The document summarizes the cost variations for introducing islands on Nabuyonga Rise and Mugisu Hill. It provides a breakdown of costs for different items like kerb-stones, landscaping, and solar lights. For Nabuyonga Rise, which is 1.166km long, the total estimated cost is UGX 902,340,000. For Mugisu Hill, which is 0.500km long, the total is UGX 416,329,200. The overall grand total cost for both roads is UGX 1,318,669,200. Activities like installing kerb-stones is estimated to take 75 days, while landscaping and installing solar lights
The document summarizes the cost variations for introducing islands on Nabuyonga Rise and Mugisu Hill. It provides a breakdown of costs for different items like kerb-stones, landscaping, and solar lights. For Nabuyonga Rise, which is 1.166km long, the total estimated cost is UGX 902,340,000. For Mugisu Hill, which is 0.500km long, the total is UGX 416,329,200. The overall grand total cost for both roads is UGX 1,318,669,200. Activities like installing kerb-stones is estimated to take 75 days, while landscaping and installing solar lights
The document summarizes the cost variations for introducing islands on Nabuyonga Rise and Mugisu Hill. It provides a breakdown of costs for different items like kerb-stones, landscaping, and solar lights. For Nabuyonga Rise, which is 1.166km long, the total estimated cost is UGX 902,340,000. For Mugisu Hill, which is 0.500km long, the total is UGX 416,329,200. The overall grand total cost for both roads is UGX 1,318,669,200. Activities like installing kerb-stones is estimated to take 75 days, while landscaping and installing solar lights
COST VARIATIONS FOR THE INTRODUCTION OF ISLANDS ON BOTH NABUYONGA RISE AND MUGISU HILL
NABUYONGA RISE (1.166KM) MUGISU HILL (0.500KM)
Item Description Unit Unit Rate (UGX) Quantity Amount (UGX) Quantity Amount (UGX) KERB-STONES ON ISLANDS 23.01 Concrete kerbing Precast concrete class 30 barrier kerbs, including concrete bedding as shown in Dwg No. KBSEC002 m 43,200 2592 111,974,400 1118 48,297,600 23.03 Concrete gutter - - Precast concrete grade ST2 gutter m 144,000 2592 373,248,000 1118 160,992,000 55.01 Road marking using road-marking paint m - - Kerb markings (black and white) m 5,400 2592 13,996,800 1118 6,037,200 SUB-TOTAL (KERB-STONES ON ISLANDS) UGX 499,219,200 215,326,800 LANDSCAPING AND GRASSING ON ISLANDS - - 56.03 Preparing the areas for grasssing - - Top soil obtained from within the road reserve, stockpiles or borrow areas (including all haul) cu.m 10,800 350 3,780,000 150 1,620,000 56.04 Grassing - - Planting of grass cuttings ha. 36,000,000 0.3 10,800,000 0.15 5,400,000 Tree planting no. 144,000 30 4,320,000 13 1,872,000 SUB-TOTAL (LANDSCAPING AND GRASSING ON ISLANDS) UGX 18,900,000 8,892,000 SOLAR LIGHTS (DOUBLE SIDE ENTRY BRACKETS) - - Road Lighting Columns, Brackets and Wall Mountings - - 9m steel road lighting column complete with double side entry brackets and other components/accessories no. 6,300,000 60 378,000,000 30 189,000,000
Concrete blocks 300mm x 300mm x 800mm above finished
pavement/sidewalk to protect the lighting columns from motorists no. 103,680 60 6,220,800 30 3,110,400 SUB-TOTAL (SOLAR LIGHTS (DOUBLE SIDE ENTRY BRACKETS) UGX 384,220,800 192,110,400
TOTAL ON EACH ROAD UGX 902,340,000 416,329,200
GRAND TOTAL FOR BOTH ROADS UGX 1,318,669,200
ACTIVITY PROPOSED TIME OF EXECUTION (DAYS)
KERB-STONES ON ISLANDS 75 LANDSCAPING AND GRASSING ON ISLANDS 90 SOLAR LIGHTS (DOUBLE SIDE ENTRY BRACKETS) 90