Professional Documents
Culture Documents
Clarification Issue 0006 - Swamps Draft Rev D
Clarification Issue 0006 - Swamps Draft Rev D
Clarification Issue 0006 - Swamps Draft Rev D
Some issues below as noted with a “?”, are to be discussed at the next design consultants forum and
resolved before this note becomes final.
An overall plan of the road should show location of swamps, bridges and any other
important work areas
For seasonal swamps solution should be simpler if we are certain it dries out.
Consider we state when it is expected to be dry and for how long or hope it matches
dry season??
Show depth material to be removed, what replaced width and width of layer up to
xmm above expect high water level when it rains
Issues
How accurate can we be in specifying depth to be removed, varies on depth
water etc?
How accurately can we calculate volume to be removed?
How do we access level of risk?
Where augers are not long enough to locate hard material, boreholes to be used as
we need to know depth of soft material and should take samples in order to estimate
time for consolidation
For permanent swamps where all the soft material is not to be removed, design
calculations and drawings (cross section and long section) to show:-
depth water contractor expected to work in, there is a limit!
depth of material to be removed, how accurate can we be?
if not all removed depth remaining soft material
depth and type backfill (how high above water, 250mm(??) + expected
settlement? (is slope now 1:4 as per General Specification??)
estimation of settlement depth and time to consolidate (Any problem doing
this??)
need for surcharge(height) and duration, removal of surcharge
Tender drawings for each type of swamp are to show staged construction and
provide clear guidance on construction to include
SI data
Longitudinal section of SI’s at 100m centres or less showing material to be
removed
realistic shape of backfill for each swamp for the depth ranges, show
widening on one or both sides, show staged construction, tables to show
surcharge/height and duration
height of rock fill above water allowing for expected settlement
materials to be used, if bottom layer is rock backfill do we need a graded
material above (possibly more than one layer required??) The above rock /
material should be designed so as to not pass (filter ) into lower layer,
grading for next layer (is it a filter layer?), embankment fill
need for geotextiles including cost benefit as expensive??
Drainage
What provision included, extending the culverts and/or new culverts
How implemented if section widened settles?
Contractor must not block culverts, so how is temporary drainage
managed?