Download as pdf or txt
Download as pdf or txt
You are on page 1of 79

Controlling Design and

Construction Costs of the


World’s Largest Double-Deck
Road Tunnel: Case Study –
Chongming Tunnel
Mr Eddie Wong
23 June 2011
AECOM’s Role

• Design Review

Project Background
• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Chong Ming Island

 Approximately
1040 sq km
 Current population
600,000
 Huge development
potential

Presentation Title June 24, 2011 Page 3


Chang Jiang Tunnel & Bridge Project

 7.5 km twin bore tunnel:


Pudong to Changxing
Island
 15.1 km Viaduct and
Cable Stayed Bridge
Changxing to Chong
Ming
 2.9 km at grade
approaches
Project Objectives

 Currently journey from Down Town Shanghai to Chong Ming


takes 1 - 2 hours by ferry
 The link will cut journey time between Chong Ming and the
Pudong to 30 minutes

Estimated Cost
 12.6 billion Yuan (12,600,000,000)
 US$1.58 billion
Parties to the Tunnel Construction
 Client:
Shanghai Changjiang Tunnel and Bridge Development Co
Ltd
 Designer:
Shanghai Tunnel Engineering Design Institute (STEDI)
 Contractor
JV of Shanghai Tunnel Engineering Corporation (STEC)
& Bouygues Asia
 Special Advisor
AECOM Asia Company Ltd
Chong Ming Tunnel Layout

Pudong Man-made Island Changxing Island


(Ventilation Shaft 1) (Ventilation Shaft 2) (Ventilation Shaft 3)
Longitudinal Section of Chongming Tunnel
Ground Conditions

Sandy Silt

Clay

Silty clay

Clayey Silt

Silty clay
Clayey Silt
Features of the Tunnel
 Diameter and length of tunnel
15.0m in diameter and approx. 7.5km long
13.7m is the internal diameter
 Ground conditions
soft material (silt and clay)
 Water Pressure
about 60m water head
 Man-made Island
The island is for ventilation and emergency situation
AECOM’s Role

• Design Review

Design Control
• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Factors Controlling the Construction Cost
 Ground conditions
 High water pressure
 Ventilation
 Tunnel lining
 Tunnel internal structure
 TBM
 Provision of railway services
 Cross passage
 Sump pit
AECOM’s Role

• Design Review

Design Developments
• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Initial Typical Cross Section
Revised Tunnel Typical Cross Section

 Twin bores13.7 m
Internal diameter
 7.5 km Long
 Volume of
excavation 2.7
million m3
 3 x 3.75 m traffic
lanes
 LRT in invert
Cross Passage Layout

 8 Cross Passages
 Spacing : 830m
Developed Plan of Intrados For universal
Tapered Ring
AECOM’s Role

• Design Review

Tunnel Ventilation
• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Tunnel Alignment
Man-
Man-made Island
(Ventilation Shaft 2)

Layout 1 Layout 2
Original Man-made Island Layout

Retaining Wall
Rubber
550kg
100kg Rock Fender
100kg Rock Rock
fill (0.5m fill (2m Thick) Amour San
Thick) (2 layers) d
Fill

20~100kg Existing
Rock fill Soil

Layout 1
Ø1700m
m Pipe
Pile

Retaining Wall

250kg Rock
100kg Rock fill 100kg Rock
San Amour (2 layers)
(2m Thick) fill (0.5m
d Thick)
Fill

Existing 20~100kg
Soil Rock fill

Layout 2
Ø1700m
m Pipe
Pile
Man-made Island Design Considerations
 Scouring Effect
 Ship Collision Design
 Environmental Impact
 Wave Action
 Interim and Long Term Settlement
 Overall Stability
 Liquefaction
 Temporary Working Platform
Alternative Ventilation Solution
 Hybrid solution
AECOM’s Role

• Design Review

Tunnel Lining
• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Segmental Lining

Critical Design Issues


 Buoyancy
– Large diameter tunnels in soft soils must be ‘ballasted’ to achieve
neutral buoyancy during construction phase

 Longitudinal deflection
– Connection between the ‘rigid’ approach structures and ‘floating’
tunnel
Arrangement Full-scale Ring Test
Full-scale Ring Test
Segmental Lining

 11 No. precast concrete


segments per ring
– total no. 90,000 pieces

 Each segment
– Weight 16 tonnes
– Width 2.0 m
– Thickness 650 mm
– Reinforcement 135 to165 kg/m3

Sealed against a maximum


water pressure of 8.5bar by
EPDM compression gaskets
Lining: Reinforcement Cage
Lining: Segment Mould
Lining: Storage & Curing
AECOM’s Role

• Design Review

Tunnel Internal
Structure
• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Original Road Deck Structure

 The road deck is divided


into 3 units
 The central unit is pre-cast
 The left and right units are
cast in-situ
Alternative Road Deck Structure

