UTILITY & INFRASTRUCTURE
Island
an
W
ra ROW
y ROW
T3
JUBAIL INDUSTRIAL CITY BOUNDARY
Al-Kahleej
District
TS6 T100
T6
Al-Huwaylat
Al-Huwaylat Island
District
Al-Lulu
T138 District
Al-Shati
District
Al-Bahar
District
Jubail 1 Industrial Area A r a b i a n G u l f
T218
TS1
T121
T21
8
T272
T274
TS King Fahd
7 Industrial Port
3
TS
T1
0 3
Jubail
Commercial
1
TS
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
MOT
613
JUBAIL INDUSTRIAL CITY
Al-Batinah MASTER PLAN UPDATE
Island
Community Area
FIGURE 1-3
CURRENT PLANNED LAND USE
TS 7
District COMMUNITY AREA WITHOUT APPROVED
T2 PLANS
Saudi Elec
Kh arsa nia
TS 4
Al-Fanateer INDUSTRIAL AREA BUILT
District
Railroad RO
Al-Deffi FUTURE INDUSTRIAL AREA
h Ra s Tanu
tric Com pa
District
Al-Fasil Al-Mutrafiah POST SECONDARY INSTITUTION
District
Al-Fanateer
District
Island
W
BUFFER ZONE
ra ROW
ny RO W
T3
NATURAL ENVIRONMENTAL MONITORING
Al-Kahleej AREA
District
GOVERNMENT RESERVE
Al-Huwaylat
T6
TS6 T100 PORT/AIRPORT AREA
Al-Huwaylat Island
District UTILITY & INFRASTRUCTURE
T295
District
T251
Al-Bahar
District
Jubail 2 Industrial Area Jubail 1 Industrial Area Ar a b i a n G u l f
T198
T218
T218
T241
T195
T315
T335
T121
TS1
TS9
TS3
T2 1
8
T272
T2 74
TS8
TS King Fahd
7 Industrial Port
3
TS
T1
0 3
Jubail
Commercial
1
TS
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
MOT
6 13
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
In 2010 this structure was modified by moving from DG and DDG to a more
corporate structure with a Chief Executive Officer (CEO) and General Managers
(GM). The system is now such that there are eight GM’s responsible as
follows:
GM for Technical Affairs - responsible for the following departments;
Urban Planning, Engineering, Construction, Project Management, and
Environmental Control.
GM for O&M - responsible for the following departments; General
Utilities, Buildings, Landscaping and Irrigation, Sanitation, and Roads.
GM for Public Services - responsible for the following departments;
Healthcare Programs, General Education Services, Social Services, and
Property.
GM for Strategic Planning and Investment Development - responsible for
the following departments; Strategic Planning and Performance
Management, Economic Planning, Investment Development, Tenant
Relations, and Cluster Support.
GM for Finance - responsible for the following departments; Finance and
Budgeting, Financial Accounting and Insurance.
GM for Human Resources - responsible for the following departments;
Manpower Planning and recruitment, Manpower Development, Employee
Services, Benefits and Compensation and Organization Excellence.
GM for Support Services - responsible for the following departments;
Information Technology, Legal Affairs, Supply Management, Industrial
Security and Safety, Administrative Services, Transportation and
Equipment Design.
This means that five of the eight GM’s oversee a department that can directly
impact the requirements for, and provision of, utilities and infrastructure. In
addition, there is a GM of the RIC Program.
Table 2-1 outlines the specific areas of responsibility for the provision of
utilities/infrastructure in JIC.
Table 2-1
JIC Management and O&M of Utilities & Infrastructure
ACTIVITY
Development Approvals
Investment Planning
Enforcement
RESPONSIBLE PARTY
ACTIVITY
Development Approvals
Investment Planning
Enforcement
RESPONSIBLE PARTY
There are many sectors and departments within RCJ that have interactive
responsibilities with utilities and infrastructure development that requires on-
going and effective coordination to ensure that the system works in an
economically sustainable manner and meets the needs of JIC. This is
discussed further under Section2.2.
The Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) was
established under the Royal Decree M 29 dated 18th October, 2000. The
Decree was issued pursuant to Council of Ministers Decision No. 171 dated
October 9, 2000, based on COM Decision No. 57 dated July 11, 1999.
MARAFIQ was established as a private limited company created from within the
RCJY. The separation was made with the objective that MARAFIQ start
operating as a commercial enterprise and eventually become a public limited
company to achieve sustained viable utility operations.
The Council of Ministers approved the formation of the company that will run
the project facilities of MARAFIQ’s IWPP as Jubail Water and Power Company
(JWAP). JWAP will build, own, operate and then transfer the plant to MARAFIQ
after a period of 20 years from the start of commercial operations. The new
company is owned jointly by MARAFIQ, the Suez Consortium through its
holding company, SGA MARAFIQ Holdings WLL, the Public Investment Fund
and Saudi Electric Company (SEC). JWAP has assumed responsibility for the
development, financing, construction, operation and maintenance (O&M) of the
power generation and water desalination plant.
“The report on the special meeting held between the Royal Commission for
Jubail & Yanbu and “MARAFIQ” Company for determining the tasks and
responsibilities” (May 18, 2002) was used for reference regarding clarification
of MARAFIQ and RCJ responsibilities. This report indicated that for new
industrial parks, RCJ is required to perform the development works in these
areas to ensure attracting as many industrial investors as possible, as this will
result in boosting the country’s economy. This is due to the possible increase
of utility tariffs on industrial investors resulting from the costs MARAFIQ will
incur for power and water based infrastructure development. Currently the
MARAFIQ Board of Directors is responsible for setting tariffs; however a new
independent regulator is anticipated to be announced soon by the
Government.
MARAFIQ does not have its own standards or guidelines and currently most of
their projects use RCJ standards. A budget was requested and approved in
2009 for development of engineering guidelines for Jubail & Yanbu and the
contract was awarded in 2010. When available, these standards will need to
be reviewed for consistency with RCJ standards, and a combined review done
to identify any modifications required to either of these guidelines.
MARAFIQ is responsible for the JIC SWC system, which provides seawater for
non-contact process cooling to primary industries. Heavy industries in JIC
require large volumes of cooling water as part of their operations and they are
supplied with filtered and chlorinated seawater. The system is comprised of
dredged intake channels, pumping stations (PSs), and a gravity distribution
canal connected to the J1 primary industry customers through underground
lateral pipes and the return water flows by gravity back to the sea.
MARAFIQ is responsible for the production and delivery of PW. This includes
all works for the PW system operations up to the end user limits in the
industrial areas, as well as all PW system operations up to the areas to be
developed in the community area. Development works within the
sector/neighbourhood or block and connecting to the MARAFIQ PW system will
be the responsibility of the RCJ or its investors, however O&M are the
responsibility of MARAFIQ. When developing new areas, MARAFIQ has
indicated that the RCJ and its investors shall use sleeves necessary for the
future utility service connections to avoid road cutting in the future.
There were previously two main sources of PW supply to the city being
desalinated water from the Saline Water Conversion Corporation's (SWCC)
Desalination Plant and MARAFIQ’s (formerly the Royal Commission's)
Desalination Plants I and II. In July 2008, Saudi Arabia announced the
privatization of the SWCC. SWCC is a Saudi government corporation
responsible for desalinating sea water that started its works by constructing
single purpose plants (to produce PW only) and later dual purpose plants (to
produce PW and power). Water supply from this plant ceased in 2009/2010
upon commissioning of the IWPP facility. The secondary PW source was
MARAFIQ’s (formerly the RCJ's) Desalination Plants I and II, which use MSF.
Desalination Plant I was retired in 2009 and Desalination Plant II was retired in
2010 after the commissioning of IWPP facility.
MARAFIQ has partnered with IWPP for setting up a combined cycle plant for
production of power and water in JIC. The contract for the IWPP was awarded
in January 2007. The combined power generation and desalination plant will
have a capacity of 2,750 Megawatt of power and 800,000 m3/day of water.
The IWPP uses Multi Effect Desalination (MED) technology. The first power
block and desalination units came on-stream towards in 2009 and the IWPP
was fully commissioned in early 2010, however the production is limited due to
a delay in the SWCC PW line from the IWPP to the Eastern Province which will
deliver 500,000 m3/day to that system. JIC is receiving 300,000 m3/day.
MARAFIQ is also responsible for ensuring that water quality meets stringent
Environmental Standards and complies with the World Health Organization's
Guidelines for Drinking Water Quality. MARAFIQ assures delivery at standard
quality and pressure, and for each user, a specified maximum flow rate
through a single connection point.
MARAFIQ is responsible for billings for the use of these systems, which are
based on consumption of PW and there are no separate charges for disposal of
wastewater.
Table 2-2 shows current tariffs for PW (effective January 10, 2010).
Table 2-2
Potable Water Tariffs for Industry (2010)
This is a change in the way PW was previously billed with rates varying based
on monthly consumption.
Table 2-3
Potable Water Tariffs for Residential (2010)
The 2010 tariffs were the same as those stipulated in 2008 and 1999.
As indicated above, MARAFIQ is responsible for billings for the use of these
systems, and the current tariff is 2.60 SR/m3, an increase of 10% from 2008.
As indicated above, MARAFIQ is responsible for billings for the use of these
systems, which are based on consumption of PW and there are no separate
charges for collection and treatment of wastewater for the community. The
current tariff for industry is 3.58 SR/m3, an increase of 10% from 2008.
Rates for disposal of SWW from Al-Jubail were instituted in 2010. The rate
being 1.61 SR/m3 up to the award of contract for the SWTP expansion and
1.94 SR/m3 after that date. For SWW received from Al-Jubail through tankers,
costs are per tanker based on tanker capacity as follows:
Table 2-4
Sanitary Wastewater Tariffs for Al-Jubail Tankers (2010)
Some of the TWW from both the SWTP 9 and IWTP 8 plants are used for
irrigation and industrial use. All TWW works (i.e. irrigation pipeline network)
from outside of treatment plant fences up to landscaping sites is the
responsibility of the RCJ. MARAFIQ’s responsibility ends at the boundary limit
of the SWTP 9 and IWTP 8 properties.
The guidelines for TWW and irrigation water are maintained as per the Jubail
Management Procedures (JMP) prepared by the RCJ. The allocation of use of
TWW and irrigation is managed by the RCJ.
The current tariffs for TWW (effective January 10, 2010) is 1.65 SR/m3,
whether provided through the pipeline network or truck fill. This is a 10%
increase over 2008. The rates in 2008 and 1999 were the same. A new rate
was introduced in 2010 of 0.60 SR/m3 for RCJ use.
RCJ is responsible for approval of the surface water drainage systems. In the
community, drainage is via a storm sewer system within the road rights-of-
way (ROW). The design of these systems is completed through the detailed
block design per the approved RCJ Guidelines.
Industrial sites are to be graded to effectively drain each block, and this is the
responsibility of the developer. Internally on the industrial site, rainwater
must be impounded, and it is found to be contaminated, it must receive
treatment before being discharged to the ditches. The grading allows flow into
secondary drainage ditches surrounding each lot. The overall system external
to the industrial sites is approved and maintained by the RCJ.
Power
In early 2000, the Saudi Electricity Company (SEC) was formed by virtue of a
Cabinet Order (No. 169 Dated 11/08/1419H), which stipulated the merger of
all Saudi electricity companies in the Central, Eastern, Western and Southern
Regions in addition to the ten small companies operating in the north of the
Kingdom as well as all other electricity operations managed by the General
Electricity Corporation. The Saudi Consolidated Electric Company (SCECO)
forms part of the SEC.
The RCJ is in the practice of constructing distribution facilities which are then
taken over by SEC for care, custody and control after acceptance although this
is contrary to the RCJ/SEC Agreement currently in effect. RCJ has, out of
necessity to maintain schedules of power delivery to customers in a rapidly
developing JIC has installed the distribution facilities themselves. Users are
subject to SEC's established connection fee or actual capital cost, whichever is
higher.
MARAFIQ has partnered with IWPP for setting up of the IWPP combined cycle
plant for production of power and water in JIC. The combined power
generation and desalination plant will have a capacity of 2,750 MW of power.
The IWPP was fully commissioned in early 2010. MARAFIQ and SEC have
agreed on the power generated by the IWPP and SEC is purchasing the power
from the IWPP and transmitting it into the network.
Generally, supplies to all users are metered. SEC charges for consumption
based on Kingdom decreed tariff rates. Industrial users execute Bulk Power
Agreements with SEC upon prior RCJ approval. Table 2-5 shows current tariffs
for electricity (established January 2010).
Table 2-5
Non-Industrial Customer Electricity Tariffs (2010)
There are different charges for small and large industrial customers based on
seasonal and time of use meters. The time of use rates are outlined in Tables
2-6 and 2-7 below. The seasonal tariff for small industrial customers (having a
contracted load up to 1,000 KVA) with electro-mechanical meters is 0.12
SR/kWh from October 1st to April 30th and 0.15 SR/kWh for the rest of the
year. For seasonal tariff for large industrial customers (having a contracted
load above 1,000 KVA) with electro-mechanical meters is 0.14 SR/kWh from
October 1st to April 30th and 0.15 SR/kWh for the rest of the year.
Table 2-6
Small Industrial Customer Time of Use Electricity Tariffs (2010)
Table 2-7
Large Industrial Customer Time of Use Electricity Tariffs (2010)
Telecommunications
All telephone services and Digital Subscriber Lines (DSL) are coming from Al
Khober exchange and Lasilki exchange. JIC has its own exchanges. All data
services are provided by the RCJ. All the existing telephone and DSL services
are provided by STC. Mobile services are provided by STC (Al Jawal), Ethihad
Etisalat (Mobily) and ZAIN. In future telephone and DSL services shall be
provided by STC and Atheeb company. Table 2-8 shows the responsibility for
design and construction of facilities expansion. Telecom charges are in
accordance with published STC tariffs.
Table 2-8
Responsibility for Telecommunications Service
The collection, transfer, and disposal of solid wastes generated within the
residential and industrial areas of JIC are conducted by a solid waste
management contractor under the direct supervision of the RCJ. The landfill
contractor ensures that where possible, waste recovery and recycling is
actually promoted, and that wastes are separated into their appropriate
classes for disposal. Solid waste trucks are weighed as they enter the landfill
and this is the method of monitoring the volumes processed. The RCJ
Sanitation Department has an active presence at the landfill site to promptly
respond to any of the contractor's challenges. The contractor has access to all
of the RCJ provided solid waste management facilities, plant, and equipment
administered by the RCJ Department of Sanitation.
Municipal solid waste disposal (refuse disposal) has no charge. Solid industrial
waste and hazardous waste charges are in accordance with BeeA’h and EDCO
commercial tariffs.
In recent years there have been improvements made to the coordination and
management of utilities and infrastructure, including modifications within RCJ
and MARAFIQ. In particular, some of the new fee structures being used will
help with cost recovery and encouraging better use of resources. However, as
is outlined above, the responsibility for the provision of each utility is still
spread over many departments within, and external to, the RCJ. As such,
coordination to ensure that planning, construction, and O&M of the utilities is
of paramount importance.
The RCJ’s core responsibility is to ensure timely delivery of all utilities and
infrastructure in JIC to match the pace of development through their own
initiative or through the mechanism of agreements with utility companies. It is
imperative that RCJ communications should always follow this principle .
Accordingly RCJ must supply short and long term JIC requirements to Utility
companies and those companies , in return, must provide the RCJ with their
long-term plans of expansion and individual capital works projects. Where
policy matters are an issue , communication with the utility companies should
be from the highest level of the CEO.
Tariffs
The revisions to tariffs instituted in 2010 will generally assist in better cost
recovery as well as encouraging conservation of resources. In particular,
instituting time of day rates for power consumption by industrial users was an
appropriate modifications.
We recommend that instituting time of day rates for power consumption non-
industrial users also be considered. It is also recommended that rates be
reviewed semi-annually (or at least annually) to ensure that cost recovery is
achieved. Further we recommend that tariffs for utilities be discussed as part
of the liaison committee activities.
Many governments use asset management that include the following asset
groups:
Transportation
Structures
Sewer network
Water network
Pumping stations
Buildings and facilities
Parks and recreation assets
Often as the GIS systems are operated and maintained with information
regarding parks and recreation assets as well as institutional uses (mosques,
schools, libraries, hospitals, etc), while the as-built drawings of infrastructure
projects are maintained in the Engineering department and the roads
department may have other information on transportation assets. In addition,
this information is available in a combination of hard copy drawings, excel
spreadsheets, CAD, GIS or in some cases there are large data gaps.
Figure 2-1
Geographic Information Systems Model for Optimization
OPTIMIZED
Capital Plan
Development
Asset Management
Capital Planning
Infrastructure Maintenance
As-Built Data
Collection
GIS
Preliminary Design
Preliminary
Design
Internal Clients
External Clients
Detailed Design/
Contact
Documentation
Source: GIS Systems and As-Built Data, 2008
The design criteria used for the design of utilities has generally been done on a
road by road basis, rather than instituting a general standard based on, for
example, road classification. Basing ROW widths on road classifications is
typical in many international settings.
Some typical international ROW’s (which include both road and utility) based
on road hierarchy would be as follows:
Rear Lane – 6-8 m
Local – 15-25 m
Collector – 20-36 m
Arterial – 35-50 m
The 1978 MP shows typical cross sections for ROW’s (including road and utility)
of:
Parking access – 14 m
Local/Residential – 18.6 m plus 7 m for stormwater drainage
Collector/Corniche – 55.2 m
Freeway/Expressway – 80.8 m
Designed ROWs for higher level roads in Mardumah range from 81 m to 121 m
plus 40 to 80 m for storm drainage.
In JIC, land restrictions have not been a concern in the past and this has lead
to very large ROW’s (as shown above), typically with the utility ROW’s
paralleling each side of a road ROW. While this does make maintenance of
utilities easier and has less impact on traffic as roads do not often need to be
impacted for utility maintenance, this leads to very large ROW’s that impact
urban design. MARAFIQ has indicated that when developing new areas that
the RCJ and its investors shall use sleeves necessary for the future utility
service connections to avoid road cutting in the future.
The SWC system is a once through system to supply seawater for cooling
purpose to primary industries and a limited number of secondary industries in
J1. Since SWC serves various primary industries with large volumes of non-
contact cooling water, it is a vital utility for primary industries. J2 will adopt
the use of cooling towers. In J1 in 2010, there are many industries also
utilizing large cooling towers. Industries in J1 have been advised to build
cooling towers for their expansion projects and new projects.
SWC users are required to return their discharge water free from pollution and
at a temperature no higher than 10 degrees Celsius above the inlet
temperature. Users are responsible for the cooling and distribution systems
within their premises and the methods for meeting the discharge temperature
requirements.
Major equipment/systems include, but are not limited to, the dredged intake
channel; coarse trash screens, drum screens and wash water system; main
seawater pumps; canal distribution system and auxiliary systems including
chlorination plant and dosing systems; electrical systems; central control
room; distribution control system (DCS); gantry cranes; gas turbines;
outstations for each industry; and cathodic protection systems.
Figure 3-2
Schematic Diagram of Seawater Cooling System
Source: "Supply Plan 2009-2013", MARAFIQ Facilities Planning Department (October 29, 2008)
An intake channel has been dredged from the shoreline and extends 2.5 km
seaward in an easterly direction from the SWC pump stations (PS) 1 and 2, to
a point where the sea bed level is approximately 4 m below the lowest
astronomical tide. The channel is of constant depth with a bottom width of
between 60 m and 190 m.
It is bounded by the King Fahd Industrial Port (KFIP) causeway to the south
and by break water to the north. The capacity of the channel is such that, at
low water level, during periods of maximum water demand, the velocity of the
water is no more than 0.3 m/sec. The dredged portion is designed to maintain
a seawater flow of about 300 m3/sec, without excessive silt migration. As the
inflow rate increases, the channel flow rate velocity will increase in the same
proportion. Figure 3-3 (Seawater Cooling Intake Facilities) illustrates the
current intake facilities.
The PSs and distribution facilities are connected to the Central Control Room
through a DCS and System Control and Data Analysis (SCADA) system. The
SCADA system has been upgraded since the 1999 MPU. The DCS was installed
to monitor and control the PS facilities.
T3
District
Airport Area
O&M Al-Khaleej
Centre District
Evap. Jubail
Stn. Industrial
RC College
WTP #3 T6 HQ
TS6 T100
T106
T112
Al-Huwaylat
Al-Huwaylat
Block E-South District
Stage 3 and 4
T113
Stg.2 St. 1 Block N
Island
SWTP Block J-South
T289
Stormwater Strm.W SWTP #9 Storm- T120
(Exp.)
Holding Pond H.Pond water NWPS
Pond
T1 0
T130
1
Al-
Lulu
District
T138 T138
T147
T148
T150
T154
Kh a
Al-
Ar a b i a n
Shati
T295
rsa
Sa u
T162 District
Gu l f
niah
di E
le ct
R as
O&S
T263
T251
T241
T195
Ra il
ric
Centre
Jubail 1
Ta n
T174
C om
ro a
u
Jubail 2 Industrial Area
ra R
dR
pan
Industrial Area
OW
OW
yR
T184
OW
Block P Block K Block F
T259
T143
T163
T198
CANAL 3
Sanitary T204 IWPP
T289
Landfill Fac.
IWTP #8
T223
T218
Desal.
T218 #2
Pump House
For Jubail 2 CANAL 1
CANAL 2 SWC
RC Fac.
T230
CANAL 4
Scap
Fac.
T2 1
8
TS9
Sanitary
T315
T335
TS1
Landfill
T241
T121
T195
T183
T161
T261
Block Q Block L Block G
TS3
T2 74
MOT
BeeA'h T272
85
T2 74
3
TS
PUMP HOUSE
EXISTING INDUSTRIAL, MAJOR ROADS
JUBAIL INDUSTRIAL CITY
INVERTED SIPHONS AND LATERALS PROPOSED INDUSTRIAL, MAJOR ROADS
MASTER PLAN UPDATE
SEAWATER COOLING CANAL PRIMARY INDUSTRY SERVICING AREA
BASE DATA PROVIDED BY MAP PROJECTION: AIN EL ABD UTM ZONE 39N
THE ROYAL COMMISSION FOR JUBAIL AND YANBU. PROJECT #: 078523
STATUS: FINAL
0 0.5 1 2 km FILE LOCATION: G:\GIS\078523 JUBAIL MP SAUDI ARABIA\ DATE: 12/21/11
GIS DATA\MXDS\MP FIGURES - MXD'S\
Security
Fence
JUBAIL INDUSTRIAL CITY
MASTER PLAN UPDATE
FIGURE 3-3
SEAWATER COOLING INTAKE
FACILITIES
8 Inch Diameter Pipe ARAMCO
10 Inch Diameter Pipe Gas
32 Inch Diameter Pipe Pipeline
New Pumping
Station 2
Complex
Supply Channel
Diffusers Drainage Conduit New Diffusers New Ramp and Bridge
to Supply Diffusers
Workshop
EL - 4.52
Seawall
Seawall
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
Two oil boom anchoring bollards are fitted at opposite sides of the intake
channel on the breakwater and industrial causeway to protect SWC from an oil
spillage. The coarse trash screen is designed to prevent large pieces of
submerged debris from entering the drum screens. There are 7 drum screens
each in the upstream of main seawater pumps.
MARAFIQ filters and chlorinates the water in a specially designed water intake
and PS before supplying it to the industries. To prevent algal growth, a free
chlorine residual is maintained in the water by continual and intermittent shock
dosing with sodium hypochlorite. Chlorine dioxide, a more powerful
disinfection technology, has been used on a trial basis and the decision to
install a permanent injection system is pending.
Two seawater PSs are located on the east side of J1. They have the capacity
to supply a total of 1,245,600 m3/hr of SWC (with no spare pumps). SWC PS
1 has a total capacity of 565,200 m3/hour, while SWC PS 2 has a total capacity
of 680,400 m3/hr. The capacity for summer operation (24 pumps operating,
four spare pumps that are kept under maintenance at all times) is 1,062,720
m3/hr. As it is MARAFIQ’s current O&M philosophy to maintain four pumps
under maintenance at all times the winter operation capacity is the same
(although the demand is reduced by 10-15% in the winter) with 24 pumps
operating and four spare pumps.
Table 3-1
Existing Seawater Cooling Major Auxiliary Systems
Cooling water is drawn from and returned to the seawater canals at off take
and return structures that are built into the canal dividing walls. The off take
and return structures consist of a series of chambers, each of which connects
with two adjacent compartments by two openings which are fitted with sluice
gates.
The off take and return structures are connected to the users plot boundary by
laterals. The laterals, which are of 2.0 m or 1.6 m diameter, extend beneath
the canal and its embankment through a flow measurement chamber where
each pipeline incorporates ultrasonic flow measurement instrumentation.
Canals
SWC is currently supplied to industries in J1 via a main canal (canal 1) and two
branches (canal 2 and canal 3). The canal network is approximately 12 km
long. The main seawater pumps discharge the water through underground
discharge mains to weir gates at supply head works into the canal.
The canal sections are connected by inverted siphons. Siphons 1, 2, and 4 are
3.0 meters in diameter and Siphon 3 is 3.6 metres in diameter. Siphon 1
connects canal 1 and 2. Siphon 2 interconnects canal 1 and 3 South. Siphon 3
connects canal 3 South and 3 North. The siphons are designed to function at
an adequate level of service even when one pipe is out of service.
FIGURE 3-4
RETURN SUPPLY/RETURN SUPPLY TYPICAL SEAWATER
COMPARTMENT COMPARTMENT COMPARTMENT COOLING CANAL SECTION
A B C
ACCESS ROAD
D E
ROUGH GRADE
1
R. Flow Rate S/R. Flow Rate S. Flow Rate
2.25
970,000 m³/hr 840,000 m³/hr 840,000 m³/hr
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
The single canal capacity for supply and supply/return compartment is 840,000
m3/hr as per hydraulic model and return canal capacity was 970,000 m3/hr,
increasing to 1,100,000 m3/hr in 2010. The velocity of flow in the
compartment is designed for 1.5 m/sec. The 2010 construction of the
Seawater Return Bypass line increased the return canal capacity of which
130,000 m3/hr is the allocation from Petrokemya.
The demand for SWC by secondary industries has failed to develop, primarily
due to this proving uneconomical for the small volumes needed.
Laterals
Laterals are installed to supply seawater from the canal to the users for cooling
and to return the hot used water back to the canal. Laterals are classified in
three categories based on their current status as active laterals, non-active
laterals and future laterals.
Laterals are constructed in small lengths and generally constructed in two sizes
(1.6 m and 2.0 m diameter) in J1. The size and number of laterals in any one
installation is selected to limit the mean velocity of flow to 2.5 m/sec. This
includes outage of one supply and one return lateral for maintenance at any
point of time.
The All Time Allocation (ATA) for each industry is determined by the User
Utility Agreement (UUA) between MARAFIQ and the user. The laterals are
designed to the contractual amount.
There are no current expansion plans for SWC supply (generation) other than
dredging of the intake channel as required. A report prepared by Jacobs for
MARAFIQ titled “Additional Feasibility Activities Addendum Report” (dated
August 2010) also recommends upgrading PS 1 by replacing six of the 10.3
m3/sec pumps with six new 13.5 m3/sec pumps, but this will be included in
SWC debottlenecking major project. The limiting factor for the expansion of of
PS 1 is to maintain an intake velocity of 0.3 m/sec. A greater velocity will
require additional dredging in the intake channel.
In June 2006, BOSS International prepared two reports for MARAFIQ regarding
the JIC SWC system. The first report titled “Hydraulic and Thermal Modeling of
the Seawater Cooling System” which resulted in the creation of a RiverCAD XP
model that can be used to predict water surface profiles in the supply and
return canals and temperature in the return canal. The second report was
titled “Ultimate Capacity Simulation and Recommendations of the Seawater
Cooling System”. This report is a continuation of the conceptual study and
hydraulic and thermal modeling of the SWC system. The report looked at
various options for the enhancement of the flow carrying capacity of the SWC
system.
The report indicated that based on technical feasibility “a 1.4 Mm3/hr flow rate
through the supply and return canals could be best achieved by implementing
one 0.32 Mm3/hr capacity cooling tower on Return Canal 2 near Siphon 1 and
one 0.23 Mm3/hr capacity cooling tower on Return Canal 3 near Siphon
2…...BOSS International used the supply canal plus the supply/return canal in
supply mode for Canal 1 and regular operation of the supply and return canals
for Canal 2 and Canal 3 to simulate the ultimate flow carrying capacity of the
SWC system.” This proposal did not move forward and RCJ indicated that
there is not an appropriate site available near the SWC canals that did not
have other potential conflicts with other utilities, including power lines. As
such, in the interim MARAFIQ proposes the following to mitigate the gap
between supply-demand, as identified in the MARAFIQ Supply Plan (2009 –
2013):
Conduct feasibility studies regarding the removal of siphon 1 to remove
the bottleneck in supply system; identifying and removing bottlenecks in
siphon 4 in return water system; and reducing the hydraulic losses in
the canal system.
Carry out siphon 1 removal and siphon 4 modification as per
recommendations from feasibility study.
Carry out canal structure modifications as per recommendations from
feasibility study.
MARAFIQ must obtain approvals from RCJ for the proposed modifications to
the SWC network and moreover must justify that there is or will be a shortage
in SWC supply. It is anticipated that the removal of siphon 1 and 4 will
increase the supply compartment capacity and the return compartment
capacity each to 1,222,000 m3/hr.
The presentation on recommendations from the Jacobs Study was given to the
RCJ Engineering and Environmental Departments in 2010.
Table 3-2 outlines the current proposed expansions to the SWC supply and
return compartment capacities.
Table 3-2
Seawater Cooling Canal Existing Capacity and Proposed Expansions
The major difference between J2 and the existing J1 is the cooling system. J1
relies on "once through" cooling system by circulating seawater and J2 will
employ an evaporative cooling system using cooling towers. Additionally, J2
seawater supply will use a pressurized system while J1 is a gravity flow
system. The infrastructure for bringing water to the site will be in-place before
industries move in and the cooling towers would be built by the industries. J2
SWC PS will be supplied water from Canal 2 by gravity and then it will be
pumped to J2 through a pipeline network. SWC will be distributed to end-
users via a network of pipelines that extend west across the KRT corridor.
The main supply laterals to J2 are 4 m in diameter, with subsequent
distribution pipes of various sizes.
The J2 SWC PS was initially equipped with three 50,000 m3/hr pumps, capable
of expanding to six 50,000 m3/hr pumps for the supply of 200,000 m3/hr of
SWC based on four pumps operating while the other two will be on standby.
Currently the capacity is 100,000 m3/hr based on two units operating and one
on standby. The construction of the SWC PS and pressurized pipe network to
J2, Stages 1 and 2 has been completed by the RCJ. The J2 SWC distribution
system is a full reticulation network. This a major difference between J1 and J2
as unused capacity in the fixed speed pumps will be returned without being
used which reduces system efficiency as the current arrangement allows only
for pumping in 50,000 m3/hr increments.
MARAFIQ also intends to construct a local chlorination plant at the end of canal
1 which will produce hypochlorite solution with 2,000 PPM chlorine to dose in
the canal before siphons 2 and 3 in order to control bio-growth and algae
formation in these canals.
Figure 3-5 (Current Planned Seawater Cooling System) illustrates the current
proposed expansions to the SWC distribution network.
Overall, the RCJ criteria outlined with respect to the SWC has been adequately
tested in the systems installed to date. Table 3-3 summarizes assessment of
the relevant criteria under 2.03 subsections A (General) and F (Cooling Water
Criteria).
T3
District
Airport Area
O&M Al-Khaleej
Centre District
Evap. Jubail
Stn. Industrial
RC College
WTP #3 T6 HQ
TS6 T100
T106
T112
Al-Huwaylat
Block E-South District
Stage 3 and 4 Stg.2 Al-Huwaylat
T113
St. 1 Block N
SWTP Block J-South
T289
Stormwater Strm.W SWTP #9 Storm- T120
Holding Pond H.Pond
(Exp.)
water NWPS Island
Pond
T10
T130
1
Al-
Lulu
District
T138
T147
T148
T150
T154
Kha
Al-
A r a b i a n
Shati
T295
r
Sau
san
T162 District
G u l f
ia
d
i E le
hR
as T
O&S
ctr ic
T263
T251
T241
T195
Rail
Centre
Jubail 1 T174
anu
Com
ro
Industrial Area
ad R
Jubail 2
ra R
pan
Industrial Area
OW
OW
yR
T184
OW
Block P Block K Block F
T259
T143
T163
T198
CANAL 3
Sanitary T204 IWPP
T289
Landfill Fac.
IWTP #8
T223
Desal.
T218 #2
Pump House
For Jubail 2 CANAL 1
CANAL 2 SWC
RC Fac.
T230
CA NAL 4
Scap
Fac.
T2 1
8
Sanitary
TS1
Landfill
T241
T121
T261
T183
T161
Block L Block G
T195
TS3
Block Q
T2 74
MOT
BeeA'h
BeeA'h T272
85
3
TS
PUMP HOUSE EXISTING INDUSTRIAL, MAJOR ROADS SECONDARY INDUSTRY SERVICING AREA
JUBAIL INDUSTRIAL CITY
EXISTING SEAWATER COOLING CANAL PROPOSED INDUSTRIAL, MAJOR ROADS FUTURE SECONDARY INDUSTRY SERVICING AREA
MASTER PLAN UPDATE
FUTURE SEAWATER COOLING PRIMARY INDUSTRY SERVICING AREA SUPPORT INDUSTRY/NORTHERN CORRIDOR SERVICING AREA
INVERTED SIPHONS AND LATERALS FUTURE PRIMARY INDUSTRY SERVICING AREA FUTURE SUPPORT INDUSTRY SERVICING AREA
BASE DATA PROVIDED BY MAP PROJECTION: AIN EL ABD UTM ZONE 39N
THE ROYAL COMMISSION FOR JUBAIL AND YANBU. PROJECT #: 078523
STATUS: FINAL
0 0.5 1 2 km FILE LOCATION: G:\GIS\078523 JUBAIL MP SAUDI ARABIA\ DATE: 1/3/12
GIS DATA\MXDS\MP FIGURES - MXD'S\
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
Table 3-3
Summary of Pertinent Design Guidelines for Seawater Cooling and MPU Assessment
In August 2010, there were 25 primary industries operating in J1, two new
primary industries under construction, two new primary industries under
planning and eight existing primary industries under expansion. Though J1 is
nearly fully leased (approximately 99%), many of the existing industries are
not fully utilizing the land they have leased. It is estimated that most
industries are using 70-80% of the land they have leased. In the past year,
there has been a significant increase in the anticipated demand for SWC in J1,
largely due to the proposed expansions of existing industries. Based on
MARAFIQ’s sales records over the six year period from 2003 to 2009 the
demand for SWC in J1 increased at the average rate of 5%.
Figure 3-6
Seawater Cooling Actual Use 2004-2008
1200
1000
800
x 000 m3/hr-pk
600
400
200
-200
2004 2005 2006 2007 2008
Peak Availability 970 970 970 970 970
Peak Production Demand 709 740 760 774 747
Peak Surplus/Deficit 261 230 210 196 223
Yearly Growth 6.1% 4.4% 2.7% 1.8% -3.5%
Year
(Source "MARAFIQ Demand Forecast 2008-2017 (DF2008) for RC Jubail - Master Plan Input",
MARAFIQ Demand Forecast Department (March 31, 2008) and information provided by MARAFIQ
in March/April 2009)
This shows that SWC use increased by 6.1%, 4.4%, 2.7% and 1.8% annually
between 2003 and 2007, and then decreased by 3.5% in 2008. It is reasoned
that the decrease in SWC demand in 2008 was due to the slowdown of
industries in 2008 due to global market factors that resulted in less
consumption by industries. Actual use in 2008 was 747,000 m3/hr and that
was a surplus in the system of 223,000 m3/hr-peak.
