Professional Documents
Culture Documents
Equipment Status Report - 20190707
Equipment Status Report - 20190707
Miscellaneou
Description Vessel Column Heat Ex. Filter Reactor Agitator Fan & Blower Pump Package Total Ratio
s
Total Equipment 66 6 39 30 4 10 7 50 77 400 689
Last week
25/Jun/19
EQ installation 5 4 2 0 0 0 0 2 0 14 27 4.21%
Plan
Miscellaneou
This week (variation)
Description Vessel Column Heat Ex. Filter Reactor Agitator Fan & Blower Pump Package Total Ratio
s
Total Equipment 0 0 0 0 0 0 0 0 0 0 0
Foundation check 0 0 0 0 0 0 0 0 0 0 0
Inspection Test
Mechanical
EQ installation 4 0 0 5 0 0 0 11 0 14 34
Plan
Miscellaneou
Description Vessel Column Heat Ex. Filter Reactor Agitator Fan & Blower Pump Package Total Ratio
s
Total Equipment 66 6 39 30 4 10 7 50 77 400 689
Cumulation
6/Aug/20
EQ installation 9 4 2 5 0 0 0 13 0 28 61 8.85%
Plan
689 147 61 11 89 0
DETAIL EQUIPMENT INSPECTION STATUS FOR UTILITY AREA
JOB NO. :
CLIENT HYOSUNG VINA CHEMICALS CO., LTD.
PROJECT HSVC1 PP4 PROJECT
680 47 27 0 4 0
1 P- 1101 A/B BFW PUMP FOR 30 TPH BOILER 2 TYPE : CENTRIFUGAL 111A
5 18/Jun/19
CAP. : 40 M3/H
A PK- 1101 30TPH BOILER PACKAGE 1 HEAD: 30
CAP : 599M
TPH HP STEAM 111A~G
1 SP.GR : 0.947 15/Jun/19
SEAL TYPE : SINGLE MECH.
2 D- 1101 DEAERATOR FOR 30TPH BOILER 1 CAP
SEAL: 2.9 M3 (DEAERATOR) 111A INCLUDED IN PK-1101
2 17.4 M3 (TANK)
DRIVER : ELECTRIC
2 E- 1101 ECONOMIZER 1 SIZE (OD
TYPE : FINX TUBE
TL) : 1390 X 1573 MM 111B / INCLUDED IN PK-1101
7 (DEAERATOR)
DUTY : 2,270,477 KCAL/H 111D
22/Jun/19 3/Jul/19 28/Jun/19
SIZE (OD X L)Nox 2206
: 38.1 MMX /3920
5 MMMM
1 BU- 1101 BURNER 1 TYPE : LOW 111D / INCLUDED IN PK-1101
9 TH'K : 24,700,000 (TANK)
CAP. KCAL/H 111E
AREA (EFF.) : 650.5 M2
2 C- 1101 F.D FAN 1 TYPE : CENTRIFUGAL
NO. OF TUBE : 111D INCLUDED IN PK-1101
10 CAP. : 575 M3/MIN
2 Z- 1101 STACK 1 TDH : 478
TYPE : SELFMMH2O
STANDING 111D INCLUDED IN PK-1101
11 DRIVER
SIZE (ID :XELECTRIC
H) : 1100 X 30000 MM
22/Jun/19
HSVC1 PP4 PROJECT
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
SUB-CON eTEC HYOSUNG
May 3, 2019 Center line & Padding for Foundation Mr. Thai
1 YSE/PTSC Pelletizer area PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0001 Acceptable DONE Mr. Phuc Mr. Dinh
08:00AM ZR-4801 & ZM-4801 (PTCS)
Center line & Padding for Foundation
Z-4804~4804, ZM-4804, ZR-4804, Z-
4803, Z-4801A, ZM-4801A, N2 Purge
May 7, 2019 Unit, E-4808A/B, F-4808A/B, P- Mr. Thai
2 YSE/PTSC Pelletizer area PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0002 Acceptable DONE Mr. Cuong Mr. Dinh
08:00AM 4808A/B, Lube Oil Unit for Mixer (PTCS)
Motor, Lube Oil Unit for mixer G/R,
CCW Unit,
Center line &Control Panel,
Padding Local
for Foundation
Start-up panel, Z-4808A/B, D-4808
T-4302, D-4606
May 9, 2019 Mr. Thai
3 YSE/PTSC Pelletizer area, ISBL Lube oil unit for mizer motor, Lube PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0003 Acceptable DONE Mr. Cuong Mr. Dinh
08:00AM (PTCS)
oil unit for mixer G/R, D-4830, Lube
oil unit for gear pump GR
May 14 2019 Center line & Padding for foundation Mr. Thai
4 YSE/PTSC ISBL PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0004 Acceptable DONE Mr. Cuong Mr. Dinh
