Dayshift Activities (05-Jan.2018)

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 15

DAY SHIFT ACTIVITY& PERFORMANCE REPORT

FULA CPF, MOGA, FNE, JAKE, KEYI, HADIDA& Sufyan EPF


Date: Jan,05,2018
Report Number: 05,01,2018
Report Prepared By: Ibnauf
Report Approved by: Khalid Rahamtallah

CPF
Site personnel:-

Name Company Position


Dayshift Personnel
Luai Gammar Alden P.E CPF Supervisor
Abdelrahman Hussein P.E Operation Coordinator
Khalid Rahamtallah P.E CPF Foreman
Esmail Elshafie P.E CPF S. Operator
Mutaz Abdalmonim P.E CPF C.R Operator
Mohammed Ibnauf P.E CPF C.R Operator
Yasir Ahmed P.E CPF Operator
Eltahir Okasha P.E CPF Operator
Ahmed Mohamed Ali P.E CPF Operator
Mohamed Elshami P.E CPF Operator
Nightshift Personnel
Almaki Hamid P.E CPF Foreman
Ali Abdalla P.E CPF C.R Operator
Anwar Mohammed P.E CPF C.R Operator
Siddig Abdelrahman P.E CPF Operator
Hassan Elmogtaba P.E CPF Operator
Ongoing Operations and Evaluation
CPF: Dayshift Activities
1. Patrol check for all production facilities has been done, monitor & record the parameters.
2. FNE pig in pig received position.
3. Cooperate with mechanic crew to fed lube oil to IGS compressor unit A.
4. Cooperate with mechanic crew to fed lube oil to HADEDA & Sufyan chemical pump.
5. Water drained from TK-1202/3, TK-1501/2/3/4/5/6 and TK-1507.
6. Average flow rate to CPF: 240Sm3/hr., PS#1 248Sm3/hr., BV2:117Sm3/hr.

Shipping Tanks level


TK-1507 (mm) TK-1506 (mm) TK-1505 (mm) TK-1504 (mm) TK-1503 (mm) TK-1502 (mm) TK-1501 (mm)

14127 6750 10463 11367 11779 11972 11130


Chemical and Heater Operation Activities:.
1. Routine check for all chemical pumps and heaters has been done.
2. Feed chemical:-

Evaporation pond:
1. Reclaiming oil from retention pond by reclaim oil pump P-1602.
2. Reclaiming oil from evaporation pond NO#1 by E. pond pump.

Star Oil Ongoing Operations:-


1. Metering skid stream (A/B) online
Metering skid and line parameters:

Time Pressure (K Pa) Temperature (C°) Flow rate(m3/h) 1.7


CPF
06:00 70 37.3 20.585 AGR:
12:00 106 37.4 20.495
Site Personal
Dayshift Personnel
Name Company Position
Ayman Yasin P.E AGR Operator
Mohamed Hassan P.E AGR Operator
Nightshift Personnel
Ahmed Ali P.E AGR Operator
Modathir Abdeen P.E AGR Operator
Activities of AGR
1. Patrol check for engines, vessels and compressors have been done, monitor &
record its parameter.
2. Stopped unit A at 7:15 due to rewiring temperature sensor in the engine, and
restarted at 9:10.
3. Units A, B& C are running normally.
CPF AGR daily running and performance report:
AGR Units Running (hr) Outlet Pressure (Mpa) Flow Rate (m3/hr.)
1409-A 13 7.88 3547
1409-B 15 7.87 3373
1409-C 15 7.91 3972
Natural Gas treatment Package Outlet Pressure (Mpa) Total Flow Rate
1420-A Not lined up - -
1420-B Stopped - -
FNE 4.04 0
Total Outlet Gas Volume (m3)
156288

1.4Fula Field
1.4.1 Site Personnel:
Name Company Position
Dayshift Personnel
Abdelrhim Mohamed P.E Field Foreman
Fkhrelden Mohamed P.E Field Operator
Mohamed Hamid P.E Field Operator
Yasir Fathelrhman P.E Field Operator
Nightshift Personnel
Abdelrhman Gmarelden P.E Field Foreman
Salaheldin Gadelrab P.E Field Operator