The All Time Allocation (ATA) for JIC is currently 1,222,000 m3/hr and for each
industry this is based on the lateral capacity to their site. 200,000 m3/hr of
the ATA is reserved for J2. This represents the total allocation of SWC,
however the actual use of SWC by J1 industries has often been less than what
they have been allocated under the ATA. MARAFIQ is currently required to
meet the ATA and at this time, are approximately 160,000 m3/hr (13%) short
of this requirement with the limiting factor being normal operating capacity of
the pumps (1,062,720 m3/hr).
The 1999 MPU indicated that seawater demand would exceed supply in
1999/2000, as PS II was being constructed. The 1999 MPU also noted that
beyond 2013, the limit of the SWC system would be exceeded by the average
SWC demand, however, it was anticipated that summer peak demand could
exceed the SWC system limit as early as 2006. System expansions and
changes in demand avoided these projected shortfalls. Since the 1999 MPU a
few significant changes have occurred that will impact SWC demand, including:
Confirmation of J2 including Stage 4 and changes in anticipated
feedstock and industry types.
J2 will employ an evaporative cooling system using cooling towers.
Some secondary industries were converted to primary industries and
these did not have planned connection to the SWC system. At present,
there is a plan to supply these industries with SWC.
Many industries in J1 are using cooling towers.
Some facilities are expanding without using all of their allocated capacity
while others have build-out plans that will exceed their site's lateral
supply capacity.
Two of the three planned refineries (with lower SWC requirements) were
cancelled, and the sites made available for petrochemical or other
development.
The PETMARK Site was released when the refineries were cancelled,
making it available for alternative development, however the 240 ha
parcel had no seawater supply. New off take structures have been built
to supply this site with SWC.
The demand for SWC by secondary industries has failed to develop due
as it has proven uneconomical for the small volumes needed.
In 2007, Nexant prepared a study for the RCJ titled “Feasibility Study of Jubail
2 Expansion (Stage 4)” to determine the impacts of expanding J2 from 3
stages to 4 stages. This report undertook a high level review of the design
prepared for J2 Stages 1 to 3 in order to assess whether it presented any
constraints to the development of J2 Stage 4. The J2 system was originally
designed with a capacity to supply 200,000 m3/hr of SWC, with a possible
expansion to 400,000 m3/hr. MARAFIQ has committed to ensuring that a total
of 200,000 m3/hr of SWC will be provided to J2. The report concluded that
based on once through SWC demand J2 being projected to reach a peak of
1,290,000 m3/hr by 2030 (equivalent to a make-up water rate of 109,000
m3/hr) and once through SWC demand for Stage 4 being expected to reach a
The MARAFIQ Supply Plan indicated that there will not be a deficit in SWC
generation supply during their forecast period to 2017, which was predicted to
have peak production demand on 1,063,000 m3/hr. It also concluded that
chlorine plant capacity is sufficient to meet the requirements with an
availability factor of 90%. The demand beyond 2014 was anticipated to be
above the 300 m3/sec dredged channel design (1,080,000 m3/hr intake flow)
and therefore canal dredging may be required beyond 2014. It also
recommended that a bathymetry study should be conducted periodically by
O&M to assess the condition of the dredged channel and to initiate dredging if
required. The conclusion of that report being that the plant is capable to meet
the customer requirements for supply plan period to 2015.
The MARAFIQ Supply Plan indicated that there will not be a deficit in SWC
return volume through the 2015 forecast period. They determined that the
distribution system cannot handle the flow beyond 2014 with single
compartment operation, while the second compartment is taken out of service
for maintenance.
The August 2010 RCJ projections through 2018 show SWC demand of
1,305,000 m3/hr, which would result in a shortfall in capacity for all
components of the system including normal operating capacity, dredged
channel intake, supply and return compartment capacity.
Findings of MPU
The ATA of SWC to individual industries agreed between MARAFIQ and RCJ is
1,222,000 m3/hr and based on this, there is an approximate shortfall of:
159,000 m3/hr (13%) based on the normal operating capacity of the
pumps.
142,000 m3/hr (12%) in the dredged channel intake.
382,000 m3/hr (32%) in the supply compartment capacity.
MARAFIQ and RCJ are currently working on options to enhance both the supply
and return canal capacity to meet the ATA. The current demand forecasts by
RCJ exceed the ATA.
Table 3-4 and Figure 3-7 illustrate the MPU SWC demand forecast through
2030.
Table 3-4
Seawater Cooling Supply and MPU Demand Forecast to 2030
SWC Demand
(x'000 m3/hr) SWC Supply (x'000 m3/hr)
PS (Normal Dredged
Supply Return Supply/Return Operating Channel
Year J1 J2 Total Compartment Compartment Compartment Capacity) Intake
2010 820 0 820 840 1,100 840 1,063 1,080
2011 870 0 870 840 1,100 840 1,063 1,080
2012 893 4 897 840 1,100 840 1,063 1,080
2013 936 7 943 840 1,222 1,222 1,063 1,080
2014 1,155 8 1,163 840 1,222 1,222 1,063 1,080
2015 1,255 9 1,264 840 1,222 1,222 1,063 1,080
2016 1,255 9 1,264 840 1,222 1,222 1,063 1,080
2017 1,255 34 1,289 840 1,222 1,222 1,063 1,080
2018 1,255 59 1,314 840 1,222 1,222 1,063 1,080
2019 1,255 61 1,316 840 1,222 1,222 1,063 1,080
2020 1,255 63 1,318 840 1,222 1,222 1,063 1,080
2021 1,255 63 1,318 840 1,222 1,222 1,063 1,080
2022 1,255 63 1,318 840 1,222 1,222 1,063 1,080
2023 1,255 63 1,318 840 1,222 1,222 1,063 1,080
2024 1,255 67 1,322 840 1,222 1,222 1,063 1,080
2025 1,255 71 1,326 840 1,222 1,222 1,063 1,080
2026 1,255 71 1,326 840 1,222 1,222 1,063 1,080
2027 1,255 71 1,326 840 1,222 1,222 1,063 1,080
2028 1,255 71 1,326 840 1,222 1,222 1,063 1,080
2029 1,255 71 1,326 840 1,222 1,222 1,063 1,080
2030 1,255 71 1,326 840 1,222 1,222 1,063 1,080
Figure 3-7
Seawater Cooling Supply and MPU Demand Forecast to 2030
1,400
1,200
1,000
800
x' 000 m3/hr
600
400
200
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Year
SWC Demand Supply Compartment
Return Compartment Supply/Return Compartment
PS (Normal Operating Capacity) Dredged Channel Intake
In 2014 there will be a deficit in both PS normal operating capacity and intake
channel capacity. Even if the six PS1 pumps be upgraded from 10.3 m3/sec to
13.5 m3/sec (as recommended in the Jacob report), the total capacity of
1,131,840 m3/sec (still with four spare pumps) would still have a deficit in
2015.
Tables 3-5 and 3-6 summarize the SWC supply (generation) and distribution
shortfalls anticipated for the planning period, split into the short term, mid
term and long term.
Table 3-5
Seawater Cooling Supply (Generation) Shortfalls
Table 3-6
Seawater Cooling Distribution Shortfalls
Due to the limited quantity of SWC available for use in J2, mechanical draft
cooling towers have been suggested as the most practical and economical
option for industries to meet their cooling requirements. Mechanical draft
cooling towers use fans to move air instead of depending on natural draft or
wind. This speeds the cooling process and increases the efficiency of the tower
by increasing the air velocity over droplets of water falling through the tower.
Mechanical draft towers can, therefore, evaporate much more water than
natural draft towers of the same size. The use of this technology significantly
reduces the volume of SWC required to meet industry demands. As previously
indicated, in addition to use in J2, in 2010 there were only two significantly
large cooling tower installations in J1 and a some smaller installations. At a
meeting between RCJ and MARAFIQ on April 6, 2006 a number of industries
under construction or planned in J1 were expected to use cooling towers and
estimates of their make-up SWC requirements were provided by the RCJ.
Industries in J1 have been advised to build cooling towers for their expansion
projects and new projects. The use of cooling towers reduces the demand for
seawater as the requirements for cooling tower make-up water rate is
approximately 8.5-10% (as indicated by RCJ,MARAFIQ and Nexant).
3.5.2 Supply
The major limiting factor for the distribution network is that there is not
sufficient space within J1 to allow for a major expansion of the system.
The gap is based on the SWC distribution system operating as desired, with
one of the three compartments only used when another compartment requires
maintenance. As previously identified, the supply gap can be mitigated in the
short term if all three compartments are used. Canal structures are protected
from corrosion by cathodic protection using sacrificial anodes, which are
periodically replaced. Options for maintenance need to be explored if all three
compartments are required to be online to meet demand. MARAFIQ has
indicated that they are exploring all available technologies for maintenance of
debris and deposit removal, replacement of mechanical components etc
including non-dewatering technologies with divers, robotic devices and other
techniques.
3.6 Recommendations
The following table outlines the key recommendations related to SWC. Many of the recommended studies need to occur in the short term, however their results will be implemented over the
mid and long term to meet the SWC requirements of JIC.
Table 3-7
Seawater Cooling Recommendations
Confirm if using TWW in cooling towers is a possible option. RCJ reported that Saudi Aramco and Dow
expressed concern over the inconsistent quality of TWW and the effect this would have on any RO Plant
required to treat the water for cooling applications. This would need to be adequately addressed before
this could move forward. However we note that the latest information provided by the RCJ indicates
that Dow-Aramco will use PW or TWW in place of SWC.
Prepare MPUs approximately every 5 years for a 20-25 year time horizon. To provide updated demand projections and an overall review of the status of SWC system. This process RCJ Mid Term
should be done in conjunction with input from MARAFIQ and the industries. MARAFIQ through to
Industry Long Term
Implement a technical/operations liaison committee with MARAFIQ and Discuss and coordinate projections and upgrades which is currently done in a manner that is unclear MARAFIQ Short Term
appropriate RCJ, as described in Chapter 2. who is responsible for this. RCJ through to
Long Term
Finalize MARAFIQ design guidelines currently under preparation and The proposed MARAFIQ and existing RCJ guidelines need to be compatible and a comprehensive review RCJ Short Term
incorporate into RCJ guidelines as appropriate. of both guidelines is required to ensure consistency in approach. Having their own guidelines will MARAFIQ On-going
provide MARAFIQ better control over changes that affect their business and allow for greater
consistency across their departments.
Continue to identify ways to address short-falls in system, including The Jacobs report identified potential modifications to the design criteria and the possibility of cooling MARAFIQ Short Term
continued review and resolution of the recommendations from the Jacobs towers if appropriate locations can be determined. Also need to address the provision of infrastructure RCJ through to
report. that is necessary to complete the recommended option including extension of the control system, Mid Term
construction of a new chlorination plant and provision of new electrical infrastructure. Measures should
be investigated to supply SWC to J2 by an alternative route, for example by constructing a new supply
pipeline from the north.
RCJ and MARAFIQ consult with each other on annual projections for SWC To ensure up to date projections are available for planning purposes. RCJ Short Term
demand. This can be done via the liaison committee recommended in MARAFIQ through to
Chapter 2. Long Term
Until 2009-2010, the primary PW source was desalinated water from the
Saline Water Conversion Corporation's (SWCC) Desalination Plant. The
secondary PW source is MARAFIQ’s (formerly the RCJ’s) Desalination Plants I
and II. In 2009-2010, these supplies were retired when the IWPP came
online. The IWPP is now providing 300,000 m3/day to JIC, and an additional
500,000 m3/day outside of JIC.
In addition, there are three RO plants with a total capacity of 29,470 m3/day,
however 6,970 m3/day of this was retired in 2010.
LI
T-AB U-A
Al-Gurmah
Island Jalmudah
JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
Ø900
Mardumah
T6
Ø5 00
Bay
TS4 B1 PS
Community Al-Fanateer
District POTABLE WATER WELLS
Al-Mutrafiah Area
District Al-Deffi BULK POTABLE WATER STORAGE TANKS
Dist. 'B'
District Dist. 'D' PS
Al-Fasil TS 4 PUMP STATIONS
Ø900 PS
District
PRIMARY PUMPING FACILITIES
Ø1400
Ø3 00
No. 9 B3 PS WATER TREATMENT PLANTS
TS 7
Ø1400
Ø2 00
No. 8
DESALINATION PLANT
No. 7
T3
00
No. 6
Ø2
RW Well Al-Fanateer IWPP FACILITY
Island
No. 5
Ø3 00
Al-Khaleej
No. 6
PS
No. 4 SWRO (TEMPORARY)
O&M Al-Khaleej
Ø1400 Centre JIC (T) District
No. 3 PS POTABLE WATER TRANSMISSION
Ø1400 RW Well RW Well Jubail
& DISTRIBUTION NETWORK
Ø4 50
WTP 3 RW Well
RW Well No. 10C No. 11C Industrial
No. 21
Ø350
(RO 3) RC
No. 12C Booster College Camp
T6 HQ 11B PS RW Well EXISTING INDUSTRIAL, MAJOR ROADS
Ø350 Ø300 PS
TS6 T100 No. 28E
Camp
Al-Huwaylat
Camp
T106 Ø450 Camp Ø300 PROPOSED INDUSTRIAL, MAJOR ROADS
Ø1400
5 PS 1 PS
Island
Ø300 T112 4 PS Ø450 No. 12
RW Well Block N Camp Al-Huwaylat
Camp
PERMANENT COMMUNITY SERVICING AREA
Ø700
St. 1 No. 20 Coastal
T113
Stage 3 and 4 Stg.2 N Block 3 PS 2 PS District
SWTP
T289
Stormwater Strm.W SWTP #9 Storm- Ø300 Ø300 PS
(Exp.) PS T120 Ø350
Holding Pond H.Pond water NWPS J-Block Block E-Block Block Camp EASTERN CORRIDOR SERVICING AREA
No. 11
Pond PS J-South PS E-South 11A PS
T1 0
Ø1200 Ø300 T130 Ø300 Al-
Ø1200
Lulu RW Well PRIMARY INDUSTRY SERVICING AREA
1
Ø800
District No. 27E
T138
Ø1200 T138 Ø700 No. 10 SECONDARY INDUSTRY SERVICING AREA
T147
T148 PS 8 Camp
Kh a
13 PS SERVICING AREA
Ø700T154
rsa
Ø800
Ø1400
Camp
Ar a b i a n G u l f
Camp Shati No. 26E
T295
di E
15 PS 4 PS
niah
T162 District
AIRPORT SERVICING AREA
le ct
No. 2 No. 1
R as
Ø600
O&S
Ra il
T263
T251
T241
T195
ric
Centre RW Well
Jubail 2 Jubail 1 T174
Ta n
ro a
No. 22
C om W
ura
Ø1 0
pan
O
T184
RO
RW Well
Ø6
0
yR
T259
Block P Block K Block F No. 23
W
Ø700
Ø600
00
Ø300
0
OW
T143
T163
0
Ø1 5
PS 6
T198
Sanitary PS 5 T204 IWPP
T289
EPS
Landfill Ø900 Facility
T223
T218 IWTP #8
Desalination
T218 Ø800 Ø1000 Plant #2
Ø800
Ø300
T183
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
Ø300
Ø450
Ø300 0 0.5 1 2 km
T2 74
BeeA'h Ø450 T272 King Fahd
Industrial Port
Ø150
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 4/15/11
MP FIGURES - MXD'S\
TS
MOT
SWCC
85
Supply Pipeline
(to be discontinued)
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
JIC water supply from SWCC ceased in 2010, after the IWPP facility was
commissioned.
Water from the two desalination plants previously provided a total capacity of
57,600 m3/day using MSF. Desal I (a large plant) was placed in service in
1979 and is located off-shore adjacent to the King Fahd Industrial Port. Desal
II was placed in operation in 1981 and is an on-shore plant, located in the
East Corridor near the SWC PS. The water from Desal I and II was
transferred to the EPS storage tanks for conditioning, storage, chlorinating,
and distribution.
JIC water supply from Desal I and Desal II ceased in 2010, after the IWPP
facility was commissioned. It is anticipated that these plants will be
decommissioned.
The product water from WTP 1 and WTP 2 is supplied directly to the PW
network. The product water from WTP 3 is sent to both NWPS and to the
network directly.
These supplies are in service and are not planned for decommissioning by
MARAFIQ. They are considered essential for re-mineralization and to be used
as back up supply and for supplementing potable water. Volume VIII
MARAFIQ has partnered with IWPP on a combined cycle plant for production
of power and water in JIC. The IWPP is comprised of 4 blocks and is based on
Combined Cycle Generation Gas Turbines where extraction steam from the
turbines supplies process steam to the desalination plant which itself
comprises 27 units that use Multiple Effect Distillation (MED) technology. The
IWPP has added 2,745 MW of power and 800,000 m3/day of desalinated
water to JIC and the Eastern Province of Saudi Arabia
Of the total water production from the IWPP facility, MARAFIQ will ultimately
receive 300,000 m 3/day for JIC. This was brought online in stages through
2009 and 2010. Figure 4-2 illustrates the conceptual design of the IWPP
facility.
Figure 4-2
MARAFIQ IWPP Conceptual Design
Source: MARAFIQ
Source: See:http://www.utilities-me.com/article-199-jubail_iwpp_grinds_into_action/
Pumping Facilities
The NWPS Stage I pump station was commissioned in 1981 while the Stage
II pump station was constructed in 1986. Stage III was commissioned in
2002. The EPS was commissioned in 1981. Currently the NWPS can handle
17,946 m3/hr (430,704 m3/day) at design capacity and the EPS can currently
handle 4,800 m3/hr (115,200 m3/day).
The NWPS and the EPS both previously received desalinated water from
Desal I and II, as well as from SWCC. With these supplies taken offline, the
supply has been replaced by the IWPP. PW from the EPS and NWPS is
distributed to the primary, secondary and support industrial areas, and to the
residential areas: Al-Fanateer, Al-Deffi and Jalmudah through a pipe network
consisting of ductile iron, PVC, and concrete pipes.
The NWPS has two PSs: Stage I/II and Stage III. It has a total of 11 bulk
storage tanks, seven in Stage I/II and four in Stage III. The EPS has a total
of 10 bulk storage tanks.
Storage Tanks
Storage tanks are classified into two categories, bulk storage tanks and local
storage tanks. Bulk storage is located at the NWPS and EPS. The operating
capacity of NWPS after the recent 2010 expansion is 1,529,686 m3. The
operating capacity of EPS is 561,988 m3. This results in a total operating
capacity of all bulk storage tanks (NWPS and EPS) of 2,091,674 m3. The
total operating capacity of the local storage tanks is 333,000 m3 once the
Jalmudah PS is finished construction. The total of 2,424,674 m3 equates to
nearly 7-days of water consumption.
There are five manned pump stations and 24 unmanned PSs in the PW
network system. PW is pumped from NWPS I/II, NWPS III and EPS to the
transmission lines. The transmission lines are interconnected and have
multiple pipes and each can be operated independently.
The primary supply from IWPP can be received at EPS, and NWPS. The
product water from the temporary SWRO plant is received at the EPS tank
farm. The product water from WTP 1 and WTP 2 is directly fed to the network
system. WTP 3 product water is partially sent to the network and the
remaining to NWPS.
The product water from WTP 3 (which has a high TDS) is partially collected
and distributed along with IWPP water, to the community area through the
NWPS.
From the NWPS there are two 1400 mm diameter pipes leading to the
community area and two 1200 mm diameter pipes leading to J1. From the
EPS, there is a 900 mm diameter pipe feeding to J1.
J1 Primary Industry
The majority of the pipe distribution network for the primary industry area is
ductile iron. PW is supplied to each of the primary industry users through a
bulk supply meter station located at the industry's property line.
The J1 support industry area is located in the central part of the primary
distribution network, and extends from the NWPS area to the Eastern
Corridor. The support industry area is separated into three sections, each
equipped with local storage tanks and a local PS.
J2 Industrial Park
Community
Table 4-1
Potable Water Supply - Proposed Retirements and Expansions
Also there is space allocated in Stage 2 of the NWPS for two additional
pumps.
Table 4-2 summarizes the bulk storage tank (NWPS and EPS) capacity and
local storage tank capacity.
Table 4-2
Potable Water Bulk and Local Storage Tank Capacity
Installed Total
No. of Storage Operating
Location Tanks Capacity (m3) Capacity (m3)
BULK STORAGE
North West Pumping Station (NWPS)
Stage I & II 7 95,426 667,982
Stage III 4 95,426 381,704
2010 Expansion 5 96,000 480,000
Total for NWPS - 1,529,686
East Pumping Station (EPS)
PS Tanks-small 2 10,260 20,520
PS Tanks-large 4 39,941 159,764
Farm Tanks in Camp 7 4 95,426 381,704
Total for EPS - 561,988
Bulk Storage Total 2,091,674
LOCAL STORAGE
District “B” Pump Station - 55,000
District “D” Pump Station - 55,000
Other Locations - 168,000
Jalmudah Pump Station - 55,000
(under construction)
Local Storage Total - 333,000
TOTAL STORAGE 2,424,674
(Source: "Supply Plan 2009-2013", MARAFIQ Facilities Planning Department (October 29,
2008))
Figure 4-3 (Current Planned Potable Water System) illustrates the current
proposed modifications to the PW distribution network.
Overall, the RCJ criteria outlined with respect to the PW has been adequately
tested in the water systems installed to date.
LI
T-AB U-A
Ø90 0
Mardumah
T6
Ø50 0
B1 PS
Bay
TS4
Community Al-Fanateer
District EXISTING POTABLE WATER WELLS
Area
Al-Deffi EXISTING BULK POTABLE WATER STORAGE
Dist. 'B'
Dist. 'D'
TANKS
PS
District
Al-Fasil TS 4 PS
District Ø900 FUTURE BULK POTABLE WATER STORAGE
Al-Mutrafiah TANKS
District
EXISTING PUMP STATIONS
Ø14 00
B3 PS
Ø30 0
No. 9
TS 7
EXISTING PRIMARY PUMPING FACILITIES
Ø14 00
No. 8
Ø20 0
No. 7 No. 6
EXISTING WATER TREATMENT PLANTS
T3
20
Ø
No. 5 RW Well Al-Fanateer EXISTING DESALINATION PLANT (RETIRED)
Al-Khaleej
No. 6 Island
Ø30 0
PS
No. 4
O&M Al-Khaleej EXISTING IWPP FACILITY
Ø1400 Centre JIC (T) District
No. 3 PS
RW Well Ø1400 RW Well RW Well EXISTING SWRO (TEMPORARY/RETIRED)
WTP 3
Jubail
Ø450
No. 21 RW Well No. 10C No. 11C
(RO 3)
Industrial
No. 12C College Camp
Ø350
Booster
RC
PS 11B PS RW Well EXISTING SWRO 4 & 5
Ø300
HQ
Ø350
T6
Camp No. 28E
Camp
TS6 T100
Ø450 Camp Ø300
T106 5 PS 1 PS Al-Huwaylat
Ø1400
No. 12
FUTURE PROPOSED DISTRICT PUMP STATION
Ø300 4 PS Ø450
Camp Island
T112
Camp Al-Huwaylat
RW Well Coastal
Block N
N Block 2 PS
Ø700
3 PS
St. 1
T113
Stage 3 and 4 Stg.2 District EXISTING POTABLE WATER TRANSMISSION
SWTP No. 20 Ø300 Ø300 PS
T289
PS
Stormwater Strm.W Storm-
Ø350
SWTP #9 T120 & DISTRIBUTION NETWORK
Camp
(Exp.)
Holding Pond H.Pond water NWPS J-Block Block E-Block Block No. 11
Pond
Ø300 PS Ø300 PS 11A PS
Ø1200
J-South E-South FUTURE POTABLE WATER TRANSMISSION
T1 0
Al-
RW Well
T130
Ø1200
Lulu & DISTRIBUTION NETWORK
No. 27E
1
Ø800
District
Ø1200 T138 Ø700 No. 10 EXISTING INDUSTRIAL, MAJOR ROADS
T147
PS 8 Camp Camp
Kh a
Ø1400 Ar a b i a n G u l f
15 PS
Shati
T295 4 PS PERMANENT COMMUNITY SERVICING AREA
di E
niah
T162 District
No. 2 No. 1
le ct
Ø600
R as
RW Well
T263
T251
T241
T195
ric
Centre
Jubail 1 T174
No. 22
Ta n
ro a
C om W
ura
Ø10
pan
RW Well
O
00
Ø6
No. 23
yR
T259
Block P Block K Block F
W
Ø700
Ø600
00
Ø30 0
FUTURE PRIMARY INDUSTRY SERVICING
OW
00
T143
T163
PS 6 AREA
Ø15
T198
IWPP
PS 5 EPS Facility
Sanitary T204
T289
Landfill Ø900
SECONDARY INDUSTRY SERVICING AREA
SWRO 4 & 5
T223
IWTP #8
FUTURE SECONDARY INDUSTRY SERVICING
Ø800 Desalination
T218 Ø1000
Plant #2 (Retired)
AREA
Ø800
Ø300
AREA
T183
Sanitary
TS1
T241
T121
T261
T195
T161
T2 1
TS3
Landfill Block Q Block L Block G 8 AIRPORT SERVICING AREA
Ø300
Ø450
Ø300
Ø450
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
Ø150
MP FIGURES - MXD'S\
MOT
SWCC
85
Supply Pipeline
(to be discontinued)
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
Table 4-3
Summary of Pertinent Design Guidelines for Potable Water and MPU Assessment
b) The water consumption largely depends on the class of property served and the lifestyle of the population. Type of Service Connection Daily flow for design
This can be symbolized by the result of investigations performed in different residential areas. The Residential 1500L/ connection
difference is caused by the standard of living and extent of irrigation, which is included in the figures in Mobile Home Parks 950L/ connection
Table 5C. Campground and travel trailer parks 380L/space
Marina 38 L/boat slip
Table 5C: Water Consumption in Difference Residential Areas Marina with bathhouse 110 L/boat slip
Residential Type Consumption in Lpcd Rest homes and Nursing Homes 450 L/bed (With laundry)
Single residential unit 595 225 L/bed (Without laundry)
Residential duplex 565
Apartment blocks 400 The Department of Natural Resources and Mines of the Queensland Government, Australia
suggests the following figures to be used for estimating the apartment/home unit water demand.
d) The average daily per capita requirement of potable water for domestic purposes used in many projects These figures are for indicative and comparative purposes only:
in Saudi Arabia has been between 200 to 250 Lpcd. Consequently, the figures in Table 5C do not include
potable water for irrigation purposes and for institutional and commercial demands or losses in the Development Water demand
system. Apartment/ home unit 300 to 500/ 1 bed
Apartment/ home unit 550 to 750/ 2 bed
e) The exact figure must be determined in each project depending on the local conditions as described Apartment/ home unit 750 to 900/ 3 bed
above.
For design purposes, existing reliable records should be used if available. If there is no record,
an average daily water demand is appropriate to use.
It appears that the water usage requirements identified in the RCJ Design Criteria are very
conservative and would lead to a large overestimation of the PW requirements of JIC if they
In 2009, actual community consumption was approximately 500 Lpcd, based on data provided by
MARAFIQ (water usage of 52,000 m3/day and a population of 105,367). Therefore for the
purposes of estimating demand, 500 Lpcd was used. JIC water consumption is very high when
compared to other cities in the Kingdom and is very high compared to other countries. Actions
should be taken to decrease this rate and this is discussed in sections 3.5 and 3.6.
W2. Institutional, Commercial and Light Industries The following criteria are used by the Canadian Ontario Ministry of the Environment:
The specific water use in the different categories of institutional, recreational and commercial areas can be Shopping Center = 2.5-5 L/m2
calculated using the values in Table 5D. For light industrial users, an individual assessment must each time Hotel = 225 L/bed/day
be carried out. Schools = 70 - 140 L/pupil
Hospital= 900 - 1800 L/bed/day
Table 5D: Specific Daily Water Use in Different Categories
Mosque 94 L/ worshipper The North Carolina, USA, Administrative code stated that, a public water system shall meet the
Small Business 7 L/m2 daily flow requirements specified in the following table:
Shopping Center 37 L/m2
Restaurant 32 L/patron + 57 L/employee Type of Service Connection Daily flow for design
Coffee House 22 L/patron + 57 L/employee Schools 55 L/student
Hotel 15 L/m2 Day Care Facilities 55 L/student
Kindergarten 76 L/pupil Construction work or summer camps 225 L/person
Elementary School 76 L/pupil Business, office, factory 95 L/person/shift (Without showers)
Intermediate School 95 L/pupil 132 L/person/shift (With showers)
Secondary School 95 L/pupil Hospital 1130 L/bed
Offices 9 L/m2
Hospital 1,230 L/bed + 57 L/employee The Department of Natural Resources and Mines of the Queensland Government, Australia
Clinic 378 L/patient + 57 L/employee suggests the following figures to be used for estimating the water demand in the different
Sports Stadium 20 L/seat categories of institutional, recreational and commercial. These figures are for indicative and
comparative purposes only:
For the design, it may be impossible to do a detailed calculation using the values proposed above, and for
the determination of the water consumption for commercial and light industries, it is proposed to use a water Development Water demand
consumption of 12 m3/1,000 m2/day. However, the designer must each time - based on his detailed Central Business 1.2 – 2 L/m2
knowledge of the project - make an assessment of this value. Child Care Centre 40-70 L/person
Commercial Premises 5-8 L/m2
Convalescent Home 600-1100 L/bed
Primary School 50-80 L/staff & pupils
Secondary School 90-150 L/staff & pupils
Tertiary Institution 50-90 L/staff & pupils
Fast food store 14-42 L/m2
Food Service 12-20 L/m2
Hospital 500-1800 L/bed
Hotel accommodation 200-600 L/bed
These conservative assumptions are applied for pipe network design at the district or
neighbourhood design level. If no data is available, an average flow if 28 m3/ha/day is
recommended.
For planning at the master plan level, the average community demand identified above under
community (500 Lpcd) includes community uses (institutional, commercial, etc). The examples
provided above are suitable for the pipe design to ensure adequate flows, however are not
required to be applied at a master plan level.
3. Heavy Industries The Department of Natural Resources and Mines of the Queensland Government, Australia
a) It is impossible to set-up guidelines for the water consumption in areas with heavy industries (being provide the following figures for industrial water demand These figures are for indicative and
industries with an extensive consumption for the industrial production). The designer must each time, comparative purposes only:
based on interviews with the potential heavy industries, make an assessment of the expected
consumption. Development Water demand
Heavy Industry 1.0 – 3.5 L/m2
Light Industry 1.0 – 3.5 L/m2
The approach currently used by JIC is appropriate, however coordination of this information
between MARAFIQ, RCJ and industries is imperative.
4. Fire Fighting Internationally, there are various methods applied for fire fighting water demand allocation.
a) Fire fighting water for the residential and commercial areas is obtained from fire hydrants located on the Most of these methods consider the following aspects in the allocation of the fire fighting water
potable water distribution network. demand and the design of fire fighting engineering system:
Type and geometry of the building
b) In the hydraulic calculations of the distribution network, it must be checked if the network can supply the Type of occupancy
fire fighting flows as detailed in Table 5E. Adjacent properties
Variable fire scenario
Table 5E: Fire Fighting Flows in Residential and Commercial Areas Fire detection system
Land Use Fire Flow in m3/s Fire Suppressions system
Medium rise commercial 0.095 - 0.189 Effectiveness of fire service
High rise commercial 0.189 - 0.379
Low rise residential 0.047 - 0.063 In the Water Supply for Public Protection produced Canadian Fire Underwriters Survey (1999)
Medium rise residential 0.063 - 0.095 assessment of a water supply system, the major emphasis in placed upon its ability to deliver
High rise residential 0.126 - 0.158 adequate water to control major fires throughout the municipality on a reliable basis via
sufficient hydrants. What is ultimately available to the fire department is the critical test in this
c) In the industrial areas, each industry shall in principle be responsible for making their own arrangements fire protection evaluation. In Canada meeting these requirements impacts the insurance
for fire fighting within their boundaries as per instructions earlier issued by the Royal Commission. premiums. The Fire Underwriters Survey recommends the following for fire flow:
d) However, the hydraulic calculations of the network system should examine to what extent a major F = 220 C A
prolonged fire can be fought with water outside the industry's boundary.
Where:
6. Irrigation
a) Water for domestic gardening shall be included in the potable water demands and an individual As PW is not generally used for irrigation, removal of this reference in determining PW demand
assessment will have to be done in each project, as it may be influenced by the distribution between the from the Design Criteria Manual is appropriate.
different residential types. In many projects an allowance for residential irrigation of 145 Lpcd has been
included. Reference is made to the standards for irrigation water in RCER 2004.
b) Lawn areas shall be irrigated by surface spray sprinklers using only potable water.
7. Physical Losses (Leakage) Physical losses from the PW system goes beyond just physical loses from leakage and should be
a) The physical losses from pipes in the water supply system will depend on the age of the pipes, pipe called “unaccounted for water”, which includes leakage, non-chargeable (or illegal) use, metering
material and joints, pressure in the system and construction conditions. discrepancies, etc. It is anticipated that leakage would be the largest contributor.
b) Very often 10% of the total water consumption is added to cater for the water losses, but in some Based on experiences in other locations, “unaccounted for water ” can account for up to 15%. A
examples actual studies have showed losses less than 2%. Therefore, the designers must each time PW unaccounted for water survey should be conducted. The results may account for the high PW
make an individual assessment of the expected water losses. use in JIC.
F. The Concept of the Systems
1. The primary system is made up of a grid of mains and booster pumping stations including necessary storage This is an appropriate approach.
facilities. Further distribution to the consumers is accomplished through secondary and tertiary systems.
Pumping stations located at the storage tanks provide the hydraulic head for the secondary and tertiary
systems; those pump stations, however, are included as part of the primary system.
2. The water demands in industrial areas can be quite erratic, and as these industries come and go over the
years, the water demand at any particular location may vary drastically. This is true and should continue to be monitored.
To serve these areas with a high degree of flexibility, subordinate water systems can be established consisting
of receiving tanks (day tanks), independent pump stations downstream to maintain pressures at any desired
level, and reticulation systems with adequate margins to serve future needs. An allowable demand rate is
established for each of these points; peaking above these rates is balanced by site day tanks.
Currently most of municipalities in Ontario (Canada) request two days storage capacity for
emergency and breakdown needs.
The USA Army Corps of Engineers has proposed the Unified Facility Criteria for Water Supply:
Water Storage. Section 3.1 proposed the following approach to calculate water storage
requirement:
Total storage capacity, including elevated and ground storage, will be provided in an amount not
less than the greatest of the following items:
Item 1: Fifty percent of the average total daily domestic requirements plus all industrial
requirements. This will provide minimum operational storage needed to balance average daily
peak demands on the system and to provide an emergency supply for outages of up to a one-
day duration. For the purposes of this item, essential water needs do not include the fire
demand.
Item 2: The fire demand. The fire demand is the required fire flow needed to fight a fire in the
facility (including water required to support the fire suppression systems) which constitutes the
largest requirement for any facility served the water supply system plus 50% of the average
domestic demand rate plus industrial or other demand that cannot be reduced during a fire
period. This amount will be reduced by the amount of water available under emergency
Item3: The sum of item 1 and 2 above, that is, the sum of 50% of the average total daily
domestic requirements, all industrial requirements for an average day which cannot be shut off
during emergency conditions, and the required fire demand. The sum of the above items will be
reduced by the amount of water available in 24 hours under emergency conditions. This will
provide maximum storage where emergency water supply is a minimum over a 24 hours period
or a supply main outage would significantly affect overall supply conditions.
The current 7 days storage requirements should be revisited in light of the change in PW supply.
The IWPP and future SWRO plants are within JIC, so JIC is not reliant on the two pipelines from
SWCC. In the past, there was a fear that if the supply lines from SWCC went out that the whole
city would have to rely on the strategic reserve. Now that there are generating facilities within
the city, this will ensure a constant supply source and redundant units will be built into the
supply system to address planned and forced outages.