08:00AM of D-4304, T-4501, T-4701, D-4302 (PTCS)
May 18 2019 Center line & Padding for foundation Mr. Thai
9 YSE/PTSC ISBL PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0008 Acceptable DONE Mr. Cuong Mr. Dinh
08:00AM of C-4610, D-4009, D-4604 (PTCS)
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
May 26 2019 Mr. Long
15 eTEC Material laydown Material receive ET-HSVC1 PP4-RFI-MC-0066 Acceptable Mr. Cuong
08:00AM (eTec)
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
- Centerline, Padding Inspection
* P-4106B, P-4502B SUBMITTED TO ZR-4801, Z-4803 anchor bolt
June 4, 2019 Mr. Khôi
30 YSE/PTSC ISBL - Centerline Inspection PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0020 Acceptable HSVC & ETEC Mr. Cuong Mr. Dinh grouting is kept until post-
08:00AM (PTCS)
* D-4804, D-4805, D-4809 KEEPING grouting
- Levelling,Centerline, Elev, Grouting
-Poket
Centerline, Padding Inspection
Inspection
June 5, 2019 *ZR-4801,
P-4107A/B, P-4110A/B
Z-4803 Mr. Khôi
31 YSE/PTSC ISBL P-4309A/B, T-4503A/B PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0021 Acceptable SUBMITTED TO HSVC Mr. Cuong Mr. Dinh T-4503A/B were be rejected
08:00AM (PTCS)
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
- Centerline, Padding Inspection
June 12, 2019 * F-4601, P-4109, P-4302A/B Mr. Khôi
43 YSE/PTSC ISBL P-4401, R-4201, R-4202 PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0032 Acceptable SUBMITTED TO HSVC Mr. Cuong Mr. Dinh
08:00AM (PTCS)
- Centerline Inspection
June 13, 2019 * F-4812, Z-4811, W-4804, W-4805, W- Mr. Khôi - Foundation not yet done W-
46 YSE/PTSC ISBL 4809 PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0033 Acceptable SUBMITTED TO HSVC Mr. Cuong Mr. Dinh
08:00AM (PTCS) 4804/4805/4809
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
- Centreline,Padding Inspection
June 18, 2019 -P-1101A/B, PK-1601A/B/C Mr. Khôi
58 YSE/PTSC ISBL and Boiler, Utility PK-1602A/B/C PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0044 Acceptable Mr. Cuong Mr. Dinh
08:00AM (PTCS)
-PK-4501, PK4603, PK-4709A/B
'- Bolts Tightening and anchor bolts
June 18, 2019 tightening of ZR-4801, Z-4803 Mr. Khôi
59 YSE/PTSC ISBL PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0045 Acceptable Mr. Cuong Mr. Dinh
08:00AM (PTCS)
MATERIAL RECEIVING
June 18, 2019 INSPECTION SIKA 214-11 Mr. Lee
63 HYG Water Treatment, Utility PP4-QC-PP-0010 Rev. A HYG-HSVC1 PP4 - RFI -ME -WT - 0005 Acceptable Mr. Cuong Mr. Dinh
08:00AM (HYG)
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
- Centerline check and Grouting Anchor
Bols
"- Z-4808A/B, D-4808, F-4808A/B, E-
June 21, 2019 4808A/B
72 YSE/PTSC
08:00AM
ISBL PP4-QC-PP-0010 Rev. A YSE-HSVC1 PP4-RFI-ME-0054 Cancel condition is not ready
- P4701A/B, P4113, P4205, P4309A/B,
P4302A/B"
Installation Inspection:
June 25, 2019 *D-1321A/B/C, D-1322, TK-1311, TK- Mr. Lee
84 HYG Water Treatment, Utility 1312 PP4-QC-PP-0010 Rev. A HYG-HSVC1 PP4-RFI-ME-WT-0010 Acceptable Mr. Cuong Mr. Dinh
08:00AM (HYG)
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
- Centerline, Padding Inspection.