 The road deck is divided


into 3 units
 The left and right units are
cast in-situ and supported
by corbels
 Rebar are drilled and
inserted into the concrete
lining
Road Deck Structure Construction
Road Deck Structure Construction
Road Deck: Central Precast Unit
Road Deck: Insitu Construction
Road Deck: Final Construction
AECOM’s Role

• Design Review

Tunnel Boring Machine


• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Tunnel Boring Machines

 Herrenknecht S 317 & 318 Mixshields


• Diameter 15.43m
• Length 125m

 Weight
• 2,300tonnes total
• 170tonnes main drive unit

 Cutter Head Power 3,500kW


 Design and fabrication 13 months
 Site assembly 4 months
TBM Assembly
TBM Cutterhead Chamber for Changing Tools
TBM Cutter Head Site Assembly
TBM Site Assembly
TBM Site Assembly Tailskin in Place
Slurry Treatment Plant

 Slurry treatment plant


capacity
3,000m3/hour/TBM

Treatment Process
 Rotating Drum Screens
 Hydrocyclones
– Primary
– Secondary
Slurry Treatment Plant
Tunnel Spoil After Separation
Segmental Lining Transportation

Original Scheme
Purpose Built Transporters

Final Scheme

But Nothing is Ever Perfect


TBM Segment Feeder
Segmental Lining Erection

 Ring built to within +/-10mm


 Average build time
 Initially 150 minutes
 Generally 50 minutes
 44 rings / week
Tunnelling Progress

TBM Drive Best Shift Best Day Best Week Best Month

East 6 (12) 11 (22) 65 (130) 241 (482)

West 6 (12) 11 (22) 62 (124) 255 (510)

TBM Advance rings (m)


Erector Arm: Loss of Vacuum

Re-welding head to seal


air leakage paths

Replacing vacuum seals


Erector Arm: Vacuum Test
West: TBM Break Through
AECOM’s Role

• Design Review

Provision of (LRT)
• Independent Design Check
Light Rail Transit
• Technical Advisory Service during Design and
Construction Stage

• Participation in Expert Panel Meetings


Provision of Light Rail Transit

Decision made after tender award and TBM Fabrication


Commenced
Impossible to ‘create’ additional space not only to
accommodate LRT itself but also:

 Repositioned sumps
 Evacuation provisions
Provision of Light Rail Transit

Cross Passages

 Original provision 8 no. inter-connecting cross passages at


road level

 Options considered
– Enlarged combined use cross passages
– Dedicated cross passages for each level
Provision of Light Rail Transit

Combined Use Cross Passage


Provision of Light Rail Transit
Dedicated Cross Passages
Provision of Light Rail Transit

Solution emergency stair connection lower to


upper deck every 175 m
Provision of Light Rail Transit
AECOM’s Role

• Design Review

Construction of Cross
Passage
• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Cross Passage: Ground Freezing

Ground freezing only feasible method to secure ground


during excavation
Design Considerations
 Heave pressure due to expansion of water
 Loss of freeze due to heat transfer
Cross Passage: Ground Freezing

 A thermal and mechanical (TM) analysis conducted to


evaluate the influence of ground freezing
 The 3-D finite difference program FLAC-3D adopted
 Five major steps are involved in the simulations:
– The initial stress condition of the underground;
– The excavation of the tunnel;
– The freezing effect of the cooling pipes;
– The excavation of the crossway passage
– The effect of the crossway excavation to the tunnel.
Cross Passage: 3-D FLAC Model
Cross Passage: 3-D FLAC Model Ground Freezing
Cross Passage: Freezing Pipe Arrangement
Cross Passage: Ground Freezing

Fixing of door frame in steel


opening set

Freeze started with calcium


chloride brine at -35o C
Cross Passage: Ground Freezing

Emergency Door
Cross Passage Excavation & Temporary
Support

Unfrozen core

Steel ribs with timber lagging


Cross Passage: Lining & Waterproofing

Shotcrete infill to ribs with grout tubes

Water proof membrane in place


Cross Passage: Permanent Lining
AECOM’s Role

• Design Review

Tunnel Sump Pit


• Independent Design Check

• Technical Advisory Service during Design and


Construction Stage

• Participation in Expert Panel Meetings


Low Point Sumps

Original Scheme: Standard Solution of Internal Sumps

LRT envelope not only,


 encroached on space
provided for sumps,
but also
 dropped the elevation
of the low point

Sump
Tank
Low Point Sumps - External

External sump disadvantages


 Rings have to be broken
 External hydrostatic head
65m
 Ground treatment required
only option ground freezing

Sump
Tank
Alternative Solution

Advantages
 No ring is required broken
 Construct inside the shield
 Less cost and risk

Sump
Tank
Low Point Sumps

Solution ‘split’ sumps


 Road Deck to original
location
 LRT to a series of sumps in
invert

Special steel invert


segments fabricated to form
sumps for the LRT Level
Thank You

You might also like