Dayshift Activities (05-Jan.2018)
Dayshift Activities (05-Jan.2018)
Dayshift Activities (05-Jan.2018)
CPF
Site personnel:-
Evaporation pond:
1. Reclaiming oil from retention pond by reclaim oil pump P-1602.
2. Reclaiming oil from evaporation pond NO#1 by E. pond pump.
1.4Fula Field
1.4.1 Site Personnel:
Name Company Position
Dayshift Personnel
Abdelrhim Mohamed P.E Field Foreman
Fkhrelden Mohamed P.E Field Operator
Mohamed Hamid P.E Field Operator
Yasir Fathelrhman P.E Field Operator
Nightshift Personnel
Abdelrhman Gmarelden P.E Field Foreman
Salaheldin Gadelrab P.E Field Operator
Fula Field:-
Moga FPF:
1.1 Site Personnel:
Name Company Position
Dayshift Personnel
Moawia Mohammed P.E FPF Foreman
Hassan Eltoum P.E C.R Operator
Momen Mohammed P.E FPF Operator
Alaa Mustafa P.E FPF Operator
Nightshift Personnel
Mohammed Elkhalifa P.E FPF Foreman
Khatim Abdalla P.E C.R Operator
Elrafie Eltigani P.E FPF Operator
1.3.1 FPF
1. Patrol check for all production facilities has been done, monitor & record the
parameter.
2. Drained FPF sand trap and reclaimed oil by vacuum truck to CPF.
3. Added 1000L of heavy demulsifier (KT-1903) to (PK-2912-TK1).
4. Flushed suction and discharge flow line of skimmed pump (P-2601 A&B) by hot
water.
Surge tank level: 3.1m.
Average transit line pressure: 0.58Mpa
Average transit line flow rate: 45m3/h
1.3.3 Field:
1.3.4 Field personnel:
1. Routine check for all production wells and OGMs has been done.
2. Tested M17 & M33-4.
1. Tightened stuffing box of M33-2.
2. Cooperated with Ram Company to check RTU system of OGM5.
AGR Activities:
Name Company Position
Dayshift Personnel
Abdelmunem Alamin P.E AGR Operator
Night shift
Ehab Abdelftah Khalifa P.E AGR Operator
1. Patrol check for engines, vessels and compressors has been done, monitor & record
its parameters.
2. Unit A (PK-2409A) stopped on Feb.03, 2015 due to compressor 2nd stage
piston damage.
3. Unit B (PK-2409B) running normal.
Engine No. Running (hrs.) Outlet Pressure (Mpa) Average Flow Rate(m3/h)
A
B 15 7.59 2026
FNE FPF
1Site Personnel:
Tanks Level:
2.0 Field:-
2.1 Field personnel:
2. Field:-
2.1 Site personnel:-
Nightshift Personnel
Emad Ibrahim P.E Field Operator
Field Activities:-
1. Routine check for all production wells has been done.
2.Continue N2 lifting for JS-15 by (PSNI#2).
3.Continue N2 injection for JS-18 by (PSNI#1).
4.Continue N2 injection for JS-19 by (PSNI#3).
5.Cooperated with mechanic staff to tighten the stuffing box of JS-24 and JS-38.
3. JAKE AGR:-
3.1 Site Personnel:-
Engine No. Running Status Outlet Pressure (Mpa) Average Flow Rate(m3/h)
PK-7402-A Stopped - -
PK-7402-B Stopped - -
PK-7402-C Running 10.96 8325
PK-7402-D Running 10.92 6708
Total Flow Rate 15033
3.3 Jake
Activities:-
1. HP units (A&B) stopped for maintenance due to malfunctions.
2. Handover AGR unit (B) to contractor for 16000hrs (engine) routine maintenance,
(ongoing).
Engine No. Running Status Outlet Pressure (Mpa) Suction (Mpa) Average Rate(m3/hr)
PK7403-A Stopped - - -
PK7403-B Stopped - - -
Total Flow Rate -
KEYI FPF
1.1Site Personnel:-
Name Company Position
1.2 Dayshift Personnel
Sirag Omer P.E FPF Foreman
Musab Ibrahim P.E FPF Operator
Ahmed Hassan P.E FPF Operator
Mohamed Ahmed P.E FPF Operator
Nightshift Personnel
Mohammed Mahdi P.E FPF Foreman
Assad Almosalami P.E FPF Operator
Mozamel Yousif P.E FPF Operator
Ongoing Operations and Evaluation:
1.3 Day Activities:
1. Patrol check for all FPF equipment’s has been done.
2. Continue draining water from Storage Tank TK-6501B.
3. Reclaimed oil from retention pond by vacuum truck.
4. Fully isolated the gas injection to OGM-1 from FPF gas distribution.
1. Field:
2.1. Site Personnel:
1. Routine check for all wells & OGMs has been done.
2. Cooperated with mechanic staff to change the drive head of K-23 by new
one & restarted @ 15:15.
3. Handed over K-N-1 to rig service Tiger 10.
4. Full closed the gas injection line of OGM-1.
5. Full closed the gas injection line of K-N-1@15:00.
6. Cooperated with Vicom staff to energize VSD of K-N-7(ongoing).
7. Adjusted the gas injection line of K-10, K-11 & K-20.
8. Tested one wells.
2. AGR:
3.1 Site Personnel:
Name Company Position
Day shift Personnel
Ahmed Hassan P.E AGR Operator
Mustafa Ahmed P.E AGR Operator
Night shift Personnel
Telal Hussein P.E AGR Operator
3.2 Day Activities:
1 Patrol check for engines, vessels and compressors has been done, monitor& record
parameter.
2 Unit C is running normally.
3 Unit B is standby.
4 Unit A stopped.
A Stopped - -
B Standby - -
C Running 5449
7.7
1.5HADIDA FPF :-
Site Personnel:-
Dayshift Personnel
Musa Abu Makeen P.E Operation Supervisor
Muaz Awad P.E FPF Foreman
Omer Osman P.E CR Operator
Basil Ahmed P.E FPF Operator
Almahadi Mohammed P.E Field Operator
Nightshift Personnel
Alamin Awad P.E FPF Foreman
Ahmed Ali P.E FPF Operator
Farah Nasir P.E FPF Operator
Hosam Musa P.E FPF Operator
Field:
1. Patrol check for all production wells has been done.
2. H-9 restarted by 15 Hz and diverted to OGM-2 production line at 09:30 after
work over finished.
3. Cooperated with electrician & DCS staffs to disconnect power cables and DCS
devices of HN-2 for the work over preparation.
4. Tested HN-9 & H3-3.
Mud Pump Activity
1. Patrol check has been done, monitor & record the parameter.
2. Mud pumps-B stand by & A stand by.
Sufyan FPF
Site Personnel:-
1.4 Parameters:-
2.0 Field:
2.1 Field personnel: