Torts 2

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 34

21 duty, Alfredo Espina, to make a spot report.

The incident
was reported to Atty. Du, petitioner's vice-president for
legal and corporate affairs. Atty. Du in turn sent formal
SECOND DIVISION demand letters to private respondents. Marine surveyor
Carlos Degamo inspected the damage on the pile cluster
G.R. No. 125483      February 1, 2001 and found that one post was uprooted while two others
were loosened and that the pile cluster was leaning
LUDO AND LUYM CORPORATION, petitioner,  shoreward. Degamo hired skin diver Marvin Alferez, who
vs. found that one post was broken at about 7 inches from
COURT OF APPEALS, GABISAN SHIPPING LINES, the seabed and two other posts rose and cracked at the
INC. and/or ANSELMO OLASIMAN, respondents. bottom. Based on these findings, Degamo concluded
that the two raised posts were also broken under the
QUISUMBING, J.: seabed and estimated the cost of repair and
replacement at P95,000.00.
This petition for review1 under Rule 45 of the Revised
Rules of Court seeks to annul and set aside the Private respondents denied the incident and the
decision2dated January 10, 1996 of the Court of Appeals damage. Their witnesses claimed that the damage, if
which reversed and set aside the decision of the any, must have occurred prior to their arrival and caused
Regional Trial Court of Cebu City, Branch IX, and the by another vessel or by ordinary wear and tear. They
resolution3 dated June 11, 1996, denying petitioner's averred that MV Miguela started to slow down at 100
motion for reconsideration.1âwphi1.nêt meters and the crew stopped the engine at 50 meters
from the pier; that Capt. Anselmo Olasiman did not order
the anchor's release and chief mate Manuel Gabisan did
Petitioner Ludo & Luym Corporation is a domestic
not hear Naval shout "Reverse". Respondents claimed
corporation engaged in copra processing with plant and
that Naval had no business in the vessels' maneuvering.
business offices in Cebu City. Private Respondent
When Naval informed the vessel's officers of the
Gabisan Shipping Lines was the registered owner and
incident, Olasiman sent their bodega man, Ronilo
operator of the motor vessel MV Miguela, while the other
Lazara, to dive on the same afternoon to check on the
private respondent, Anselmo Olasiman, was its captain.
alleged damage. Lazara told Olasiman that there was no
damage. However, during direct examination, Lazara
Petitioner owns and operates a private wharf used by testified that he found a crack on the side of the pile
vessels for loading and unloading of copra and other cluster, one post detached from the seabed at a distance
processed products. Among its wharf's facilities are of about 7 inches, and seashells and seaweeds directly
fender pile clusters for docking and mooring. underneath the uprooted post. There were scattered
pieces of copra at the place where MV Miguela docked,
On May 21, 1990, at around 1:30 P.M., while MV which indicated the prior docking by other vessels.
Miguela  was docking at petitioner's wharf, it rammed After MV Miguela left, another vessel docked in the
and destroyed a fender pile cluster. Petitioner demanded same area. Petitioner did not prevent MV Miguela from
damages from private respondents. The latter refused. departing. When chiefmate Gabisan went to Atty. Du, the
Hence, petitioner filed a complaint for damages before latter told him not to mind the incident.
the Regional Trial Court of Cebu.
On rebuttal, petitioner presented Atty. Du who testified
Petitioner's evidence during trial showed that on May 21, that Gabisan never went to his office after receiving the
1990, at 1:30 P.M., MV Miguela came to dock at letter-complaint; that petitioner never received any reply
petitioner's wharf. Ireneo Naval, petitioner's employee, to its demand letters; and that the first time Atty. Du saw
guided the vessel to its docking place. After the guide Gabisan was during the pre-trial.
(small rope) was thrown from the vessel and while the
petitioner's security guard was pulling the big rope to be On May 14, 1993, the trial court disposed the case in
tied to the bolar, MV Miguela did not slow down. The favor of petitioner, thus:
crew did not release the vessel's anchor. Naval shouted
"Reverse" to the vessel's crew, but it was too late when
WHEREFORE, premises considered, this court
the latter responded, for the vessel already rammed the
hereby renders judgment in favor of the plaintiff,
pile cluster. The impact disinclined the pile cluster and
ordering the defendants, jointly and severally, to
deformed the cable wires wound around it. Naval
pay the plaintiff the following:
immediately informed the vessel's captain and its
chiefmate of the incident, and instructed the guard-on-