Recognizing that there are other reasons for the 7 day storage requirement, including conflict,
the storage capacity in JIC should be based on:
The reliability and size of the primary potable water sources (IWPP and SWRO).
The capacity of these plants relative to both industrial and domestic demand.
The potential for total breakdown of supply and how fast the supply can be restored.
The industrial consumer’s vulnerability to water shortage.
Based on this, we recommend that a study be conducted to determine the appropriate and
acceptable (to MARAFIQ and RCJ) number of days storage.
Figure 4-4
Potable Water Actual Use 2004-2008
300
250
200
x 000 m3/day-pk
150
100
50
-50
2004 2005 2006 2007 2008
Peak Availability 232 237 266 255 255
Peak Production Demand 215 237 244 245 231
Peak Surplus/Deficit 17 0 22 10 24
Yearly Growth 15.0% 10.2% 3.0% 0.4% -5.7%
Year
Source "MARAFIQ Demand Forecast 2008-2017 (DF2008) for RC Jubail - Master Plan Input",
MARAFIQ Demand Forecast Department (March 31, 2008), and information provided by
MARAFIQ in March/April 2009
This shows that PW use increased by 15%, 10.2%, 3.0% and 0.4% annually
between 2004 and 2007, and then decreased by 5.7% in 2008. It is
reasoned that the decrease in SWC demand in 2008 was due to the
slowdown of industries in 2008 due to global market factors that resulted in
less consumption by industries. Actual use in 2008 was 231,000 m3/day and
there was a surplus in the system of 24,000 m3/day-peak.
The 1999 MPU indicated that the city's PW supply system required immediate
expansion and enhancement to meet forecasted shortfalls in meeting
demand as early as the summer of 2000. Expansions, new facilities, and a
change in demand forecasting avoided this projected shortfall. It also
indicated that the existing Industrial Park distribution systems were deemed
to be generally adequate through 2013, except that there needed to be a
redistribution of the flow of water and the extension of the secondary system
into the undeveloped Sections P-2, P-3 and K was needed.
In 2007, Nexant prepared a study for the RCJ titled “Feasibility Study of
Jubail 2 Expansion (Stage 4)” to determine the impacts of expanding J2 from
3 stages to 4 stages. This report found that the total demand for PW from
primary industries in J2 (Stages 1 to 4), which includes demand for process
water, was expected to reach a peak of approximately 164,500 m3/day by
2030, which was under the design capacity of the PW supply system planned
for J2 (200,000 m3/day). Based on the Alternative Feedstock Basis for J2,
this number is now expected to top 230,000 m3/day by 2030, which is not
even full-build out for J2.
The MARAFIQ Supply Plan indicated that demand beyond 2011 is above the
production capacity of the existing plant as well as imports from the IWPP
facility and Al-Fatah. The implementation of the approved SWRO 4 and the
remineralisation plant proposed to help meet the supply-demand gap. In
addition, the plan determined the existing distribution network is capable to
meet the customer demand to 2013 and then there is a deficit in pumping
capacity for the community which they propose to mitigate by importing the
required amount from the industrial distribution network from NWPS Stage
II. They also indicate that the storage system is capable to meet the
demand, but the 7 days critical storage as per RCJ guidelines is not available
so new storage tanks are required.
The minimum quantity of water to be received at the EPS after Desal I and II
retirement and SWRO 4 and SWRO 5 commissioning will be 150,000 m3/day.
The existing pump station can handle only 100,000 m3/hr at design pressure
or up to 112,000 m3/day at a reduced pressure. MARAFIQ has indicated that
this gap in pumping capacity should be mitigated by expansion projects,
matching with the project schedule of SWRO plants and that it is anticipated
that the EPS expansion to 150,000 m3/day will be completed in 2012 and the
NWPS requires expansion beyond 2013. The existing network should be
evaluated using a hydraulic model before expansion of each PS.
Findings of MPU
Table 4-4 and Figure 4-5 illustrate the MPU PW demand forecast through
2030.
Table 4-4
Potable Water Supply and MPU Demand Forecast to 2030
Figure 4-5
Potable Water Supply and MPU Demand Forecast to 2030
1,400
1,200
1,000
800
x' 000 m3/day
600
400
200
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Year
Should the temporary SWRO not go offline in 2010, this would address the
short term deficit in 2011 and 2012 .
In addition, if SWRO 5 comes online (not shown in the above graph), this will
provide an additional 75,000 m3/day.
Volume VIII discusses the potential impacts on groundwater quality from the
TWW discharge area being in such close proximity to some of the
groundwater wells, and recommends studies regarding source water
protection. Based on the results of these studies, the groundwater wells
may be recommended to be decommissioned. The groundwater wells are
currently primarily used for back-up supply (36,440 m3/day). The
groundwater wells by the TWW discharge area can provide supply of 21,440
m3/day. If these are taken offline it will increase the deficit identified above.
Tables 4-5 and 4-6 summarize the PW supply (generation) and distribution
shortfalls anticipated for the planning period, split into the short term, mid
term and long term.
Table 4-5
Potable Water Supply (Generation) Shortfalls
Year Shortfall Anticipated/Amount of Shortfall (m3/day)
Short Term
30,000 (2011) - 75,000
(To 2012)
Mid Term
120,000 – 370,000
(2013-2019)
Long Term
410,000 - 690,000
(2020-2030)
Table 4-6
Potable Water Distribution (Primary PS) Aggregate Shortfalls
Short Term
-
(To 2012)
Mid Term
51,000 (2014) – 256,000
(2013-2019)
Long Term
294,000 - 577,000
(2020-2030)
Table 4-7
Community Potable Water Demand Forecast (2030)
Table 4-8 and Figure 4-6 illustrate the MPU PW bulk storage tank demand
forecast through 2030.
Table 4-8
Potable Water Storage and MPU Demand Forecast to 2030
Figure 4-6
Potable Water Storage and MPU Demand Forecast to 2030
9,000
8,000
7,000
6,000
x' 000 m3/day
5,000
4,000
3,000
2,000
1,000
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Year
Table 4-9
Potable Water Storage Shortfalls under different Scenarios
Land allocation to meet bulk storage requirements could be very large (up to
an additional 115 ha by 2030). The bulk storage requirements need to be
carefully reviewed and if appropriate, modifications made.
In 2010 in J1, TWW was being used for process application in one industry,
Gulf Guardian Glass, and in two other industries for cooling water use.
Industries need to be encouraged to use alternative sources of water to meet
their process water needs. Process water accounts for approximately 80%
of the industries total PW demand.
move forward. Information provided by the RCJ in June 2011 indicted that
Dow-Aramco and SABIC Verbund may use TWW instead of PW or SWC, this
would decrease demand by 43,700 m3/day in 2015 and an additional 55,000
m3/day in 2018. However, the current J2 plan does not include TWW
pipelines and this would need to be investigated to ensure that ROWs and
pipelines are provided.
MARAFIQ has indicated that only PW could meet the high demand, however if
a portion of industries could use TWW, this would help with the demand on
the PW supply. This option would also require hydraulic analysis of the TWW
system to ensure capacities can be conveyed in the current network or if
upgrades would be required. Use of TWW can be good alternative provided
the customer can effectively control the bacterial growth in the cooling water
and also to maintain the blow down water quality as per RCER 2009
specifications, for discharging to the SWC canal.
The potential gains from attention to water demand management and water
conservation are far from marginal, even for domestic uses (where leakage
can be higher than actual consumption in some parts of the world). For
example, in Egypt water losses amount to approximately 34% of the national
water consumption, ranging between governorates from 15% to 65%. A
significant part of the losses consists of leakage losses in the supply system
as well as the distribution system. Studies show that with minor changes in
lifestyles and in urban and industrial settings, plus in this case some shift
away from irrigated agriculture; savings would exceed half of current water
use in the Middle East.
Industrial demand for water increased substantially in the last three decades
in Saudi Arabia. The increase resulted from the development of industrial
cities (such as JIC, Yanbu and King Abdullah Industrial City) and the
expansion of industrial activities all over the Kingdom. The growing industrial
water demand is satisfied mainly by costly desalinated water. The following
legislation and measures have been taken to improve industrial water
demand management:
Saudi Arabia Government has established large industrial cities in
different parts of the Kingdom. The establishment of centralized
industrial city aimed to minimize industrial water demand, to maximize
wastewater recycling, and to protect the environment. Industrial
wastewater is collected, treated, and recycled within each city for
industrial process and landscape irrigation.
Closed water cycles have been introduced in industrial plants to
minimize wastewater disposal, reduce groundwater pumping, and
protect the environment. In this approach, wastewater is converted
into good quality condensate by evaporation at low temperature under
vacuum. This technology was introduced to large industrial plants in
1995.
4.5.2 Supply
Should the temporary SWRO not go offline in 2010, this would primarily
address the short term deficit in 2011 and 2012, by providing and additional
75,000 m3/day.
Bring SWRO 5 comes online (not shown in the supply graph as timing
unknown), this will provide an additional 75,000 m3/day.
IWPP is state of the art and the multi-stage flash distillation process is suited
for large scale plants. The IWPP will have a capacity of 800,000 m3/day, and
currently only 300,000 m3/day has been allocated for JIC, the remaining
amount has been committed elsewhere. MARAFIQ has indicated that no
additional PW would be available from the IWPP. Should the IWPP expand in
the future, it may be possible to negotiate for increased supply from the
IWPP facility.
Groundwater accounts for less than 10% of the PW supply available and it is
currently used as back-up. New groundwater supply sources could be
investigated to increase this supply in locations that would not be subject to
concerns about contamination. Volume VIII provide recommendations
regarding source water protection. Based on the results of these studies,
the existing groundwater wells may be recommended to be
decommissioned.
Hooking into the supply proposed for RIC should also be investigated. At this
time, information is not been provided regarding the proposed supply for
RIC, however as there is only one network for PW and process water in JIC
this would need to be investigated to ensure that any step to connect it with
regional network will need to considering the quality of water in the regional
network.
The demands outlined in Section 4.4 will need to be run through the
computerized hydraulic network analysis model to determine if the existing
infrastructure is large enough to accommodate the new demands as the
community expands and to confirm that the system is adequate to meet the
flows (normal and fire), pressure, velocities and the looping configuration.
The model can assist in the location of any requirements for increased
pipeline diameters or booster PSs as well as any additional storage tanks.
Based on the Alternative Feedstock Basis for J2, this number is now expected
to top 230,000 m3/day by 2030, which is not even full-build out for J2.
Reportedly the original design capacity of the PW distribution system planned
for J2 was 200,000 m3/day. This apparent hydraulic deficiency should be
reviewed and any remedial measures that are identified be implemented .
4.6 Recommendations
The following table outlines the key recommendations related to PW. Many of the recommended studies need to occur in the short term, however their results will be implemented over the mid
and long term to meet the PW requirements of JIC.
Table 4-10
Potable Water Recommendations
IWTP 8 was designed in stages, the design capacities of Stage I and Stage II
were originally designed for 26,000 m3/day and 41,700 m3/day respectively.
IWTP 8 was designed and constructed in stages Stage I (commissioned in
1983), Stage II (commissioned in 1989), and in 2000 Stage I and Stage II
were commissioned to have an upgrade with a total treatment capacity of
65,000 m3/day.
IWTP 8 currently complies with RCER 1999, and any expansions will comply
with RCER 2004.
Industries are supposed to pre-treat their IWW to comply with point source
discharge criteria and IWTP 8 then processes the IWW to meet the required
standards, however there are concerns about the industry point charge
quality being achieved.
T3
District
Airport Area
O&M Al-Khaleej
Centre District
Evap. Jubail
Stn. Industrial
RC College
WTP #3 T6 HQ
TS6 T100
T106
T112
Al-Huwaylat
Al-Huwaylat
Block E-South District
Stage 3 and 4
T113
Stg.2 St. 1 Block N
Island
SWTP Block J-South
T289
Stormwater Strm.W SWTP #9 Storm- T120
(Exp.)
Holding Pond H.Pond water NWPS
Pond
T1 0
T130
1
Al-
Lulu
District
T138 T138
T147
68 69 T148 47
T150 6
24 T154
Kh a
Al-
Ar a b i a n
Shati
T295
rsa
7
Sa u
74 9
T162 District
Gu l f
niah
5
di E
79
le ct
R as
O&S 23
T263
T251
T241
Ra il
ric
Centre
Jubail 1
Ta n
Block P T174
C om
ro a
u
49 4
Jubail 2 Industrial Area
ra R
dR
pan
47 55
Industrial Area
OW
OW
46
yR
T184
OW
22
T259
T195
Block K Block F
T143
51 52 53 54
T163
T198
3
T289
Sanitary 59 T204 IWPP
Landfill 56 Fac.
IWTP #8
T223
T218 57 58
Desal.
2 10 11 #2
1 T218
RC T230
Scap
Fac. 21 18 20 15 16
T2 1
8
TS9
Sanitary
T315
T335
TS1
Landfill
T241
T121
T195
T183
T161
T261
Block Q Block L Block G
TS3
T2 74
MOT
BeeA'h T272
85
T2 74
3
TS
INDUSTRIAL WASTEWATER LINE PRIMARY INDUSTRY SERVICING AREA
JUBAIL INDUSTRIAL CITY
PUMPSTATIONS SECONDARY INDUSTRY SERVICING AREA
MASTER PLAN UPDATE
INDUSTRIAL WASTEWATER TREATMENT PLANT SUPPORT INDUSTRY/NORTHERN CORRIDOR SERVICING AREA
EXISTING INDUSTRIAL
WASTEWATER SYSTEM
BASE DATA PROVIDED BY MAP PROJECTION: AIN EL ABD UTM ZONE 39N
THE ROYAL COMMISSION FOR JUBAIL AND YANBU. PROJECT #: 078523
STATUS: FINAL
0 0.5 1 2 km FILE LOCATION: G:\GIS\078523 JUBAIL MP SAUDI ARABIA\ DATE: 12/22/11
GIS DATA\MXDS\MP FIGURES - MXD'S\
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
Waste from the screening and grit removal process are disposed of at the
RCSLF. Also, sludge is thickened and press filtered to 30% solids and
landfilled within lined cells of the RCSLF. This is addressed under Chapter
11.
Treated water from IWTP 8 can be conveyed to the irrigation system of the
industrial area or to any irrigation area in the community through a series of
interconnection lines and valve system. TWW is addressed in Chapter 7.
In J2, the IWW system will be a low pressure force main system. The
required pressure will come from industry elevated discharge towers which
each industry is required to provide on-site (these could be some 20 metres
above ground level). The wastewater level in the industry elevated discharge
towers shall be sufficient to provide the total dynamic head required to
deliver the IWW from the industry site, through the IWW system and across
the KRT Corridor to IWTP 8.
The industrial wastewater collection schemes in the two industrial areas are
dramatically different in hydraulic design, jurisdiction of ownership and
operational responsibility. The J2 system is a marked improvement over the
earlier constructed system which has been dependent on the principle of
pumping in series which has led to bottleneck difficulties during its
development and operation.
The largest flow in terms of sizing the network is rainwater that is incident
upon paved industry areas within the industrial fence. Each industry
undertakes primary treatment of the collected water from all potential
sources and must provide 72 hours storage.
SWW and IWTP 8 for IWW). The IWW pump stations are designed in series,
ultimately leading to IWTP 8.
There are 35 IWW pump stations with pumping capacities ranging from 557
to 120,700 m3/day. The pump stations are either dual-function, transferring
IWW and SWW or single-function transferring only SWW. The pump stations
were equipped with odour and corrosion control treatment injecting oxygen
and or ozone into the pipelines on an automatic basis at rates sufficient to
maintain the industrial wastewater in an aerobic condition. However this
odour control is no longer functioning and needs to be ungraded or replaced
with suitable technology.
The J1 primary industry area systems have a designed average flow capacity
of 332,700 m3/day. Due to heavier PETROKEMYA demand than originally
anticipated, MARAFIQ debottlenecked PS-16 and PS-15 by installing larger
IWW pumps, which were upgraded again in 2009 (PS-16 to 800 m3/hr and
PS-15 to 1,500 m3/hr).
The MARAFIQ Supply Plan IWW Treatment System proposes to mitigate the
supply-demand gap using Stage I of IWTP 8 with enhancement of aeration
system (implemented through the approved CAPEX for plant expansion in
2009). The long term peak supply deficit is proposed to be met through the
expansion of IWTP 8 to add 55,000 m3/day to be online in 2011 as per
approved CAPEX.
Table 5-1 summarizes the current IWTP 8 capacity and proposed expansions.
Table 5-1
IWTP 8 Existing Capacity and Proposed Expansions
Capacity Timing
(m3/day)
IWTP Stage I & II 41,700 Original Design
IWTP Stage I & II Refurb (Total) 65,000 In service now (will be
reduced to 41,700 again in
2012 to meet 2004 RCER)
IWTP Stage III Expansion 55,000 2011 (Stage I and II will
(Conventional Activated Sludge serve as a standby unit for
Biological Process) emergencies)
IWTP Stage IV 55,000 2019 (can be brought
online earlier if required)
The system is made up of a single 900 mm pipe running down the central
east-west corridor of J2, with 700 mm connections to individual industry
plots. Redundancy has been incorporated into the system by the inclusion of
two parallel pipelines across the KRT Corridor, each of which has the capacity
to carry the full design flow of 100,000 m3/day. Redundancy is also provided
by the fact that all industries are required to maintain on-site storage,
equivalent to a minimum of 72 hours of production.
The MARAFIQ Supply Plan Network Analysis for IWW proposed that upgrades
to PS-15 and PS-16 pumping capacity (completed in 2010) would meet the
supply deficit from 2010 onwards. Expansion of pumping capacity of PS-10
and PS-11 (completed in 2010) would meet the supply deficit from 2010
onwards. The disposal of surplus TWW will be provided through the
proposed installation of a dedicated surplus TWW line from IWTP 8 to the
TWW discharge area. MARAFIQ is also proposing the provision of inlet works
IWTP 8 for J2 IWW.
The following table summarizes the current primary PS capacity and exp.
Table 5-2
IWW Primary Pumping Station Capacity and Proposed Expansions
MARAFIQ has indicated that currently these PSs are operating well below
design capacity. Figure 5-2 (Current Planned Industrial Wastewater System)
illustrates the current proposed modifications to the IWW distribution
network.
Overall, the RCJ criteria outlined with respect to IWW have been adequately
tested in the systems installed to date. However, there have been problems
with meeting some of the quality parameters identified. Recommendations
for this are provided in sections 5.6, 6.6 and 7.6.
T3
District
Airport Area
O&M Al-Khaleej
Centre District
Evap. Jubail
Stn. Industrial
RC College
WTP #3 T6 HQ
TS6 T100
T106
T112
Al-Huwaylat
Al-Huwaylat
Block E-South District
Stage 3 and 4
T113
Stg.2 St. 1 Block N
Island
SWTP Block J-South
T289
Stormwater Strm.W SWTP #9 Storm- T120
(Exp.)
Holding Pond H.Pond water NWPS
Pond
T1 0
T130
1
Al-
Lulu
District
T138
T147
68 69 T148 47
T150 6
24 T154
Kh a
Al-
Ar a b i a n
Shati
T295
rsa
9 7
Sa u
74
T162 District
Gu l f
niah
5
di E
79
le ct
R as
O&S 23
T263
T251
T241
Ra il
ric
Centre Jubail 1
Ta n
Block P T174
C om
ro a
u
49 4
Industrial Area
ra R
dR
pan
47 55
OW
OW
46
yR
T184
OW
22
T259
T195
Block K Block F
53 54
T143
51 52
T163
T198
3
T289
Sanitary 59 T204 IWPP
56 Fac.
Landfill
IWTP #8
T223
57 58
Desal.
2 10 11 #2
1 T218
RC T230
Scap
15 16
Jubail 2 Fac. 21 18 20
Industrial Area T2 1
8
Sanitary
TS1
Landfill
T241
T121
T195
T183
T161
T261
Block Q Block L Block G
TS3
T2 74
MOT
BeeA'h T272
85
T2 74
3
TS
EXISTING INDUSTRIAL WASTEWATER LINE EXISTING INDUSTRIAL, MAJOR ROADS SECONDARY INDUSTRY SERVICING AREA
JUBAIL INDUSTRIAL CITY
FUTURE INDUSTRIAL WASTEWATER LINE PROPOSED INDUSTRIAL, MAJOR ROADS FUTURE SECONDARY INDUSTRY SERVICING AREA
MASTER PLAN UPDATE
EXISTING PUMPSTATIONS PRIMARY INDUSTRY SERVICING AREA SUPPORT INDUSTRY/NORTHERN CORRIDOR SERVICING AREA
EXISTING INDUSTRIAL WASTEWATER TREATMENT PLANT FUTURE PRIMARY INDUSTRY SERVICING AREA FUTURE SUPPORT INDUSTRY SERVICING AREA
FIGURE 5-2
CURRENT PLANNED INDUSTRIAL
WASTEWATER SYSTEM
BASE DATA PROVIDED BY MAP PROJECTION: AIN EL ABD UTM ZONE 39N
THE ROYAL COMMISSION FOR JUBAIL AND YANBU. PROJECT #: 078523
STATUS: FINAL
0 0.5 1 2 km FILE LOCATION: G:\GIS\078523 JUBAIL MP SAUDI ARABIA\ DATE: 12/21/11
GIS DATA\MXDS\MP FIGURES - MXD'S\
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
Table 5-3
Summary of Pertinent Design Guidelines for Industrial Wastewater and MPU Assessment
Figure 5-3
Industrial Wastewater Actual Use 2004-2008
60
50
40
x 000 m3/day-pk
30
20
10
-10
2004 2005 2006 2007 2008
Peak Availability 57 57 57 57 57
Peak Production Demand 43 43 52 50 48
Peak Surplus/Deficit 13.9 13.7 5.1 7.5 8.7
Yearly Growth -0.5% 0.6% 19.9% -4.5% -2.4%
Year
Source "MARAFIQ Demand Forecast 2008-2017 (DF2008) for RC Jubail - Master Plan Input",
MARAFIQ Demand Forecast Department (March 31, 2008), and information provided by
MARAFIQ in March/April 2009
This shows that IWW generation increased by 0.6% and 19.9% in 2005 and
2006, and decreased by 4.5% and 2.4% in 2007 and 2008. It is reasoned
that the decrease in IWW in 2007 and 2008 was due to the slowdown of
industries due to global market factors that resulted in less production by
industries. Actual use in 2008 was 48,000 m3/day and there was a surplus in
the system of 8,700 m3/day-peak.
who are concentrating the effluent and sending less quantity with more
organic loading. This may be to decrease the cost of disposal as MARAFIQ
charges for IWW treatment based on quantity, not quality. MARAFIQ has
also indicated that Stages I and II can only treat 41,700 m3/day (about 70%
of design capacity) due to the increase of IWW strength in the influent flows.
In 2007, Nexant prepared a study for the RCJ titled “Feasibility Study of
Jubail 2 Expansion (Stage 4)” to determine the impacts of expanding J2 from
3 stages to 4 stages. This report undertook a high level review of the design
prepared for J2 Stages 1 to 3 in order to assess whether it presented any
constraints to the development of J2 Stage 4. This report indicated that the
total volume of IWW generated by industries in J2 (Stage 1 through 4) was
expected to be around 51,000 m3/day by 2030, including an allowance of
approximately 1,600 m3/day for secondary industries and that the capacity of
the IWTP (60,000 m3/day) was insufficient to meet the estimated demand in
2030 from J1 (102,000 m3/day) and J2 (51,000 m3/day). The report
concluded that the total volume of IWW generated by industries in J2 is lower
than the design capacity of the system (100,000 m3/day). Based on the
Alternative Feedstock Basis for J2, this number is now expected to top
126,000 m3/day by 2030, which is not even full-build out for J2.
The MARAFIQ Supply Plan indicated that there could be a short term deficit in
2009. Stage I (which is reserved capacity lagoon based treatment) was used
provide relief during daily peak and also during the 2009 deficit with efficient
aeration. Stage I will later transform into balancing, equalization and
emergency reserve. There is an approved CAPEX for the Stage III expansion
of 55,000 m3 /day using conventional biological process (activated sludge)
which is anticipated to be online in 2011.
The major findings of the MARAFIQ Supply Plan Network Analysis for IWW
indicated that there is a deficit in IWW PS capacity in PS-10, PS-11, PS-15
and PS-16. A CAPEX to upgrade these PS’s was approved and completed in
2010. They also determined that there was a concern with emissions of
odour due to inadequate odour control system.
The August 2010 MARAFIQ projections show IWW demand in 2009 as 49,000
m3/day and anticipated sales of 95,000 m3/hr by 2020, which can be met for
both treatment and conveyance.
The August 2010 RCJ projections showed IWW demand in 2009 as 64,000
m3/day and a forecasted demand of 148,000 m3/day in 2018, which would
result in a shortfall in capacity of the current planned treatment capacity.
Once flows for J2 are increased, this would add to the deficit.
Findings of MPU
Table 5-4 and Figure 5-4 illustrate the MPU IWW demand forecast through
2030.
Table 5-4
Industrial Wastewater Capacity and MPU Demand Forecast to 2030
Figure 5-4
Industrial Wastewater Treatment Capacity and MPU Demand
Forecast to 2030
300
250
200
x' 000 m3/day
150
100
50
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Year
Table 5-5 Summarizes the IWW treatment capacity shortfalls anticipated for
the planning period, split into the short term, mid term and long term.
Table 5-5
Industrial Wastewater Treatment Shortfalls
Table 5-6 illustrate the MPU IWW demand forecast for J1 through 2030.
Table 5-6
Jubail 1 Primary Pumping Station Capacity and MPU Demand
Forecast to 2030
J1 Primary PS Capacity
Year (m3/day) J1 Demand (m3/day)
2010 333 88
2011 333 95
2012 333 105
2013 333 116
2014 333 132
2015 333 147
2016 333 147
2017 333 148
2018 333 148
2019 333 149
2020 333 149
2021 333 150
2022 333 151
2023 333 152
2024 333 152
2025 333 153
2026 333 154
2027 333 155
2028 333 156
2029 333 156
2030 333 157
Though on an aggregate level the primary PSs have the capacity to meet the
demand in J1, the PSs should be reviewed individually to confirm this. Also,
the secondary PSs need to be reviewed.
Any actions undertaken to reduce process water demand will reduce the IWW
that needs to be treated. A Process Water Demand Management and Water
Conservation Strategy should be investigated as discussed under Section4.5.
The process currently used by industries for tank washing should be reviewed
to ensure that they are using the most economical, sustainable and
appropriate methods and schedules for tank washing.
MARAFIQ has indicated that industries are currently not meeting the
discharge quality criteria where flows enter the wastewater collection system,
however verification of this was not provided. This needs to be further
investigated to verify if this is currently monitored and enforced and if it is
not, this needs to be done. In Canada this is generally done through the
implementation of a sewer use by-law which restricts the quality of effluent
that can be discharged into municipal sewers combined with a rigorous
monitoring and penalty system for infractions.
The 1999 MPU also identified Industrial Wastewater TDS Limit concerns and
recommended that in order to comply with the combined total dissolved
solids (TDS) limits, as established in the RCER, some industries have used
PW to dilute their effluent streams. To minimize the use of PW, it was
recommended that industries be provided with incentives to recycle process
water, potentially using the following approaches; charging fair market value
for PW; restricting industrial water outflow; requiring industry to pre-treat
process water other than by dilution. In the interest of PW conservation, it
was recommended that analysis of this issue should proceed on the following
basis:
Determine the extent by which the industries practice PW dilution of
their effluent streams.
Determine the extent by which the TDS limits at individual discharge
points could be relaxed without raising the TWW TDC and TDS content
beyond the prescribed limits.
Determine the extent by which the TWW TDS and TDC limits could be
raised without adverse effects on plant life. TDS and TSS are a concern
for irrigation system too as clogging and other problems are common
with irrigation system that have a higher TDS and TSS values.
Assess the ability of the industrial wastewater treatment system to
treat wastewater with higher TDS limits.
If the current influent quality continues, this could reduce the plant capacity
by 125,000 m3/day (70%).
On-site Reuse
5.5.2 Supply
MARAFIQ has indicated that the Stage I aeration system was used to
mitigate the 2009 shortfall and can be used to continue to help mitigate the
shortfall.
If the Stage IV expansion is brought online earlier they could address the
shortfall in the short/mid term and postpone a complete shortage until 2014.
If point source treatment criteria is not being met by industries, one solution
would be upgrading the current IWTP to address the additional
environmental criteria that are limiting the current capabilities of the plant.
This should be investigated and tariffs reflecting that IWTP 8 (rather than the
individual industries) are carrying the costs of meeting the RCER quality
criteria.
The COD/BOD ratio of the IWW is quite low for industrial effluent and has
dropped marginally between 2006 and 2009.
Outlet BOD has risen from an average of 20 mg/l in 2006 to 40 mg/l in 2009.
No clear trend was apparent for total suspended solids (TSS). In 2006 TSS
was 30 mg/l, increasing to over 60 mg/l in 2007 and then decreasing again.
Turbidity follows a similar trend to TSS.
The report shows compliance with RCER 1999 maximum standards as follows
(generally showing improvement with the exception of BOD):
Ammonia – SWW enters plant at less than the RCER maximum
standard of 40 mg/l so plant performance is 100%.
COD – maximum standard is 350 mg/l, so plant performance is 100%.
TSS – in 2006 compliance was 25% and in 2009 was 80%.
The report shows compliance with RCER 1999 monthly average standards
(using annual average) as follows:
Ammonia – monthly average standard is 15 mg/l and was 19 mg/l in
2009.
COD – monthly average standard is 150 mg/l and was 113 mg/l in
2009.
TSS – monthly average standard is 10 mg/l and was 9.9 mg/l in 2009.
Turbidity – monthly average standard is 2 NTU and was 7 NTU in
2009.
BOD – monthly average standard is 25 mg/l and was 39 mg/l in 2009.
MARAFIQ has indicated that the 2004 RCER revisions will particularly create
problems with the IWTP process requirements. The criteria for organic
loading are based on a maximum concentration of Total Organic Carbon
(TOC) of 800 mg/L. This parameter does not correspondingly regulate the
organic loadings of BOD and COD which more dramatically affect the
treatment process. Consequently it is difficult to assess the actual hydraulic
and organic load capacity of the treatment plant. MARAIQ previously
indicated that IWTP 8 would unlikely to be able to meet the 2004 RCER with
respect to COD and perhaps BOD and other parameters. Based on the
available data, chlorination is problematic as evidenced by high Total
Coliforms (TC) and very low residual chlorines. The combined upgrade of
Stages I and II occurred to a capacity upgrade of 65,000 m3/day with 120
mg/l BOD & 500 mg/l COD. However based on more recent information,
they have indicated that the plant will meet RCER 2004 in 2012, but at a
reduced capacity (41,700 m3/day).
A review of the 2004 RCER standards found that IWW discharge, SWW
discharge, and irrigation water standards met the RCJ environmental
objectives and the international state-of-the-art parameters. The regulations
also comply with the RCJ zero discharge policy. In case treated IWW
discharged from industries does not meet the quality standards, the RCJ
Penalty System has the capacity to alleviate such problems and enforce
compliance.
The IWW pump stations are designed in series, ultimately leading to IWTP 8.
Blocks E, J, and N in the J1 Support Industries Area are served by a Sanitary
Wastewater network only. This should be looked at to determine if these
areas should be included in the IWW system. This should be determined by
reviewing the quality of the water being discharged by the industries to the
SWW system.
J2 IWW will connect direction to ITWP 8 and there will be no tie in point
between the J1 and J2 networks, therefore J2 will not impact the J1 network
capacity. On an aggregate level it appears that there should be sufficient
pumping capacity available in the primary J1 IWW PS’s (1, 18 and 22) for the
projected flows, however a hydraulic analysis should be conducted to confirm
this. Also, the secondary PS’s need to be reviewed.
The TWW pipeline network is owned by RCJ where MARAFIQ disposes their
surplus TWW through this network and MARAFIQ has no control of this
network. MARAFIQ’S responsibility ends at the boundary limit of SWTP 9 and
IWTP 8 and the boundary wall of the Al-Fanateer and Al-Deffi PSs. MARAFIQ
has proposed that the disposal of surplus TWW be provided through the
installation of a dedicated surplus TWW line from IWTP 8 to the TWW
discharge area. This is discussed further in Chapter 7.
5.6 Recommendations
The following table outlines the key recommendations related to IWW. Many of the recommended studies need to occur in the short term, however their results will be implemented over the
mid and long term to meet the IWW requirements of JIC.
Table 5-7
Industrial Wastewater Recommendations
This study should assess the impacts of IWW quality being discharged from industries on the performance
and treatment efficiency of IWTP 8. Regular wastewater flow monitoring through installation of temporary
flow meters and samplers at the main wastewater collection junctions is a recommended Best
Management Practice. Flow metering will provide more in depth wastewater flow characteristics (Peak
flow, average daily and monthly). This information has great value for short term and long term
planning, design and monitoring of the wastewater system. A CAPEX project for installing on-line
analyzers to monitor most of the primary industries has already been proposed.
MARAFIQ has recommended that tankered wastewater no longer be accepted from JANA as it is high in
TOC and TDS which is excessively loading the plant.
Review of RCER: Development of categorical standards based on industry This approach is effectively applied in different jurisdictions. There are no pre-treatment standards for RCJ Short Term
specific wastewater discharges is recommended. As recommended in the some important parameters (BOD, COD, and Silver). We recommend updating Table 2-G to include these MARAFIQ
1999 MPU, review RCER to: parameters.
Determine the extent by which the TDS limits at individual
discharge points could be relaxed without raising the TWW TDC and To ensure that RCER are providing the most appropriate criteria for the function of the plant and the
TDS content beyond the prescribed limits. impact on the environment.
Determine the extent by which the TWW TDS and TDC limits could
MARAFIQ has indicated that all PSs need to be upgraded and that all PSs are the relay type so if one is
increased in capacity, it will overload all subsequent PSs. RCJ has identified that this study is required but
a Task Number has not been issued to date.
Review current design capacity of J2 network. It is our understanding that the IWW system for J2 has been designed based on the assumption of total RCJ Short Term
demand of 100,000 m3/day. This MPU has projected higher demands, so the system design should be
reviewed.
Investigate feasibility of dosing chemical coagulant to augment To ensure proper performance of network and to meet demand. MARAFIQ Short Term
performance on clarifier or PST and dosing polymer to augment IWTP 8 RCJ
performance.
SWTP 9 was constructed in stages through the 1980’s. The original plant has
a capacity of 72,000 m3/day. An expansion was undertaken in 2010 to
provide an additional capacity of 15,000 m3/day. MARAFIQ has indicated that
SWTP 9 currently complies with RCER 1999, and any expansions will comply
with RCER 2004, and then RCER 2009 as appropriate once adopted. They
have indicated that the above noted expansion for 15,000 m3/day will be
reduced to 10,000 m3/day in 2014 to comply with RCER 2004.
Preliminary Treatment
Screening: To remove large objects from the incoming raw sewage,
which could foul pumps and other equipment.
Grit removal: To remove, sand, and fine and heavy inorganic
materials, which could cause abnormal, wear to pumps and excessive
deposits of grit in sludge digesters.
