3.1 Status and Progress of Kathmandu Sustainable Urban Transport Project PDF
3.1 Status and Progress of Kathmandu Sustainable Urban Transport Project PDF
3.1 Status and Progress of Kathmandu Sustainable Urban Transport Project PDF
s
Present Public Transport in
Kathmandu
Public
Transport
Walkability
Project Organisation
Ministry of Physical Infrastructure and Transport
Project Management Coordination Office
PMCB Consultant : SMEC International JV
Project Implementation Units (Five):
• Department of Roads (DOR)
• Department of Transport Management (DOTM)
• Metropolitan Traffic Police Department (MTPD)
• Kathmandu Metropolitan City (KMC)
• Department of Environment (DOEnv)
Design Supervision Consultants:
• SIDEF – BEAM JV for KMC works
• Soil Test for DOR works
Consultant for Mass Transit Study
Consultant KSUTP for DOTM works
Transport Enterprenuers / Committes
Town Development Fund
Component 1
Public Transport Tasks
Develop Public Transport Develop DoTM institutional Mass Transit Options &
restructuring policy restructuring plan prioritisation Study
Requires action
Component 1:
Public Transport
Outputs expected:
• Re-structuring of DOTM with creation of a new
Public Transport Division
• Restructuring of Public Transport Routes in the
Kathmandu Valley
• Selection and Implementation of 2 Pilot Bus Routes
• Transformation of current public transport
operators into companies or cooperatives
(franchising)
• Purchase of electric or low emission buses through
the TDF on the 2 selected pilot routes
• Feasibility Study on the mass transport system in
Kathmandu Valley
Fleet rationalisation
• 8 Primary Routes: Requires a fleet of 470
buses, (12-Metre Rigid)
• 16 Secondary Routes: Fleet of 250 buses,
9 to 10 m in length
• 40 Tertiary Routes: Predominately using
existing vehicle fleet, with some routes
operated by new Electric vehicles
• Vehicle-km reduced by 332,000 per day
• Vehicle Operating Costs reduced by US$
34 Million per year
• 10% Reduction in road space used
(PCU’s)
PRIMARY PUBLIC TRANSPORT ROUTES
Component 2:
Traffic Management
Outputs expected:
• Construction of the 2 new bridges at Dallu & Teku.
(ICB-02)
• Construction of crossing junction at Teku.
• Construction of the remaining road section of BLR
on east bank. (ICB-02)
• Improvements at 35 Junctions. (ICB-03)
• Traffic Signals (37) and Installation of CCTV cameras,
traffic lights, equipment and Traffic Management
Centre. ITS installation. (ICB-04)
• Launch road users’ awareness programs
Component 3:
Walkability Improvements
Outputs expected:
• Improvement of 8 km of preliminary heritage
pedestrian routes and 15 Km of sidewalk in the city
center. ICB-01
• Construction of 1 new pedestrian bridge and
renovation of 2 existing footbridges along BLR. NCB-
02
• PPP investigations for car parking and the
redevelopment of the Old Bus Park under KMC
Component 4:
Air Quality Monitoring
Outputs expected:
• Expedite programs to restore operations at the existing
AQM stations with solar-powered backup systems:
Completed
• Procurement of 4 new AQM mobile stations completed
• Procurement of 4 sets emissions testing equipment :
Completed
Project Status
In general
Component 4 : Air Quality Monitoring satisfactorily completed.
Component 3 : Walkway is proceeding satisfactorily
Component 2 : Traffic Management some lagging specially in ITS (ICB-04)
Some extension required.
Component 1: Public Transport is very much lagging behind.
S5 route association came to agreement.
Challenges