1
1) Php 70,000.00 actual damages, plus interest A. THE COURT OF APPEALS ACTED IN
at the rate of 12% per annum from the time the EXCESS OF ITS JURISDICTION WHEN IT
decision is received by defendants until fully WENT BEYOND THE ISSUES RAISED IN THE
paid; ASSIGNMENT OF ERRORS OF PRIVATE
RESPONDENT.
2) Php 15,000.00 exemplary damages;
B. THE DECISION OF THE COURT OF
3) Php 15,000.00 attorney's fees; APPEALS IS GROUNDED ON SPECULATION,
SURMISES AND CONJECTURES AND HAS
DEPARTED FROM THE RULES ON
4) Php 10,000.00 litigation expenses.
EVIDENCE.
COSTS AGAINST THE DEFENDANTS.
C. THE COURT OF APPEALS
4
MISAPPREHENDED THE FACTS AND ITS
SO ORDERED. FINDINGS IS TOTALLY NOT IN ACCORD
WITH THE EVIDENCE ON RECORD.
In finding in favor of petitioner, the trial court found that it
was able to prove by preponderance of evidence D. THE COURT OF APPEALS DEPARTED
that MV Miguela rammed and damaged the pile cluster; FROM THE RULE OF RES IPSA LOQUITUR.6
that petitioner's witnesses, Naval and Espina, actually
saw the incident; that respondents failed to refute the
The issues for resolution can be reduced into three:
testimony of marine surveyor Degamo and skin diver
Alferez on the damages; that the officers and crew
of MV Miguela were negligent; and that respondents are 1. Did the CA go beyond the issues raised?
solidarily liable for the damages.
2. Can this Court review factual questions in this
Upon private respondent's appeal, the Court of Appeals case?
reversed the trial court on January 10, 1996, in its
decision that reads: 3. Is the doctrine of res ipsa loquitur applicable
to this case?
WHEREFORE, in view of the foregoing,
judgment is rendered REVERSING and On the first issue, petitioner argues that private
SETTING aside the decision of the Court a quo, respondents did not assign as an error eyewitness
hereby entering a new one DISMISSING the Ireneo Naval's incompetence to testify on the negligence
Complaint for lack of merit. of MV Miguela's officers and crew. Private respondent's
brief contained nothing but general statements and
No pronouncement as to costs. reproductions of excerpts of the transcript of
stenographic notes (TSN) which could not pass for a
valid assignment of errors.
SO ORDERED.5

We note that Naval's incompetence was not one of the


The CA found that petitioner's eyewitness Naval was
assigned errors in private respondents' brief. 7 However,
incompetent to testify on the negligence of the crew and
private respondents raised it in connection with the issue
officers of MV Miguela; that there were other vessels that
of their negligence, which appeared in the second
used the wharf for berthing the petitioner's evidence did
assigned error. In reproducing the portion of the TSN
not positively prove that it was MV Miguela that rammed
consisting of Naval's cross examination, private
the pile cluster; that the photographs of the pile cluster
respondents' counsel was indirectly attacking Naval's
taken after the incident showed no visible damages; that,
competence and invoking it vis a vis the trial court's
as shown by private respondents' witness, there were
finding, based on Naval's testimony, that MV
seashells and seaweeds directly under the uprooted
Miguela was sailing at a speed unusual for a docking
post, which indicated that the breaking happened a long
vessel.8 The CA did not err in addressing the matter. An
time ago.
appellate court can consider an unassigned error on
which depends the determination of the question in the
The CA denied the motion for reconsideration. Hence, properly assigned error.9 The issue of negligence of MV
this petition for review where petitioner assigns the Miguela's officers and crew depends significantly on the
following errors:
2
determination of whether Naval is competent to testify on shoreward and misalligned.14 Alferez, under oath,
the maneuvering of a docking vessel. testified that he dived two or three times and saw one
broken post and two slightly uprooted ones with a crack
The second issue is whether or not we can review on each.15
questions of fact. Petitioner, in its second and third
assigned errors, claims that the appellate court relied on On the other hand, private respondents' evidence on this
speculations and conjectures when it ruled that MV matter was contradictory. As testified by Olasiman, when
Miguela could not have rammed the pile cluster because he asked Lazara on the result of his diving, the latter
of the presence of other vessels; that petitioner's said that there was no damage.16 However, when Lazara
evidence, corroborated by those of private respondents, testified in court, he said he found a crack on the side of
is positive and sufficient to prove respondents' liability; the pile cluster, with one pile no longer touching the
that evidence on record showed the negligence and seabed and directly underneath it were seashells and
recklessness of MV Miguela's officers and crew; and that seaweeds. Further, he said that he informed the captain
the crew were grossly incompetent and incapable to man about this.17 We find Lazara's testimony as an
the vessel. afterthought, lacking credibility. In addition, Leonilo
Lazara, was a mere bodegero of MV Miguela. He could
Private respondents claim that the above are not possibly be a competent witness on marine
conclusions of fact which this Court may not review. surveys.18