Fula Field:-

1. Patrol check has been done normal and carefully.


2. Restarted FN-65 after finished work over at 07:00.
3. Tighten seal stuffing box of 2wells.

Moga FPF:
1.1 Site Personnel:
Name Company Position
Dayshift Personnel
Moawia Mohammed P.E FPF Foreman
Hassan Eltoum P.E C.R Operator
Momen Mohammed P.E FPF Operator
Alaa Mustafa P.E FPF Operator
Nightshift Personnel
Mohammed Elkhalifa P.E FPF Foreman
Khatim Abdalla P.E C.R Operator
Elrafie Eltigani P.E FPF Operator

1.2 Ongoing Operations and Evaluation

1.3 Day Shift Activities

1.3.1 FPF
1. Patrol check for all production facilities has been done, monitor & record the
parameter.
2. Drained FPF sand trap and reclaimed oil by vacuum truck to CPF.
3. Added 1000L of heavy demulsifier (KT-1903) to (PK-2912-TK1).
4. Flushed suction and discharge flow line of skimmed pump (P-2601 A&B) by hot
water.
Surge tank level: 3.1m.
Average transit line pressure: 0.58Mpa
Average transit line flow rate: 45m3/h

1.3.3 Field:
1.3.4 Field personnel:

Name Company Position


Dayshift Personnel
Ibrahim Mohamed P.E Field Operator
Mohamed Ali P.E Field Operator
Nightshift Personnel
Mohammed Hashim P.E Field Operator

1. Routine check for all production wells and OGMs has been done.
2. Tested M17 & M33-4.
1. Tightened stuffing box of M33-2.
2. Cooperated with Ram Company to check RTU system of OGM5.
AGR Activities:
Name Company Position
Dayshift Personnel
Abdelmunem Alamin P.E AGR Operator
Night shift
Ehab Abdelftah Khalifa P.E AGR Operator

1. Patrol check for engines, vessels and compressors has been done, monitor & record
its parameters.
2. Unit A (PK-2409A) stopped on Feb.03, 2015 due to compressor 2nd stage
piston damage.
3. Unit B (PK-2409B) running normal.

1.3.5 AGR daily running and performance report:

Engine No. Running (hrs.) Outlet Pressure (Mpa) Average Flow Rate(m3/h)

A
B 15 7.59 2026

Total Gas Volume(m3) 30390

FNE FPF
1Site Personnel:

Name Company Position


Dayshift Personnel
Mohammed Khidir P.E FPF Foreman
Mohamed Mahjoub P.E CR Operator
Ali Abdalla P.E FPF Operator
Nightshift Personnel
Rashid Mahdi P.E FPF Foreman
Osama Eltahir P.E FPF Operator
Mirghani Belal P.E FPF Operator

1.2 FPF Activities:


1. Patrol check for production facilities has been done, monitor & record its
parameters.
2. Drained storage tank TK-8501 & sedimentation tank TK-8201-B for 3hours.
3. Cooperated with maintenance team to Fabricate and Install Overflow pipe
Between Evaporation Ponds No-3 and No-4 (on going).
4. Firefighting training has been done for FNE staff by civil defense.

Tanks Level:

TK-8201-A TK-8201-B TK-8501


15493 mm 13048 mm 5802mm

2.0 Field:-
2.1 Field personnel:

Mohammed Abass P.E Field Operator


Name Company Position
Gorashi Ahmed P.E Field Operator
Dayshift Personnel
Nightshift Personnel
Abu Obaida Basheer P.E Field Operator
Nimir Abdalsalam P.E Field Operator