LI
T-AB U-A
Al-Gurmah
Island JUBAIL INDUSTRIAL CITY
Al-Reggah Jalmudah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
C1
Airport Area FIGURE 6-1
A1
T2 EXISTING SANITARY
WASTEWATER SYSTEM
Mardumah
T6
D1
Bay Community
TS4
TS 7
District
EXISTING INDUSTRIAL, MAJOR ROADS
T3
Al-Fanateer PERMANENT COMMUNITY SERVICING AREA
P1
P2 Island
EASTERN CORRIDOR SERVICING AREA
O&M Al-Khaleej
Centre District
PRIMARY INDUSTRY SERVICING AREA
Evap. Jubail
Stn. P3 Industrial
See Detailed RC SECONDARY INDUSTRY SERVICING AREA
College
WTP #3 T6 HQ
Figure SUPPORT INDUSTRY/NORTHERN CORRIDOR
TS6 T100
Al-Huwaylat
T106
SERVICING AREA
Block J-South
43 42 41 T112 Island
T289
St. 1
T113
Stage 3 and 4 Stg.2 28 29 30 31 32 33
SWTP Storm-
Stormwater Strm.W T120 Al-Huwaylat
(Exp.) SWTP #9 water NWPS Block N
Holding Pond H.Pond 38 39 40 District
Pond 35 36 37
T1 0
P4 T130 Block E-South
Al-
1
Lulu
T138 T138
District
T147
Kh a
T150 69 70 T148
68 6 47
Sa u
T154
rsa
24
T295 Ar a b i a n G u l f
di E
niah
9 7
T251
74 T162 Al-
5 Shati
le ct
R as
O&S 79
Ra il
T195
District
T263
T241
Block P 23
ric
Centre
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
49 4
Industrial Area
dR
ura
47 55 Industrial Area
pan
46
O
T184
RO
yR
22 Block K Block F
W
T259
OW
T143
T163
51 52 53 54
Sanitary 3
59 T204
Landfill 56
T223
T218 57 58
IWTP #8
1 T218 2 10 11 12 14
RC
Scap T230
Fac. 21 18 20 15 16
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
56 King Fahd
BeeA'h T272
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
JUBAIL INDUSTRIAL CITY
MASTER PLAN UPDATE
FIGURE 6-2
Stores Garage Workshop Warehouse
SANITARY WASTEWATER
TREATMENT PLANT 9 SITE
PLAN
Blower
Tanks Sedimentation Tank #3
House
Sedimentation Tank #4
Centrifuge
Chemical Building Building
Thickening Tanks
NOT TO SCALE
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
Primary Treatment
Primary sedimentation: Primary sedimentation tanks are designed to
remove heavy coarse settable solids and scum from the wastewater.
Primary effluent flows to secondary treatment and primary sludge is
pumped to the primary digester for treatment. The process removes
30-35% of raw wastewater BOD and 40% of suspended solids.
Secondary Treatment
Biological treatment: A process to remove dissolved pollutants (non-
settable) from wastewater by converting them to settable solids
(biological sludge), which can be removed by settling. The aeration
tanks provide a place for mixing bacteria with primary effluent as well
as providing oxygen for the bacteria. The biological process takes place
in the aeration tanks. In the secondary settling tanks, return activated
sludge (biological sludge) settles by gravity and is returned by
pumping to the aeration tanks. Secondary effluent passes over the
weirs to the filter feed pump station. Approximately 85-90% BOD and
suspended solids are removed.
Tertiary Treatment
Filtration: The secondary effluent is pumped to the pressure dual
media (anthracite/grit) filters.
Disinfection: Chlorine is added to the filtered effluent for disinfection
(killing of disease causing bacteria) so that the effluent conforms to
health standards stipulated for landscape irrigation.
Advanced Treatment
The purpose of the advanced treatment is to improve the effluent
quality for unrestricted landscape irrigation. The plant applies flow
balancing and post-precipitation and has the ability to operate in a
high lime, low lime or alum precipitation mode. Chemical coagulants
such as lime or alum can be added to wastewater for enhancing the
removal of suspended solids and phosphorus. This plant is on standby
mode.
Waste from the screening and grit removal process are disposed of at the
RCSLF. In addition, sludge is thickened and press filtered to 30% solids and
landfilled at the RCSLF. This is addressed under Chapter 11.
The SWW network provides collection and conveyance systems for SWW
from JIC and Al-Jubail. The network is comprised of gravity, force mains, and
PSs. The SWW is conveyed to SWTP 9 via primary PSs 3, 4, 24 and 56. In
order to provide odour control, oxygen injection systems are installed at
primary, secondary and support industries area PSs. Oxygen is injected into
the sewers on an automatic basis at rates sufficient to maintain the SWW in
an aerobic condition to avoid septic conditions.
The SWW network consists of 58 pump stations and 222 lift stations. The
pumping capacity ranges from 557 to 248,000 m3/day. These PSs are
indoors, which help to keep pumps in good condition since the PSs were
commissioned throughout the 1980’s. The first expansions of PS-15 and PS-
16 were completed in 2003 and the next stage was completed in 2009/2010.
Community
SWW from the community area is conveyed for treatment through a system
of inter-connecting pumping mains and PSs. The collection system in the
community consists of three (3) levels of operation, primary, secondary and
tertiary. Gravity sewers discharge into the lift stations, which in turn pumps
into the secondary system then to the primary system and finally to SWTP 9
for treatment.
Al-Jubail
SWW from Al-Jubail is pumped through a force main line from the Al-Jubail
PS, collected and conveyed to SWTP 9 via PS-56 and P-4.
Industrial Area
The JIC SWW collection system, is made up of the following five service
areas, each delivering directly to SWTP 9:
In the primary industry park, dual function PSs are located within the
boundary line of each industrial site. The SWW design capacity in the
primary industry park is 248,000 m3/day. Exceptions are the IBN
SINA and SASREF sites which are served by PSs located on the SAMAD
(PS-6) and PETROKEMYA (PS-16) sites respectively, and the SADAF
site (PS-12), which has only a SWW PS. Industries are responsible for
transferring their effluents by pipelines to the PSs.
Table 6-1 summarizes the current proposed expansion plans for treatment of
SWW.
Table 6-1
SWTP 9 Existing Capacity and Proposed Expansions
Table 6-2
Sanitary Wastewater Primary Pumping Station Capacity
LI
T-AB U-A
C2
Al-Gurmah
Island JUBAIL INDUSTRIAL CITY
A2
G2 Al-Reggah Jalmudah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah E2
District
C1
Airport Area FIGURE 6-3
A1
G1 T2 CURRENT PLANNED SANITARY
E1 WASTEWATER SYSTEM
Mardumah
T6
D1
Bay Community
TS4
TS 7
Pumping District
Station FUTURE PUMPSTATIONS (TO 2030)
T3
FUTURE PUMPSTATIONS (AFTER 2030)
Al-Fanateer
P1
Future Primary P2 Island EXISTING LIFTSTATIONS
Sewage Pumpstation
(To Replace Existing P-2) P2 O&M Al-Khaleej EXISTING PACKAGE TREATMENT PLANT
Centre District
Evap. Jubail
Stn.
EXISTING WASTEWATER TREATMENT PLANT
P3 Industrial
See Detailed RC College
WTP #3 T6 HQ EXISTING INDUSTRIAL, MAJOR ROADS
Figure
TS6 T100
T106 Block J-South Al-Huwaylat PROPOSED INDUSTRIAL, MAJOR ROADS
43 42 41 T112 Island
T289
St. 1
T113
Stage 3 and 4 Stg.2 28 29 30 31 32 33 PERMANENT COMMUNITY SERVICING AREA
SWTP Storm-
Stormwater Strm.W T120 Al-Huwaylat
(Exp.) SWTP #9 water NWPS Block N
Holding Pond H.Pond 38 39 40 District
Pond 35 36 37 FUTURE COMMUNITY SERVICING AREA
T1 0
P4 T130 Block E-South
Al-
EASTERN CORRIDOR SERVICING AREA
1
Lulu
T138 T138
District PRIMARY INDUSTRY SERVICING AREA
T147
Kh a
T150 68 69 70 T148
6
FUTURE PRIMARY INDUSTRY SERVICING
47
Sa u
T154 AREA
rsa
24
T295 Ar a b i a n G u l f
di E
niah
9 7
T251
74 T162 Al-
5
SECONDARY INDUSTRY SERVICING AREA
Shati
le ct
R as
O&S 79
Ra il
T195
District
T263
T241
Block P 23
ric
Centre T174
FUTURE SECONDARY INDUSTRY SERVICING
Jubail 1
Ta n
ro a
C om W
49 4 AREA
dR
ura
46
O
T184
RO
SERVICING AREA
yR
22 Block K Block F
W
T259
OW
T143
FUTURE SUPPORT INDUSTRY SERVICING
T163
51 52 53 54
3
AREA
Sanitary 59 T204
Landfill 56
T223
T218 57 58
IWTP #8
1 T218 2 10 11 12 14
RC
Scap T230
Jubail 2 Fac. 21 18 20 15 16
Industrial Area
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
56 King Fahd
BeeA'h T272
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/21/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
Overall, the criteria outlined with respect to SWW has been adequately tested
in the wastewater systems installed to date. However, there have been
problems with meeting some of the quality parameters identified.
Recommendations for this are provided in sections 5.6, 6.6 and 7.6. Table 6-
3 summarizes comments on the relevant criteria under 5.05 Subsections A
and C and on portions of 2.03 Subsection A.
Table 6-3
Summary of Pertinent Design Guidelines for Sanitary Wastewater and MPU Assessment
Figure 6-4
Sanitary Wastewater Actual Use 2004-2008
90
80
70
60
50
x 000 m3/day-pk
40
30
20
10
-10
-20
2004 2005 2006 2007 2008
Peak Availability 68 68 67 70 70
Peak Production Demand 58 63 66 71 76
Peak Surplus/Deficit 11 5 1 -1 -6
Yearly Growth 3.6% 8.7% 4.9% 6.8% 7.0%
Year
Source "MARAFIQ Demand Forecast 2008-2017 (DF2008) for RC Jubail - Master Plan Input",
MARAFIQ Demand Forecast Department (March 31, 2008), and information provided by
MARAFIQ in March/April 2009
This shows that SWW generation increased by 8.7%, 4.9% and 6.8% and
7% annually between 2004 and 2008. It also shows that in 2008, based on
actual use of 76,000 m3/day, that there was a shortage in the system of
6,000 m3/day-peak.
In 2009, the flow rate was approximately 77,000 m3/day, which is 7% over
the design capacity.
In 2007, Nexant prepared a study for the RCJ titled “Feasibility Study of
Jubail 2 Expansion (Stage 4)” to determine the impacts of expanding J2 from
3 stages to 4 stages. This report found that SWW production from J2 is
expected to reach a peak of 8,200 m3/day by 2030. This was made up of
6,000 m3/day from primary industries or industrial clusters, and 2,300
m3/day from secondary and support industries. Given that the J2 SWW
system will be developed as a branched system, the design of J2 stages 1
through 3 will not be a constraint on the development of Stage 4. Based on
the Alternative Feedstock Basis for J2, this number is now expected to top
36,000 m3/day by 2030, which is not even full-build out for J2.
The MARAFIQ Supply Plan predicted a short term deficit in 2010/2011 and no
deficit in SWW treatment capacity during the remainder of forecast period,
2017. They used the Stage 1 aerators to help mitigate this. The report
indicated that the long-term deficit in treatment plant capacity could be met
by the expansion of SWTP 9 Phase 2 to add 55,000 m3/day treatment
capacity. PS-56 will have inadequate pumping capacity to receive Al-Jubail
SWW. An upgrade is proposed for PS-56 to help meet this demand. In the
short term, a portion of Al-Jubail SWW flow was diverted to PS-20 and the
tankered wastewater disposal from PS-56 was shifted to SWTP 9.
The August 2010 RCJ projections through 2018 show SWW demand of
94,000 m3/day in 2009 increasing to 177,000 m3/day by 2018 (with J2
showing as 0), which would result in a shortfall in capacity the current
planned treatment capacity. Once flows for J2 are included, this would
increase the deficit further.
Findings of MPU
Table 6-4 and Figure 6-5 illustrate the MPU SWW demand forecast through
2030.
Table 6-4
Sanitary Wastewater Capacity and MPU Demand Forecast to 2030
Capacity
(x 000 m3/day) Demand (x 000 m3/day)
Primary Al-
Year SWTP 9 PSs Community Jubail J1 J2 Total
2010 87 616 46 41 26 0 113
2011 142 616 49 43 27 0 119
2012 142 616 54 44 28 1 127
2013 142 616 59 45 29 2 135
2014 137 616 63 47 30 9 150
2015 137 616 68 48 30 16 163
2016 137 616 73 49 30 16 169
2017 137 616 78 51 30 20 179
2018 137 616 83 52 30 23 188
2019 137 616 87 54 30 27 197
2020 137 616 91 55 31 30 207
2021 137 616 96 57 31 30 214
2022 137 616 101 59 32 30 221
2023 137 616 105 60 32 30 228
2024 137 616 110 62 33 33 238
2025 137 616 115 64 33 36 248
2026 137 616 120 66 34 36 255
2027 137 616 124 68 34 36 262
2028 137 616 129 70 35 36 270
2029 137 616 134 72 35 36 277
2030 137 616 139 74 36 36 284
Figure 6-5
Sanitary Wastewater Capacity and MPU Demand Forecast to 2030
700
600
500
400
x' 000 m3/day
300
200
100
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Year
Though on an aggregate level the primary PSs have the capacity to meet the
demand in J1, the PSs should be reviewed individually to confirm this. Also,
the secondary PSs need to be reviewed.
Table 6-5
Sanitary Wastewater Treatment Shortfalls
Table 6-6
Community Sanitary Wastewater Demand Forecast (2030)
Any reduction for demand for PW in the community and in the industrial
areas for domestic water use will decrease the SWW that needs to be
treated. Refer to Section 4.5 for information regarding water demand
management and conservation.
Al-Jubail currently has no SWW treatment facility and disposes of their SWW
and IWW to JIC’s SWTP 9 via the JIC separate SWW sewer network..
Recently, Al-Jubail has accounted for approximately 35% of the effluent
treated at SWTP 9. This practice has proven to be a serious detriment to
JIC’s SWW collection system, SWTP 9 performance and the production of
excess TWW. It is strongly recommended that this practice be discontinued
and the construction of a separate treatment facility in Al-Jubail be promoted
and implemented.
The SWW characteristics and organic loadings from Al-Jubail have posed
significant problems in the SWW system. It is known that industrial
wastewater is included in the SWW from Al-Jubail as it is a combined
BOD would have been expected to be 20 mg/l or lower. This could indicate a
problem with the secondary (or biological) treatment at the plant.
The total suspended solids (TSS) in early 2006 was 12 mg/l and in 2009 this
has increased to 34 mg/l. This is well above the RCJ average monthly
standard of 10 mg/l. Turbidity has risen from 4 NTU in 2006 to 25 NRU in
2009. The RCJ average monthly standard is 2 NTU and the maximum is 5.
Both of these will impact the performance of the pressure filter. There are
also concerns with the secondary (or biological) treatment at the plant.
6.5.2 Supply
Reduction of Organic and Hydraulic Loading in JIC with new Al-Jubail SWTP
In the past SWTP 9 has been upset due to high concentration of COD which
MARAFIQ has indicated that this could be from IWW and/or tanker waste
shock loadings. The treatment process took about 40 days to revive. During
this time the effluent quality was seriously affected, obnoxious odors
emanating from the plant upset the public, and an environmental report was
submitted to the RCJ Environment Control Department.
Upgrade/Expand SWTP 9
This would need to be investigated to ensure that expansions to the existing
plant make economic sense and to confirm that it is possible with the
remaining land available.
MARAFIQ has indicated that all PSs need to be upgraded and that all PSs are
the relay type operating in series so if one is increased in capacity, it will
overload all subsequent PSs). PS-56 is particularly affected if RCJ continues
to allow Al-Jubail’s SWW to be connected to the JIC system. As identified
above, a comprehensive hydraulic study and wastewater loading survey
should be conducted on the Al-Jubail SWW collection system including a
feasibility study for separately treating all wastewater from Al-Jubail.
6.6 Recommendations
The following table outlines the key recommendations related to SWW. Many of the recommended studies need to occur in the short term, however their results will be implemented over the
mid and long term to meet the SWW requirements of JIC.
Table 6-7
Sanitary Wastewater Recommendations
MARAFIQ has indicated that all PSs need to be upgraded and that all PSs are the relay type so if
one is increased in capacity, it will overload all subsequent PSs.
Review current design capacity of J2 network. It is our understanding that the SWW system for J2 has been designed based on the assumption RCJ Short Term
of total demand of 8,200 m3/day. This MPU has projected higher demands, so the system design
should be reviewed.
Conduct a feasibility study to identify upgrades required for PSs and the piping To ensure proper performance of network and to meet demand. This should include identifying MARAFIQ Short-Term
network. upgrades to PS-56 to allow it to continue to receive Al-Jubail SWW beyond 2010.
Implement upgrades to PS-56 per approved CAPEX. To ensure proper performance of network and to meet demand. MARAFIQ Short-Term
Implement source testing at treatment plants and identify best means for odor To ensure additional control of VOC emission and to identify air quality and odor contamination. MARAFIQ Short-Term
control. RGME recommended that immediate source testing at the treatment plants be conducted for through to
establishing emission rates, and assessing the best technology for odor control. Future designs Mid-Term
The TWW is pumped from SWTP 9 and IWTP 8 to TWW storage tanks located
at each treatment plant. It is then pumped into the distribution network
where it is primarily used in irrigation of community and industrial
landscaping. Although the daily rate remains relatively constant throughout
the year, there are seasonal variations in actual operational cycles. In the
summer months, the systems are operated six days per week, except Friday.
In the winter months, operation is on alternate days or four days per week.
The TWW from IWTP 8 is filtered, disinfected and stored in TWW storage
tanks at the IWTP 8 site. The installed ground storage capacity at IWTP 8 is
sufficient to store 40 hours of treated effluent at the IWTP Stage II design
flow rate (41,700 m3/day). Future stage development will incorporate
additional capacity to meet the 40 hours storage requirement. If dilution is
needed to attain the desired effluent quality, PW can be added into one of
the storage tanks.
TWW from IWTP 8 currently serves J1 and the eastern corridor. The TWW
distribution system for J1 is limited to accommodate only the highway and
corridor irrigation requirements within the parks. Irrigation in the support
and light industries area uses the TWW from SWTP 9 and IWTP 8.
Previously, areas within each industry's plot were irrigated mostly with PW,
however the RCJ has indicated that PW is no longer used.
LI
T-AB U-A
Al-Gurmah
Island Jalmudah JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
Mardumah
T6
Bay
TS4
Community TREATED WASTEWATER STORAGE TANKS
Al-Mutrafiah Area
District TREATED WASTEWATER STORAGE PONDS
Al-Deffi
Al-Fasil TREATED WASTEWATER PUMPSTATIONS
TS4
District
District
Al-Fanateer TREATED WASTEWATER NETWORK
District
WASTEWATER TREATMENT PLANTS
TS 7
EXISTING INDUSTRIAL, MAJOR ROADS
T3
Al-Fanateer PERMANENT COMMUNITY SERVICING AREA
Island
EASTERN CORRIDOR SERVICING AREA
O&M Al-Khaleej
Centre District
PRIMARY INDUSTRY SERVICING AREA
Evap. RC Jubail
Stn. HQ Industrial SECONDARY INDUSTRY SERVICING AREA
College
WTP #3 T6
TS6 T100 SUPPORT INDUSTRY/NORTHERN CORRIDOR
T106 Block E-South Al-Huwaylat SERVICING AREA
T112 Island
T113
Al-Huwaylat
Stage 3 and 4 Stg.2 St. 1 AIRPORT SERVICING AREA
SWTP Block N District
T289
Stormwater Strm.W Storm- Block J-South T120
Holding Pond H.Pond
(Exp.) SWTP #9 water NWPS
Pond
T1 0
T130 Al-
Lulu
1
T138 District
T138
T147
Kh a
T150 T148
Al-
Sa u
T154
rsa
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S
Ra il
T263
T251
T241
T195
ric
Centre Block P
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
ura
pan
O
T184
RO
yR
Block K Block F
W
T259
OW
T143
T163
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218
#2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 4/15/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
TWW distribution network for primary and secondary industry areas in J1 are
connected to the TWW distribution system for the support industry area at
three locations. At each junction, sectional valves are installed for isolating
the two systems. TWW for the support industry area, eastern corridor,
northern corridor camps, Royal Commission building, and Jubail Industrial
College can be pumped either from IWTP 8 or SWTP 9 by closing and opening
certain sectional valves, allowing the primary and secondary industry areas
to be isolated from the rest of the TWW system in JIC.
TWW PS’s at IWTP 8, have two separate sets of pumps. Four high lift pumps
discharge into the TWW system, which will normally operate over a period of
16 hours maximum. These are controlled by the TWW distribution grid
system pressure. Excess TWW is discharged to SWTP 9 for further storage or
to the TWW discharge area for disposal by evaporation and infiltration. This
transfer is controlled manually.
7.1.2 Community
TWW from SWTP 9 is used for landscape irrigation for the permanent
community and eastern corridor residential camps, including all public parks.
The community irrigation system consists of a primary, secondary, and
tertiary system. These systems include storage, transmission mains, district
PSs and lateral irrigation lines which are responsible for transferring TWW
from SWTP 9 to points of application.
In the primary system, the TWW from the SWTP 9 is filtered, disinfected and
stored in the TWW storage tanks at SWTP 9. TWW is pumped from SWTP 9
storage tanks to ground level irrigation storage tanks at each district's water
PS in the community. The pumps are sized to transfer all of the stored water
at SWTP 9 during the 12 hour period when irrigation is to occur. Sufficient
storage capacity is provided for 32 hours of treated effluent output at the
SWTP 9 design flow rate.
and distribute the water to the tertiary irrigation systems. The distribution
mains are usually located along the roadways in secondary utility ROWs.
In the tertiary irrigation system, TWW is distributed for landscaping irrigation
along freeways, expressways, collector, local and residential roads, utility
ROW, parks, pedestrian walkways, incidental open spaces and in the
landscaped corridors within the community. The tertiary system provides for
fully automatic timed control to minimize labour requirements and maximize
reliability. Most irrigation is typically applied in the early morning and/or
evening hours in order to reduce evaporation losses.
SWTP 9 TWW pumps are controlled by the demand for TWW for irrigation as
determined by the water level in the district's irrigation storage tank in the
community. As the water level in the community ground storage tank drops,
an electrically operated valve opens allowing water from the transmission
mains to fill the tank. This decreases water pressure in the transmission
mains, and a pressure sensor at the SWTP 9 TWW PS starts the transfer
pumps.
A transfer pipeline was constructed to transfer any excess TWW from IWTP 8
to the TWW storage tanks at SWTP 9. If there is more TWW generated at
SWTP 9 than the storage tanks can hold, the excess can be discharged via
force main to the TWW discharge area located north of the NWPS.
Surplus TWW from SWTP 9 and IWTP 8 that is not used for irrigation or
process water is discharged to the TWW discharge area, north of the NWPS.
The TWW discharge area has expanded far beyond its original design limits of
approximately 38 ha (as shown in the 1999 MPU) and has now spread to an
area that ranges seasonally from approximately 700 ha to over 2,000 ha,
well into Al-Fasil and Al-Mutrafiah in the future community area. Al-
Mutrafiah is in the initial stages of development.
MARAFIQ has proposed the installation of a dedicated surplus TWW line from
IWTP 8 to the TWW discharge area.
The system design for J2 does not include a TWW/irrigation network within
the utilities corridor.
7.2.2 Community
The RCJ has been undertaking various studies regarding the options for
disposal of surplus TWW. These are discussed under sections 7.4 and 7.5.
LI
T-AB U-A
Al-Gurmah
Island
Al-Surouge
District Jalmudah JUBAIL INDUSTRIAL CITY
Al-Reggah
District
District MASTER PLAN UPDATE
Mardumah
District
Mardumah
T6
Bay
TS4
Community EXISTING TREATED WASTEWATER STORAGE
Area TANKS
EXISTING TREATED WASTEWATER STORAGE
Al-Deffi PONDS
Al-Fasil
TS4 District
District Al-Mutrafiah EXISTING TREATED WASTEWATER
District Al-Fanateer PUMPSTATIONS
District
FUTURE TREATED WASTEWATER DISTRICT
PUMPSTATIONS
TS 7
EXISTING WASTEWATER TREATMENT PLANTS
T3
EXISTING TREATED WASTEWATER NETWORK
Al-Fanateer
Island FUTURE TREATED WASTEWATER NETWORK
O&M Al-Khaleej EXISTING INDUSTRIAL, MAJOR ROADS
Centre District
Evap. RC Jubail PROPOSED INDUSTRIAL, MAJOR ROADS
Stn. HQ Industrial
College PERMANENT COMMUNITY SERVICING AREA
WTP #3 T6
TS6 T100
T106 Block E-South Al-Huwaylat FUTURE COMMUNITY SERVICING AREA
T112 Island
T113
Al-Huwaylat
Stage 3 and 4 Stg.2 St. 1 EASTERN CORRIDOR SERVICING AREA
SWTP Block N District
T289
Stormwater Strm.W Storm- Block J-South T120
Holding Pond H.Pond
(Exp.) SWTP #9 water NWPS PRIMARY INDUSTRY SERVICING AREA
Pond
T1 0
T130 Al-
Lulu
FUTURE PRIMARY INDUSTRY SERVICING
1
District AREA
T138 T138
SECONDARY INDUSTRY SERVICING AREA
T147
Kh a
T150 T148
Al- FUTURE SECONDARY INDUSTRY SERVICING
Sa u
T154
rsa
Ar a b i a n G u l f
Shati AREA
T295
di E
niah
T162 District
SUPPORT INDUSTRY/NORTHERN CORRIDOR
le ct
R as
T263
T251
T241
T195
ric
Centre Block P
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
ura
AREA
pan
O
T184
RO
yR
T259
OW
T143
T163
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218
#2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/21/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
These sections are directly applicable to detailed design and construction and
therefore beyond the level of analysis required at the master plan level. The
discussion in this Volume will be limited to the design criteria that are
pertinent at the master plan level.
Overall, the criteria outlined with respect to TWW has been adequately tested
in the wastewater and TWW systems installed to date. However, there have
been problems with meeting some of the quality parameters identified.
Recommendations for this are provided in sections 5.6, 6.6 and 7.6.
Additional options for use of TWW are outlined in Section7.5 which are not
included in the above list as these are new areas for use that need to be
explored in greater detail to determine volumes.
Figure 7-3
Irrigation Actual Use 2004-2008
140
120
100
80
x 000 m3/day-pk
60
40
20
-20
2004 2005 2006 2007 2008
Peak Availability 101 106 118 120 125
Peak Production Demand 72 65 62 64 73
Peak Surplus/Deficit 29 41 56 56 52
Yearly Growth 5.2% -9.7% -5.4% 3.5% 14.1%
Year
Source "MARAFIQ Demand Forecast 2008-2017 (DF2008) for RC Jubail - Master Plan Input",
MARAFIQ Demand Forecast Department (March 31, 2008), and information provided by
MARAFIQ in March/April 2009
This shows that irrigation use decreased by 9.7% and 5.4% in 2005 and
2006 and increased by 3.5% and 14.7% in 2007 and 2008. It also shows
that in 2008, based on actual use of 73,000 m3/day, that there was a surplus
of 52,000 m3/day-peak.
Table 7-1 outlines the 2007 and 2008 surplus TWW statistics for JIC:
Table 7-1
Surplus Treated Wastewater (2007 and 2008)
The 1978 MP indicated that TWW was to be used for irrigation on local roads,
collectors, expressways and freeways, but not on residential access roads
and that the SWTP 9 TWW was to be used for these areas in the community.
IWTP 8 was to be considered for use, but plans only showed TWW from
SWTP 9 to the community.
The 1984 MPU identified TWW as the main source of supply for irrigation, and
PW was to be used when TWW was insufficient to meet demand. At that
time, only PW was available for irrigation in primary and secondary
industries. A decision was made to connect IWTP 8 to SWTP 9 since all of
industrial TWW could not be used and there was an anticipation of shortage
from the SWTP for the community. It was also not supposed to result in
ponding.
The 1999 MPU was the first to identify the “SABKHA” as being used to
discharge surplus TWW, though it had existed before this MPU. This was also
the first indication of using limited amounts of TWW for industrial processes.
Excess TWW was discharged through force mains to the evaporation basins
located north of the NWPS. In 1998, 18,000 m3/day was disposed of in the
“marsh”. It was recommended that the 1998 levels of excess disposal be
maintained in order to sustain the environmentally desirable marsh area that
had developed. The 1999 MPU projected excess TWW of 18,000 m3/day in
2003. This number was based on an assumption of industries using 39,000
m3/day of TWW (up from 5,500 m3/day actual use in 1998). Current use of
TWW for industrial use only approximately 6,000 m3/day. The assumptions
for use by industry was largely overestimated compared to what was actually
used. This has lead to a much larger surplus than anticipated.
MARAFIQ has indicated that the surplus TWW could increase to as much as
120,000 m3/day in the future if present practices continue including
acceptance of Al-Jubail SWW.
MARAFIQ and RCJ have discussed the following options for surplus TWW:
Options to increase use of TWW:
o To convert TWW to process water for industry use.
o To utilize TWW as cooling water make-up.
o To utilize the TWW as a primary cooling water in the industry.
Options to modify where surplus TWW discharged:
o To discharge the surplus TWW to SWC canal.
o To discharge the surplus TWW to the south of JIC airport.
These demands are not yet confirmed so have not been carried in the
following Table and Figure, but are discussed in Sections 7.4 and 7.5. This
would also require major expansions to the TWW distribution system.
Findings of MPU
Table 7-2 and Figure 7-3 illustrate the MPU TWW demand forecast through
2030.
Table 7-2
Treated Wastewater Supply and MPU Demand Forecast to 2030
Figure 7-4
Treated Wastewater Supply and MPU Demand Forecast to 2030
600
500
400
x' 000 m3/day
300
200
100
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Year
If SWW is no longer treated from Al-Jubail (after 2015) the surplus decreases
to 263,000 m3/day by 2030.
Also, should the potential demands discussed by RCJ in the previous section
become actual demands, then this demand of 468,000 m 3/day which would
reduce the surplus in 2030 to 80,000 m3/day, or if combined with no longer
treating SWW from Al-Jubail would mean no excess TWW.
In 2008 the split was approximately 65% from the SWTP and 35% from the
IWTP, and in 2030 this split will be approximately 50% and 40%,
Table 7-3 outlines the surplus TWW anticipated for the planning period, split
into the short term, mid term and long term.
Table 7-3
Surplus Treated Wastewater Volumes
The opportunities and constraints can generally be broken down into three
areas; supply, demand, and disposal of surplus.
TWW from the IWTP 8 can be added to the reclaimed water storage tank at
SWTP 9. This provision allows the supply of additional irrigation water to the
community. TWW, however, cannot be pumped from SWTP 9 to IWTP 8.
This means that TWW from IWTP 8 is the only source for industrial irrigation
and industrial use.
Irrigation
TWW has quality criteria that restrict its use for vegetation, not food crops.
Irrigation is currently used along freeways such as TS-1, and extension of the
irrigation system to these areas could help improve the landscaping and
aesthetic appeal.
In a presentation made by RCJ in July 2010, regarding the disposal and re-
use of surplus TWW, they recommended using water for parks and ponds at
a new proposed City Park (Green Belt), at the west side of the Buffer Zone,
and for a new proposed Regional Park, west of the airport.
These recommendations are sound, but providing TWW to the Regional Park
will require a major extension of the irrigation system.
In 1999 only one industry was using 1,100 m3/day. This has now increased
to three industries using 6,000 m3/day, however this is much less than that
predicted in the 1999 MPU.
If TWW were used in place of PW for use by industries for process water, this
would have the double benefit of decreasing the demand on the PW system
and using the available TWW which will decrease the surplus that needs to be
disposed of.
Use of TWW can be good alternative to PW or SWC for use in cooling towers
provided the customer can effectively control the bacterial growth in the
cooling water and also to maintain the blow down water quality as per RCER
2009 specifications, for discharging to the SWC canal. This is an important
and potentially significant use of excess TWW to maintain the zero discharge
policy.
To meet industrial process water quality criteria, MARAFIQ has indicated that
it will become necessary to provide post treatment of the TWW to be
compliant with RCER and that this has proven to be prohibitively expensive.
The demin system would be designed considering the RCER 2004 effluent
discharge standards as its design feed water. It is very important that
effluent supplied from IWTP 8 meets the RCER 2004 regulations as it will
impact the demin plant performance. Section 5.5 outlines how the ITWP 8
effluent is not currently meeting RCER.
There are currently no specific standards for the rejects from the DI plant
which uses TWW and not PW as its feedstock.
The ultimate treated water plant capacity at the demin plant would be
expected to be approximately 2,600 m3/hr. It is anticipated that a property
approximately 20,200 m2 (2 ha) would be required for the 3 phases of the
demin plant.
This plant would have one 11,000 m3 raw water storage tank and two 5,200
m3 demin water storage tanks.
If demand for process water for J2 facilities Dow-Aramco and SABIC Verbund
can be provided via TWW instead of PW, this would increase TWW demand
by 43,700 m3/day in 2015 and an additional 55,000 m3/day in 2018. At this
7.5.2 Supply
RCJ has indicated that the is unclear if IWTP 8 was ever designed to provide
TWW for irrigation. They recommend installing a membrane process after
the pressure filter and in the short term use an iron or aluminum coagulant
dose into the aeration tank to improve settlement in the clarifier. They also
recommend providing post chlorination at the Al-Deffi and Al-Fanateer PSs
using Cl2 drums, flushing the system more frequently, and modifying when
the irrigation occurs so that the spray systems are not working when people
are in proximity.
RGME prepared an Environmental Impact Study for the JIC Industrial Area in
2004. It identified that the existing quality of TWW made it unsuitable for
reuse and that it is essential the deficiencies need to be corrected. RGME
also recommended that immediate source testing at the treatment plants be
conducted for establishing emission rates, and assessing the best technology
for odour control and that future designs should accommodate sealed covers
for tanks, if necessary, for controlling VOC emissions and odour control.
They indicated that the existing quality of TWW made it unsuitable for reuse
and that it is essential the deficiencies need to be corrected and they noted
that disposal of surplus TWW to the discharge area should only be continued
if standards are met.
To prevent TWW from carrying water borne pathogens that may be present
in SWW, stringent effluent standards equivalent to the California Standards
(1972) were adopted in JIC. The standards require that the median number
of Coliform organisms in the TWW do not exceed 2.2 total coliforms MPN per
100 ml for 7 days and 23 total coliforms MPN per 100 ml in any one sample.
In addition, to further reduce the levels of BOD and TSS, an advanced
treatment plant (Stage IV) with 72,000 m3/day capacity was constructed.
The Stage IV plant encompasses chemical coagulation, and sedimentation
units. Stage IV was used for less than a year for treatment and is available
as a standby facility only. Eventually this facility will be eliminated.
Meeting the specified TWW quality is of crucial importance for human health.
The results of two monitoring days (April 11 and 12, 2009), were provided
for limited parameters, not including bacteriological or parasitological
parameters, which are important to assess the potential impacts of human
health. The analysis results show high concentrations of TDS, Turbidity, COD
and DO that exceed RCER. Refer to sections 5.5 and 6.5 for fuller discussion
of the current quality concerns at IWTP 8 and SWTP 9.
The current volume of surplus TWW is about 124,000 m3/day which could
increase to 337,000 m3/day by 2030 if SWW continues to be accepted from
Al-Jubail. Options for disposal of this surplus include:
1. Provide more storage tanks
2. Totally use reclaimed water so no surplus
3. Discharge of TWW to the Gulf
4. Modify the TWW discharge area:
a. Reduce the current TWW discharge area
b. Eliminate current TWW discharge area
c. Establish a new constructed wetland
The 1984 MPU identified that if there was more treated SWW generated than
storage tanks could hold, the excess was to be discharged to a primary
drainage channel, pumped to the industrial area system or discharged to the
Gulf via the SWC canal. In winter it was anticipated that there would be an
excess of TWW available that could be used to make up the summer deficit if
it could be stored and this was to be studied. There is a pipe line from IWTP
8 to the SWC canal to facilitate the disposal of treated effluent via SWC
canal, however this has not been used.