While the rule is that this Court is limited only to Finally, is the doctrine of res ipsa loquitur applicable to
questions of law in a petition for review, there are this case? Petitioner argues that the Court of Appeals
exceptions, among which are when the factual findings erred when it reversed the trial court for the latter's
of the Court of Appeals and the trial court conflict, and heavy reliance on Naval's testimony. The appellate court
when the appellate court based its conclusion entirely on overlooked the fact that aside from Naval's testimony,
speculations, surmises, or conjectures.10 the trial court also relied on the principle of res ipsa
loquitur to establish private respondents' negligence.
Our review of the records constrains us to conclude that
indeed MV Miguela rammed and damaged petitioner's The doctrine of res ipsa loquitur was explained
fender pile cluster. Naval and Espina witnessed the in Batiquin vs. Court of Appeals, 258 SCRA 334 (1996),
incident, saw the impact and heard cracking sounds thus:
thereafter. The trial court found them credible. We
respect this observation of the trial court, for in the Where the thing which causes injury is shown to
appreciation of testimonial evidence and attribution of be under the management of the defendant, and
values to the declaration of witnesses, it is the trial judge the accident is such as in the ordinary course of
who had the chance to observe the witnesses and was things does not happen if those who have the
in a position to determine if the witnesses are telling the management use proper care, it affords
truth or not.11Further, private respondents' witnesses, reasonable evidence, in the absence of an
Olasiman and Gabisan, acknowledged that Naval was at explanation by the defendant, that the accident
the pier waving a handkerchief to direct them to their arose from want of care.
berthing place.12
The doctrine recognizes that parties may establish prima
Private respondents' claim that they could not have facie negligence without direct proof and allows the
rammed and damaged the pile cluster because other principle to substitute for specific proof of negligence.
vessels used the same area for berthing is a mere This is invoked when under the circumstances, direct
speculation unworthy of credence. evidence is absent and not readily available.19

Petitioner's witnesses, marine surveyor Degamo and In our view, all the requisites for recourse to this doctrine
diver Alferez, confirmed the damage. Degamo had exist. First, MV Miguela was under the exclusive control
eighteen years of experience as marine surveyor and of its officers and crew. Petitioner did not have direct
belonged to an independent survey company. Alferez evidence on what transpired within as the officers and
was hired and directly supervised by Degamo for the crew maneuvered the vessel to its berthing place. We
task.13 The latter testified during trial that he examined note the Court of Appeals' finding that Naval and Espina
the pile cluster at the portion above the water line by were not knowledgeable on the vessel's maneuverings,
going near it and found that one cluster pile was moving, and could not testify on the negligence of the officers
two were loose, and the whole pile cluster was leaning and crew. Second, aside from the testimony that MV

3
Miguela rammed the cluster pile, private respondent did Respondent company's negligence consists in allowing
not show persuasively other possible causes of the incompetent crew to man its vessel. As shown also by
damage. petitioner, both Captain Olasiman and Chief Mate
Gabisan did not have a formal training in marine
Applying now the above, there exists a presumption of navigation. The former was a mere elementary
negligence against private respondents which we opine graduate21 while the latter is a high school graduate.
the latter failed to overcome. Additionally, petitioner Their experience in navigation22 was only as a watchman
presented tangible proof that demonstrated private and a quartermaster, respectively.1âwphi1.nêt
respondents' negligence. As testified by Capt. Olasiman,
from command of "slow ahead" to "stop engine", the WHEREFORE, the petition is GRANTED. The decision
vessel will still travel 100 meters before it finally stops. and resolution of the Court of Appeals are ANNULLED
However, he ordered "stop engine" when the vessel was AND SET ASIDE, and the decision of the Regional Trial
only 50 meters from the pier. Further, he testified that Court of Cebu City, Branch IX, is hereby REINSTATED.
before the vessel is put to slow astern, the engine has to
be restarted. However, Olasiman can not estimate how Costs against private respondents.
long it takes before the engine goes to slow astern after
the engine is restarted. From these declarations, the SO ORDERED.
conclusion is that it was already too late when the
captain ordered reverse. By then, the vessel was only 4
meters from the pier,20 and thus rammed it.

