Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Daily Progress Report (CPEC-2C)

Project Name Hakla to D.I.Khan Motorway PKG-2C Indus Bridge Rehmani Khel To Balian
Project Commencement Date: 10-Dec-17 Weather
Revised Completion Date (EOT#1): 30-Jun-20 Fair Sunny

Original Cost of Project: 7,138 Million Cloudy Rainy


Date: 18-Jul-20

Activity BOQ Progress Qty Remaining


Activities Unit Prev. Achvd % age Plan To Actual To
ID Quantity To Date Var. Quantity
Total Today Completion date date
1 2 3 4 5 6 7=5+6 8 12 13=7 14=13-11 15
Right Abutment Approach Road (3.2 Km)
C1000 Clearing & Grubbing and CNG 152,064 SM 152,064 - 152,064 100% 152,064 152,064 - -
C1010 Formation of Embankment 601,619 CM 202,924 - 202,924 34% 499,770 202,924 -296,847 398,696
C1020 Improved subgrade 29,526 CM 29,526
C2000 Granular Sub base 15,176 CM 15,176
C2010 Aggregate Base 30,019 CM 30,019
C2020 Asphaltic Base Course 9,860 CM 9,860
C3010 TST 23823.36 SM 23,823
C3020 Asphaltic Wearing Course 2560 CM 2,560
Left Abutment Approach Road (1.8 Km)
C1017 Clearing & Grubbing and CNG 85,536 SM 10347 -10,347 85,536
C1040 Formation of Embankment 338,411 CM 32901 -32,901 338,411
C1050 Improved subgrade 16,608 CM 1560 -1,560 16,608
C2040 Granular Sub base 8,537 CM 0 8,537
C2050 Aggregate Base 16,885 CM 16,885
C2060 Asphaltic Base Course 5,547 CM 5,547
C3010 TST 13400.64 SM 13,401
C3020 Asphaltic Wearing Course 1440 CM 1,440
Structures (Indus Bridge)
B0988 Coffer dam & Misc. 1 Job 0.9 - 0.9 90% 0.6 0.6 - 0
B1010 Piles Works 198 No. 184 184 93% 198 184 -14 14
B1040 Pier Works 198 No. 167 167 84% 198 167 -31 31
B1030 Transoms Works 66 No. 55 55 83% 66 55 -11 11
B1060 Casting of Girders 448 No. 179 179 40% 448 179 -269 269
B1060 Stressing of Girders 448 No. 192 192 43% 448 192 -256 256
B1060 Launching of Girders 448 No. 180 1 181 40% 448 181 -267 267
B1090 Construction of Diaphrams 1,980 No. 675 14 689 35% 1980 689 -1,291 1,291
B1090 Construction of deck Slab 64 No. 20 1 21 33% 64 21 -43 43
B1092 Expansion Joints 1,195 M 1195 0 -1,195 1,195
A2040 NJB 1,086 CM 91.20 91.20 0.08 285 91 -194 995
B1120 Rip Rap Works including filter layers 826 SM - - - - 826 - -826 826
Construction of Right Guide Bank(RGB)
Embankment Works-Right Guide
D0999 528,000 CM 98,199 - 98,199 19% 528,000 98,199 -429,801 429,801
Bank(RGB)
D1000 Stone Work of Right Guide Bank 319,896 CM 45,168 45,168 14% 319,896 45,168 -274,728 274,728
Construction of Left Guide Bank(LGB)
Embankment Works-Left Guide
D1009 528,000 CM - 46,067 -46,067 528,000
Bank(LGB)
D1010 Stone Work of Left Guide Bank 319,896 CM - 0 319,896
Other Drainage & Erosion Works
D1020 Construction of Chutes 1,393 CM 273 -273 1,393
RCC Pipe Culverts-1070 &910 mm dia &
D1030 1,430 M 345 -345 1,430
encasements
RCC Pipe Culverts-1070 &910 mm dia &
D1031 0 M 0 0 -
encasements
D1040 Stone Gabions 17,469 CM 3,348 -3,348 17,469
Grouted Rip Rap & Grouted Stone
D1050 32,896 SM 6,608 -6,608 32,896
Pitching
D1060 Dry Stone Pitching 74,088 SM 14,882 -14,882 74,088
Ancillary Works
A2040 New jersey Barriers 8,484 M 2,227 -2,227 8,484
A2041 Pre cast Kerb Stone 8,564 M 8,564
A2050 Metal beam Guard Rail works 6,600 M 1,049 -1,049 6,600
A2060 Traffic Road Signs 510 Each 510
A2070 Pavement Marking 33,716 M 33,716
A2080 GI wire mesh Fence 13,734 M 13,734
A2090 Gantry Signs 4 Each 4
Provision of Service Ducts along the
A2100 80 CM 0 80
Road
A2110 Provision of ITS for project 0 PS -
A2120 Sprigging & Sodding of Grass on Slopes 57,750 SM 0 57,750
Quantities Executed
1 Concrete A-1 (Chutes) 1,473 CM 1,473
Concrete A-2 (Underground and On
2 1,171 CM 1,171
Ground)
Concrete A-3 (Underground and
3 53,844 CM 42,820 193 43,013 80% 10,831
Elevated)