June 26, 2019 * Support PK-1101, SP-2 ITP No.: PP4-QC-PP- Mr. Khôi
86 YSE/PTSC Boiler YSE-HSVC1 PP4-RFI-ME-0065 Acceptable Mr. Cuong Mr. Dinh
8:00 AM 0011 (PTCS)
- Sika Inspection
June 26, 2019 * Sika 214-11 ITP No.: PP4-QC-PP- Mr. Khôi
89 YSE/PTSC ISBL * Sika dur 42mp YSE-HSVC1 PP4-RFI-ME-0068 Acceptable Mr. Cuong Mr. Dinh
8:00 AM 0011 (PTCS)
- Base Grouting.
June 27 2019 * D-4707, D-4114 ITP No.: PP4-QC-PP- Mr. Khôi DOC g to be kept until post-
95 YSE/PTSC ISBL Area YSE-HSVC1 PP4-RFI-ME-0074 Acceptable ETEC KEEPING Mr. Cuong Mr. Dinh
08.00AM 0011 (PTCS) grout
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
- Sika 214-11 Test (7 days).
* Z-4808A/B, D-4808, F-4808A/B, E-
4808A/B
June 29 2019 * P-4701A/B, P-4113, P-4205, P- ITP No.: PP4-QC-PP- Mr. Khôi
100 YSE/PTSC ISBL Area 4309A/B, P-4302A/B YSE-HSVC1 PP4-RFI-ME-0078 Acceptable Mr. Cuong Mr. Dinh
8:00AM 0011 (PTCS)
'- SikaDUR 42MP Test (7 days)
* ZM-4801
- Base Grouting.
* ZR-4804, ITP No.: PP4-QC-PP-
Jul 03 2019 Mr. Khôi
111 YSE/PTSC Pelletizer Area 0010 YSE-HSVC1 PP4-RFI-ME-0090 Acceptable ETEC KEEPING Mr. Cuong
10.00AM (PTCS)
Rev A
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
GROUNTING WORK INSPECTION
July,03,2019 (COMPRESSIVE STRENGTH OF Mr. Khôi
114 HYG WT Area SIKA) PP4-QC-PP-0010 HYG-HSVC1 PP4-RFI-ME-WT-0013 Acceptable Mr. Cuong
09:00 AM (PTCS)
- Leveling Inspection.
* Z-4801A ITP No.: PP4-QC-PP-
05 Jul 2019
123 YSE/PTSC Pelletizer Area 0010 YSE-HSVC1 PP4-RFI-ME-0098 ETEC KEEPING
08.30AM
Rev: A
- Leveling Inspection.
* PK-1101 ITP No.: PP4-QC-PP-
05 Jul 2019
125 YSE/PTSC Utility Area 0010 YSE-HSVC1 PP4-RFI-ME-0102
01.30PM
Rev A
Update 6-Aug-2020
INSPECTION ATTENDEE
INSPECTION ITP No
S/N- SUB CON INSPECTION DATE INSPECTION ACTIVITY RFI No RESULT DOCUMENT STATUS REMARKS/ Reprot Number
LOCATION ITP Rev
- Grouting Anchor Bolts
* P-1101A/B, Chemical Dosing System ITP No.: PP4-QC-PP-
05 Jul 2019
127 YSE/PTSC Utility Area For PK-1101 0011 YSE-HSVC1 PP4-RFI-ME-0104 ETEC KEEPING
01.30PM
Rev A