22 (Corinthian). On the other hand, respondents-spouses


Frank and Teresita Cuaso (the Cuasos) own Lot 65
which is adjacent to the Tanjangcos’ lots.
THIRD DIVISION
Before the Cuasos constructed their house on Lot 65, a
G.R. No. 160795             June 27, 2008 relocation survey was necessary. As Geodetic Engineer
Democrito De Dios (Engr. De Dios), operating under the
CORINTHIAN GARDENS ASSOCIATION, business name D.M. De Dios Realty and Surveying,
INC., petitioner,  conducted all the previous surveys for the subdivision's
vs. developer, Corinthian referred Engr. De Dios to the
SPOUSES REYNALDO and MARIA LUISA Cuasos. Before, during and after the construction of the
TANJANGCO, and SPOUSES FRANK and TERESITA said house, Corinthian conducted periodic ocular
CUASO,respondent. inspections in order to determine compliance with the
approved plans pursuant to the Manual of Rules and
DECISION Regulations of Corinthian.6 Unfortunately, after the
Cuasos constructed their house employing the services
NACHURA, J.: of C.B. Paraz & Construction Co., Inc. (C.B. Paraz) as
builder, their perimeter fence encroached on the
Tanjangcos’ Lot 69 by 87 square meters.
Before this Court is a Petition for Review
on Certiorari1 under Rule 45 of the Rules of Civil
Procedure seeking the reversal of the Court of Appeals No amicable settlement was reached between the
(CA) Decision2 dated January 31, 2003 in CA-G.R. CV parties. Thus, the Tanjangcos demanded that the
No. 43217, which reversed and set aside the Cuasos demolish the perimeter fence but the latter failed
Decision3 of the Regional Trial Court (RTC) of Quezon and refused, prompting the Tanjangcos to file with the
City, dated March 30, 1993. RTC a suit against the Cuasos for Recovery of
Possession with Damages.7
The Antecedents:
Eventually, the Cuasos filed a Third-Party
Complaint8 against Corinthian, C.B. Paraz and Engr. De
Respondents-spouses Reynaldo and Maria Luisa
Dios. The Cuasos ascribed negligence to C.B. Paraz for
Tanjangco (the Tanjangcos) own Lots 68 and 69
its failure to ascertain the proper specifications of their
covered by Transfer Certificates of Title (TCT) No.
house, and to Engr. De Dios for his failure to undertake
2422454 and 2829615 respectively, located at Corinthian
an accurate relocation survey, thereby, exposing them to
Gardens Subdivision, Quezon City, which is managed by
litigation. The Cuasos also faulted Corinthian for
petitioner Corinthian Gardens Association, Inc.
approving their relocation survey and building plans
4
without verifying their accuracy and in making awards. The Cuasos’ appeal against the Tanjangcos, on
representations as to Engr. De Dios' integrity and the other hand, was dismissed for lack of merit. On the
competence. The Cuasos alleged that had Corinthian third-party complaints, Corinthian, C.B. Paraz and Engr.
exercised diligence in performing its duty, they would not De Dios were all found negligent in performing their
have been involved in a boundary dispute with the respective duties and so they were ordered to contribute
Tanjangcos. Thus, the Cuasos opined that Corinthian five percent (5%) each, or a total of fifteen percent (15%)
should also be held answerable for any damages that to all judgment sums and amounts that the Cuasos shall
they might incur as a result of such construction. eventually pay under the decision, also with interest of
six percent (6%) per annum.
On March 30, 1993, the RTC rendered a Decision in
favor of the Tanjangcos. It ruled that the Cuasos’ Only Corinthian filed a Motion for Reconsideration 11 of
perimeter wall encroached on the land of the Tanjangos the CA Decision within the 15-day reglementary period.
by 87 square meters. It, however, ruled that the Cuasos No motion for reconsideration was filed by the Cuasos,
were builders in good faith, and gave the Tanjangcos the C.B. Paraz and/or Engr. De Dios.
option to sell and the Cuasos the option to buy the
encroaching portion of the land, at a price to be agreed About six (6) months later, or on August 12, 2003, the
upon by the parties within sixty (60) days from receipt of Cuasos filed a Comment/Manifestation 12 praying that
the said Decision. In the event that the Cuasos were they be allowed to adopt Corinthian’s Motion for
unable and unwilling to purchase the said portion, the Reconsideration.
perimeter wall should be demolished at the latter’s
expense. The RTC also ordered the Cuasos to pay In its Resolution13 dated November 14, 2003, the CA
