In this week we saw that how to dismantle formwork from column and slab
after it gains minimum requirement to be harden. we have been told by the
workers it is dangerous if we not make the dismantling one by one. also in this
week we has been seen how to correct a formwork alignment which is shifted from
the position stated in the drawing.
beside this works there is also a formwork work to the second floor beam. also
there is an establishment of probs for supporting the second floor beam and make a
sponda and phondo for the beam.
Preparation of probs, modini, and morale work for second floor slab is started
and check its horizontal alignment. by using nail fixing and tauten string.
Also there is reinforcement work for elevator and for ground slab.in
reinforcing the slab we must provide a spacer between the upper negative bar
and the bottom bar like an anchorage shape to separate and to have the same
thickness in the overall part of the slab. there is an establishment of probs for
the cantilever slab.
Methodology
In this week we saw that how to make a test of concrete if it gains its strength
or not gain its minimum requirement. This work is done by taking the
concrete into the cube, and compact it 5 times with in 3 layers make it dry
and take it to the laboratory and place it in water for 28 day’s after this by
using a machine and by applying a constant load test the concrete how much
load it can impose up to it crushed.
On these week we saw a building of a new Store room, dressing room and
office room transferring
Of materials those stored in the old store to the new one.in the building of the
store the workers told as the store should placed in a place of not water
addressing area specially for cement.
Small and Valuable Items ~ these should be kept in a secure and lockable
store. Similar items should be stored together in a rack or bin system and only
issued against an authorized requisition.
The location and size(s) of space to be allocated for any particular material
should be planned by calculating the area(s) required and by taking into
account all the relevant factors before selecting the most appropriate position
on site in terms of handling, storage and convenience.
Abstract on activities covered during the week
On these week there is concreting of elevator house wall on axis 2-3 between
axis D-E after it gains the required minimum strength dismantling the
formwork is done in this week.
Beside this works reinforcement work for ground for the ground floor slab is
done based on the bar bending schedule stated in the drawing.
Bar schedule is a detail which gives the exact length of bars, and total weight
of bars needed for a particular structural member.
In reinforcing the slab, column, beam we use a concrete spacer which makes a
space between the formwork and the bar.