Rgbel Eot-2 PDF
Rgbel Eot-2 PDF
in Association with
LTelford Consulting Engineers Pvt. Ltd.
980012/3-Proj/Client/ 20.05.2020
To,
The Executive Engineer
NH, Division RWD,
Rudraprayag, Uttarakhand
Sub: Widening and Strengthening of existing intermediate/ 2 lane to 2 lane with paved shoulders
configuration from Km 0.000 (Design Km 0.000) to Km 16.440 (Design Km 18.700) including existing 3.740 km
of Rudraprayag Bypass of NH -109 in the State of Uttarakhand on EPC mode. Recommendation of Extension
of Time-2 regarding:
Dear Sirs,
The Authority vide letter cited at sl. no. (iii) had granted an interim Extension of Time (EOT-1) of 137 days
on the following enlisted grounds to the EPC Contractor.
a. Delay due to handing over of unencumbered land / ROW as per Article-8 of EPC.
b. Delay due to Hon’ble High Court order regarding Disposal of Muck.
c. Delay Due to Unseasonal Rain.
The EPC Contractor, vide letter cited at sl. no. (ii), has once again submitted the EOT-2 proposal on the
mentioned/cumulative below grounds and requested to re-calculate the determined up to 10th May 2020.
a. Delay due to handing over of unencumbered land / ROW as per Article-8 of EPC.
b. Delay due to Hon’ble High Court order regarding Disposal of Muck.
c. Delay Due to Unseasonal Rain.
d. Delay Due to stoppage of hill side cutting due to Chardham Yatra.
e. Delay Due to landslide during monsoon.
f. Delay Due to Pandemic Covid-19.
The Authority vide letter cited at sl. no. (i), instructed Authority’s Engineer to determine & examine the
Extension of Time (EOT) case as per Article 18 of EPC Agreement. The determination of Extension of Time
(EOT) by Authority’s Engineer as follows:
A. Delay due to handing over of unencumbered land / ROW as per Article-8 of EPC:
As per provisions of Schedule-A Annex-II Authority shall provide Right of Way to the contractor on different
stretches of site i.e. (1.) Rudraprayag By-Pass & Existing NH-109 (0+000 to 3+740 & 3+740 to 18+700) within
15 days after appointed date. (2.) Balance Right of Way i.e. Rest Area at Km 6+120 to 6+220 (1250 Sqm Area)
within 90 days from appointed date. As per Article-8 clause 8.2: the Authority representative and the
contractor shall inspect the stretch and prepare a memorandum containing an inventory of the site including
the vacant and unencumbered land, building, structures, road works, trees and any other immovable
property on or attached to the site within 15 days of the date of agreement. Subject to the provisions of
clause 8.2.3, such memorandum shall have appended hereto an appendix (the “Appendix”) specifying in
reasonable detail those parts of the site to which vacant access and Right of Way has not been given to the
Contractor.
HEC Office: JM-89/3C, Behind Panchwati Market, Saket Nagar, Bhopal (M P) PIN- 462024 Phone: +91-755-4236317
LTCE Office:RZF-779/2, Lane No-17, Raj Nagar-2,Dwarka, Sector-8, Palam, New Delhi-110077 Phone: +91-11- 49095718 (Email- ltelford.consultant@gmail.com)
CIN No.: U74999DL2016PTC305247
“The Infr
Infra Advisor”
Advisor”
As per above mention Article & Clause Authority representative and Contractor prepare Memorandum on
dated 06.12.2017, as per memorandum 1.421 Km Length Hindered out of 18.700 which is 10% as per section
8.2.3. After starting of the work and during construction Contractor intimate Authority through several letter
related to unencumbered land and ROW.
Up to 31st July-2019 the 3.760 Km Length Hindered out of 18.700 Km at site including Tilwara Market & Silli
Market which is 20% of project length. The EOT consider for said hindrance is mentioned below:-
Therefore EOT admissible for 3.760 Km Hindered Length is 124.060 Days (146.78 X 617 Days)/730 Days
Say 124 Days consider for 3.760 Km Hindered Length.
From 1st August’2019 to 31st October’2019 2.680 Km Length Hindered out of 18.700 Km at site including
Tilwara Market, Silli Market which is 14% of project length. The EOT consider for said hindrance is mentioned
below:
Therefore EOT admissible for 2.680 Km Hindered Length is: - 13.042 Days (104.62 X 91 Days)/730 Days
Say 13 Days consider for 2.680 Km Hindered Length.
From 1st November ’2019 to 10th may’2020 2.264 Km Length Hindered out of 18.700 Km at site including
Tilwara Market, Silli Market & others which is 12% of project length. The EOT consider for said hindrance is
mentioned below:
As on date Rest Area Land is not provided to Contractor due to Hindrances at Km 6+120 to 6+220 (1250 Sqm
Area). As per contractor EOT request for Rest Area development required 75 Days for development of rest
area i.e. structure work, junction development & all public utilities as per drawings. EOT for rest area
considered only 50% of 75 days rest days is consider for overlapping. Say 38 Days consider Rest Area
Hindrances.
“The Infr
Infra Advisor”
Advisor”
B. Delay Due to stoppage of hill side cutting due to Chardham Yatra:
Contractor claim 91 days due to stoppage of hill side cutting on account of Chardham yatra, as per Article-6
(Disclaimer clause 6.1.1 :- The Contractor acknowledges that prior to the execution of the Agreement, the
contractor has, after a complete and careful examination, made an independent evaluation of the Request
for Qualification, request for Proposal, Scope of the Project, Specifications and standards of design,
construction and maintenance, site, local conditions, physical qualities of ground, subsoil and geology,
traffic volumes, suitability and availability of access routes. Contractor confirms it shall have no claim
whatsoever against the Authority in this regard. The Chardham Yatra is a known fixed scheduled yatra for
Hindus pilgrims celebrating since from long time ago and this may not be considered while computing the
time frame of EOT.
Authority’s Engineer consulted the EPC contractor as per article-18.5 of EPC, during determination/
Consultation of cumulative EOT of 364 days has been agreed by the EPC contractor; accordingly, the
Authority’s Engineer is recommending additional EOT of 227 days on account of above mentioned reasons.
It is further stated that due to previously granted total extension of time (EOT) of 137 days the date of
respective project milestone-IV in reference of clause 2.1 of schedule J was modified from 20-11-2018 to 05-
04-2020.
It is further also stated that if above determined total granted Extension of Time (EOT) of 227 days is
approved by the authority, the date of respective project milestones in reference of clause 2.1 of schedule J
shall further be modified from 5-04-2020 to 18-11-2020 & upon approval of EOT, the project milestones or
scheduled completion dates shall be amended as per clause 6 of schedule-N.
We would also suggest that, no further EOT shall be entertained on this account. However, the final decision
of the Authority shall prevail in this regard.
Thanking you,
Yours faithfully,
Manjul Kumar
Team Leader
CC:
1. The Chief Engineer NH&B, PWD Dehradun
2. The Superintending Engineer, 10th circle, Yamuna Colony Dehradun.