2.2 Field Activities:


1. Routine check for all production wells and OGMs has been done.
2. Shut in FNE-7 from 08:00 to 14:00 due to low Pump submergence.
3. Shut in FNE-42 from 08:00 to 20:00 due to low Pump submergence.
4. FNE-108 restarted at 90:00 after changed stuffing box seal.
5. FNE-109 shut-in from 8:00 to 10:00 due to adjust belt.
6. FNE-14 restarted at 15:00 after flow line flushed.
7. FNE-76 shut-in at 15:00 due to adjust aliment by BPU service
engineer.
8. FNE-70 shutdown from 14:30 to 15:30 due to power problem.
9. FNE-124 shut-in at 15:00 due to serious leakage at stuffing box.
10. Located cables & flowlines at FNE-110.
11. Updated parameters for some wells.
12. Tighten stuffing box for some wells.

3.0 Sand Cleaning


3.1 Sand Cleaning Personnel:

Name Company Position


Sand cleaning Personnel
Mohammed Ahmed Bakheet P.E Sand clean Operator

Ahmed Awadelkreem P.E Sand clean Operator


3.2 Sand
Clean Activities:

1. Launched 12” formal pig from FNE-FPF to CPF at 10:30 AM.


2. Sand Trap at FNE-FPF cleaned on line & Drain bit reclaimed.
3. FNE-14 Flow line flushed to OGM-01.
4. Reclaimed Temporary tank at OGM-1.            

        Jake FPF


Site Personnel:-

Name Company Position


Dayshift Personnel
Mohammed Abdalla P.E Operation Supervisor
Hussien Hassan P.E FPF Foreman
Ahmed Imam Alaalim P.E C.R Operator
Alwathig Mohamed P.E FPF Operator
Tarig Hayder Babo P.E Trainee FPF Operator
Nightshift Personnel
Mohammed Mahmoud P.E FPF Foreman
Subhi Amin P.E FPF Operator
Abdalla Ali P.E FPF Operator
1.2 Ongoing Operations and Evaluation
FPF Activities:-
1. Patrol check for production facilities has been done.
2. Weekly test for firefighting pump and emergency generator has been done.
3. Cooperated with maintenance team to as following:
 Repair to reset fault alarm in heater unit (A) P-7971-H-1(ongoing).
 Repair circulation pump P-7971-P-1-A (ongoing).
4. Average flow rate to FPF 58.61 M³/hr. and to CPF 57.73 M³/hr.

Storage Tank parameter:-.

Tank Number Level (M) Temp (˚C)


TK-7501 7.7 58

2. Field:-
2.1 Site personnel:-

Abubaker Mahjoub P.E Field Operator

Nightshift Personnel
Emad Ibrahim P.E Field Operator

Field Activities:-
1. Routine check for all production wells has been done.
2.Continue N2 lifting for JS-15 by (PSNI#2).
3.Continue N2 injection for JS-18 by (PSNI#1).
4.Continue N2 injection for JS-19 by (PSNI#3).
5.Cooperated with mechanic staff to tighten the stuffing box of JS-24 and JS-38.

Wells parameters (HP, MP& N2)


No. TP CP FLP T Choke Open Gas Close Gas Daily Injectio
(Mpa) (Mpa) (Mpa) (˚C) Size Injection Total Injection injection n Type
(mm) (m3)(15:00) Total (M3) And AGR
(m3)(15:00) (HP ,MP
or N2)

JS-1 9.1 N/A 0.83 64 50/50 97177777 97245337 67560 MP


JS-2 1.1 N/A 1.05 52 50 MP
JS-3 1.3 5.1 0.85 70 50 MP
JS-4 7.7 1.2 0.91 65 50 MP
JS-10 N/A N/A 1.25 63 50/50 75710675 75819995 109320 MP
JS-14 1.2 N/A 0.85 73 50
JS-15 1.4 N/A 1.15 60 50 N2
JS-22 8.4 N/A
JS-26 1.5 1.05 0.75 56 50 MP
JS-28 1.5 9 1.1 62 50 MP
JS-35 7.8 0.9 1.1 66 40 30042090 30110730 68640 MP
JS-29 0.95 4.5 0.9 37