4 Concrete B (Underground) 2,633 CM 841 841 31.94% 1,792
5 Concrete D-1 (Pre-cast) 27,007 CM 15,882 15,882 59% 11,125
6 Reinforcement 14,793 Ton 11,393 38 11,431 77% 3,362
7 Asphalt Concrete Ton -
Major activities involved
1-Launching of girder,casting of deck slab and casting of diaphragms.
2-Stressing of girders is in progress
3-Steel fixing and shuttering of diaphragms is in progress
4-Steel fixing and shuttering of deck slab is in progress
5-steel fixing and shuttering of girders is in progress
6-Casting of barriers is in progress.
Plan For The Next Day
1-stressing of girders
2- Folding and shuttering of diaphragms is in progress
3-Folding and shuttering of deck slab is in progress
4-steel fixing and shuttering of girders is in progress
5- Launching of girders is in progress
6-Casting of girders
Manpower & Material Summary
Sr. Vehicle Diesel Per m3
Type Activities Status
No ID Drawn Quantity Consumpti
CM Umair
1 Loader 950E 100 For launching of girders Rental
2 Tractor 8791 15 Pipes,joints,steel shifting for slab
3 Pickup 8129 20 For electrician staff
4 Transit mixture 40 For casting of deck slab,diaphragms
5 Excavator Ex200 130 For removing materials from span
6 Generator 50 For girder yard
7 Generator 165 For camp
8 Loader 966 100 For launching of girders Rental
9 Dozer D85 100 For launching of girders Rental
10 Dozer D76 100 For launching of girders Rental
11 Generator 30 For deck slab
12 Excavator 150 For stressing Rental
13 Pickup 2869 45 For nespak
14 Loader 130 For batching plant
15 Crane 3504 80 For launching of girder
16 Generator 76 For batching plant
17 Transit mixture 336 75 For casting of deck slab,diaphragms
18 Transit mixture 289 70 For casting of deck slab,diaphragms Rental
19 Transit mixture 710 70 For casting of deck slab,diaphragms Rental
20 Diesel 15 For shuttering plates
21 Transit mixture 4929 90 For casting of deck slab,diaphragms Rental
22 Concrete pump 5856 130 For casting of deck slab,diaphragms Rental
23 Loader 930 50 For road work
24 Roller 188 For road work
25 Diesel 44 Shuttering plates for girders
26 Pickup 1943 15 For admin
27
28
29
30
31
32
34
35
37
38
SUB TOTAL 2078
Manpower Status Report
Project CPEC-2C, 6.4 Km + Indus Bridge-Rehmani Khel To Kot Balian
Location Hakla (On M-1) To D.I.Khan Motorway
Package 2C
MANPOWER SKB Nos. MANPOWER SKB Nos.
Project Manager 1 WORK SHOP
STRUCTURE STAFF HTV Mechanic 3
Construction Manager 1 Asst.Mechanic 1
Engineer 1 Auto Electrician 1
Supervisor 2 Auto Electrician Helper 1
Foremen 1 Welder & Tiremen 1
Surveyor 3 OPERATOR STAFF
Surveyor Asst. /Helper 4 Loader operator 2
GUID BANK Excavator operator 2
Construction Manager 1 Crane operator 1
Foremen 2 Crane helper 1
Surveyor 3 Grader operator 1
Surveyor Asst. /Helper 2 Roller operator 2
ADMINSTRATION STAFF Generator operator 1
Admin 1 Dozer operator 1
Admin Asistant 1 Water pump operator 1
ACCOUNT STAFF DRIVER STAFF
Accountant 1 HTV driver 6
QUANTITY SECTION LTV driver 4
Quantity surveyor 1 Tractor driver 3
Cad operator 2 GENERAL STAFF
LIBORTORY STAFF Cook 3
Lab Technision 1 Office Boy 1
Asst.Lab Technision 1 Cook helper 2
STORE STAFF Washerman 1
Store keeper 1 Sweeper 1
Material supervisor 2
MANPOWER SUB-CONTRACTOR Nos.
BATCHING PLANT STAFF
Batching Plant Incharge 1 Sub-Contractor
Plant Operator 2 Sub-Contractor 3
Electrician 3 STRUCTURE STAFF
Plant Helper 1 Foremen 5
SECURITY STAFF WORKERS STAFF
Security incharge 1 Labours 119
Security guard 13

SKB Manpower Total 93 Sub-Contractor Toal 127


Site Photos

[PHOTO DESCRIPTION] [PHOTO DESCRIPTION]

[PHOTO DESCRIPTION] [PHOTO DESCRIPTION]

[PHOTO DESCRIPTION] [PHOTO DESCRIPTION]

[PHOTO DESCRIPTION] [PHOTO DESCRIPTION]

You might also like