EXHIBIT II

SCHEDULE OF WORKS AND EXECUTION PLAN

TABLE OF CONTENTS

SECTION TITLE

II-1.0 SCHEDULE AND EXECUTION PLAN

APPENDIX

II-1 CONTRACT SCHEDULE


EXHIBIT II

SCHEDULE OF WORKS AND EXECUTION PLAN

II-1.0 SCHEDULE

II-1.1 Schedule of WORKS

It is assumed that DH-1P, DH-2P & DH-3P will be ready for hand-over to
CONTRACTOR to perform the P&A Work tentatively on 15th October 2018. It
is noted that the actual hand-over date shall be notified to CONTRACTOR one
(1) month in advance before performing the WORKS at offshore site (Dai Hung
Field). CONTRACTOR is requested to complete the WORKS, excluding one (1)
year warranty period.
The actual nomination of Milestones shall be proposed by CONTRACTOR,
appropriate to its chosen execution methodology and in accordance with
APPENDIX II-1 – CONTRACT SCHEDULE. CLIENT shall incorporate the
agreed Milestones Schedule (submitted as part of the Technical proposal, after
reviewing updating and acceptance by the CLIENT) into this Section.

Calendar
No. Description
Date
General

01-01 Effective Date


Completion of preparation including engineering,
procurement, and fabrications, Project control
01-02 procedures, project quality plan, project safety plan,
interface register and Sub-contract Schedule Baseline
(initial version)
Onshore/Offshore Equipment and Tool function tests
01-03
witnessed and accepted by CLIENT
01-04 Procedures for Offshore Works approved by CLIENT.

01-05 Full Final Documentation Accepted by CLIENT.

Offshore Execution for Wells P&A


Start and complete for Site survey Xmas-tree
02-01
Inspection prior to DP Floating unit mobilization
Start for mobilization of DP Floating unit for well
02-02
abandonment
Handover DH-1P, DH-2P & DH-3P well to
02-03
CONTRACTOR
Complete mobilization of DP Floating unit for well
02-04
abandonment

TENDER NO.: PVEP POC-18-10108 EXHIBIT II


PROVISION OF ENGINEERING AND EXECUTION OF PLUGGING AND ABANDONMENT OF DH-1P, DH-2P, DH-3P WELL AT
DAI HUNG FIELD, BLOCK 05.1A, OFFSHORE VIETNAM PAGE 2 OF 4
Calendar
No. Description
Date
02-05 Completion of DH-1P, DH-2P & DH-3P well P&A
ROV survey for seabed clearance (as evidenced by
02-06 CLIENT’s signature on Offshore Work Completion
Certificates)
02-07 Start and complete Demobilization of DP Floating unit
All removed items are placed in the designated
02-08
location
Post P&A work survey is to be carried out at the last
02-09 moth of the warrantied year or any time when any
issues are observed from the P&A wells.
Final documentation

03-01 Approval of final documentation

CONTRACTROR is requested to submit the Schedule and Execution Plan as


required in EXHIBIT I – SPECIAL PROVISIONS AND SCOPE OF WORKS.
There shall be no change to the Milestones descriptions and/or dates as set out in
Section 1 except by issuance of CLIENT Approved Change Order.

II-1.2 Scheduled Completion Date

The Completion Date (Delay Liquidated Damage) as set out in ARTICLE 30 –


“LIQUIDATED DAMAGE” of CONTRACT FORM shall apply to Milestone
No. 02-02 and No. 02-05 as evidenced by CLIENT’s signature.

There shall be no change to the Milestone dates as set out in Section II-1.1 except
by issuance of CLIENT Approved Change Order.

II-2.0 EXECUTION PLAN

II-2.1 CONTRACTOR shall be required to provide execution plan that cover:


- Project management;
- Coordination between CLIENT and CONTRACTOR;
- Concise project organization chart (with names, responsibilities and
reporting relationships);
- Location of all offices where work will be performed, each office's facilities.
- Major subcontractors for P&A work;
- Facilities and service for CLIENT.
- Equipment and tool description.
- Source of equipment and tool.
TENDER NO.: PVEP POC-18-10108 EXHIBIT II
PROVISION OF ENGINEERING AND EXECUTION OF PLUGGING AND ABANDONMENT OF DH-1P, DH-2P, DH-3P WELL AT
DAI HUNG FIELD, BLOCK 05.1A, OFFSHORE VIETNAM PAGE 3 OF 4
- Engineering.
- Procurement strategy.
- Logistics strategy.
- Site establishment, recruitment of labors;
- P&A work sequencing & schedules.
- Project progress reporting - (format).
- P&A work methodology/technology.
- P&A Work supervision philosophy.
- P&A Work Warranty and Insurance
- Quality Assurance.
- Safety.

TENDER NO.: PVEP POC-18-10108 EXHIBIT II


PROVISION OF ENGINEERING AND EXECUTION OF PLUGGING AND ABANDONMENT OF DH-1P, DH-2P, DH-3P WELL AT
DAI HUNG FIELD, BLOCK 05.1A, OFFSHORE VIETNAM PAGE 4 OF 4