monthly rentals of P2,000.00 commencing from the time denied Corinthian’s Motion for Reconsideration.
of the filing of the complaint. The RTC likewise held that
C.B. Paraz was grossly negligent in not taking into
account the correct boundaries of Cuasos’ lot when it Hence, Corinthian filed the instant Petition for Review on
constructed the house. It, thus, ordered C.B. Paraz to Certiorari assailing the CA Decision and Resolution, and
pay moral and exemplary damages as well as attorney’s impleading the Cuasos as one of the respondents being
fees to the Tanjangcos and the Cuasos. The third-party the third-party plaintiffs in the RTC.
complaint against Corinthian and Engr. De Dios, on the
other hand, was dismissed for lack of cause of action. This Court gave due course to Corinthian’s petition and
required the parties to submit their respective
The Tanjangcos filed a Motion for Reconsideration 9 of memorandum.14 In compliance, the Cuasos submitted
the said RTC Decision which the RTC, however, denied their Memorandum15 and Supplement to
in its Order10 dated June 28, 1993. Memorandum,16which were both noted by this Court in
its Resolutions dated January 10, 200517 and February
2, 2005, 18respectively.
Dissatisfied with the RTC ruling, the Tanjangcos, the
Cuasos, and C.B. Paraz all appealed to the CA.
In the meantime, the Tanjangcos moved for partial entry
of judgment of the CA Decision which was granted by
On appeal, the CA reversed and set aside the RTC the CA in its Resolution 19 dated May 26, 2006, directing
Decision. It held that the Cuasos acted in bad faith in the issuance of an Entry of Judgment and a Certification
land-grabbing the 87 square meter-portion of Lot 69 as that its Decision dated January 31 2003 has become
of April 5, 1989. Correlatively, the CA allowed the final and executory with respect to the Cuasos, C.B.
Tanjangcos to exercise the rights granted under Articles Paraz and Engr. De Dios for their failure to file an appeal
449, 450, 451 and 549 of the New Civil Code, which assailing the said Decision before this Court.
include the right to demand the demolition of the
offending perimeter wall after reimbursing the Cuasos
the necessary expenses for the preservation of the The Tanjangcos then moved for the execution of the
encroached area. The Cuasos were ordered to pay judgment against the Cuasos, specifically the demolition
monthly rentals of P10,000.00 for the use, enjoyment of the perimeter fence,20 which was also granted by the
and occupancy of the lot from 1989 up to the time they RTC in its Order21 dated December 18, 2006.
vacate the property considering the location and
category of the same. They were, likewise, ordered to Other than the filing of an Opposition 22 and a Motion for
pay the Tanjangcos P100,000.00, as moral Reconsideration23 before the RTC, the Cuasos prayed
damages, P50,000.00 as exemplary damages, for the issuance of a temporary restraining order (TRO)
and P150,000.00 as attorney’s fees. The CA also and/or preliminary injunction before this Court to enjoin
imposed six percent (6%) interest per annum on all the the demolition of the perimeter fence. They averred that
5
the premature demolition of the alleged encroaching In the Cuasos’ case, their right to injunctive relief had not
perimeter wall and other improvements will cause grave been clearly and unmistakably demonstrated. They
and irreparable damage to them, because what is sought failed to show proof that there is material and substantial
to be demolished is part of their residence. They claimed invasion of their right to warrant the issuance of an
that no amount of money will compensate for the injunctive writ. Indeed, the enforcement of the writ of
damage they stand to suffer should any demolition execution, which would demolish the Cuasos’ perimeter
subsequently prove to be wrongful. They argued that fence, is manifestly prejudicial to their interest. However,
before any execution can be carried out, it is necessary they possess no clear and unmistakable legal right that
to first determine whether or not Corinthian was merits protection through the writ of preliminary
negligent in approving the building plan and whether or injunction.27 Their right to maintain the said fence had
not it acted in good faith in doing so. Such determination, been declared inferior to the Tanjangcos’ right to the
according to the Cuasos, will in turn determine whether demolition of the fence, after the CA judgment had
or not they were in good faith in constructing the house.24 become final and executory as to the Cuasos.