3. JAKE AGR:-
3.1 Site Personnel:-

Name Company Position


Dayshift Personnel
Awad Mohamed Awad P.E AGR Operator
Mohamed Dalil P.E AGR Operator
Nightshift Personnel
Elsiddig Kardman P.E AGR Operator
Hatim Mohamed P.E AGR Operator

3.2 Jake M.P AGR Performance Report:-


Activities:-
1. Patrol check for engines, vessels and compressors has been done, monitor & record its
parameter.
2. Cooperated with mechanic team to replace the packing seal parts for AGR unit (B)
compressor stages. (Ongoing).
3. Cooperated with maintenance to repair the leakage in drain line of 2 nd stage scrubber in
AGR-A (ongoing).
4. Fed lube oil for compressor makeup tank in units C&D.
5. Units (C & D) running normally.

Engine No. Running Status Outlet Pressure (Mpa) Average Flow Rate(m3/h)
PK-7402-A Stopped - -
PK-7402-B Stopped - -
PK-7402-C Running 10.96 8325
PK-7402-D Running 10.92 6708
Total Flow Rate 15033
3.3 Jake
Activities:-
1. HP units (A&B) stopped for maintenance due to malfunctions.
2. Handover AGR unit (B) to contractor for 16000hrs (engine) routine maintenance,
(ongoing).

Engine No. Running Status Outlet Pressure (Mpa) Suction (Mpa) Average Rate(m3/hr)
PK7403-A Stopped - - -
PK7403-B Stopped - - -
Total Flow Rate -

4. Reclaim System and retention pond progress:-


1. Level at evaporation pond#1 approximately 90%.

KEYI FPF
1.1Site Personnel:-
Name Company Position
1.2 Dayshift Personnel
Sirag Omer P.E FPF Foreman
Musab Ibrahim P.E FPF Operator
Ahmed Hassan P.E FPF Operator
Mohamed Ahmed         P.E FPF Operator
Nightshift Personnel
Mohammed Mahdi P.E FPF Foreman
Assad Almosalami P.E FPF Operator
Mozamel Yousif P.E FPF Operator
Ongoing Operations and Evaluation:
1.3 Day Activities:
1. Patrol check for all FPF equipment’s has been done.
2. Continue draining water from Storage Tank TK-6501B.
3. Reclaimed oil from retention pond by vacuum truck.
4. Fully isolated the gas injection to OGM-1 from FPF gas distribution.

1.4 .Tanks level:


Tank Number Level (m) Temp. (˚C)
TK-6501-A 9.1 53
TK-6501-B 7.2 56
Total Flow rate to CPF (m3/hr.) 3
27 m /h

1. Field:
2.1. Site Personnel:

Day shift Personnel


Name Company Position
Faiz Elsidig P.E Field Operator
Night shift Personnel
Name Company Position
2.2. Waiel Abbas P.E Field Operator Day
Activities:

1. Routine check for all wells & OGMs has been done.
2. Cooperated with mechanic staff to change the drive head of K-23 by new
one & restarted @ 15:15.
3. Handed over K-N-1 to rig service Tiger 10.
4. Full closed the gas injection line of OGM-1.
5. Full closed the gas injection line of K-N-1@15:00.
6. Cooperated with Vicom staff to energize VSD of K-N-7(ongoing).
7. Adjusted the gas injection line of K-10, K-11 & K-20.
8. Tested one wells.

Well name Liquid Bbl/day


K-10 422

2. AGR:
3.1 Site Personnel:
Name Company Position
Day shift Personnel
Ahmed Hassan P.E AGR Operator
Mustafa Ahmed P.E AGR Operator
Night shift Personnel
Telal Hussein P.E AGR Operator
3.2 Day Activities:
1 Patrol check for engines, vessels and compressors has been done, monitor& record
parameter.
2 Unit C is running normally.
3 Unit B is standby.
4 Unit A stopped.

4.1 Units Performance:


Engine No. Running Status Outlet Pressure (Mpa) AV-Flow rate (m3/hr.)