In many coastal cities TWW is released into an adjacent water body. Should
the RCJ determine to not use TWW discharge area, the reclaimed water could
be directly discharged to sea, subject to meeting appropriate discharge
quality requirements. RCJ Environmental Department has informed us that
as per regulations no effluent water is allowed to be disposed in the Gulf and
the no discharge policy will continue. However the practice in Yanbu does
allow treated wastewater effluents to be discharged to the Red Sea.
The RCJY should review the merits of allowing adequately treated wastewater
to be discharged to the Gulf to address the excess TWW issue.
In the original design of the TWW discharge area, it was anticipated that the
area would cover approximately 38 ha (as shown in the 1999 MPU), however
the area now covered ranges seasonally from approximately 700 ha to over
2,000 ha and covers portions of the future community area. The Al-
Mutrafiah property is at the initial stage of site preparation necessitating
urgent reduction and relocation of this effluent disposal operation.
Development of Al-Mutrafiah started in 2010 and Al-Fasil and Al-Sourouge
are not anticipated to start development until the end of this MPU planning
period.
Figure 7-5 illustrates alternative locations for the TWW discharge area.
Any new site should not be immediately adjacent to the airport because of
the potential and serious hazard of water fowl and migratory birds close to
aircraft, and the history of accidents that has occurred from such situations.
Any new site should not be adjacent to the coastline due to the risk of some
flow reaching the Gulf, contrary to the “zero discharge policy” in JIC.
Any new site should not interfere with any other long term land use plans in
the MPU.
One of the most viable immediate solutions from environmental, future land
use, and public awareness perspectives is to relocate the site as far inland
and remote as possible, namely the site west of the Dammam/ Abu Hadriyah
Expressway recommended by the Consultants for the Drainage Study for the
Discharge of surplus TWW from the SWTP 9.
TS 7
Al-Surouge Al-Reggah Jalmudah
Airport Area District Mardumah District District
EXISTING WASTEWATER DISCHARGE AREA
District
T2 ALTERNATIVE WASTEWATER DISCHARGE
AREAS
District
h Ras Ta nu
District District
tric Com pa
T3
W
Discharge Area
Al-Kahleej
Opt. #3 (234 ha)
ra RO W
ny RO W
(2,352 ha)
District
T6
TS6
Al-Huwaylat
T112
District
T295
Al-Lulu
T138 T138 District
Al-Shati
T251
T195
TS3
T241
District
Al-Bahar
District
A r a bi a n G u l f
Jubail 2 Industrial Area Jubail 1 Industrial Area
T218
T218
T315
T335
TS1
T121
TS9
T2 1
8
T272
T2 74
TS8
TS King Fahd
3
7 Industrial Port
TS
T1
0 3 0 1 2 4 km
Jubail
Commercial
1
Al-
TS
Port
Jubail
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
MOT
6 13
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
7.6 Recommendations
Table 7-4
Treated Wastewater Reuse Recommendations
This should also include options regarding extending irrigation system to the J2, This should include identifying the engineering requirements for treatment of the discharge
the proposed Regional City Park, Al-Jubail, and Freeways. brine and the integrated RO process.
This study is needed to determine system viability. This could include a pilot study to
determine additional pre-treatment and brine treatment requirements and establish design
parameters. Further interface with equipment suppliers is required to determine if there is an
alternative to a pilot study.
Disposal of Surplus TWW: Conduct a feasibility study to identify best ways to To ensure that appropriate means of discharge of surplus are provided in the future. MARAFIQ Short Term
dispose of surplus TWW including those identified under Section5.5 (provide RCJ through to Mid
more storage tanks; totally use TWW so no surplus; modify the TWW discharge Term
area).
Review of RCER: Update RCER to include discharge criteria for rejects from the To ensure that RCER guidelines are up to date to reflect potential use in JIC. RCJ Short Term
DI plant which uses TWW and not PW as its feedstock. through to Mid
Term
Review of Design Guidelines related to separation distances for new irrigation To ensure that separation distances are appropriate. RCJ Short Term
pipes, from potable pipes as well as setbacks to protect well fields. through to Mid
Term
Implement a groundwater monitoring program. This is discussed in Volume To ensure no significant impact on groundwater from TWW. RCJ Short Term
VIII. through to Mid
Term
Prepare MPUs approximately every 5 years for a 20-25 year time horizon. To provide updated demand projections and an overall review of the status of SWC system. RCJ Mid Term
This process should be done in conjunction with input from MARAFIQ and the industries. MARAFIQ through to Long
Industry Term
Implement a technical/operations liaison committee with MARAFIQ and Discuss and coordinate projections and upgrades which is currently done in a manner that is MARAFIQ Short Term
appropriate RCJ, as described in Chapter 2. unclear who is responsible for this. RCJ through to Long
Term
The reclaimed water pipeline network is owned by RCJ and MARAFIQ dispose of their surplus
reclaimed water through the RCJ network, as such, coordination between RCJ and MARAFIQ is
required in order to ensure that the system is working properly and being planned for properly.
MARAFIQ has indicated that there is a lack of flexibility to dispose surplus reclaimed water
during emergencies due to treatment process upset and pipe breaks. The TWW pipeline
network is owned by RCJ where MARAFIQ dispose their surplus reclaimed water through this
network and MARAFIQ has no control of this network. MARAFIQ’S responsibility ends at the
boundary limit of SWTP 9 and IWTP 8 and the boundary wall of the Al-Fanateer and Al-Deffi
As noted in the RCJ Design Criteria, JIC is quite arid, as the occurrence of
rain is not common. The average annual rainfall in JIC is 100 mm (31 year
duration records), falling in short, and high intensity winter storms. The RCJ
Environmental Control Department (ECD) monitoring stations (seven fixed and
two mobile) measure rainfall, and this information is used for design.
The maximum annual precipitation reported was 250 mm in 1995/96 and the
maximum storm occurred on November 2, 1982 with a rainfall of 110 mm
almost half of that year’s annual precipitation of 212 mm now considered as
equivalent to the 100 Year Return Storm event. The minimum annual recorded
precipitation was 10.4 mm in 1981. Almost all of the rainfall occurs between
the months of November and May, and generally no precipitation occurs during
the intervening months of June through to October.
Primary systems are designed for a 50 year storm with provisions for storage
run-off within a flood plain based on a 100 year storm and with the outfall
completely tide locked. Channels are lined and have zero freeboard for the 50
year storm flow, and maintain 0.30 m freeboards for the minimum rough
grading level at the edges of adjacent developed areas for the 100 year storm
storage.
Secondary systems are designed for a 25 year storm with zero freeboard.
Intersections with primary systems are engineered using concrete protection.
Auxiliary systems are swales and/or depressed areas, where flooding can be
tolerated for short periods of time without adverse effect on any building,
structure or facility such as parks, beaches, roadway medians, recreation
facilities and open spaces. The design capacity is based on a 5 year storm;
however, the capacity may be enlarged if used as temporary storage in
conjunction with Primary System 100 year criteria.
There are four relatively large stormwater channels draining the J1 primary
industrial area. The existing storm drainage layout for J1 is shown in Figure 8-
1 (Existing Jubail 1 Stormwater Drainage System). For monitoring purposes,
RCJ designated these from south to north as Channels 1 through 4 inclusive.
LI
T-AB U-A
Al-Gurmah
Island Jalmudah
JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
T6
Bay
TS4
Community
Al-Mutrafiah Area Al-Fanateer PRIMARY DRAINAGE CHANNELS *
District Al-Deffi
District District
EXISTING INDUSTRIAL, MAJOR ROADS
Al-Fasil
District TS4
PROPOSED INDUSTRIAL, MAJOR ROADS
TS 7
EASTERN CORRIDOR SERVICING AREA
T3
SECONDARY INDUSTRY SERVICING AREA
Al-Fanateer
Island SUPPORT INDUSTRY/NORTHERN CORRIDOR
O&M Al-Khaleej SERVICING AREA
Centre District
Evap. CHANNEL 4 Jubail
Stn. * STORMWATER IN THE COMMUNITY EAST OF MARDUMAH
Industrial
RC College
BAY IS NOT AVAILABLE
WTP #3 T6 HQ
TS6 T100
T106 Al-Huwaylat
T112
Al-Huwaylat Island
St. 1
T113
Stage 3 and 4 Stg.2 District
SWTP Block N Block E-South
T289
Stormwater Strm.W SWTP #9 Storm- Block J-South T120
(Exp.) water NWPS
Holding Pond H.Pond
Pond
T1 0
T130 Al-
CHANNEL 3 Lulu
1
District
T138 T138
T147
Kh a
T150 T148
Al-
Sa u
T154
rsa
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S
Ra il
T263
T251
T241
T195
ric
Centre
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
ura
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218
CHANNEL 2
#2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
CHANNEL 1 Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
These channels are normally inspected weekly and any abnormal flows
reported in ECD monthly reports for the period. Increased inspections are
carried out during or immediately following significant storm periods. The first
flush stormwater (first 30 mm of rainfall) at primary and secondary industries
process areas are, if polluted, directed to the IWW system.
Channel 3 also receives drainage from a significant part of the existing support
industries park and there have been several small spills of polluted water from
these factories to ditches that eventually drain into the main channel. Most of
these incidents have been minor.
Under RCJ policy for 100 year return storms, the corridor ROWs can be used
for flood storage with the design requirement that the top surface of the
floodwater must be at least 0.3 m below the property line elevation of the
adjacent industrial lots. This is shown graphically in Figure 8-2 (Typical
Industrial Drainage Channel Cross Section).
Figure 8-2
Typical Industrial Primary Drainage Channel Cross Section
Source: RGPK
The servicing plans prepared by RCJ for each district include the layout of all
surface water collection systems when the grading and utility services of each
Sector or District are planned and designed on an individual development
area basis. It is evident that many of these community sub-areas are being
As part of their May 2002 Report Jubail Park West Developments Study,
Nexant prepared a high level conceptual design for the site preparation and
drainage of J2. The scope covered Stages 1 and 2, and included an
assessment of rough grading site levels, storm drainage system, stormwater
retention ponds and stormwater tie-in to J1. The stormwater drainage system
concept proposed for J2 was to utilize the existing drainage ditches in J1 to
drain J2 into the Arabian Gulf. In order to ensure that the J1 system did not
overflow, the rainwater from J2 was planned to be held in a retention pond
adjacent to SWTP 9 and subsequently flow by gravity through a siphon into the
existing J1 channels. Consideration was also given to the use of detention
lagoons to dispose of stormwater by evaporation and percolation. This
technique was not considered viable given the topography of the site. The
quantities of stormwater generated in the design storm were determined to
require very large lagoons, which would obviously reduce the amount of land
available for lease to industries.
Due to the high costs associated with the Nexant proposal, alternate concepts
were examined and construction of an evaporation retention ponds located to
the north of J2 was deemed to be the most viable option.
The retention ponds are designed to retain stormwater generated during the 50
year return design storm of 5-hour and 79.6 mm as indicated in the RCJ Civil
Design Manual with a minimum freeboard of 0.30 m. The retention ponds
can also accommodate the more severe 100 year return storm, without
flooding on to the industrial areas.
The J2 surface water drainage network of channels allows for gravity flow to
the three evaporation ponds for all industrial blocks in J2 with the exception of
the east – west strip of land on the south limit of J2, most of which is currently
designated as “Logistics Areas”. There are four separate parcels of land of 112
ha, 120 ha, 35 ha and 150 ha allocated in this strip for logistics purposes.
Drainage of these lands cannot be accommodated by gravity to the J2 channel
network and will therefore require additional evaporation ponds to be
constructed.
The secondary drainage channels will discharge via three points. Channels
near the coastline will discharge through uncontrolled outfalls directly to the
sea. During high spring tides these outfalls will be submerged and some minor
flooding could occur in the lower reaches during a rainstorm. Channels located
inland will be discharged through uncontrolled outfalls at a higher level to open
sabkha or desert areas where run-off will disperse by evaporation or
percolation into the ground. Measures to prevent uncontrolled discharge into
the desert could include low earth bunds enclosing collection basins designed
to take the 5 year return period storm from the catchment area. Channels
that are neither close to the sea nor an inland boundary will discharge to large
open trapezoidal-section channels located in the landscape corridors and
discharged via the discharge options above.
PSs will typically be built with at least two pumps so that one is available for
standby.
The tertiary PSs have been considered as of wet well only construction,
housing submersible pumping units in the wet well. The stations would
incorporate two or three submersible pump units arranged to operate
either one on duty and one on standby or two on duty and one on standby,
depending on the required output from the station. The total number of
tertiary PSs required in the community will be mainly controlled by the
limiting depth of 5 m of laying incoming sewers. Each district will require
approximately 4 tertiary PSs, but the final number and their locations will be
dependent on detailed design.
Al-Mutrafiah will be divided into two areas (north and south) with flows from
the north being disposed of in Mardumah Bay through the eastern outfall and
the south being disposed of into existing primary drainage channel N-13, which
ultimately leads to the sea.
LI
T-AB U-A
Al-Gurmah
Island JUBAIL INDUSTRIAL CITY
Al-Reggah Jalmudah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
T6
Bay
TS4
Community
Al-Mutrafiah Area
District Al-Deffi Al-Fanateer EXISTING PRIMARY DRAINAGE CHANNELS *
District District
Al-Fasil FUTURE PRIMARY DRAINAGE CHANNELS
District TS4
FUTURE STORMWATER HOLDING POND
TS 7
PROPOSED INDUSTRIAL, MAJOR ROADS
T3
Al-Fanateer
FUTURE COMMUNITY SERVICING AREA
Island
EASTERN CORRIDOR SERVICING AREA
O&M Al-Khaleej
Centre District PRIMARY INDUSTRY SERVICING AREA
Evap. CHANNEL 4 Jubail
Stn. FUTURE PRIMARY INDUSTRY SERVICING
Industrial
RC College AREA
WTP #3 T6 HQ
TS6 T100 SECONDARY INDUSTRY SERVICING AREA
T106 Al-Huwaylat
T112
Al-Huwaylat Island FUTURE SECONDARY INDUSTRY SERVICING
Stage 3 and 4 Stg.2 St. 1
T113
SWTP Block N Block E-South District AREA
T289
Stormwater Strm.W SWTP #9 Storm- Block J-South T120
(Exp.) NWPS
Holding Pond H.Pond water SUPPORT INDUSTRY/NORTHERN CORRIDOR
Pond SERVICING AREA
T1 0
T130 Al-
CHANNEL 3 Lulu
1
District
FUTURE SUPPORT INDUSTRY SERVICING
T138 T138 AREA
T147
Kh a
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S
Ra il
T263
T251
T241
T195
ric
Centre
Jubail 1 T174
Ta n
ro a
C om W
Industrial Area
dR
ura
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218
CHANNEL 2
#2
RC
Scap T230
Jubail 2 Fac.
Industrial Area
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
CHANNEL 1 Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/21/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
Chapter 3 Civil Design Criteria and Chapter 4 Roads Design Criteria are directly
applicable to detailed design and construction and therefore beyond the level
of analysis required at the master plan level. The discussion in this Volume
will be limited to the design criteria that are pertinent at the master plan level.
Overall, the criteria outlined with respect to the surface water drainage has
been adequately tested in the systems installed to date. Table 8-1
summarizes comments on portions of 2.03 Subsection D (Stormwater Runoff
Criteria).
Table 8-1
Summary of Pertinent Design Guidelines for Stormwater and MPU Assessment
b) Clean stormwaters which run off from grassed or recreational areas outside the confined
drainage area of the process and transportation section of JIC & YIC may be discharged to
the stormwater drainage system leading directly to the sea if such clean stormwaters meet
criteria listed in TABLE 2-I.
c) Potentially contaminated stormwaters originating from bermed storage areas and from
drainage along transportation routes within industry property shall be contained and
analyzed for acceptability before discharging to the stormwater drainage system as set out
in TABLE 2-I. If they do not meet these criteria, then the water shall be directed through
appropriate treatment facilities to meet pretreatment criteria.
d) Contaminated stormwaters which run off from areas surrounding process units and from
areas around shipping points shall be directed through appropriate treatment facilities to
meet pretreatment criteria before discharging to the stormwater drainage system.
8.5 Recommendations
Table 8-2
Surface Water Recommendations
Study/Action Rationale Action By Timing
Policy and Strategic Planning
Prepare BMPs for industries to Industries need to exercise Best Management Practices (BMPs) RCJ Short Term
reference. for management of stormwater to safeguard water quality through to
during both the construction and operation phases of Mid Term
development through programs of mitigating spills, leaks, and
unintentional release of contaminants.
Utility Planning and Design
Prepare a comprehensive Storm The community should continue with the integrated stormwater RCJ Short Term
Water Drainage Management sewer system approach, however need to ensure that adjacent through to
Plan. community plans are appropriately accounting for flows from Mid Term
adjacent community areas.
The transmission system is connected with SEC power plants and main grid
stations. Electricity supplies are available at four distribution voltages; 230
KV, 115 KV, 34.5 KV and 13.8 KV depending on the size and distributing
effects of the load and on the reliability level required.
Supplies to industries at 34.5 KV and above are fed directly from SEC
substations or the 230 KV power distribution network. Supplies to
infrastructure and small loads are served by switching stations. In J1 the
switching stations are designed for 20 MVA load and in J2 for 25 MVA load,
which act as power centers from which individual loads are served.
In the industrial area, power is distributed at dual feed 380, 230, 115 and
34.5 KV. In the community area power, is distributed at 13.8 KV. The
dual feeders (100 percent redundancy) are bussed so that each can
carry the full design load.
Figure 9-1 (Key Power Dispatching Diagram - SEC Eastern Operating Area)
illustrates SEC's key power dispatching system for the eastern operating
area.
The description of the key elements of the power distribution network for
the JI and J2 Industrial areas and the Community Areas follows.
9.1.1 Jubail 1
directions. SEC has provided five 230 KV feeders that will directly link Jubail's
internal power grid system to the Ghazlan Power Station (Qatif) No. 2 via the
380 KV/230 KV Al-Fadhili Substation.
9.1.2 Jubail 2
A 200 MVA (170 MW) capacity secondary 115/34.5 kV substation (ST4) will
provide power to secondary and support industries located along the
northern boundary of J2. Substation ST4 will be needed in the near term in
the light of investor indications.
The power distribution system for the entire community area of the city was
originally planned to encompass eight districts, with each district containing
four or five sectors. Each district was to have a centrally located 115/13.8 KV
Substation with an ultimate capacity of 200 MVA.
However, foreseeing the rapid growth in power demand, the RCJ has taken
initiatives to promote independent power generation in JIC that will ensure
power availability in the vicinity and help supporting SEC to ensure reliability
of power supply to JIC. The following are some examples of independent
power generation in JIC:
Jubail Water and Power Company (JWAP)
Jubail Energy Company (JEC)
SADAF Auxiliary Power Generation
JWAP will be owned jointly by MARAFIQ, Saudi Electric Company (SEC), the
Public Investment Fund (PIF), and the Developers through its holding
The IWPP is tied to the SEC grid, and is expected service the needs of both
the JIC and others. Although SEC has not revealed its plans for the
distribution of this power capacity, the IWPP is expected to meet some or
most of the future demand from industries in JIC.
The IWPP was commissioned in stages and achieved full power production
capacity of 2745 MW in 2010.
JEC is a joint venture between National Power Company (NPC), which holds
75% interest and CMS Generation, a subsidiary of US based CMS Energy
(Consumers Energy), which holds 25% interest. NPC is a joint stock
company established in Saudi Arabia by Al-Zamil and El-Saif groups, each
holding 50% interest. CMS Energy is an integrated energy company, with
primary business interests in electric and natural gas utilities, natural gas
pipeline systems and independent power generation.
The SADAF cogeneration plant came on stream in 2005. The plant is located
within SADAF’s complex in JIC; and is currently operated by JEC. This
cogeneration plant is the first Independent Power Producer (IPP) in Saudi
Arabia and is providing SADAF with 250 MW of electricity (some 85% of its
power needs) and 510 Tons of industrial steam per hour (some 45% of its
requirements for steam).
FIGURE 9-1
KEY P OW ER DISPATCH ING
DIAGRAM (SEC EASTER N
OP ERATIN G AREA)
² NOT TO SCALE
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
To Khursaniyah
Al-Batinah
Island
LI
T-ABU-A
T6
Bay
TS4 Substation
21-BD Al-Fanateer
TS4 (Under Construction) District 34.5 KV SWITCHING STATIONS
Substation SUBSTATIONS
17-BD
Al-Fasil
Al-Deffi 380 KV Feeder
District
230 KV Feeder
Al-Mutrafiah District
District
115 KV Feeder
TS7
34.5 KV FEEDER
Substation
13.8 KV FEEDER
T3
24-BD
Al-Fanateer
(Under Design)
T113
District
T1 0
Support Support SWTP Block N Block E-South
T289
Stormwater Strm.W SWTP #9 Storm- Block J-South T120
Industries Industries (Exp.) NWPS FUTURE PRIMARY INDUSTRY SERVICING
1
Holding Pond H.Pond water
Pond Substation
AREA
Future T130 43BD
Substation 5 Al- SECONDARY INDUSTRY SERVICING AREA
(Under Construction) T138 T138 Lulu
District
FUTURE SECONDARY INDUSTRY SERVICING
T147
Plas-Chem Allocated
Plas-Chem
Kha
T154 Al-
rsan
Future Damman 7
d
District
i Ele ilroad
SERVICING AREA
iah
Substation 4 T162
(Under Construction) Substation
Ra s
A r a b i a n G u l f
ctr ic
O&S
Ra
T251
T241
T195
GAS Centre Jubail 1
Jubail 2 T174 AREA
Tan
Substation
Co m W
Sabic
Verbund Industrial Area 45BC Industrial Area
u ra
RO
pan
Sabic
Chem-Value Chem-Value Cracker 2
yR
T143
OW
T163
Substation
Substation 1 Future T198 38CD
Substation
(Completed) Clusters Sanitary
T289
T223
Fac.
T218 IWTP #8
Desal.
T218 #2
RC
Cracker 1 Scap T230
(2020) Fac.
Saudi Aramco Total Southwest Southeast
Potential Refining and Cracker 1 Substation
Substation 3 Substation
Cracker/Refinery Petrochemical Co. (2020)
(Under Construction) Sanitary
TS9
T315
T335
(Beyond 2035) T2 1
TS1
T121
T241
T183
T161
T261
T195
8
TS3
PTA, PTE, Landfill Block Q Block L Block G
Saudi Substation 2
Aramco Preforms, SBR,
(Under Construction) Caprolactam,
380 KV/230 KV Dow
To Fadhili SEC Substation Chemical Nylon '6'
(Completed) T2 74 0 0.5 1 2 km
BeeA'h T272
T2 74
Logistics Services Area
ED Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
TS8
Logistics Services Area CO
To Ghazlan MAP PROJECTION: AIN EL ABD UTM ZONE 39N
Logistics Services Area TS PROJECT #: 078523
7 STATUS: FINAL
King Fahd Causeway DATE: 1/3/12
Industrial Port Substation
3
MP FIGURES - MXD'S\
MOT
85
To Berri PP,
Jub-SWCC, T1
03
and Ghazlan PP
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
The SADAF auxiliary power generation plant is equipped with four turbo
generators, each rated at 10 MW (max), 13.8 KV, 3 Phase, 60 Hz, which
produce power through extraction type steam turbines. High pressure steam
is produced in seven boilers. The turbines work on this high pressure steam.
Medium pressure and low pressure steam are extracted and used by SADAF
in process for manufacturing petrochemicals, Chlorine and Caustic. The
power generated by the turbo generators is fed to auxiliary bus. This power
is mainly used for priority loads and for Ethylene plant.
The auxiliary bus is synchronized and kept in parallel operation with grid
supply at 13.8 KV level. In case of failure of SEC power or low frequency of
grid supply, the auxiliary power generation is islanded and priority loads and
Ethylene Plant are kept on line. Priority power supply is required for safe
shutdown of plants. The priority loads are connected through automatic
transfer switch to supply power from auxiliary power generation or SEC
power.
9.1.5 Jubail 1
Table 9-1
Existing Jubail 1 Power Supply Capacity
three main substations from two directions. SEC has provided five 230 KV
feeders that will directly link JIC’s internal power grid system to the Ghazlan
Power Station (Qatif) No. 2 via the 380/230 KV Al-Fadhili Substation.
The primary industries are served by the main SEC substations or by direct
feeders from the SEC network. In accordance with the RCJ mandates for
underground installation of feeders along specified routes, direct buried
cables are used in all the new development areas, with the exception of
overhead 230 KV power transmission lines along the designated power ROW.
The one exception is SAFCO which is fed from Substation 7AB at the 115kV
level through underground cables since the 1990’s This arrangement was
originally on a temporary basis which became permanent. It would be
desirable to free 7AB from the SAFCO load so that this Substation could
serve the community expansion as originally planned.
Initially, the RCJ required underground ducting of power cables and has
installed a system of multi-barrel ducting to accommodate 115 KV and 34.5
KV cabling in J1 primary and secondary industrial parks.
The secondary industry area is divided into three sections, Section K, P and
Q. For Section K, power is from the North S/S and 45 BC S/S, mainly via dual
34.5 KV feeders. After commissioning of new 133 MVA North S/S, the
industries in Section K currently fed from 45 BC, will be shifted to new North
S/S.
SEC has upgraded this substation connecting it via 115 KV feeders to the
Southwest substation.
The originally planned development of sub-sections P-2 and P-3 was deferred
because the trend in these sections was for larger and fewer industries. Due
to the changing trend of industries in this area, the originally planned
substation for sub-section P-3 was eliminated leaving the option to feed the
industrial sites direct from the North substation or from the centrally located
45BC substation. Consequently, the RCJ has redesigned the feeder network
in this area as precise industry requirements were known. The
reconfiguration has also resulted in an increased load on the 230/34.5KV
North main substation. This substation supplies power to primary, secondary
and support industries; and also to the residential camps.
The sub-sections P-2 and P-3 are fed from the 115/34.5 KV secondary
substation 45BC providing dedicated 115 KV and 34.5 KV dual feeders to the
industrial sites. This substation is connected by dual 115 KV feeders from the
Southwest Substation.
The trend in Section Q was similar to that of Section P to have larger and
fewer industries and accordingly the area was allotted to major industrial
uses. These industrial sites are supplied by dedicated feeders from the
existing busses from the Southwest Substation.
In accordance with the RCJ design guidelines, all feeders in the Park are
underground in ducts or direct buried along prescribed routes leading to SEC
interface points and metering locations.
The Support and Light Manufacturing Industries Park (SLMIP) is divided into
three sections, Section E, J, and N. These three sections are fed power from
the SEC North Substation located on the southern side of Section J of the
SLMIP. This substation is at 230/34.5 KV, and feeds power loads of the
primary and secondary industries as well as the power loads of the
residential Camps 4, 5, 12, 14, and 15.
Duct banks are installed around and inside Sections E and J, and N. The
primary feeders to these areas are 3 x 1 x 500 mm2 copper conductor cables
with pad mounted fused switches provided at various locations. Looped
lateral feeders are installed from these fused switches to the industrial and
commercial uses located in these sections. Transformers have provided for
the uses in Sections E, J and N. Sections E and J are almost fully developed
whereas Section N is almost 75 percent developed.
LI
T-AB U-A
Al-Gurmah
Island Jalmudah
JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
T6
Bay
TS4
Al-Fanateer
Community District
SUBSTATIONS
Al-Mutrafiah
Al-Deffi
Area 115 KV DUCTBANK
District
District
Al-Fasil 34.5 KV DUCTBANK
District TS4
13.8 KV DUCTBANK
TS 7
PROPOSED INDUSTRIAL, MAJOR ROADS
T3
Al-Fanateer EASTERN CORRIDOR SERVICING AREA
Island
PRIMARY INDUSTRY SERVICING AREA
O&M Al-Khaleej
Centre District SECONDARY INDUSTRY SERVICING AREA
Community
Evap. Substation Jubail
Stn. Industrial SUPPORT INDUSTRY/NORTHERN CORRIDOR
7AB
RC College
T6 SERVICING AREA
WTP #3 HQ
TS6 T100
T106 Al-Huwaylat
Island
Block E-South
T112
Al-Huwaylat
St. 1
T113
Stage 3 and 4 Stg.2 District
SWTP
T289
Stormwater Strm.W SWTP #9 Storm-
(Exp.) water NWPS Block N Block J-South T120
Holding Pond H.Pond
Pond
T1 0
T130 Al-
Substation Lulu
1
43BD District
T138 T138
T147
Kh a
T150 T148
North Al-
Sa u
T154
rsa
Substation
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S
Ra il
T263
T251
T241
T195
ric
Centre Substation
Jubail 2 Jubail 1 T174
Ta n
ro a
42CD
C om W
Substation
Industrial Area Industrial Area
dR
ura
45BC
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary Substation
T204
T289
38CD IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218 #2
RC
Scap Substation T230
Fac. 44BC
Southwest Southeast
Substation Substation
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
9.1.6 Community
The power distribution system for the entire community area was originally
planned to encompass eight districts, with each district containing four or five
sectors. Each district was to have a centrally located 115/13.8 KV substation
with an ultimate capacity of 200 MVA. The power distribution at 13.8 KV was
planned to be carried out using 500 mm2 copper conductor cables that were
to be installed in duct banks.
Until the early 1990's the power supply installations in the community used
copper conductor cables for the primary, sectoral and lateral feeder
configurations. Duct banks were also used widely to carry all these feeders.
Al-Fanateer
Each busbar associated with the above substation has a number of outgoing
feeder breakers, and the power supply to each of the six sectors (B1 through
B6) is carried out through different busbars. This arrangement ensures that if
one busbar or the transformer feeding that busbar is out of service, the
power supply to the affected sector is still available through another busbar.
The duct banks from this substation have been fully installed. These duct
banks are constructed around each sector for the primary feeders and within
each sector for sectoral or lateral feeders.
The power supply to the Peninsula (Sector B6) area has been accomplished
using SEC standards. Aluminum conductor cables are used for both 13.8 KV
and LV distribution. The primary, sectoral, and lateral feeder configuration
concept is no more used; instead the simple loop feeder system is followed
for primary distribution. From the 17BD substation, copper conductor cables
are installed up to manholes M06084 and M06229 outside the Peninsula, and
from these manholes 3 core, 300 mm2 aluminum conductor cables are
installed around the Peninsula. EOSs are installed near manholes to connect
500 mm2 copper cables with 30 mm2 aluminum cables.
In the early 1990's, a plan was prepared for the development of Sector A2 of
Jalmudah district. Sector A2 was temporarily energized through four (4)
feeders from 17BD. It was planned that eventually this load would be shifted
to 16 BD.
Al-Deffi
Substation 19BD has a firm capacity of 100 MVA and will be expanded to a
capacity of 150 MVA.
Jalmudah
Substation 16BD has an installed capacity of 200 MVA and a firm capacity of
150 MVA.
Al-Mutrafiah
Substation 21BD reportedly has an installed capacity of 250 MVA and a firm
capacity of 200 MVA.
The power supply for Camps 1 to 5 which are located in the northern part of
Section E of the SLMIP, the Eastern Corridor Camps, 8A, 9, and the coastal
areas of in the Eastern Corridor is provided at 13.8 KV. Some of the camps
previously operational in this area are now converted to alternate land use.
There is one substation, designated 38CD, located on the south side of Camp
8, and a second substation designated 43BD, located between the SLMIP
Section E and Al-Huwaylat. Substation 38CD is rated at 34.5/13.8KV and
substation 43BD is rated at 115/13.8KV. A duct bank is located all around
the North and Eastern Corridor camps, and both of the substations (38CD
and 43BD) are interlinked through these duct banks. The loads of all the
North and Eastern Corridor camps and the developments in the coastal area
are fed through these substations.
9.2.1 Jubail 1
The actual 34.5 KV load on the North main substation as of 2008 has
exceeded the firm capacity of this substation. The SEC load projections on
the North main substation indicate an immediate need for a reinforcement
and upgrade of this substation. RCJ and SEC have plans to upgrade this
substation with an additional capacity of 133 MVA. SEC has indicated that
based on the development trend in J1, another upgrade of the North main
substation may be necessary by 2016.
The 2009 load projection for the 115/34.5KV secondary substation 45BC
exceeds the 50 MVA firm capacity of this substation. This substation supplies
to the sub-sections P-2 and P-3 of the secondary industry park. The
9.2.2 Jubail 2
SEC constructed the main 380/230KV substation with a capacity of 2000 MVA
and the associated 380KV and 230KV overhead transmission system in J2
and is supplying power to JIC through a 230kV double circuit line from Jubail
380/230kV sub to 230/115/34.5kV substation-1. This substation is expected
to add stability and flexibility of power supply to JIC and to adequately
provide for the load projections of J2 developments. The new main 380/230
KV J2 SEC substation is planned to be reinforced with power at 380 KV from
the new MARAFIQ IWPP, Ghazlan Power Plant-2 and Al-Fadhili 380/230KV
Substation, which is fed from RIC Power Plant and Ma'aden Power Plant.
In 2007, Nexant prepared a study for the RCJ titled “Feasibility Study of
Jubail 2 Expansion (Stage 4)” to determine the impacts of expanding J2 from
3 stages to 4 stages. Nexant modelling assumptions under the industrial
development scenario proposes two additional 750 MVA capacity substations
(substation-5 and substation-6) to meet the shortfall in the supply of
electricity to Stages 1 to 3 and to meet the demands of industries in J2,
Stage 4. Keeping in view of the current thinking of the bigger lots as per the
original plan and the recent Stage 4 development plans, space for only
Substation -5 is allocated in Stage 4
The establishment of the substations has been timed to match demand, and
is shown in Table 9-2.
Table 9-2
Jubail 2 Planned and Proposed Substation Capacity
Figure 9-4 (Existing and Current Planned Power Distribution and Main
Substation Layout) illustrates the existing and proposed locations of the main
and secondary substations and the internal grid routings between them.
Internal grid systems are available within J1, J2 and Community. These
internal grids are interconnected together and tied to the SEC grid (Figure 9-
1).
To Khursaniyah
Al-Batinah
Island
LI
T-ABU-A
Community
Al-Gurmah Area JUBAIL INDUSTRIAL CITY
Island
Al-Surouge
Al-Reggah
District Substation District Jalmudah MASTER PLAN UPDATE
18-BD District
Mardumah
Substation
Substation District 25-BD
22-BD (Main Substation Substation FIGURE 9-4
16-BD
Airport Area for City Centre)
T2 EXISTING AND CURRENT
Substation
PLANNED POWER
Substation 19-BD
20-BD (Expansion Under DISTRIBUTION AND MAIN
Mardumah
Construction)
SUBSTATION SYSTEM LAYOUT
T6
Bay
TS4 Al-Fanateer
TS4
District
Al-Mutrafiah
District Substation EXISTING SUBSTATIONS
17-BD
Substation
Al-Fasil Al-Deffi FUTURE SUBSTATIONS
23-BD District District
EXISTING FEEDER
Substation
21-BD FUTURE FEEDER
TS7
(Under Construction)
EXISTING INDUSTRIAL, MAJOR ROADS
Substation
T3
24-BD PROPOSED INDUSTRIAL, MAJOR ROADS
Al-Fanateer
(Under Design)
T113
Support SWTP Block N Block E-South District SECONDARY INDUSTRY SERVICING AREA
T289
Stormwater Support Strm.W SWTP #9 Storm-
(Exp.) Block J-South T120
Industries Holding Pond Industries H.Pond water NWPS
Substation
Pond 43BD FUTURE SECONDARY INDUSTRY SERVICING
Al-
T1 0
T130
Lulu AREA
1
Future District
T138 T138 SUPPORT INDUSTRY/NORTHERN CORRIDOR
Substation 5
(Under Construction) SERVICING AREA
T147
Plas-Chem Allocated
Plas-Chem
Kha
T150 T148
Allocated North FUTURE SUPPORT INDUSTRY SERVICING
Sau
A r a b i a n G u l f
IDEA Substation Shati AREA
T295
Future Damman 7
d
District
i Ele ilroad
iah
Substation 4 T162
Substation
T263
(Under Construction)
Ra s
ctr ic
O&S
Ra
T251
T241
T195
42CD
GAS Centre Jubail 1 T174
Jubail 2
Tan
Co m W
Sabic Substation
Verbund Industrial Area
u ra
T143
OW
T163
Future T198
Substation 1 Substation
Clusters Sanitary
T289
T223
IWTP #8 Fac.
