COST VARIATIONS FOR THE INTRODUCTION OF ISLANDS ON BOTH NABUYONGA RISE AND MUGISU HILL

NABUYONGA RISE (1.166KM) MUGISU HILL (0.500KM)


Item Description Unit Unit Rate (UGX)
Quantity Amount (UGX) Quantity Amount (UGX)
KERB-STONES ON ISLANDS
23.01 Concrete kerbing
Precast concrete class 30 barrier kerbs, including concrete bedding
as shown in Dwg No. KBSEC002 m 43,200 2592 111,974,400 1118 48,297,600
23.03 Concrete gutter - -
Precast concrete grade ST2 gutter m 144,000 2592 373,248,000 1118 160,992,000
55.01 Road marking using road-marking paint m - -
Kerb markings (black and white) m 5,400 2592 13,996,800 1118 6,037,200
SUB-TOTAL (KERB-STONES ON ISLANDS) UGX 499,219,200 215,326,800
LANDSCAPING AND GRASSING ON ISLANDS - -
56.03 Preparing the areas for grasssing - -
Top soil obtained from within the road reserve, stockpiles or
borrow areas (including all haul) cu.m 10,800 350 3,780,000 150 1,620,000
56.04 Grassing - -
Planting of grass cuttings ha. 36,000,000 0.3 10,800,000 0.15 5,400,000
Tree planting no. 144,000 30 4,320,000 13 1,872,000
SUB-TOTAL (LANDSCAPING AND GRASSING ON ISLANDS) UGX 18,900,000 8,892,000
SOLAR LIGHTS (DOUBLE SIDE ENTRY BRACKETS) - -
Road Lighting Columns, Brackets and Wall Mountings - -
9m steel road lighting column complete with double side entry
brackets and other components/accessories no. 6,300,000 60 378,000,000 30 189,000,000

Concrete blocks 300mm x 300mm x 800mm above finished


pavement/sidewalk to protect the lighting columns from motorists no. 103,680 60 6,220,800 30 3,110,400
SUB-TOTAL (SOLAR LIGHTS (DOUBLE SIDE ENTRY BRACKETS) UGX 384,220,800 192,110,400

TOTAL ON EACH ROAD UGX 902,340,000 416,329,200

GRAND TOTAL FOR BOTH ROADS UGX 1,318,669,200

ACTIVITY PROPOSED TIME OF EXECUTION (DAYS)


KERB-STONES ON ISLANDS 75
LANDSCAPING AND GRASSING ON ISLANDS 90
SOLAR LIGHTS (DOUBLE SIDE ENTRY BRACKETS) 90