A Stopped - -
B Standby - -
C Running 5449
7.7

Total Flow rate (m3/hr.) 5449


Remark

3. Vehicles & Utilities:


Vehicle Quantity Company Job Description Work Time Standby Time Remarks
Vacuum Truck 1 ZPEB Reclaimed oil from retention pond 2 Hrs /
Vacuum Truck 1 GTS Reclaimed oil from retention pond 45 minutes 3

1.5HADIDA FPF :-
Site Personnel:-

Name Company Position

Dayshift Personnel
Musa Abu Makeen P.E Operation Supervisor
Muaz Awad P.E FPF Foreman
Omer Osman P.E CR Operator
Basil Ahmed P.E FPF Operator
Almahadi Mohammed P.E Field Operator

Nightshift Personnel
Alamin Awad P.E FPF Foreman
Ahmed Ali P.E FPF Operator
Farah Nasir P.E FPF Operator
Hosam Musa P.E FPF Operator

1.2 Ongoing Operations and Evaluation


1.3 Day shift Activities
FPF:
1. Patrol check for all production facilities has been done, monitor & record the
parameters.
2. Continue draining bottom water from storage tanks.
3. Water injection pump running for 24 hrs.
4. Centrifugal pump P-4501B running for 24 hrs.
5. Screw pump P-4501C running for 07 hrs.
6. Recvied 10m3 fluid from rig DQ 100.

Storage tank level A:5.69m. B:5.76m.

Transit line pressure 2205Kpa


Average flow rate 82 m3/h

Field:
1. Patrol check for all production wells has been done.
2. H-9 restarted by 15 Hz and diverted to OGM-2 production line at 09:30 after
work over finished.
3. Cooperated with electrician & DCS staffs to disconnect power cables and DCS
devices of HN-2 for the work over preparation.
4. Tested HN-9 & H3-3.
Mud Pump Activity

1. Patrol check has been done, monitor & record the parameter.
2. Mud pumps-B stand by & A stand by.
Sufyan FPF
Site Personnel:-

Name Company Position


Dayshift Personnel
Sun Ming Shan P.E Op. superintendent
Mohammed Nasur P.E Operation Supervisor
Abdelmohsen Abdallah P.E FPF Foreman
Asem Fatihalaleem P.E C.R Operator
Ali Mohamed Ali P.E FPF Operator
Ayman Gadien P.E FPF Operator
Nightshift Personnel
Ayman Mohammed P.E FPF Foreman
Hassan Abaker P.E C.R Operator
Mohammed Alfatih P.E FPF Operator
1.2 Osman
Ongoing Operations and Evaluation:
1.3 Day Shift Activities:
FPF:
1. Patrol check for all production facilities have been done, monitor & record the
parameters.
2. Drain the condensate from fuel gas scrubber (continuously).
3. 18m3 of hot water loaded from EPF to well site.

1.4 Parameters:-

Storage tank level A:5.4m B: 5.3m


Transit line pressure 2628Kpa
Transit line temperature 70°C
Average flow rate 11.3m3/h

2.0 Field:
2.1 Field personnel:

Name Company Position


Dayshift Personnel

Omer Ahmed Alfaki P.E Field


Operator
2.2 Mohammed Bashir Khalid P.E Field Activities:
Operator

1. Routine check for all production wells have been done.


2. OGM-3 flow line flushed by hot water.
3. OGM-3 transfer pump restarted in auto position (running normal & under
observation).
4. Cooperate with RAM CO to repair the problems of OGM-2&3 test
separator (ongoing).

Transfer Pump parameters OGM-2 OGM-3 OGM-4


Suction Pressure 0.64 Mpa 0.898 Mpa 1.54 Mpa
Discharge pressure 2.46 Mpa 0.235 Mpa 2.39 Mpa
Differential Pressure (DP) N/A - 0.0 Mpa
Temp. N/A - 47°C
Set point 0.76 Mpa 0.9 1.55 Mpa
Freq. 5 Hz 18 Hz 16.5 Hz

You might also like