T218 Substation
44BC Desal.
T218 #2
RC
Cracker 1 Scap T230
(2020) Southeast
Fac. Southwest Substation
Saudi Aramco Total
Potential Refining and Cracker 1 Substation
Cracker/Refinery Substation 3 Petrochemical Co. (2020) Sanitary
TS9
T315
T335
(Beyond 2035)
TS1
(Under Construction)
T121
T241
T183
T161
T261
T195
T2 1
TS3
PTA, PTE, Landfill Block Q Block L Block G 8
Substation 2 Preforms, SBR,
Saudi
(Under Construction) Caprolactam,
380 KV/230 KV Aramco
Dow Nylon '6'
To Fadhili SEC Substation
(Completed) Chemical T2 74 0 0.5 1 2 km
T272 King Fahd
BeeA'h
Industrial Port
T2 74
Logistics Services Area
ED Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
TS8
Logistics Services Area CO
To Ghazlan MAP PROJECTION: AIN EL ABD UTM ZONE 39N
Logistics Services Area TS PROJECT #: 078523
7 STATUS: FINAL
Causeway DATE: 1/3/12
Substation
3
MP FIGURES - MXD'S\
MOT
85
To Berri PP,
Jub-SWCC, T1
03
and Ghazlan PP
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
9.2.3 Community
The existing two district substations 17BD and 19BD are in operation and
supplying power to Al-Fanateer and Al-Deffi districts respectively. A
secondary 115/13.8KV substation 16BD has now been constructed in
Jalmudah. This substation is supplied from the community east substation
7AB located near Al-Deffi district. The opportunity to feed Jalmudah
substation (16BD) has facilitated reorganizing the sub-transmission lines
passing through the community east area resulting in replacement of portion
Substation 19BD is being expanded along with 43BD substation. Two (2)
numbers additional 115/13.8kV, 50/67MVA
The following Table 9-3 shows the historic actual non-coincidental peak
power demands in JIC.
Table 9-3
Actual Non-Coincidental Peak Power Demands from JIC
The RCJ electrical design guidelines provide the basis for design and
installation of electrical systems and services in JIC. The guidelines apply to
primary and LV power distribution systems within the premises of
residential, commercial and light industrial facilities. The design criteria
considered in the guideline highlight safety features as well as compliance
with system technical specifications. It is also focused on an economic
design that allows future expansion and system maintenance with minimum
interruption.
The design criteria give due consideration in enforcing the health and safety
legislation, regulation, standards and codes established by the Kingdom and
RCJ. In the absence of such regulations, the guidelines recommend using
best international industry practices with reference to health, safety and
welfare. Intrinsic safety features are obligatory for all electrical equipment
such as switchboards, panel boards, control centers, etc, forming part of the
electrical power circuit. It is mandatory to perform grounding and bonding of
all electrical installations and utilities.
The design criteria focus on the service conditions for the electrical
equipment and materials installed in the indoor, outdoor and classified areas
for compatibility with the prevailing ambient conditions in JIC. The electrical
equipment shall display adequate information on the nameplate. High
voltage equipment and electrical installations accessible in the open area
shall be fixed with warning/danger signs for the safety of personnel and
property. Underground installations such as ducts, cables, etc, shall be
identified with permanent markers and warning signs.
Towards the goal of energy conservation, all road and area lighting shall be
switched on and off at preset times, by photocell and timer controlled
contactors, provided with manual override switch. Interior luminaries shall
be controlled through occupancy sensor switches with optional ambient light
sensing feature.
In the early stages of development and until the early 1990s, the RCJ
enforced the use of underground ducting for power distribution in the
primary, secondary and support industry parks. Subsequent to SEC taking
over the O&M of power distribution system in JIC in the early 1980s, an
agreement was reached between SEC and RCJ to adopt the use of direct
buried cables instead of underground ducting; and as such both the RCJ and
SEC discontinued using duct banks in the new development areas. Duct
banks and manholes are still operational in the old development area;
whereas direct buried cables are used in the new development areas.
Operational problems are experienced with flooding of the chambers and
snake infestation.
Since SEC took over the O&M of the power distribution system in the
community area in the early 1980's, efforts have been made to implement a
power distribution system according to SEC’s specifications which differed
from the RCJ specifications as follows:
For 13.8 KV power distribution, SEC uses 3 core, 300 mm2 aluminum
conductor cables installed as direct buried cables, and there is no
concept of primary, sectoral and lateral feeders within SEC’s mode of
power distribution.
SEC does not use duct banks since all the cables are installed as direct
buried. Duct banks are used only at road crossings in SEC’s system
and other utilities between “roads” and “crossings”.
SEC uses ring main units to feed the power to a distribution
transformer, which, with its low voltage (LV) distribution board is
installed within a separate compartment but under an enclosure, called
a "unit substation".
LV cables in SEC’s system are aluminum conductor cables and, like the
13.8 KV cables, are installed as direct buried cables.
SEC uses 300 KVA transformers as the minimum, as opposed to the
practice of the Royal Commission which uses 75 KVA transformers as
the minimum. The other sizes in use with SEC are 500 KVA, 1000 KVA,
Consequently, the RCJ has adopted the SEC power system distribution
specifications in the new development areas. The power distribution system
in the old development areas are still operational using the RCJ
specifications, as originally planned.
The RCJ has identified certain nominal system voltages as standard for use in
JIC. These voltages are consistent with the SEC standards. Some voltage
levels used in JIC as standard in the initial stages of development are now
identified as non-standard. These voltages are mainly 240/120 V, 480/277 V,
and 4160/2400 V. The standardization of power supply voltage from 127/220
Volt to 230/400 Volt in the Kingdom of Saudi Arabia was recently approved
by the Council of Ministers through Royal Decree,
The RCJ has restricted further use of the non-standard system voltage levels
for new installations. If a customer requires non standard voltage in his
facility, the interface point will be at MV and customer shall do as follows:
In industrial parks: they shall provide and install their own 34.5 KV
interface switchgear with protection devices and metering CTs and VTs
(and power totalizer, in case of dual feeders) with their distribution
transformers to derive power at his required voltage. SEC will install
34.5kv interface SWGR and kwh meter. Customer’s CTs and VTs,
installed in their panels, are used to connect kwh meters.
In residential and commercial areas: they shall provide and install
their own 13.8 kv interface switchgear with protection devices (and
power totalizer, in case of dual feeders) with their distribution
transformers to derive power at their own required voltage and 13.8kv
interface SWGR.. SEC will install the 13.8 kV metering units.
Community demand in JIC was estimated at 1762 watts per capita based on
population and actual community power consumption in 2008. The average
power per capita of 1762 watts for the community sector in JIC is one of the
highest per capita power consumption in the gulf region, compared to that of
Saudi Arabia as a whole (682 watts) and Qatar (1757 watts), which is the
highest among the GCC countries. The power consumption in a country or a
sector is largely dependant on its geography, climate, population and
emerging economy; and as such there is no established standard for per
capita power consumption. Table 9-4 illustrates the most recent data (2005)
on the average power per capita for selected countries worldwide. These
countries are further grouped into international and regional categories. The
average of power consumption per capita for the European Union and the
World are also given for reference purposes.
Table 9-4
Average Power Consumption Per Capita World Map (2005)
In developing the forecasts and network capacities, demand for power was
converted from MVA to MW using a power factor of 0.85.
Industry
While the present upgrade planned for North main substation will resolve the
short term demand requirements, the RCJ and SEC may evaluate the need
for another upgrade of this substation by 2016, depending on the associated
development. Alternatively, RCJ and SEC may evaluate the possibility of
feeding some of the additional loads from other substations that will relieve
the load on this substation.
It would also be desirable to free 7AB from the SAFCO load so that this
substation could serve the community expansion as originally planned.
Community
The 380 KV transmission systems that have been planned for construction
feeding substation 8AB will guarantee availability of power supply from
multiple sources to the community. The planned internal links in the
community will eventually interconnect all the district substations thereby
adding flexibility and reliability of power supply within the community. The
community main substations 7AB and 8AB upgraded in a timely manner will
be sufficient to meet the long term power demands of the planned
developments in the community.
Some of the Northern and Eastern Corridor camps have now been converted
to alternate land use. The existing substations 38CD, 42CD, and 43BD are
adequate to meet the power demands of the Northern and Eastern Corridor
Camps and the coastal area developments in the near term. Though there is
no urgent need, in view of the changing trend and the anticipated load
projections, the RCJ may consider evaluating the power supply capabilities of
substations 38CD, 42CD and 43BC presently supplying this area for a
possible upgrade in the middle term. An upgrade of substation 43BC is
already under construction by the RCJ and SEC. The SEC load projection for
substation 42CD supplying Camp 12, shows the demand reaching the firm
capacity (10MVA) by 2012. The RCJ and SEC may consider this substation
for an upgrade by 2012.
the Peninsula (sector B6). Presently, this substation is loaded to almost half
of its firm capacity of 170 MVA.
The expansion of 19BD and 43BC is under advanced stage. Two (2) numbers
50/67MVA, 115/13.8kV transformers are being installed at substation 19BD,
that will increase its capacity by 67MVA. While two (2) numbers 30/40MVA,
115/13.8kV transformers are being installed at substation 43BD, that will
increase its capacity by 40MVA.
Findings of MPU
Table 9-5 and Figure 9-5 illustrate the MPU power demand forecast through
2030.
Table 9-5
Power Supply and MPU Composite Demand Forecast to 2030
Figure 9-5
Power Supply and MPU Composite Demand Forecast to 2030
The majority of the demand is coming from J1 and J2, with only
approximately 5% of the demand coming from the community. Based on
the assumptions used in demand projections, there could be a network
capacity shortfall of 1,160 MW in 2018, increasing to 2,210 MW by 2030.
Table 9-6 summarize the consolidated power shortfalls anticipated for the
planning period, split into the short term, mid term and long term.
Table 9-6
Consolidated Network Capacity Shortfalls
The existing and planned JIC power grid is a world class utility built at the
highest reliability level with built in redundancies in all components of the
power generation, transmission and distribution facilities. There are multiple
power supplies, dual feeds throughout the network and sub-stations all of
which have been designed and built on a fail-safe approach, recognizing the
serious economic impact of even short term power outages in this intensively
industrialized city.
More than 50% of the power used in the residential sector is expended on
space conditioning (cooling), whereas it represents about 30% in the
commercial sector. Lighting, at 25% of the power consumption in
commercial sector, plays a much larger role than it does in the residential
sector. Lighting is generally the most wasteful component of commercial use.
A number of case studies indicate that more efficient lighting and elimination
In addition, the feasibility of using solar panels and wind turbines could be
studied as well as converting industrial waste heat into energy.
9.5.2 Supply
Power comes from SEC, and they are responsible for meeting the demand.
Though the SEC power sources are not committed to JIC alone, but to a
national level, the recent developments in the vicinity of JIC, such as
construction of new power stations and transmission systems including
introduction of 380 KV transmission and interconnection of all power sources
to the national grid add a lot of flexibility for SEC to meet the power demand
of JIC.
Though the power comes from SEC, it is equally important that the JIC
network shall have the capacity to utilize it, and it has to be well planned in
advance. The JIC network capacity needs to be upgraded against the
shortage by 2017. A separate study in coordination with the SEC will be
required to assess the impact of this upgrade. However, SEC has the
flexibility to supply power from multiple sources to J1, J2 and community,
since the internal grid systems are interconnected with each other and to
SEC grid.
Further analysis of the network capacity shortfall reveals that most of deficit
comes from J2 with only about 30% of the total shortfall attributed to J1 and
community areas. The JIC network capacity includes direct power supplies
given from SEC network and substations to industrial customers in J1. A
similar approach in J2 will substantially resolve the overall deficit. However,
this could be done only in coordination with SEC.
As a result of Royal Decree, the SEC was established in 2000 by merging the
ten regional power companies, which were responsible for the Kingdom’s
power supply. Currently SEC deals with generation, transmission and
distribution of electrical power. However, to provide opportunities to the
private sector to compete and alleviate the financial burden for investments,
and to meet the future power demands, the government has permitted the
private sector to invest in power generation. The government is currently
restructuring the power sector with separate generation, transmission and
distribution functions, with partial unbundling on management level of SEC
complete.
Realizing the financial burden to meet the future power demands, the GCC
countries have embarked on unbundling their power sectors into separate
generation, transmission, and distribution segments, thus providing
opportunity for these business segments to focus on their core business, and
also encouraging capital investments from private sector. Reforms are
underway in Saudi Arabia, and accordingly the Electricity Services Regulatory
Authority (ESRA) was established, which is responsible for issuance of
licenses for electricity projects.
The RCJ may undertake feasibility studies to evaluate alternative options for
local power generation (some options described below) that will relieve
burden on SEC and at the same time ensure security of power supply to
meet some of the demand in case of emergency. Close coordination with
SEC must be maintained on this matter. From the stability standpoint, SEC
strives to reduce the system spikes and unplanned outages that disrupt
industrial operations. SEC anticipates that the new Ghazlan Power Station
No. 2 and additional 380/230 KV feeders link will be stability enhancing.
However, because of the growth rate of the area, and limited generation
reserve capacities, SEC’s ability to provide power to industries during the
peak power demand period in the summer is the greatest concern.
As per the present regulations, SEC is the distributor of power in JIC and
therefore MARAFIQ supplies this power to SEC, which will be distributed to
JIC and others according to their schedule and priorities. In case of a power
supply shortage anticipated in JIC in future, MARAFIQ is prepared to expand
the production capacities provided:
RCJ allocates land to set up another power plant.
Aramco allocates the required fuel for production.
The analysis of the RCJ Supply and Demand data shows that a power supply
shortfall will start build-up in JIC by 2017, and accordingly the mid term will
be the most appropriate timing for this expansion.
While the RCJ may take initiatives to resolve these constraints, as per the
present regulations, the generated power from the IWPP will still be tied to
the SEC power grid that is committed to serve the demand on a national
level. Thus the RCJ efforts for promoting power generation in the vicinity do
not guarantee reliability of power supply in JIC, unless otherwise agreed
upon.
In view of the increasing demand in JIC, the 1999 MPU reiterated past
master plan recommendations that should SEC fall short of generating
capacity, the RCJ might consider situating a power generating station in the
industrial area. While there is no near term need for such an undertaking, it
is recommended that the RCJ may periodically review this concept with
private/public sector investors interested in establishing power production
units in JIC.
SADAF is utilizing its own Auxiliary Power Generation Plant (40 MW) and the
Cogeneration Plant (250 MW) operated by the JEC, to meet most of its power
needs since 2005. The SEC power supply is also available. The cogeneration
plant is tied to the SEC power grid that will allow energy trading between
SEC and SADAF.
The auxiliary power generation uses the high pressure steam for the turbines
to produce electricity and the medium and low pressure steam in the process
for manufacturing chemicals. The cogeneration plant uses gas turbine to
produce electricity and the hot exhaust gases to produce process steam for
manufacturing chemicals, which would otherwise go as a waste. The dual
purpose generation enables the industry to meet its own demand, helping
environmental sustainability. There are lot of opportunities in JIC for the
industries to follow the SADAF model power generation that will enable them
to meet their own demand to a considerable extent at the same time help
reducing environmental pollution.
heat islands and therefore its rejection into the environment has to be
regulated.
There seems to be a good potential in JIC for conversion of waste heat into
electrical power. The Organic Rankin Cycle (ORC) is a electricity generation
process where an organic substance is used as working medium instead of
water. The benefit is that this process can utilize lower temperatures for the
production of electricity than the regular water steam cycle. By help of ORC-
modules it is possible to turn this previously wasted energy economically into
electricity.
In view of the growing demand of electrical power in JIC and in line with the
worldwide trend of utilizing renewable energy resources, possibilities of using
alternative energy resources in JIC should be explored. This will relieve the
total dependence on SEC as the sole distributor of power by way of
facilitating decentralized local power production; and also increase the
confidence level of the customers by having flexibility in meeting the
demand.
Various options for the use of alternative energy resources in JIC have been
considered. The comparative low price of coal is a powerful incentive in
developing coal-fired power plants. But the huge amount of carbon dioxide
produced by these power plants has become a major reason for the dramatic
imbalance in greenhouse gas emissions. In view of the efforts over the world
to combat global warming, coal fired power plant is not recommended as a
viable option for JIC.
Saudi Arabia has declared that one of the most important sources of energy
for it to look at and to develop is solar energy. Research efforts have started
to make the country a center for solar energy research and hopefully over
the next 30 to 50 years a major power exporter.
SEC has recently disclosed its plan to establish solar and wind energy
projects in association with international companies. They are seeking the
cooperation of French companies to establish solar energy projects, and of
Japanese companies for wind energy projects. Some locations had been
identified for the projects.
The six Arab Gulf countries, namely the United Arab Emirates, Bahrain, Saudi
Arabia, Oman, Qatar, and Kuwait, forming the Gulf Cooperation Council
(GCC) have formally established a Power Grid Authority known as the GCC
Interconnection Authority (GCCIA) aimed at developing a GCC power grid
interconnecting the grid systems of all the GCC countries.
The GCC power grid is planned to be realized in three phases. The first
phase, known as the GCC North Grid, linking of the grids of Saudi Arabia,
Qatar, Bahrain, and Kuwait is completed by July 2009 with the official
inauguration scheduled for December 2009. The United Arab Emirates and
Oman will link to the grid in 2011.
The GCC countries hope that this power connection project will help them
meet rapidly rising power demand and avoid power outages. The GCCIA
expressed the view that with the successful linking of the electricity grids of
Saudi Arabia, Kuwait, Qatar and Bahrain, the member countries are close to
achieving their goal of having a joint power grid for all six member states.
The grid aims at guaranteeing an adequate supply of power even in
emergencies and also reducing the cost of power generation in member
countries. There will be economic gains, as well.
Now the work on the interconnection between the United Arab Emirates and
the Sultanate of Oman is under way and is scheduled to be completed in
2011. The resulting two mega-grids will be joined in the final phase. The RCJ
may keep close coordination with SEC to make use of the opportunity and
get benefit from the GCC power grid, in case of emergency.
Extending the GCC power grid to other grids in the region for a possible
interconnection forming a potential regional power grid will provide a larger
opportunity for power trading in the region. The regional power grid will
facilitate a regional electricity market. Access to a larger market will allow
private investors to develop larger projects. The GCC power grid is a
fundamental step to the liberalization of a regional power market. It is the
gateway towards the regional power pool, thus encouraging the GCC
countries to develop a regional power market. The new reform, currently
underway in the country, aiming at boosting privatization in the power sector
is expected to attract investors in power production.
JIC has good potential to establish large scale power projects, utilizing
renewable energy resources. However, feasibility studies are required to
establish this potential. It will be a pioneering endeavour in the country,
aimed at establishing a carbon neutral, zero waste, pollution free, and
environmentally benign industry, utilizing a diverse source for large scale
power production.
Making use of the above opportunities, the RCJ may take initiatives, to
promote power generation as an industry in JIC. It will primarily ensure
security of power supply to JIC, in addition to providing opportunity for the
industry to trade power in a larger market. This is in line with Saudi Arabia’s
policy to promote power production utilizing renewable resources aimed at
becoming a leader in the field and a major power exporter in the next 30 to
50 years, and thus enhancing the economies.
Further details of GCC interconnection power grid and its benefits are given
in Appendix A.
The GCC power grid will provide a common GCC electricity market that will
allow export and import of power between the GCC States. Extending the
GCC grid to other grids such as the EJILST (Egypt, Jordan, Iraq, Lebanon,
Syria, and Turkey), the Arab Maghreb grid, and the UCTE (Europe) can
provide opportunity of power trading with other regions.
A good example of power trading through the regional grid is the export of
power from the GCC region during winters when demand is low to regions in
Europe where power demand is high. The regional market will also encourage
energy interchange during seasonal diversity when need of power in the GCC
region during the hot summer seasons can be imported from regions where
demand is low.
The availability of a common market will also provide opportunity for the
establishment of power plants close to resources such as fuels. Thus giving
freedom for IPP’s or IWPP’s to select a strategic location realizing the
potential in dealing with a larger market and thus facing lower risks. A good
example would be the construction of a power plant operated by Qatari
natural gas and transmitting it to regions with high demand.
By providing trading services to the power sector, the GCCIA will have then
become the ‘launch pad’ for energy trading, not only, between the GCC
countries but with IWPP’s and other power grids such as the Pan-Arab,
European and Mediterranean Grids; making the GCC region into a major
exporter of power and thus enhancing the economies of the GCC countries.
9.5.3 Other
In the early stages of development, the RCJ has identified certain voltage
levels as standard for use in JIC, and accordingly these voltages were used
by the industries and infrastructure (street lighting and utility pump
stations). Consequent to SEC taking over the O&M of power distribution
system in JIC, they encourage the users to install systems compatible with
the SEC standard voltage levels. The RCJ has also revised its design
guidelines for the voltage levels to be consistent with the SEC standards. As
a result, some voltage levels in use in JIC are identified as non-standard. The
RCJ has restricted further use of these voltage levels for new installations,
unless the customer obtains prior approval.
Some industries are still using non-standard voltage systems where the
interface accessories such as feeder breakers, etc are not easily available.
Such long lead items may cause power supply problems and limit
development opportunities. SEC insists that in case it becomes necessary for
the industries or service commercials to establish systems requiring non-
standard voltages, they shall establish their own arrangements to convert the
standard power supply voltage provided by SEC to their requirements.
The RCJ may notify the customers using non-standard system voltages to
switch to standard voltage levels, to avoid power supply problems.
The RCJ is planning for the development of the entire J2 and community
areas within the master plan period. Though not explicit, this might also
include the coastal developments of the Eastern Corridor and Al-Batinah
Island. These developments will require a large demand in the coming years,
which need to be precisely scheduled. In view of the increasing need for
power demand in JIC in the coming years and the SEC’s commitment to meet
the demand nationwide, the RCJ may prepare the demand forecast for a
longer period. It would enable the SEC to make efficient planning and
ensure power supply availability for the JIC demand needs.
The RCJ may prepare the demand forecasts for JIC for a longer period that
would enable efficient planning for the SEC and ensure availability of power
supply to meet the future demands of JIC. This requires coordination
between RCJ and SEC.
9.6 Recommendations
Table 9-7
Power Recommendations
Study/Action Rationale Action By Timing
Policy and Strategic Planning
Negotiate and revert the responsibility of This can be done through the liaison committee RCJ Short Term
construction of substations and distribution identified in Chapter 2. There is need for a high SEC
networks in JIC back to SEC as provided in level communication (at H.H. RC Chairman level)
their Agreement. between RCJY / SEC to update the '85 agreement or
to sign a new one. The new agreement must commit
SEC to meet JIC demand. and reconcile SEC ‘s
mandate to install substations and power
distribution networks in advance of industrial
development as an essential step to improve the day
to day working relationship between RCJ and SEC as
well as the smooth implementation of the power
system expansion programs so vital to JIC. Need to
confirm and clarify responsibilities and if unbundling
of systems will improve the situation. In addition,
the funding of the construction of these utilities
needs to be confirmed.
Conduct feasibility study regarding options These represent a wide variety of options to address RCJ Short Term
for additional supply including: the need for additional supply that needs further SEC through to
Promote expansion of MARAFIQ study to determine feasibility for JIC. Industry Mid Term
IWPP Capacity
Entrust MARAFIQ to distribute
power in JIC
Industries to use SADAF model
power generation
Build RCJ power station
Convert industrial waste to energy
10.0 TELECOMMUNICATIONS
Telecommunication services in JIC were originally the responsibility of MPT&T
before the Saudi Telecom Company (STC) was established. It has been the
practice that RCJ has installed the telecommunications infrastructure
including distribution cable networks and Digital Central Offices (DCOs) in
JIC, and then turning the infrastructure over to STC for O&M. Now that the
Ministry does not exist and telecommunications has been privatized with
multiple service providers, RCJ is proposing a lease agreement with the
service providers (e.g. STC, Mobily, etc) and this new policy is currently
under negotiation with STC and subsequently with other private sector
service providers . In the future it is planned that the service providers will
construct their own DCOs on land provided by the RC, and RC will continue
installing the duct banks and cables for a fee based on individual
Agreements. No agreements are finalized to date.
When STC takes over the new exchanges in the future, all telephone services
and DSL will be coming from the Al Khober exchange and Lasilki exchange.
All data services are provided by the RCJ. The original four exchanges were
built by RCJ. Mobile services are provided by STC (Al Jawal), Ethihad Etisalat
(Mobily) and ZAIN. In future telephone and DSL services shall be provided
by STC and Atheeb Company.
The older developed community areas use copper cable for customer access
whereas new development will use fibre optic cable (FOC). In the early
1980’s RCJ built four Telecom Exchanges with a total capacity of 60,000
lines. Jalmudah and J2 have Telecom Exchanges (Data Centers) using all FOC
distribution/access networks. The RCJ has plans to replace the telecom cable
system in the older communities. STC is using FOC for access network and
will continue to use it. FOC will be used for the distribution/access network
for new development areas.
All new major developments in existing community areas will have FOC
primary lines to the electronic cabinet but the secondary network will be
copper. RCJ has instructed four companies to share new towers, and in
future, all new towers for GSM mobile communications system will be shared.
Ownership and O&M responsibilities have not yet been resolved regarding
these shared towers. Currently, RCJ leases sites to each operator. There are
currently 41 mobile towers located within JIC (22 for STC and 19 for
Mobily).The increase of mobile phone providers has provided a more
commercially competitive climate in JIC which will improve the overall service
capability and maintain a sustainably economic telecommunications industry
over the long term.
The city is served by six telecom exchanges, which are commonly known as
Central Offices (CO). The industrial area is served by:
MSND 335-00 in the northern area of J1, located in the
Support and Light Manufacturing Park with 10,000 lines
capacity.
ASYH 346-00 in the southern area of J1 located along road T-195
between 1-204 and T-218 with 10,000 lines capacity.
J2 (341-00) exchange located in new J2 (using primary Fibre Optics
Cables network).It is expected that there will be a need for 4000 line
capacity excluding data services.
Transmission Facilities
JIC link is done through DWDM technology using two rings of fibre optic
cables.
Distribution Facilities
DSL services are provided over telephone network by the STC. The Existing
Telephone Exchange Areas are shown in Figure 10-2.
Telephone pairs may be leased for special services to the subscriber. The
equipment offers basic transmission and signalling conditions and testing for
special service applications. Cable pair conditioning for higher speed data
applications is the subscriber's responsibility.
The following communication systems are managed and operated by the RCJ
for the specific purposes outlined.
The radio paging system provides service to JIC, and is accessible throughout
the city. The central digital paging terminal, including the radio transmitters
and the antenna system, are situated at the RCJ Hospital in Al-Fanateer.
There are two types of pager handheld receivers being used by subscribers.
One is tone with digital display that provides the subscriber the telephone
number to be contacted. The other is an alpha-numeric pager which allows
the caller to send alpha-numeric messages to the subscriber. The system is
also capable of handling group dialling and group messages with the
handheld receivers. Some industries have expressed in obtaining this service.
Figure 10-3 (ESS, Radio Paging and UHF Facilities) identifies the head end
equipment locations for the existing radio paging system, Emergency
Services Systems (ESS), Community Antenna Television (CATV) system and
UHF system.
The UHF radio system consists of a multiple channel network that services
handheld, mobile and base station units. The system uses repeater base
stations located in Haii Al-Bahar. It operates on an assigned frequency band
and is equipped to transmit and receive channels assigned to personnel who
are responsible for security, emergency services, public works, utilities and
construction supervision. A number of handheld radios, mobile radios and
base station radios are available. The radio repair workshop is located at the
P&T O&M center in Tareeg Sana'a, near Haii Deffi. Currently RCJ is
purchasing a new radio system that will replace the radio repeater system
where all frequencies will be included in a single group.
The UHF antennas are mounted on a 110 m tower in Haii Al-Bahar. A new
50-meter antenna tower and small building are under construction at the
back of the new P&T O&M center and will be used as future site for the main
radio system.
The JIC CATV System provides color TV and FM radio signals from a
centralized antenna/headend located at Haii Al-Bahar to TV and radio users
throughout JIC. Figure 10-4 (CATV Distribution Network Schematic)
illustrates the existing network distribution for the CATV system and head
end equipment locations. The sources are off-the-air and satellite signals
from Saudi Arabia and other Gulf States’ TV and radio stations. Channels are
also allocated to local TV & FM programming from video and audio tape units.
Coaxial cables and trunk amplifiers comprise an underground distribution
system providing service to individual dwellings. Replacement of primary
coaxial cables with fibre optic cables is completed, replacement of trunk
amplifiers with hybrid node amplifiers and installation of fibre optic
equipment at the Headend is completed. A new 50-meter antenna tower
and small building is under construction at the back of the new P&T O&M
center to be used as the Headend for future communities.
A new Head End building has been constructed in Haii Jalmudah to provide
IPTV service to the new and future communities in Jalmudah District using
the fibre-to-the-home (FTTH) technology. The new IPTV Headend and fibre-
optic distribution network is based on GPON technology eliminating the use
of coaxial cables, analog receivers, trunk amplifiers, power supplies and
modular taps.
LI
T-AB U-A
Jalmudah
District
Al-Gurmah
Island Jalmudah JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge 343-00
District
District MASTER PLAN UPDATE
Mardumah
District
T6
Bay
TS4
Al-Deffi Al-Fanateer
Al-Mutrafiah District
District District
TELECOM BUILDING
Al-Fasil Telecom FNTR
TS4 CO-10
District Building 342-00
TS 7
Area
ROYAL COMMISSION SCOPE
T3
SAUDI TELECOM SCOPE
Al-Fanateer
Island PROPOSED SCOPE FOR MUTRAFIAH
O&M Al-Khaleej
Centre District EXISTING INDUSTRIAL, MAJOR ROADS
Evap. Jubail
Stn. PROPOSED INDUSTRIAL, MAJOR ROADS
Industrial
RC College
WTP #3 T6 HQ PERMANENT COMMUNITY SERVICING AREA
TS6 T100
T106 Al-Huwaylat FUTURE COMMUNITY SERVICING AREA
T112
Al-Huwaylat Island
St. 1
T113
Stage 3 and 4 Stg.2 District EASTERN CORRIDOR SERVICING AREA
SWTP Block N CO-1
T289
Stormwater Strm.W SWTP #9 Storm- T120 Block E-South
(Exp.) water NWPS
Holding Pond H.Pond
Pond
Block J-South PRIMARY INDUSTRY SERVICING AREA
T1 0
T130 Al-
Lulu FUTURE PRIMARY INDUSTRY SERVICING
1
T138 T138
District AREA
T147
Kh a
T150 T148
Al-
Sa u
Ar a b i a n G u l f
Shati
T295 AREA
di E
niah
T162 District
le ct
O&S
Ra il
T251
T263
T241
T195
SERVICING AREA
ric
Centre
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
ura
AREA
pan
Block F
O
T184
RO
yR
Block P Block K
W
T259
OW
T198
T143
T163
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Jubail 2 ASYH
Desal.
341-00 T218 346-00
#2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/21/11
MP FIGURES - MXD'S\
TS
MOT
T1
0 3
Al-Batinah
Island
LI
T-AB U-A
Jalmudah
Al-Reggah District
District
Al-Gurmah
Area Code Island JUBAIL INDUSTRIAL CITY
"G" Al-Surouge Area Code
District Area Code MASTER PLAN UPDATE
"C" Area Code
"E"
"A"
Mardumah
Airport Area District FIGURE 10-2
T2
EXISTING TELEPHONE
EXCHANGE AREA
Mardumah Al-Deffi
T6
Bay District
TS4
Al-Mutrafiah
Area Code CENTRAL OFFICE EXCHANGE
Area Code "B"
District
"D" EXCHANGE AREA BOUNDARY
Al-Fasil
District TS4
EXISTING INDUSTRIAL, MAJOR ROADS
Area Code
Al-Fanateer PROPOSED INDUSTRIAL, MAJOR ROADS
"H" Area Code Community District
Area
TS 7
"J" PERMANENT COMMUNITY SERVICING AREA
T3
"J" PRIMARY INDUSTRY SERVICING AREA
Al-Fanateer
Island SECONDARY INDUSTRY SERVICING AREA
O&M Al-Khaleej
Centre District SUPPORT INDUSTRY/NORTHERN CORRIDOR
Evap. Jubail
SERVICING AREA
Stn. Industrial
RC College
WTP #3 T6 HQ
TS6 T100
T106 Al-Huwaylat
T112
Al-Huwaylat Island
St. 1
T113
Stage 3 and 4 Stg.2 District
SWTP Block N Block E-South
T289
Stormwater Strm.W SWTP #9 Storm- Block J-South T120
(Exp.) water NWPS
Holding Pond H.Pond
Pond
T1 0
T130 Al-
Area Code Area Code Lulu
1
T138 District
T138
"N" "L"
T147
Kh a
T150 T148
Al-
Sa u
T154
rsa
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S
Ra il
T263
T251
T241
T195
Jubail 1
ric
Centre
Jubail 2 T174
Ta n
ro a
C om W
ura
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218 #2
RC Area Code
Scap T230
Fac.
"M"
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Al-Batinah
Island
LI
T-AB U-A
Al-Gurmah
Island Jalmudah
JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
T6
Bay
TS4 Al-Fanateer
Community District
EMERGENCY SERVICES SYSTEM (ESS)
Al-Mutrafiah Area
District Al-Deffi
District RADIO PAGING SYSTEM
Al-Fasil
District TS4
FACILITY POLICE (ESS)
RC
Hospital UHF RADIO REPEATERS
TS 7
EXISTING INDUSTRIAL, MAJOR ROADS
T3
Al-Fanateer
PERMANENT COMMUNITY SERVICING AREA
Island EASTERN CORRIDOR SERVICING AREA
O&M RC Al-Khaleej
Centre Building District PRIMARY INDUSTRY SERVICING AREA
Evap. Jubail
Stn. Industrial SECONDARY INDUSTRY SERVICING AREA
College
WTP #3 T6
T100
SUPPORT INDUSTRY/NORTHERN CORRIDOR
TS6
Al-Huwaylat
T106
SERVICING AREA
T112
Al-Huwaylat Island
St. 1
T113
Stage 3 and 4 Stg.2 District
SWTP Block N Block E-South
T289
Stormwater Strm.W SWTP #9 Storm- Block J-South T120
(Exp.) water NWPS
Holding Pond H.Pond
Pond
T1 0
T130 Al-
Lulu
1
T138 District
T138
T147
Al-Bahar
Kh a
T150 T148
Al- (Camp 6)
Sa u
T154
rsa
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S Yanbu
Ra il
T263
T251
T241
T195
ric
Centre District
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
ura
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218 #2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Al-Batinah
Island
LI
T-AB U-A
Al-Gurmah
Island Jalmudah
JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
T6
Community
Mardumah Area
Bay
TS4 Al-Fanateer
Al-Deffi District
TRUNK AMPLIFIER
Al-Mutrafiah District
District NODE AMPLIFIER
Al-Fasil
District TS4 CATV HEADEND
CO-AXIAL/FIBER-OPTIC CABLE
TS 7
EXISTING INDUSTRIAL, MAJOR ROADS
T3
Al-Fanateer PERMANENT COMMUNITY SERVICING AREA
Island
EASTERN CORRIDOR SERVICING AREA
O&M
Centre
PRIMARY INDUSTRY SERVICING AREA
Evap. Jubail
Stn. Industrial SECONDARY INDUSTRY SERVICING AREA
RC College
WTP #3 T6 HQ
TS6 T100 SUPPORT INDUSTRY/NORTHERN CORRIDOR
T106 Al-Huwaylat SERVICING AREA
T112 Island
Stage 3 and 4 Stg.2 St. 1
SWTP Block N Block E-South
T289
Stormwater Strm.W Storm- Al-Huwaylat
SWTP #9 Block J-South T120
(Exp.) water NWPS District
Holding Pond H.Pond
Pond
T113
T1 0
T130
1
T138 T138
T147
Kh a
T150 T148
Al-
Sa u
T154
rsa
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S
Ra il
T263
T251
T241
T195
ric
Centre
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
ura
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218 #2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Al-Batinah
Island
LI
T-AB U-A
Al-Gurmah
Island Jalmudah
JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge District
District
District MASTER PLAN UPDATE
Mardumah
District
Mardumah
T6
Bay
TS4 GSM COMMON SITE
Community MOBILY GSM CELL SITE
Al-Mutrafiah Area Al-Fanateer
District
District MOBILY GSM CELL SITE (TEMPORARY)
Al-Fasil
District TS4
Al-Deffi STC GSM CELL SITE
District
ZAIN GSM CELL
TS 7
PROPOSED INDUSTRIAL, MAJOR ROADS
T3
PERMANENT COMMUNITY SERVICING AREA
Al-Fanateer
Island EASTERN CORRIDOR SERVICING AREA
O&M Al-Khaleej PRIMARY INDUSTRY SERVICING AREA
Centre District
Evap. Jubail SECONDARY INDUSTRY SERVICING AREA
Stn. Industrial
RC College
WTP #3 T6 HQ SUPPORT INDUSTRY/NORTHERN CORRIDOR
TS6 T100 SERVICING AREA
T106 Al-Huwaylat
T112
Al-Huwaylat Island AIRPORT SERVICING AREA
St. 1
T113
Stage 3 and 4 Stg.2 District
SWTP Block N Block E-South
T289
Stormwater Strm.W SWTP #9 Storm- Block J-South T120
(Exp.) water NWPS
Holding Pond H.Pond
Pond
T1 0
T130
Al-
1
T138 T138 Lulu
District
T147
Kh a
T150 T148
Al-
Sa u
T154
rsa
T295 Ar a b i a n G u l f
Shati
di E
niah
T162 District
le ct
R as
Ra il
T263
T251
T241
T195
ric
O&S
Jubail 2 Jubail 1 T174
Ta n
ro a
Centre
C om W
ura
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218 #2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
The Global System for Mobile (GSM) system in JIC was commissioned by STC
in December 1997. Seven cell sites were installed and strategically located
in the Industrial and Community areas. Another two cell sites were added to
provide a better signal coverage in the Community areas. There are now three
companies competing: Jawal, Mobility and Zane with the prospect of a fourth
company. One issue is the repeated installation of new towers. RC regulations
create restrictions. In new systems, RC currently owns the towers and is
pressing for all operators to share towers as a solution.
Figure 10-5 shows existing distribution of GSM cell sites in JIC. The figure
shows that there are 24 cells for STC (Al Jawal) and 19 cells for Ethihad
Etisalat (Mobily).
A 50-meter antenna tower and small building are already constructed at the
back of the new P&T O&M center and will be used as future site for the main
radio system. The future telephone exchange areas and proposed central
office exchanges are shown on Figure 10-6.
LI
T-AB U-A
Al-Gurmah
Island JUBAIL INDUSTRIAL CITY
Al-Reggah
Al-Surouge Jalmudah
District
District
District MASTER PLAN UPDATE
Mardumah
District
T6
Bay
TS4
Community
CENTRAL OFFICE EXCHANGE
Al-Mutrafiah Area Al-Fanateer
District Al-Deffi
District District
Al-Fasil PROPOSED CENTRAL OFFICE EXCHANGE
District TS4
TS 7
PROPOSED INDUSTRIAL, MAJOR ROADS
T3
Al-Fanateer FUTURE COMMUNITY SERVICING AREA
Island
O&M Al-Khaleej EASTERN CORRIDOR SERVICING AREA
Remote Centre District
Switch Unit PRIMARY INDUSTRY SERVICING AREA
Evap. Jubail
Stn. Industrial
RC
FUTURE PRIMARY INDUSTRY SERVICING
College
WTP #3 T6 HQ AREA
TS6 T100
Remote T106 Al-Huwaylat SECONDARY INDUSTRY SERVICING AREA
Switch Unit T112
Al-Huwaylat Island
St. 1 FUTURE SECONDARY INDUSTRY SERVICING
T113
Stage 3 and 4 Stg.2 District
SWTP Block N Block E-South
T289
Stormwater Strm.W SWTP #9 Storm- Block J-South T120 AREA
(Exp.) water NWPS
Holding Pond H.Pond
Pond SUPPORT INDUSTRY/NORTHERN CORRIDOR
T1 0
T130 Al-
Lulu SERVICING AREA
1
District
T138 T138 FUTURE SUPPORT INDUSTRY SERVICING
AREA
T147
Kh a
T150 T148
Al-
Sa u
T154
rsa
Ar a b i a n G u l f
Shati
T295
di E
niah
T162 District
le ct
R as
O&S
Ra il
T263
T251
T241
T195
ric
Centre
Jubail 2 Jubail 1 T174
Ta n
ro a
C om W
ura
pan
O
T184
RO
yR
T259
OW
T143
T163
T198
Sanitary T204
T289
IWPP
Landfill Fac.
T223
T218 IWTP #8
Desal.
T218 #2
RC
Scap T230
Fac.
Sanitary
TS9
T315
T335
TS1
T241
T121
T261
T195
T183
T161
T2 1
TS3
Landfill Block Q Block L Block G 8
T2 74 0 0.5 1 2 km
BeeA'h T272 King Fahd
Industrial Port
T2 74
Logistics Services Area
Logistics Services Area BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
ED
TS8
Logistics Services Area CO MAP PROJECTION: AIN EL ABD UTM ZONE 39N
PROJECT #: 078523
Logistics Services Area TS STATUS: FINAL
7 DATE: 12/22/11
MP FIGURES - MXD'S\
TS
MOT
85
T1
0 3
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
We note that the following planning criteria have been adopted for the 2010
MPU for telecommunications. Demand is split between Community (including
Institutional, Commercial, and Light Industries) and Industry (J1 and J2):
1. Community demand: is based on the Volume I forecast.
2. J1 demand: is prorated based on the ratio of developable lot areas
compared to J2, a ratio of 90%. J2 demand was forecast in the Nexant
Study below.
3. J2 demand: is based on the Feasibility Study of J2 Expansion Stage 4
by Nexant – August, 2007 since the Alternative Feedstock Study Phase
2 report by PGI/CMAI in 2011 did not encompass telecommunications.
As there is no annual demand provided for secondary and support
industries in J2, it has been assumed that these industries will require
an additional 10% of telecommunication services that has been
allocated to primary industries.
Table 10-1
Telecommunication Requirements by Stage – Jubail 2
Table 10-2
Telecommunications Demand Forecast to 2030
Expected Expected
Maximum Telecom lines Commercial lines Total lines
Exchange Exchange needed needed needed
Service Areas Capacity (2030)1 (2030)2 (2030)
Total
80,000 72,300 7,230 79,530
Community
Total Industrial
6000+5400 11,400 - 11,400
(J1 + J2)3
This shows that 90,930 telephone lines are required for the new
developments up to the year of 2030. The required telephone lines exceed
the total capacity of all existing exchanges.
Because JIC will adopt Smart City features in the near future, there is a
need to conduct a specialized consultant’s study to forecast growth of "Data
traffic" through to 2030 for internet services and bandwidth requirements
with supporting forecast calculation methods. This is a very dynamic area in
the telecommunications sector as described in the global context under
Section 10.4.1. Also a methodology for forecasting the rapid growth in data
traffic in internet services is presented in Section 10.4.2.
modules will have growth rates of 101 percent, 216 percent, 144
percent, and 258 percent, respectively.
Traffic from wireless devices will exceed traffic from wired devices by
2015. In 2015, wired devices will account for 46 percent of IP traffic,
while Wi-Fi and mobile devices will account for 54 percent of IP traffic.
In 2010, wired devices accounted for the majority of IP traffic at 63
percent.
Globally, mobile data traffic will increase 26 times between 2010 and
2015. Mobile data traffic will grow at a CAGR of 92 percent between
2010 and 2015, reaching 6.3 exabytes per month by 2015.
Global mobile data traffic will grow three times faster than fixed IP
traffic from 2010 to 2015. Global mobile data traffic was 1 percent of
total IP traffic in 2010, and will be 8 percent of total IP traffic in 2015.
Business IP traffic will grow fastest in the Middle East and Africa.
Business IP traffic in the Middle East and Africa will grow at a CAGR of
30 percent, a faster pace than the global average of 24 percent. In
volume, North America will have the largest amount of business IP
traffic in 2015 at 2.9 exabytes per month. Western Europe will be a
close second to North America at 2.7 exabytes per month.
Predicting what an end user will do once given network access is a difficult
task. Users appetite for bandwidth is insatiable and they will consume
whatever you give them.
The primary areas of focus for bandwidth sizing and capacity planning are
the Wide Area Network (WAN) and public Internet access. Typically Local
Area Networks (LANs), Metropolitan Area Networks (MANs) and Campus
Networks now run at gigabit and 10 gigabit speeds which is more than
adequate but once again it is dependent on many key things ranging from
Also, approval should be obtained from the RCJ for the design, construction
and selection of material to enable the provision of services to subscribers via
a robust and reliable telecommunications services in a timely manner.
10.6 Recommendations
Table 10-3
Telecommunications Recommendations
Continue annual or bi-annual monitoring of Tariffs need to reflect a reasonable cost recovery for STC Short
tariffs. This can be done via the liaison utility maintenance and expansion. This should RCJ Term
committee recommended in Chapter 2. include representatives from Mobily and ZAIN as through
appropriate. to Mid
Term
Prepare 5 and 10 year supply-demand To ensure future shortfalls in supply are identified in STC Short
reports. time to address them. Typically at 80% capacity RCJ Term
design plans need to start for expansions. This should through
include representatives from Mobily and ZAIN as to Long
appropriate. Term
Continue to track actual use (in community To continue to refine projections versus actual use. STC Short
and industrial areas) so that annually the RCJ Term
actual demand can be compared with the through
projections. to Mid
Term
Prepare a comprehensive communication To ensure that communication protocols in case of RCJ Short
procedure to address public evacuation in emergency are appropriate and clear. Term
case of a serious emergency.
Utility Planning and Design
Conduct feasibility studies regarding: To study options to address upgrades required for the STC Short
Providing a telecommunication system to function appropriately. RCJ Term
building for every new district to act through
as a telecommunication provider to Mid
data, telephone and video; Term
Replacing the old copper network to
fiber optics network as per STC
rules and regulation standards for
the provision of FTTH technology for
Figure 11-1 (Existing Solid and Hazardous Waste Disposal Facilities), shows
the location of the solid waste disposal facilities in JIC, which include:
Royal Commission Sanitary Landfill (RCSLF)
BeeA’h Hazardous Waste Incinerator Facility.
BeeA’h Hazardous Waste Landfill.
EDCO Hazardous Waste Landfill.
The RCSLF accepts municipal (Class II) and construction/inert (Class III)
wastes. BeeA’h and EDCO are private firms and their facilities accept
hazardous (Class I) and non-hazardous industrial wastes (Class II). They
also accept the Class I digested and dewatered wastewater treatment sludge
(or biosolids) from SWTP 9 and IWTP 8.
Inert Waste: Inert wastes are those wastes which are not biologically or
chemically active in the natural environment, such as glass, concrete and
brick materials, broken clay and manufactured rubber products.
In the past, the RCJ designated a land area for the disposal of above wastes.
The disposal site was divided into three areas, namely: Class I, Class II and
Class III.
Class III disposal is for the disposal of inert wastes. This are is unlined,
however to ensure that the quality of groundwater in the landfill area is not
altered, groundwater- monitoring to the vicinity of the landfill has been
carried out as part of the environmental monitoring program.
The RCSLF is located in the south east corner of J2 on sites that are divided
by the KRT crossing, and bounded by the J2 boundary on the west and by
the SEC and KRT ROW to the east. Cell No. 8 is 55 ha, Cells 1 to 7 are 283
ha. Figure 11-2 (Sanitary Landfill Site Layout) illustrates the current cell
layout. Cell No. 8 is completely filled and capped and Cell Nos. 1-7 are under
development. The weigh scales for the incoming trucks, the Administration
and O&M Buildings and other facilities are located in the south-east corner of
the landfill operation.
T3
District
Airport Area
O&M Al-Khaleej
Centre District
Evap. Jubail
Stn. Industrial
RC College
WTP #3 T6 HQ
TS6 T100
T106
T112
Al-Huwaylat
Al-Huwaylat
Block E-South District
Stage 3 and 4
T113
Stg.2 St. 1 Block N
Island
SWTP Block J-South
T289
Stormwater Strm.W SWTP #9 Storm- T120
(Exp.)
Holding Pond H.Pond water NWPS
Pond
T1 0
T130
1
Al-
Lulu
District
T138 T138
T147
T148
T150
T154
Kh a
Al-
Ar a b i a n
Shati
T295
rsa
Sa u
T162 District
Gu l f
niah
di E
le ct
R as
O&S
T263
T251
T241
T195
Ra il
ric
Centre
Jubail 1
Ta n
T174
C om
ro a
u
Jubail 2 Industrial Area
ra R
dR
pan
Industrial Area
OW
OW
yR
T184
OW
Block P Block K Block F
T259
T143
T163
T198
T289
Fac.
Landfill
BeeA'h IWTP #8
T223
T218
Incinerator Desal.
T218 #2
RC
Scap T230
Fac.
T2 1
8
Sanitary
TS9
T315
T335
Landfill
TS1
T241
T121
T195
T183
T161
T261
Block Q Block L Block G
TS3
BeeA'h Future T2 74
MOT
T2 74
3
TS
ROYAL COMMISSION SANITARY LANDFILL (RCSLF) EXISTING INDUSTRIAL, MAJOR ROADS
JUBAIL INDUSTRIAL CITY
ENVIRONMENTAL DEVELOPMENT COMPANY (EDCO) PROPOSED INDUSTRIAL, MAJOR ROADS
MASTER PLAN UPDATE
NATIONAL ENVIRONMENTAL PRESERVATION COMPANY (BEEA'H)
FIGURE 11-1
EXISTING SOLID AND HAZARDOUS
WASTE DISPOSAL FACILITIES
BASE DATA PROVIDED BY MAP PROJECTION: AIN EL ABD UTM ZONE 39N
THE ROYAL COMMISSION FOR JUBAIL AND YANBU. PROJECT #: 078523
STATUS: FINAL
0 0.5 1 2 km FILE LOCATION: G:\GIS\078523 JUBAIL MP SAUDI ARABIA\ DATE: 12/22/11
GIS DATA\MXDS\MP FIGURES - MXD'S\
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
2010 Master Plan Update
The RCSLF accepts municipal (Class II) and construction/inert (Class III)
wastes from the community, industries and Al-Jubail, as well as Class II
digested and dewatered wastewater treatment sludge from SWTP 9 and
IWTP 8. Primary and secondary sludge from SWTP 9 are classified as Class
II waste. Secondary sludge from IWTP 8 may be classified as either Class I
or Class II waste dependent upon actual laboratory test results. The RCJ
Sanitation Department has indicated that solid waste from RIC could be
transported to JIC in the future. Such an option would have a substantial
impact on the landfill site necessitating major expansion.
RCSLF Cell No. 8 for Class III wastes only, was in operation from 1998 to
2007. The dimensions of this cell are approximately 720 m by 220 m and 6
m deep. The compacted volume generation per year was approximately
100,000 m3 and with a total volume of approximately 893,000 m3 it took
nearly 9 years to fill. The entire operation was completed in 12 phases of 60
meter bands. Each one to two meter depth of solid waste was compacted and
overlain with 20 to 30 cm of sand cover. RCSLF Cells Nos. 1 through 7 are
under development.
Figure 11-2
Sanitary Landfill (RCSLF) Site Layout
The incinerator and the Class I landfill are reserved for hazardous waste.
Waste material from hospitals and clinics includes domestic wastes and
hazardous wastes such as human tissues, infected dressings, radioactive
material and drug residues. These hazardous medical wastes are to be
segregated from the domestic type wastes and disposed of at the BeeA’h
facility by incineration.
Scrap motor vehicles are generally conveyed to Hadeed for use as scrap
metal feedstock. Battery acid and similar hazardous materials are disposed at
BeeA'h.
The BeeA’h Hazardous Waste Landfill has been in operation since 1989 and
has an integrated modular design encompassing several treatment
technologies. At the present time, one Class I cell is operational and is
equipped with a double liner. Untreated hazardous waste is stored in drums
that are disposed in the Class I cell. Liquid waste is placed in lined lagoons.
The Class II landfill cells accept contaminated waste that is non-hazardous.
Figure 11-3 (BeeA’h Hazardous Waste Landfill (HWLF) Site Layout) illustrates
the current BeeA’h Landfill configuration.
In the 1999 MPU, BeeA'h planned future expansions for landfill operations
through to 2020. Two Class I landfills were planned as well as six new Class
II cells. Class II cell capacity was designed for 120,000 tons and 18,000 tons
for Class I.
BeeA’h landfills place drummed hazardous waste in a cell with a double liner.
The waste is stabilized with cement and lime before disposal. Contaminated
but non-hazardous waste is also landfilled in lined cells. Liquid waste is
disposed in lined lagoons. The individual processes are as follows:
Waste Handling System: The storage and feed systems handle all types of
hazardous organic wastes generated by petroleum, petrochemical, and
secondary industries, including gases, sludge, and liquids delivered in
cylinders, steel and plastic containers, laboratory packs and in bulk
consignments:
The incinerator handles medical waste and other waste requiring
special handling.
A purpose-built drum processing system has been installed to handle
containerized liquid sludge or solids.
Liquid wastes are vacuum drawn to day tanks and then blended prior
to injection into the incinerator.
Solid wastes are repackaged prior to being fed to the incinerator.
Sludge wastes are normally fed directly to a bulk bin equipped with a
mixer.
A purpose - built PCB processing system has been installed to handle
both transformers and capacitors (We note that transformers up to 10
MT gross weight have been processed through this system).
Bulk liquid wastes are discharged to a bulk storage bin.
Bulk solids may be temporarily discharged to a bulk storage bin or to
concrete bunkers and are then repackaged for processing.
A gas manifold provides direct access to the front wall of the kiln -
Halons, CFC refrigerants and a variety of other gases such as
enthylene oxide may be processed through this system.
Combustion Gas Cleaning and Scrubbing System: Hot gas from the
afterburner passes through a cyclone separator to remove coarse particulate
carried over with the gas. The gas then passes through a venturi scrubber
that separates finer particulate and rapidly cools the gas to about 80°C. Acid
gases are then scrubbed from the gas stream by passing the gas through a
packed tower in a counter-current direction to a caustic scrubbing solution.
After passing through an intermediate fan, that maintains the entire
combustion, and gas cleaning system in a negative draft condition, the gas
stream goes through a final particulate polishing step to remove the very fine
particles. The clean gas then passes through a set of mist pads and safely
discharges to the atmosphere.
Process Control System: The process control meets all United States
Environmental Protection Agency (US EPA) requirements for monitoring
discharge gases, measuring waste feed flows and providing automatic feed
cut-offs. Critical temperature parameters, pressures and gas discharge
concentrations are continuously monitored and controlled. Real times are
logged and stored in a purpose-designed database for reporting to regulatory
authorities.
The RCJ mandates that all hazardous wastes generated in JIC be disposed of
inside the city boundaries. The BeeA’h facility was previously the only one in
JIC that handled hazardous waste but a new private operator, EDCO was
established in 2010 on a site south of the BeeA’h landfill property. The
establishment of a second commercial facility will ensure competitive pricing
and alternative treatment facility contractors for the industries. The
proposed layout for the EDCO site is shown in Figure 11-5.
Pond G
Pond H
Class II - Cell No. 3 Class II - Cell No. 4 Class II - Cell No. 5
Pond E
Pond F
Pond I
Class 1
Cell
No. 1
Monitoring Well No. 2
Maintenance Pond B
Area - 2
Pond A
Office
Area - 1
Labours Truck
Waste Storage Area - 8
Cabin Washing Area
Gate House
To Jubail
Road
Abu Hadriyah
NOT TO SCALE
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
FIGURE 11-4
BEEA’H HAZARDOUS WASTE
Monitoring Well INCINERATOR FACILITY (HWIF)
SITE LAYOUT
Area - A
Area - D
Drum Storage
Area - C Administration
Evaporation & Laboratory
Solids Bunker
Pond Building
No. 1 Monitoring Well
Drum Processing
Building
Amenities
Building
Guard
House
Control Room
Weighbridge
Sludge
Pump
Maintenance
Drum Storage Workshop
Control Area - B
Room
Potable Water Car Park
Storage Tank
Pump
Station
Medical
New Incinerator Plant
Waste
Stored
Monitoring Well
NOT TO SCALE
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
FIGURE 11-5
EDCO SITE LAYOUT
NOT TO SCALE
BASE DATA PROVIDED BY THE ROYAL COMMISSION FOR JUBAIL AND YANBU.
This RGME/ Converse report covered a siting study for a new landfill for RCJ
to deposit category II and III waste. The new landfill would have sufficient
capacity for 35 years from 2007. Accordingly the new landfill would have a
sufficient capacity through year 2042. It was assumed that no significant
waste recycling would be practiced through the 35 year period. The users of
such facility would be Al-Jubail and Jubail Industrial City. RC had identified an
envelope of land 3 km wide south and west of planned J2 covering an area of
about 74 km2. Part of this land is owned by the RC.
Five areas were identified as potential new land ill sites. Starting from the
North West corner of the 3 km envelop, Areas 1, 2 and 3 are all located west
of proposed Jubail 2 and owned by RC. The heavily farmed area 4 spans the
southern and western portion of the envelope. Area 5 is the land wedged
between the Prince reserve and the farms.
As the work progressed on the siting study, it became clear, that a vertical
expansion of the existing closed or active disposal space needed to be
At this time, the vertical expansion is moving forward and the new site (when
required) is no longer planned to be located south of J2 as this area will be
used for materials handling and logistics in the future. In August 2010 RCJ
commissioned RGCK for detailed design of the RCSLF vertical expansion to
meet demands through 2025.
Section 2.05 Solid Waste Management Criteria and S, DD, FF, GG and HH of
2.07 Environmental Reporting, Testing and Monitoring Guidelines are
generally operations criteria and therefore beyond the level of analysis
required at the master plan level. The discussion in this Volume will be
limited to the design criteria that are pertinent at the master plan level.
Table 11-1
Summary of Pertinent Design Guidelines for Solid Waste Management and MPU Assessment
RCSLF Class II waste is generated from the following areas: Community, J1,
J2, sludge from SWTP 9 and IWTP 8, and Al-Jubail. Projections were
provided by RCJ in August 2010.
Class I (Hazardous) waste is generated from the following areas: J1, J2,
sludge from SWTP 9 and IWTP 8, and demand from other industries outside
of JIC. Projections through 2017 were provided for the BeeA'h Incineration
Waste Capture Forecast.
Table 11-2 summarizes the solid wastes received at the RCSLF in 2008, as
determined by the RCJ’s Sanitation Department.
Table 11-2
Composition of 2008 Class III Solid Wastes Received at RCSLF
Table 11-3 summarizes the solid wastes received at the RCSLF in 2008 by
classification (Class II and III) as well as by municipality (JIC and Al-Jubail).
Table 11-3
Classification of 2008 Solid Wastes Received at RCSLF
The quantities of Class II waste received in 2008 from Al-Jubail and JIC were
almost identical but the Class III waste in JIC was, as expected,
approximately 10 times more than in Al-Jubail.
Table 11-4 provides the historical record of waste received at the RCSLF from
1990 to 2008.
Table 11-4
Historical Record of Classification of Solid Wastes Received at RCSLF
This shows that there have been large annual fluctuations in the waste
received at the RCSLF.
The 1999 MPU predicted that in 2015 Class II Waste would total
approximately 150,500 tonnes. This was broken down into 79,000
tonnes/year for JIC community based on a generation rate of 1.3
kg/capita/day and 71,500 Tonnes/year from Al-Jubail based on a
generation’s rate of 1.35 kg/capita/day. The RGME study indicated that the
total Class II quantity of waste expected from 2007 through 2042 (35 years)
was an estimated 21.3 million tons. The estimate was based on an annual
population growth of 7% and included J2 requirements. In 2005 it was
estimated that the current the 25 year storage for Class II was 11 million
tons and that the current volume was 4-5 million tonnes. In June 2009,
there was 1,790,000 m3 remaining space which equates to approximately
1,253,000 tonnes (based on a density of 0.7 tonnes/m3).
The 1999 MPU also predicted that in 2015 there would be 475,000 tonnes
per year of Class III (Inert/construction) waste. The RGME study estimated
total quantity for Class III type waste from 2007 through 2042 as 32.2
million tons. In 2005 it was estimated that the current 25 year storage for
Class III was 15 million tons and that the current volume was 5-6 million
tonnes. In June 2009, there was 700,000 m3 remaining space which equates
to approximately 1,000,000 tonnes (based on a density of 0.7 tonnes/m3).
Findings of MPU
RCJ supplied their forecasts for Class II and Class III incoming waste:
Table 11-5
RCSLF Solid Waste Forecast to 2030
Table 11-6
2004 Hazardous Waste Production by Category
The total estimated quantity received in 2004 was a total of 72,000 tons
comprised of 12,000 tons of incinerable waste, 23,000 drums for cleaning,
780 tons of Class I waste, 28,000 tons of Class II waste and 8,200 tons of
liquid wastes.
This shows that incinerable waste was approximately 17% of the hazardous
waste produced in 2004. HWIF is estimated to be handling an excessive
loading of 13,000 MT/year.
Historic trends are outlined in Table 11-7. While waste generation was
forecast to show a 4.8% growth rate to about 27,700 MT/yr by 2017, the
overall capture rate was conservatively estimated at 75% of generation to
produce 20, 660 MT/yr.
Table 11-7
Historic BeeA'h Incineration Waste Capture
New Industries
Outside JIC (MT/yr)
Existing Industries 883 925 960 1,008 1,050 1,100
In August, 2010 BeeA’h reported that the waste capture statistics for the
period from 01.01.2005 to 30.08.2010 As shown in Table 11-8 were as
follows:
Average incinerator wastes received for the 68 month period were
12,877 MT/year.
Average non-incinerator wastes received for the 68 month period were
16,420 MT/year.
Average total hazardous waste capture per year was 29,297 MT.
Table 11-8
Historic BeeA’h Hazardous Waste Receipt Statistics
The 1999 MPU predicted that in 2015 Class I Waste would total
approximately 62,400 tonnes. In the 1999 MPU, BeeA'h planned future
expansions for landfill operations through to 2020. Two Class I landfills were
planned as well as six new Class II cells. Class II cell capacity was designed
for 120,000 tons and 18,000 tons for Class I.
The HWIF Feasibility Study outlined a forecast demand for incinerable waste
disposal between 2004-2010 was anticipated to be 16,000 MT/year,
increasing to 20,600 MT/year from 2014-2020.
During the period between October 2002 and February 2004 the National
Environmental Preservation Company (BeeA’h) undertook a comprehensive
market and demand forecasting program to assess incinerable waste demand
over a 15-20 year horizon.
Findings of MPU
The HWIF has an annual capacity of 8,500 ton (assuming 20% down time),
which is far lower than the projected demand. HWIF is estimated to
currently be handling an excessive loading of 13,000 MT/year.
Table 11-9
Incineration (Class I) Waste Forecast to 2017 (including BeeA’h capture rate)
BeeA'h
Capture
2010 2011 2012 2013 2014 2015 2016 2017 Rate
JIC (MT/yr)
Existing Industries 13,195 11,135 13,870 14,095 14,455 15,735 15,980 16,225 80-85%
Under Development 330 330 330 330 330 330 330 330 80%
New Industries 1,500 1,650 1,815 1,995 2,015 2,220 2,440 2,685 75%
Existing Industries 1,205 1,265 1,270 1,330 1,340 1,400 1,410 1,420 85%
Total Capture 16,230 16,770 17,285 17,750 18,140 19,685 20,160 20,660
Total Waste
Generation 21,790 22,590 23,230 23,950 24,415 26,505 27,090 27,700
Enforcement of RCER
One potential constraint associated with the performance of the RCSLF site
and the commercial industrial and hazardous waste treatment facilities in JIC
is the potential threat of serious groundwater contamination or other
pollution necessitating the shut down and rehabilitation of a facility. It is
therefore important that the air and water quality monitoring program be
vigorously enforced to ensure that the environment or public health is not
adversely impacted.
The potential cost impact must be identified to the industries prior to a point
in time when investment is likely to be minimal. If clear guidance is not
provided, the RCJ, as landlord, could be left with a series of derelict
properties. Such areas would negatively impact the environment and as a
result be unsuitable for redevelopment.
In 2005 it was recommended that a recycling centre be built for Category III
waste. Because of the magnitude of the municipal and industrial solid waste
land requirements for disposal and treatment there is an opportunity to
undertake waste reduction programs at both the community and industrial
operation levels to extend the life of these facilities and to avoid sizeable
property allocations in prime industrial land. In August 2010 RCJ explained
that there was an ongoing effort to commission a “Study for Alternate Uses
of Solid Waste in Jubail” with the goal of promoting an interest from the
private sector on a BOT basis. This initiative had been taken to the CEO level
for consideration. Recycling programs have been successful in larger cities in
KSA and it is hoped that JIC has reached the stage to be a commercially
viable opportunity.
Waste diversion programs as part of the ISWM are used all over the world to
varying degrees of success. Diversion rates from landfills that have been
achieved generally range from 20 % to 40 %, but some areas have goals as
high as 70%. Currently the Ontario target is 60% waste diversion from
landfills, where the diversion rate is determined by dividing the total quantity
of waste diverted by the total amount diverted and disposed. Waste
diversion programs can apply to residential as well as industrial, commercial
and institutional. Generally programs tend to start with residential waste
diversion.
Waste diversion systems must be environmentally safe and cost effective and
needs to meet government regulations and targets. A successful waste
diversion system will divert a significant quantity of waste from disposal,
build awareness and understanding, provide a balance of incentives and
disincentives and explore available technologies for diversion.
There are three main options available to divert municipal solid waste from
disposal. These options make up what is known as the 3Rs hierarchy which
states that waste should be handled in the following manner, in descending
order of importance:
Reduce.
Reuse.
Recycle.
For each of the above three options. there are a number of possible waste
diversion components. The first step in the development of a diversion plan is
to identify if any of these components are not appropriate. We recommend
that a diversion component not be considered unless it meets the following
three screening criteria:
Waste Diversion: the component must have the potential to divert at
least 1 percent of material from disposal.
Reliable Operating History: JIC should not implement a system
component that does not have a proven reliable operating history.
Each system component must be assessed on its ability to provide a
level of reliability in order to ensure an ongoing level of service for JIC.
Economic Feasibility: The capital and operating costs of the system
must be affordable for JIC or a private entity, and the waste stream
that is generated in JIC. A large facility that is economically viable for
a larger waste stream should be investigated to see if it is viable for
the amount of waste generated.
11.6 Recommendations
Table 11-10
Solid and Hazardous Waste Recommendations
Table 12-1
Summary of Key Utility Findings and Recommendations
The August 2010 RCJ projections through 2018 show SWC demand of 1,305,000 m3/hr, Implement the facility upgrades identified including Petrokemya Bypass, Siphon 1 and 2 upgrades, upgrades
which is higher than the ATA and would result in a shortfall in capacity for all components of to PS 1 by replacing six of the 10.3 m3/sec pumps with six new 13.5 m3/sec pumps, and construct a local
the system including: chlorination plant at the end of canal 1.
normal operating capacity starting in 2014.
dredged channel intake starting in 2014. Prepare a plan to determine how maintenance of compartments will be addressed as all compartments will
supply compartment capacity starting in 2011 based on single compartment use or now need to be used in order to meet demand.
2015 if two compartments used.
return compartment capacity starting in 2015. Conduct hydraulic analyses to assess the adequacy of the existing design to accommodate J2 in operational
terms.
SWC for J2 needs to be revisited based on changes to J2 as well as determining potential
impacts of J2. Although there was spare capacity within the system designed for Stages 1 Conduct a study on the existing laterals to determine any deficiencies as original designs were based on
to 3 originally to supply SWC to Stage 4, at an aggregate level, the replanning of Stages 3 different industries and volumes.
and 4 due to the change in feedstock might affect the supply of SWC to industries in all four
stages.
Encouraging industries (existing and new) to convert to cooling towers will decrease the Demand Management Strategy: Meet with existing industries to determine their actual (versus allocated)
overall demand for SWC and thus will decrease the upgrades required in the long term to needs for SWC and options to address their demand requirements.
increase generation supply. If possible, reassign allocated demand for industries to address
short-mid term shortfalls. The largest users of SWC within J1 are located close to the start
of Canal 1, with the implication that measures to reduce their load on the system could
have the greatest impact on aggregate supply capacity. In addition, it is also noted that
two of the largest users of SWC from Canal 3 are located closest to the sea.
RCJ reported that Saudi Aramco and Dow expressed concern over the inconsistent quality Confirm if using TWW in cooling towers is a viable option.
of TWW and the effect this would have on any RO Plant required to treat the water for
cooling applications. This would need to be adequately addressed before this could move
forward.
With the switch to using cooling towers in J2, and some in J1, air quality monitoring will Check air quality monitoring currently in place and identify additional monitoring required for cooling towers
need to be reviewed to ensure that programs will address the potential impacts of this reflecting the new provisions of RCER 2009 when formally published.
change.
Initiate a seawater and marine ecology monitoring program to evaluate the short and long term impacts of
In addition, there is currently no regular program monitoring the seawater and marine SWC discharge and to ensure compliance with the discharge standards.
ecology.
Potable Water (PW)
Based on the current plans for PW supply, there is an anticipated shortfall in the PW system Identify additional PW Sources: RCJ and MARAFIQ management urgently needs to address the issue of
as follows: shortage of PW in the short term in order to identify a long-term solution. The assessment should consider
supply deficit starting at 30,000 m3/day in 2011 and increasing to 690,000 m3/day the practical and economic viability of additional supply(s) from:
in 2030. IWPP beyond the current allotment of 300,000 m3/day;
aggregate shortfall in primary pumping station capacity of 51,000 m3/day in 2014 Implement plants that are on hold;
and increasing to 577,000 m3/day in 2030. Tapping into the Regional water distribution network;
New supplementary resources such as the RIC planned desalination water treatment facility or another
The highest priority to avert a PW shortage in the future because the committed supply of plant to be constructed at a closer site
PW from the IWPP facility will be fully utilized in the short term. According to MARAFIQ, Consider keeping current supplies online;
additional generation units or alternate sources for process water demand for new Implementing plants that are on-hold; and
industries may need to be investigated as soon as 2015. Use of alternative sources for process water.
According to MARAFIQ, the NWPS will require expansion beyond 2013 and the existing Prepare hydrological studies to determine the capacity of local ground water and aquifers, subject to
distribution network can meet customer demand through 2013. resolving water quality issues as identified from release of TWW. Based on this study, determine if existing
groundwater wells need to be taken offline.
There is a need to evaluate existing network through a hydraulic model analysis before Perform a network distribution analysis: This should be done through a computerized hydraulic network
expanding PSs. analysis model to determine if the existing infrastructure is large enough to accommodate the new demands
as the community expands and to confirm that the system is adequate to meet the flows (normal and fire),
pressure, velocities and the looping configuration. The model can assist in determining the location of any
requirements for increased pipeline diameters or booster pumping stations as well as any additional storage
tanks.
