Professional Documents
Culture Documents
Eddie Wong Aecom PDF
Eddie Wong Aecom PDF
• Design Review
Project Background
• Independent Design Check
Approximately
1040 sq km
Current population
600,000
Huge development
potential
Estimated Cost
12.6 billion Yuan (12,600,000,000)
US$1.58 billion
Parties to the Tunnel Construction
Client:
Shanghai Changjiang Tunnel and Bridge Development Co
Ltd
Designer:
Shanghai Tunnel Engineering Design Institute (STEDI)
Contractor
JV of Shanghai Tunnel Engineering Corporation (STEC)
& Bouygues Asia
Special Advisor
AECOM Asia Company Ltd
Chong Ming Tunnel Layout
Sandy Silt
Clay
Silty clay
Clayey Silt
Silty clay
Clayey Silt
Features of the Tunnel
Diameter and length of tunnel
15.0m in diameter and approx. 7.5km long
13.7m is the internal diameter
Ground conditions
soft material (silt and clay)
Water Pressure
about 60m water head
Man-made Island
The island is for ventilation and emergency situation
AECOM’s Role
• Design Review
Design Control
• Independent Design Check
• Design Review
Design Developments
• Independent Design Check
Twin bores13.7 m
Internal diameter
7.5 km Long
Volume of
excavation 2.7
million m3
3 x 3.75 m traffic
lanes
LRT in invert
Cross Passage Layout
8 Cross Passages
Spacing : 830m
Developed Plan of Intrados For universal
Tapered Ring
AECOM’s Role
• Design Review
Tunnel Ventilation
• Independent Design Check
Layout 1 Layout 2
Original Man-made Island Layout
Retaining Wall
Rubber
550kg
100kg Rock Fender
100kg Rock Rock
fill (0.5m fill (2m Thick) Amour San
Thick) (2 layers) d
Fill
20~100kg Existing
Rock fill Soil
Layout 1
Ø1700m
m Pipe
Pile
Retaining Wall
250kg Rock
100kg Rock fill 100kg Rock
San Amour (2 layers)
(2m Thick) fill (0.5m
d Thick)
Fill
Existing 20~100kg
Soil Rock fill
Layout 2
Ø1700m
m Pipe
Pile
Man-made Island Design Considerations
Scouring Effect
Ship Collision Design
Environmental Impact
Wave Action
Interim and Long Term Settlement
Overall Stability
Liquefaction
Temporary Working Platform
Alternative Ventilation Solution
Hybrid solution
AECOM’s Role
• Design Review
Tunnel Lining
• Independent Design Check
Longitudinal deflection
– Connection between the ‘rigid’ approach structures and ‘floating’
tunnel
Arrangement Full-scale Ring Test
Full-scale Ring Test
Segmental Lining
Each segment
– Weight 16 tonnes
– Width 2.0 m
– Thickness 650 mm
– Reinforcement 135 to165 kg/m3
• Design Review
Tunnel Internal
Structure
• Independent Design Check
• Design Review
Weight
• 2,300tonnes total
• 170tonnes main drive unit
Treatment Process
Rotating Drum Screens
Hydrocyclones
– Primary
– Secondary
Slurry Treatment Plant
Tunnel Spoil After Separation
Segmental Lining Transportation
Original Scheme
Purpose Built Transporters
Final Scheme
TBM Drive Best Shift Best Day Best Week Best Month
• Design Review
Provision of (LRT)
• Independent Design Check
Light Rail Transit
• Technical Advisory Service during Design and
Construction Stage
Repositioned sumps
Evacuation provisions
Provision of Light Rail Transit
Cross Passages
Options considered
– Enlarged combined use cross passages
– Dedicated cross passages for each level
Provision of Light Rail Transit
• Design Review
Construction of Cross
Passage
• Independent Design Check
Emergency Door
Cross Passage Excavation & Temporary
Support
Unfrozen core
• Design Review
Sump
Tank
Low Point Sumps - External
Sump
Tank
Alternative Solution
Advantages
No ring is required broken
Construct inside the shield
Less cost and risk
Sump
Tank
Low Point Sumps