Conduct a baseline engineering study to verify/modify the basic design criteria such as looping requirements,
elimination of secondary tank storage and pump houses as recommended in the 1999 MPU
Conduct a feasibility study to identify required upgrades to meet increased bulk storage requirements.
Conduct feasibility study to identify upgrades required to EPS in order to meet SWRO 4 and 5 and upgrades
required to NWPS. Determine if expanding NWPS and EPS are appropriate and/or if a new PS needs to be
planned.
Implement the facility upgrades currently identified including SWRO 4 and 5, EPS pumping capacity upgrades
and installation of bulk storage tanks at the NWPS.
Based on the current tariff schedule the community does not pay for SWW as this is Review the appropriateness of PW tariffs to also account for costs of upkeep and expansion of the SWW
accounted for under the costs for PW. Higher tariffs could be used to encourage the use of system
TWW by industries instead of PW, where possible. PW for residential is charged on a
sliding scale based on use which is appropriate. This should be investigated to see if
appropriate for industry.
Per capita water demand in JIC is higher than other cities in KSA and elsewhere in the world Demand Management Strategy: Determine which demand management and conservation options should be
and decreasing this will greatly reduce future PW needs and infrastructure costs. To ensure encouraged in JIC and implement policy changes necessary. Include a goal to reduce per capita water
sustainable use of resources. PW demand is largest from industry so their demand has the consumption and prepare a Process Water Demand Management and Water Conservation Strategy for JIC.
largest impact on deficits. This strategy should be done in conjunction with Industry and
should look at use of alternative sources for process water.
Diluting effluent stream with PW to reduce TDS concentrations is bad practice and will have Use of PW to dilute IWW effluent: The 1999 MPU identified IWW TDS Limit concerns and recommended that
negative impacts on the treatment plant capacity and will substantially increase PW in order to comply with the combined TDS limits, as established in the RCER, some industries have used PW
consumption. The 1999 MPU proposed analysis approach is appropriate to manage this to dilute their effluent streams. To minimize the use of PW, it is recommended that industries be provided
problem but it should be combined with a comprehensive flow metering and water quality with incentives to recycle process water, potentially using the following approaches: charging fair market
monitoring program. value for PW; restricting industrial water outflow; requiring industry to pre-treat process water other than by
dilution. In the interest of PW conservation, it was recommended that analysis of this issue should proceed
A flow metering and water quality monitoring program will facilitate the application of the on the following basis:
RCJ penalty system for non-compliance. Presenting financial incentives for compliance Determine the extent by which the industries practice PW dilution of their effluent streams.
could further motive industrial facilities to comply with the regulations. Determine the extent by which the TDS limits at individual discharge points could be relaxed without
raising the TWW TDC and TDS content beyond the prescribed limits.
Determine the extent by which the TWW TDS and TDC limits could be raised without adverse effects
on plant life.
Assess the ability of the IWW treatment system to treat wastewater with higher TDS limits.
The 1999 MPU also recommended performing a PW conservation study to minimize leakage. Complete study and develop an integrated network management (mass balancing, leak detection and district
This could be done under the MARAFIQ’s NOOR Program. This study should include an metering) water systems.
investigation of all “non-revenue water”, which includes leakage, unaccounted for water
(illegal use, metering discrepancies, etc). Based on information provided by MARAFIQ,
mass balance meters are being installed under the NOOR transformation programme #5
(Eliminate/Unaccounted Water Product).
Based on the 7 day storage requirement, bulk storage shortfall is currently 375,000 m3 and
increasing to 5,68,000 m3 in 2030. If the 7 day storage requirement is maintained, up to
an additional 115 ha could be required for bulk storage for 2030.
The current design criteria include PW for use in irrigation. As this is not the case in JIC, Review RCER and Design Guidelines: As PW is not generally used for irrigation, removal of this reference in
this reference should be modified. Also, PW is a main source for many nutrients essential determining PW demand from the Design Criteria Manual is appropriate. Also, incorporation of minimum
for human health such as calcium, iron and fluoride and desalinated water has low concentration for some nutrients within the PW quality guidelines is recommended.
concentration of these important nutrients. There are currently no minimum concentration
requirements in RCER.
Industrial Wastewater (IWW)
Based on the demand assumptions used, there would be a deficit anticipated starting in Implement the facility upgrades currently identified in Bechtel report including Stage III and Stage IV
2012 (15,000 m3/day), which would then increase to 132,000 m3/day by 2030. These expansions, as soon as possible to help meet demand. Also, per recent RCJ (Bechtel) recommendations,
shortfalls could increase by 125,000 m3/day if the quality of influent remains at its current implement the following to improve treatment at IWTP 8:
levels. Moderately increase MLSS to 4,000 mg/l to decrease F:M ratio and improve performance.
Dose polymer to augment pressure filter performance.
According to MARAFIQ, additional generation units or alternate sources for process water Increase Cl2 dose to ensure that compliance with FRC dosing is 100% and make flow proportional.
demand for new industries may need to be investigated as soon as 2015. Refurbish SCADA to check control loops and potential replacement of wiring.
Maintain lagoon surface aerators.
In addition, it appears that some of the unit treatment processes in IWTP 8 are not fully Calibrate inlet flow meters.
functioning and are impacting the quality of TWW from the facility.
Identification of additional treatment options: Conduct a feasibility study to review options for additional
The quality of incoming IWW discharged from industries impacts on how well IWTP 8 treatment to meet IWW demand including those identified under Section5.5 (use Stage I aeration system to
functions and there is some question about the quality of IWW from individual industries mitigate the immediate shortfall; bring the Stage IV expansion online earlier; build another expansion (Stage
being released into the IWW collection system not meeting RCER requirements. Regular V); upgrade the existing IWTP treatment system; modify RCER criteria).
wastewater flow monitoring through installation of temporary flow meters and samplers at
the main wastewater collection junctions is a recommended Best Management Practice. Wastewater Quality Assessment: Conduct a comprehensive wastewater quality assessment study to evaluate
Flow metering will provide more in depth wastewater flow characteristics (Peak flow, existing wastewater treatment facilities treatment efficiency and the compliance of industrial facilities with the
average daily and monthly). This information has great value for short term and long term RCER. This should include a monitoring program for IWW leaving industries to ensure that RCER are being
planning, design and monitoring of the wastewater system. A CAPEX project for installing met and determining the extent by which the industries practice PW dilution of their effluent streams.
on-line analyzers to monitor most of the primary industries has already been proposed.
Demand Management Strategy: Conduct a feasibility study to review options for reducing demand for IWW
Monitoring will allow for identification of concerns and a means of enforcement. treatment including those identified under Section5.5 (reduce process water demand; reduce tank washing
Enforcement of the RCER criteria is paramount. If quality criteria are not being met, then demand; and onsite reuse).
the RCER penalties must be enforced.
Charging a different tariff for off-spec water should be considered for all industries. This Ensure that tariffs appropriately account for costs of upkeep and expansion of the IWW system. This review
should be based on a sliding scale, depending on how excessive the quality parameters are should also consider instituting tariffs based on quantity of use (similar to that being used for residential use
and how these could impact treatment capacity at IWTP 8. of PW). This also should be investigated to see if charging should (and can be) done based on BOD and
COD parameters and charges for off-spec water.
In RCER, there are no pre-treatment standards for some important parameters (BOD, COD, Review of RCER: Development of categorical standards based on industry specific wastewater discharges is
and Silver). We recommend updating Table 2-G to include these parameters to ensure that recommended. As recommended in the 1999 MPU, review RCER to:
RCER are providing the most appropriate criteria for the function of the plant and the Determine the extent by which the TDS limits at individual discharge points could be relaxed without
impact on the environment. raising the TWW TDC and TDS content beyond the prescribed limits.
Determine the extent by which the TWW TDS and TDC limits could be raised without adverse effects
on plant life. TDS and TSS are a concern for irrigation system too as clogging and other problems are
common with irrigation system that have a higher TDS and TSS values.
To ensure additional control of VOC emission and to identify air quality and odor Implement upgrades to PS-10, PS-11, PS-15 and PS-16 per approved CAPEX.
contamination. RGME recommended that immediate source testing at the treatment plants
be conducted for establishing emission rates, and assessing the best technology for odor Implement source testing at treatment plants and identify best means for odor control.
control. Future designs should accommodate sealed covers for tanks, if necessary, for
controlling VOC emissions and odor control.
Sanitary Wastewater (SWW)
Based on the current plans for SWW treatment there is an anticipated shortfall in the SWW Identification of additional treatment options: Conduct a feasibility study to review options for additional
treatment capacity of 13,000 m3/day in 2014, increasing to 147,000 m3/day by 2030. If treatment to meet SWW demand including those identified under Section6.5 (use the interim sanitary
SWW is not continued to be accepted from Al-Jubail, this decreases to 73,000 m3/day by treatment plants; short-term overloading of SWTP 9; bring the current planned SWTP 9 expansions online
2030. more quickly; build additional expansions to SWTP 9; build additional sanitary wastewater treatment plants).
In addition, it appears that some of the unit processes in SWTP 9 are not fully functioning This could include diverting some tankers to IWTP 8 to assist in meeting compliance for TWW use for
and are impacting the quality of TWW from the facility. irrigation.
Demand Management Strategy: Conduct a feasibility study to review options for reducing demand for SWW
treatment including those identified under Section6.5 (promote water demand management and conservation
and determine if accepting SWW from Al-Jubail should continue).
To ensure additional control of VOC emission and to identify air quality and odor Implement upgrades to PS-56 per approved CAPEX.
contamination, RGME recommended that immediate source testing at the treatment plants
be conducted for establishing emission rates, and assessing the best technology for odor Implement source testing at treatment plants and identify best means for odor control.
control. Future designs should accommodate sealed covers for tanks, if necessary, for
controlling VOC emissions and odor control.
Treated Wastewater (TWW)
Based on current anticipated demand for TWW, there is a surplus of 124,000 m3/day in Demand Strategy: Prepare a Feasibility Study on industrial demand for TWW and options for use (process
2010 increasing to 337,000 m3/day in 2030. If SWW is not continued to be accepted from water, primary cooling water, make-up water for cooling towers). This process should be done in conjunction
Al-Jubail, this would decrease to 263,000 m3/day in 2030. with input from industries. It should also include identifying the engineering requirements for treatment of
the discharge brine and the integrated RO process. This study is needed to determine system viability. This
MARAFIQ has conducted a study regarding reclaimed water to identify and confirm the could include a pilot study to determine additional pre-treatment and brine treatment requirements and
potential for end reliability of recycling surplus, however the final report is still under establish design parameters. Further interface with equipment suppliers is required to determine if there is an
Management review. In addition, a committee has been struck at RCJ regarding TWW and alternative to a pilot study.
the recommendations of this group should be reviewed and implemented as appropriate.
Disposal of Surplus TWW: Conduct a feasibility study to identify best ways to dispose of surplus TWW
including those identified under Section5.5 (provide more storage tanks; totally use TWW so no surplus;
modify the TWW discharge area). This study should also include options regarding extending irrigation
system to the J2, the proposed Regional City Park, Al-Jubail, and Freeways.
Review of RCER: Update RCER to include discharge criteria for rejects from the DI plant which uses TWW
and not PW as its feedstock.
Review of Design Guidelines related to separation distances for new irrigation pipes, from potable pipes as
well as setbacks to protect well fields.
Perform a network analysis to determine if the existing infrastructure is large enough (pipe diameter, PS
capacity) to accommodate the new demands as the community expands. Evaluate existing network through
hydraulic model before expanding PSs. Pumping capacities will need to be investigated for the TWW PS’s at
SWTP 9 and IWTP 8.
Install a new 1200 mm diameter irrigation transmission line along Tareeg 7 and Tareeg 4 (Contract 575-
C29). This line will be connected to the existing 1200 mm irrigation line, which will complete the loop.
TWW quality is a concern due to treatment plant performance problems at both IWTP 8 and TWW Quality: Conduct feasibility study to determine best ways to immediately improve the TWW quality
SWTP 9. from IWTP 8 including installing a membrane process after the pressure filter and an iron or aluminum
coagulant dose into the aeration tank to improve settlement in the clarifier. Conduct feasibility study to
determine if providing post chlorination at the Al-Deffi and Al-Fanateer PSs using Cl2 drums is appropriate.
Surface Water Drainage
The storm water drainage system throughout the community and industrial areas of JIC is Prepare BMPs for industries to reference.
comprehensive and functions well. The systems in place are of modern design and follow
Best Management Practices. Implement a monitoring program for stormwater discharge.
The comprehensive plan should assess the feasibility of storm water ponds in J2 being used as an
environmental green space and park-like feature with landscaping attributes to improve the aesthetics.
Also the feasibility of ROWs of main and larger open channels in JI and J2 being used as temporary
holding ponds should be assessed for hydraulic viability.
Demand Management Strategy: Encourage energy conservation through customer awareness and
mandatory measures. Implement energy conservation by improved building design and using alternative
energy sources Reduction in power consumption and demand/ Relieve SEC load. Reduction in consumption
and demand per capita/ better demand management.
Enforce Industries to convert non-standard systems to SEC standard system voltage levels.
Currently projections are done separately by RCJ and SEC, and these result in very different RCJ and SEC to consult on annual projections for demand and for a longer planning period. This can be done
numbers for anticipated demand. Also, the demand is often done for the short to mid term. via the Liaison Committee recommended above.
Telecommunications
Currently projections are done separately by RCJ and STC, and these result in very different RCJ and STC consult on annual projections for demand and for longer planning periods. This can be done via
numbers for anticipated demand. Also, the demand is often done for the short to mid term the Liaison Committee recommended above. This should include representatives from Mobily and ZAIN as
only. appropriate.
JIC will adopt Smart City features in the near future and needs to accurately forecast the RCJ conduct a specialized consultant’s study to forecast growth of "Data traffic" through to 2030 for internet
dynamic growth in internet and bandwith use. services and bandwidth requirements with supporting forecast calculation methods.
It is important that the responsibilities of ongoing operation and maintenance of the Conduct feasibility studies regarding:
different components of the Telecommunications network be clearly defined and covered by Providing a telecommunication building for every new district to act as a telecommunication provider
formal agreements. data, telephone and video;
Replacing the old copper network to fiber optics network as per STC rules and regulation standards for
the provision of FTTH technology for the older districts;
Replacing the conventional UHF radio system to a Radio trunking system;
Upgrading the CATV system to Internet Protocol Television for old districts;
Upgrading and expanding the Radio Paging System;
Upgrading of the Emergency Service and UHF Radio Systems;
Installing fiber optic networks for an integrated security system to cover security for roads, hospitals,
clinics and other critical utilities by involving security agencies (National Guard, Coast Guard, Navy Air
A modern telecommunications network that exists in JIC offers the opportunity to establish Force, etc.).
a Communication process in the event of any emergencies such as industrial accidents that Prepare a comprehensive communication procedure to address public evacuation in case of a serious
may necessitate rapid evacuation of the public. emergency.
As of July 2009, there was 1,790,000 m3 of space left for Class II waste and 700,000 m3 of RCJ approve and implement recommendations from currently commissioned RGCK consultancy assignment
space left for Class III waste. The scope of the current design study being undertaken for for detailed design of the RCSLF vertical expansion to meet demands through 2025.
the RCSLF, covers vertical expansion of the existing landfill to accommodate needs until
2025. Identify future locations for solid waste disposal so that the land can be reserved.
From a waste management perspective, address the issue of future site closure and associated corrective
action as certain industrial tenants terminate or relocate their operations.
JIC’s growth has reached the stage where a formal waste diversion or recycling program Commission a “Study for Alternate Uses of Solid Waste in Jubail” with the goal of promoting an interest from
could be established as a commercially viable business similar to what is occurring in other the private sector on a BOOT basis. This will need to include programs to attract private investors to
larger cities in Saudi Arabia. undertake a comprehensive recycling program to divert wastes from the sanitary landfills. This should
include targeted volumes and achievement schedules for reduction in industrial waste generation. Incentives
The current RCER does not require municipal and inert waste minimization through toward reaching this figure can be provided by the RCJ through the permitting process such that
recycling, reuse, and recovery programs. demonstrated reduction in waste generation will be factored into decisions relating to corrective action for
non-compliance in other plant environmental issues. This will require extensive and varied educational
campaigns to sustain participation in all aspects of waste reduction.
Revise the RCER to add recycling and requirements to minimize waste as this will create opportunities for the
private sector to participate.
One potential constraint associated with the performance of the RCSLF site and the Continue with monitoring and enforcement, particularly related to air and ground water impacts.
commercial industrial and hazardous waste treatment facilities in JIC is the potential threat
of serious groundwater contamination or other pollution necessitating the shut down and Continue to closely monitor leachate collection and treatment; groundwater quality; gas collection, burning
rehabilitation of a facility. It is therefore important that the air and water quality monitoring and stripping; odor and dust control; erosion and sediment control; and slope stabilization at all landfill
program be vigorously enforced to ensure that the environment or public health is not operations.
adversely impacted.
Industrial Hazardous and Other Hazardous Waste
RCJ, EDCO and BeeA’h to consult on annual projections for hazardous waste. RCJ, EDCO and BeeA’h to consult on annual projections for demand and for a longer planning period. This
can be done via the Liaison Committee recommended above.
Prepare contracts with BeeA’h and EDCO, to ensure that enough capacity is reserved for JIC.
Identify future locations for solid waste disposal so that the land can be reserved.
In interviews with waste management officials it has been indicated that illegal dumping of Implement study regarding potential illegal dumping.
waste outside of JIC is likely occurring and that waste management contractors capture
only a portion of the total waste generated within JIC. BeeA’h has expressed concern that Continue to closely monitor leachate collection and treatment; groundwater quality; gas collection, burning
hazardous waste was not being closely monitored from origin to its final destination and and stripping; odor and dust control; erosion and sediment control; and slope stabilization at all landfill
there were likely a number of violations occurring. Violators should be prosecuted. operations.
hr hour
Ha Hectare
HADEED Saudi Iron and Steel Company
HDPE High Density Polyethylene
HFC Hybrid Fibre Cables
HV High Voltage
HVDC High Voltage Direct Current
HWIF Hazardous Waste Incineration Facility (BeeA’h)
HWLF Hazardous Waste Landfill (BeeA’h)
Hz Hertz
HGL Hydraulic Grade Line
IBN-HAYYAN National Plastic Company
IBN-SINA National Methanol Company
IBN-ZAHR Saudi European Petrochemical Company
IPP Independent Power Producer
IPTV Internet Protocol Television
IWPP Independent Water and Power Plant
IWTP 8 Industrial Wastewater Treatment Plant 8
IWW Industrial Wastewater
J1 Jubail 1 Industrial Area (Industrial Park East)
J2 Jubail 2 Industrial Area (Industrial Park West)
JCP Jubail Commercial Port
JEC Jubail Energy Company
JIC Jubail Industrial City
JMP Jubail Management Procedures
JRCC Jubail Regional Control Center
JWAP Jubail Water and Power Company
Kg Kilogram
KFIP King Fahd Industrial Port
Kingdom Kingdom of Saudi Arabia
Km Kilometre
KRT Kharsaniah Ras Tanura (Corridor)
KSA Kingdom of Saudi Arabia
KV Kilo Volt
KVA Kilo Volt Ampere
KWh Kilo Watt Hour
L Litre
LAR Land Allocation Reserve
Lpcd Litres per capita per day
LV Low Voltage
m Meter
m2 Square Metres
m3/day Cubic meters per day
m3/hr Cubic meters per hour
m3/sec Cubic meters per second
mg/l Milligrams per litre
MARAFIQ Power and Water Utility Company for Jubail & Yanbu
MED Multi Effect Desalination
Mobily Mobile Service Provider
MPU Master Plan Update
MT/year Metric Tonnes/Year
MV Medium Voltage
MVA Mega Volts Ampere
MW Megawatt (equivalent to 106 watts of electricity)
NED Northern Electricity Department
No. Number
NPC National Power Company
NWPS North West Pump Station
O&M Operation and Maintenance
ORC Organic Rankin Cycle
% Percent
PB Parsons Binkerhof Power
PGI Purvin & Gertz Inc.
PIF Public Investment Fund
PPM Parts per Million
PS Pumping Station
PW Potable Water
RCD Royal Commission Datum
RCER Royal Commission Environmental Regulations
RCJ Royal Commission in Jubail
RCJY Royal Commission for Jubail & Yanbu
RCSLF Royal Commission Sanitary Landfill
RGME Rashid Geotechnical & Materials Engineers
RIC Ras Al Khair Industrial City
RO Reverse Osmosis
ROW Rights-of-Way
SEC is the sole distributor of power in JIC. They have been reliable during
the past; except for some isolated outages reported by the RCJY. Though
SEC’s power generating capacities in the vicinity of JIC seem to be
adequate, these capacities are not committed JIC alone, but to a national
level. The generated power from the IWPP located in JIC also goes to the
SEC grid; as a result, there is no assurance of meeting JIC demand,
except for a total dependence on SEC.
While the coordination of the RCJY with SEC was effective to date in
meeting the demands, SEC distributes power to its customers nationwide
based on its priorities and schedule governed by its prevailing policies.
Unlike the early stages of development, RCJY is not maintaining any
power generating facilities on its own as either primary or secondary
power source.
In view of the growing demand of electrical power in JIC and in line with
the worldwide trend of utilizing renewable energy resources, it is now time
for the RCJY to explore possibilities of using alternative energy resources
in JIC. This will relieve the total dependence on SEC as the sole distributor
of power by way of facilitating decentralized local power production; and
also increase the confidence level of the customers by having flexibility in
meeting the demand.
Various options for the use of alternative energy resources in JIC have
been considered. The comparative low price of coal is a powerful incentive
in developing coal-fired power plants worldwide. But the huge amount of
carbon dioxide produced by these power plants has become a major
reason for the dramatic imbalance in greenhouse gas emissions. In view
of the efforts over the world to combat global warming, coal fired power
plant is not recommended as a viable option for JIC.
Experts are warning that the world needs an urgency driven concerted
effort to create a competitive renewable energy infrastructure and market.
Many countries have implemented incentives like subsidies and rebates to
encourage consumers shifting to renewable energy sources. Scientists
have suggested that Germany can power itself entirely by renewable
energy. Sustainable development and global warming groups propose a
100% renewable energy source supply, without fossil fuels and nuclear
power.
Saudi Arabia has announced its most ambitious project which will use the
new source of energy that will keep the country in the lead of energy
industry for centuries ahead providing the region a sustainable source of
energy – solar energy. In addition to being a vast petroleum repository,
the desert nation is also the heart of the most potentially productive
region on the planet for harvesting power from the sun.
Being in the center of the so-called Sun Belt, the country is part of a vast ,
rainless region reaching from the western edge of North Africa to the
eastern edge of Central Asia that boasts the best solar energy resources
on Earth. This belt is attracting the attention of a growing number of
European leaders, who are embracing an ambitious proposal to harvest
this solar energy for their nations.
Saudi Arabia has declared that one of the most important sources of
energy for it to look at and to develop is solar energy. Research efforts
have started to make the country a center for solar energy research and
hopefully over the next 30 to 50 years a major power exporter.
Solar Energy
Solar energy is the energy collected from sunlight. It can be used in many
ways for generating electricity. The following two options are
recommended as viable options for consideration in JIC.
1. Photovoltaics (PV)
Solar cells produce electricity from light, which can be used to power
equipment or to recharge battery. The first practical application of PV was
to power orbiting satellites and other spacecraft, but today the majority of
photovoltaic modules are used for grid connected power generation. A
significant market has also emerged in off-grid solar power charged
storage battery based solutions.
Due to the growing demand for clean sources of energy, the manufacture
of solar cells and photovoltaic arrays has been doubling every two years,
increasing by an average of 48% each year since 2002, making it the
world’s fastest-growing energy technology. At the end of 2008, the
cumulative global PV installations reached 15,200 MW. Roughly 90% of
this generating capacity consists of grid-tied electrical systems.
The most important issue with solar power generation, as of now, is the
high capital cost. Due to economies of scale, solar panels get less costly
as people use and buy more. Experts have claimed that recent
technological developments bring the cost of solar energy more in parity
with that of fossil fuels. Grid parity, the point at which photovoltaic
electricity is equal to or cheaper than grid power, will be achieved first in
areas with abundant sun.
STE is a technology for harnessing solar energy for thermal energy (heat).
It is different from PV, which convert solar energy directly into electricity.
The US Energy Information Administration defines solar thermal collectors
as low, medium, or high-temperature collectors. While the low and
medium temperature collectors are used for water heating and space
conditioning to conserve energy, the high temperature collectors are used
to heat water or gas to run turbines, which in turn produces electricity.
The solar thermal power plant is a reliable solution, it can deliver peak
load and does not cause pollution. Since it does not use any fuel, the
operational and maintenance cost are minor. The only obstacle for a large
deployment of CSP is mostly of capital cost, involving a large area to be
covered with mirrors or lenses to obtain a significant amount of energy.
Wind Power
Airflows can be used to run wind turbines. Modern wind turbines range
from around 600 kW to 5 MW of rated power, although turbines with rated
output of 1.5–3 MW have become the most common for commercial use;
the power output of a turbine is a function of the cube of the wind speed,
so as wind speed increases, power output increases dramatically. Areas
where winds are stronger and more constant, such as offshore and high
altitude sites are preferred locations for wind farms.
Since wind speed is not constant, a wind farm's annual energy production
is never as much as the sum of the generator nameplate ratings
multiplied by the total hours in a year. The ratio of actual productivity in a
year to this theoretical maximum is called the capacity factor. Typical
capacity factors are 20-40%, with values at the upper end of the range in
particularly favorable sites. For example, a 1 MW turbine with a capacity
factor of 35% will only produce an average of 0.35 MW. Over a year,
output would be 0.35x24x365 = 3,066 MWh instead of 24x365 = 8,760
MWh.
Wind farms require large amounts of land to be used for wind turbines,
particularly in areas of higher wind resources. Offshore resources
experience mean wind speeds of ~90% greater than that of land, so
offshore resources could contribute substantially more energy. This
number could also increase with higher altitude ground-based or airborne
wind turbines.
Since water is about 800 times denser than air, even a slow flowing
stream of water, or moderate sea swell, can yield considerable amounts of
energy. Tidal power captures energy from the tides. Two different
principles for generating energy from the tides are used at the moment:
Tidal motion in the vertical direction — Tides come in, raise water levels in
a basin, and tides roll out. Around low tide, the water in the basin is
discharged through a turbine, exploiting the stored potential energy.
Solar power is pollution free and has the highest power density among
renewable energies. Its operating cost is extremely low and the facilities
can operate with little maintenance after initial setup. However, it has the
disadvantage of high capital cost, large space needed for installation and
the unavailability of power during cloudy weather and in the night.
Residential Sector
The efficiency of air conditioners has increased steadily due to the current
technological improvements. This is attributed to the US National
Appliance Energy Conservation Act authorizing the Department of Energy
to set minimum efficiency standards for space conditioning equipment and
other appliances each year, based on what is technologically feasible and
economically justified. Beyond these minimum standards, the
Environmental Protection Agency (EPA) awards the Energy Star
designation to appliances that exceed industry efficiency averages by an
EPA-specified percentage.
As the air conditioner efficiency gets higher, there is limited room for
improvement, since the efficiencies above 85% are now common.
However, improving the building envelope through better or more
insulation, advanced windows etc. can allow larger improvements.
Improving the building envelope can be cheaper than replacing air
conditioner. The passive house approach produces super insulated
buildings that approach zero net energy consumption.
Passive houses are designed to benefit from solar gain, super insulation,
and advanced window technology. Low energy consumption standards
are used to reduce the net energy consumption. Total primary energy
consumption is minimized using low-energy lighting (such as compact
fluorescent lamps), and high-efficiency electrical appliances. Ground, Air
and Water Source Heat Pump systems (Heat Exchangers) are energy
efficient, eco-friendly, and cost-effective for space conditioning and
domestic hot water systems; and can achieve reductions of up to 69% in
energy consumption.
Commercial Sector
Solar heat loading through standard window designs usually leads to high
demand for air conditioning in summer months. An example of building
design overcoming this excessive heat loading is the Dakin Building in
Brisbane, California, where fenestration was designed to achieve an angle
with respect to sun incidence to allow maximum reflection of solar heat;
this design also assisted in reducing interior over-illumination to enhance
worker efficiency and comfort.
Recent advances include use of occupancy sensors to turn off lights when
spaces are unoccupied, and photo-sensors to dim or turn off electric
lighting when natural light is available. In air conditioning systems, overall
equipment efficiencies have increased as energy codes and consumer
information have begun to emphasize year round performance rather than
just efficiency ratings at maximum output. Controllers that automatically
vary the speeds of fans, pumps, and compressors have radically improved
part-load performance of those devices.
Industrial Sector
The energy required for delivery and treatment of fresh water constitutes
a significant quantity of electricity (an estimated 20% of California's total
energy use is water-related). In light of this a more integrated approach
to electricity and water conservation efforts need to be worked out.
The use of solar panels for water heating is an efficient means to conserve
energy in the industrial sector.
Cities around the world have recognized energy conservation and the use
of alternative energy sources to achieve environmental sustainability.
Energy conservation has been successfully achieved through planning and
development, building design, use of alternative forms of energy, and use
of environmentally friendly building materials.
In the United Arab Emirates, plans are under development to build a world
class sustainable city, called Masdar City in Abu Dhabi. Proposed as a
clean green alternative energy city, Masdar City will include 1,500
companies, 40,000 residents and 50,000 commuters, and will provide
leading research and development for renewable energy technologies.
The city intends to be a leader in sustainability and will be powered
exclusively by renewable energy, including photovoltaic energy, solar
energy, waste to energy and geothermal energy as opposed to traditional
energy sources such as coal, oil, natural gas or nuclear fuel. It will also
be carbon neutral, produce zero waste, and have the world’s greenest
commercial buildings.
The city is being designed based on local climate and cultural traditions,
particularly its solar movements and prevailing winds. Its orientation
captures cooling sea breezes from the North, while its perimeter protects
against the warmer desert winds. The Eastern wall facing the airport will
be raised to provide a buffer, reducing aircraft noise in the city. Shaded by
PV collecting canopies, courtyards and wind towers will draw cooling
breezes into the narrow streets and filter harsh sunlight, conjuring images
of ancient bazaars and market places. Intelligent design will be used in
residential and commercial spaces to reduce energy consumption.
Buildings will be draped with specially designed fabrics that will convert
sunlight into electricity. Canals will run alongside the streets, some of
which will be only 10 feet wide to protect pedestrians from the heat. There
will also be fields of solar concentrating mirrors and wind turbines in the
desert. Palm and mangrove plantations will create a green belt around
the city to provide raw material for bio-fuels that may one day
supplement oil and gas revenues. Construction materials with a high
thermal mass will be used to considerably reduce energy requirements.
The wall encircling the perimeter of the city will form an intelligent outer
shell, housing the energy, environmental and recycling services.
Compared to average urban levels, fossil fuel consumption in Masdar City
will be reduced by 75%, water demand by 300% and waste production by
400%.
Canada
Options
The formation of Marafiq in the industrial cities of Jubail and Yanbu, the
construction of several Independent Power Plants such as the
cogeneration plant for the Saudi Petrochemical Company (SADAF) in
Jubail, and the establishment of the Water and Power Corporation in the
Western Province of the country has been a major boost to privatization in
the power generation sector.
Phase I of the GCC interconnection shall link the power grids of Saudi
Arabia, Kuwait, Bahrain and Qatar. This system is known as the GCC
North Grid. The system components of Phase I include the following:
o A double-circuit 400 KV, 50Hz line from Al Zour (Kuwait) to Ghunan
(Saudi Arabia) with an intermediate connection at Al-Fadhili (Saudi
Arabia) and associated substations.
o A back-to-back High Voltage Direct Current (HVDC) interconnection to
the Saudi Arabia 380 KV, 60Hz system at Al-Fadhili. Saudi Arabia is
the only country in the Gulf with a system frequency of 60 Hz.
o A double circuit 400 KV comprising overhead lines and submarine link
from Ghunan to Al-Jasra (Bahrain) and associated substations.
o A Control Center located at Ghunan and is to be linked with each
member country’s national control center and shall:
1. Assure security of the interconnection and the member systems;
2. Control the access to the interconnection;
3. Perform frequency and interchange regulation;
4. Coordinate the operation of the interconnection;
5. Perform transaction recording and billing.
Phase III of the GCC interconnection shall link the GCC North Grid with
the GCC South Grid. This Phase completes interconnection of the six (6)
Gulf States. The system components of Phase III include the following:
o A double circuit 400 KV line from Salwa to Shuwaihat (UAE) and
associated substations.
o A double circuit 220 KV from Al Ouhah (UAE) to Al Waseet (Oman)
and associated substations.
o A single circuit 220 kV line from Al Ouhah (UAE) to Al Waseet (Oman)
and associated substations.
Two basic topologies are used for the interconnection namely: the
common link topology and the neighbor to neighbor topology. In the
‘common link’ topology each system is tied to the link, providing direct
access to any other interconnected system like in the case for the phase I
interconnection. The ‘neighbor to neighbor’ topology principle is to tie one
power system to another like in the case of Oman and the UAE.
The GCC power grid consists of a mix of the two basic topologies which
joins in the ‘common link’ representing the phase I and the ‘neighbor to
neighbor’ representing the phase II forming the ‘hybrid link’. This ‘hybrid
link’ will provide all countries direct access to any other system except
that of Oman, which will require all transactions with the other five GCC
countries the use of the UAE power system.
Figure B-1 (Geographical Layout of GCC Interconnection Hybrid Link)
depicts the geographical layout of the GCC Interconnection.
Figure B-2 (Electrical Single Line Block Diagram of GCC Power Grid)
depicts the schematic layout of the GCC Interconnection.
Figure B-2
Electrical Single Line Block Diagram of GCC Power Grid
(Source: GCCIA)
Status of the GCC Power Grid
The first phase of the GCC power grid has been completed as of July 2009
linking the power grids of Saudi Arabia, Kuwait, Bahrain, and Qatar, the
formal inauguration is scheduled for December 2009. The GCC countries
hope that this power connection project will help them meet rapidly rising
power demand and avoid power outages. The United Arab Emirates and
Oman would hook up to the grid in 2011 that would be a year later than
previously expected.
With the successful linking of the electricity grids of Saudi Arabia, Kuwait,
Qatar and Bahrain, the member countries are close to achieving their goal
of having a joint power grid for all six member states. The grid aims at
guaranteeing an adequate supply of power even in emergencies and also
reducing the cost of power generation in member countries. There will of
course be other economic gains, as well.
Besides the usual benefits of interconnection, the GCC power grid will
provide a common GCC electricity market that will ultimately provide a
number of benefits to the GCC States. Newly reformed laws will promote
participation of local and external investors resulting in lower production
costs and consequently lower electricity prices.
Extending the GCC grid to other grids such as the EJILST (Egypt, Jordan,
Iraq, Lebanon, Syria, and Turkey), the Arab Maghreb grid and the UCTE
(Europe) can provide opportunity of power trading with other regions. A
good example is the export of power from the GCC region during winters
when demand is low to regions in Europe where power demand is high.
The market will also encourage energy interchange during seasonal
diversity when need of power in the GCC region during the hot summer
seasons can be imported from regions where demand is low.
Figure B-3
Potential Regional Interconnections
(Source: GCCIA)
With the reform of the power sector currently in process, the development
of the GCC Power Grid will be considered to be a fundamental step to the
liberalization of a regional power market. The GCC interconnection will act
as a gateway towards a regional and pan-Arab power pools, thus
encouraging the GCC countries to develop a regional power market and
henceforth promoting social, economic and environmental development
and cooperation in the Middle East and North African countries.
By providing trading services to the power sector, the GCCIA will have
then become the ‘launch pad’ for energy trading, not only, between the
GCC countries but with IWPPs and other power grids such as the Pan-
Arab, European and Mediterranean Grids; making the GCC region into a
major exporter of power and thus enhancing the economies of the GCC
countries.