The Tanjangcos opposed the Cuasos' application for It bears stressing that the Cuasos failed to appeal the
TRO. They countered that the only pending matter with ruling of the CA. This failure to contest the CA decision
this Court is the appeal by Corinthian; hence, the before this Court was fatal to their cause. It had the
implementation of the January 31, 2003 Decision of the effect of an admission that they indeed acted in bad
CA against the Cuasos will not preempt the outcome of faith, as they accepted the CA ruling. The decision of the
the said pending incidents. Also, any action taken by this CA, therefore, became binding and final as to them. 28 As
Court on Corinthian’s petition would not benefit the a matter of fact, the CA already issued a partial entry of
Cuasos for they did not appeal the adverse decision judgment against the Cuasos.
against them. Accordingly, they cannot obtain affirmative
relief from this Court by reason or on account of the An injunction to stay a final and executory decision is
appeal taken by Corinthian. The appeal, they added, is unavailing except only after a showing that facts and
personal to Corinthian. Finally, they argued that the circumstances exist which would render execution unjust
Cuasos are now estopped from questioning the or inequitable, or that a change in the situation of the
enforcement of the CA Decision since they issued a parties occurred. Here, no such exception exists as
manager’s check to pay the money judgment.25 shown by the facts earlier narrated.29

In this Court's Resolution dated July 18, 2007, we denied While it is true that this Court noted the Memorandum
the Cuasos' application for TRO and/or writ of and Supplemental Memorandum filed by the Cuasos,
preliminary injunction for lack of merit. such notation was made only insofar as Corinthian made
them respondents in this petition. This Court cannot
The denial was based on sound legal principles. It is grant to the Cuasos any affirmative relief as they did not
axiomatic that to be entitled to the injunctive writ, one file a petition questioning the CA ruling. Consequently,
must show that there exists a right to be protected which the Decision of the CA holding that the Cuasos acted in
is directly threatened by the act sought to be enjoined. bad faith and that the perimeter fence may now be
Furthermore, there must be a showing that the invasion demolished cannot be put in issue by the Cuasos. It is a
of the right is material and substantial, that the right of fundamental principle that a party who does not appeal,
complainant is clear and unmistakable, and that there is or file a petition for certiorari, is not entitled to any
an urgent and paramount necessity for the writ to issue affirmative relief.30 An appellee who is not an appellant
in order to prevent serious damage.26 may assign errors in his brief where his purpose is to
maintain the judgment, but he cannot seek modification
or reversal of the judgment or claim affirmative relief
unless he has also appealed.31 This applies to C.B.
Paraz and Engr. De Dios who likewise failed to assail the
aforementioned CA Decision.

With this matter put to rest, we now go to the main


issues raised by Corinthian, the sole petitioner in this
case, to wit:

a) Whether or not there is legal basis for the


Court of Appeals to hold petitioner Corinthian
Gardens Association, Inc. liable to pay 5% of the
6
judgment money to Sps. Tanjangco on account Corinthian Gardens Subdivision and the fact that they
of the encroachment made by Sps. Cuaso[; and] were deprived of it for almost two decades. The
Tanjangcos pray that this Court sustain the ruling of the
b) Whether or not the Court of Appeals has legal CA.34
basis to increase unilaterally and without proof
the amount prayed for in the The instant case is obviously one for tort, as governed
Complaint, i.e., P2,000.00, as reasonable by Article 2176 of the Civil Code, which provides:
compensation for the use and enjoyment of the
portion of the lot encroached upon, ART. 2176. Whoever by act or omission causes
to P10,000.00.32 damage to another, there being fault or
negligence, is obliged to pay for the damage
Corinthian claims that the approval of the building plan of done. Such fault or negligence, if there is no pre-
the Cuasos was not tainted with negligence as it did not existing contractual relation between the parties,
approve the survey relocation plan but merely the is called a quasi-delict and is governed by the
architectural, structural and sanitary plans for Cuasos' provisions of this Chapter.
house; that the purpose of the said approval is not to
ensure that the house to be erected on a particular lot is In every tort case filed under this provision, plaintiff has
constructed within its boundaries but only to ensure to prove by a preponderance of evidence: (1) the
compliance with the Manual of Rules and Regulations; damages suffered by the plaintiff; (2) the fault or
that while Corinthian conducts actual site inspections, negligence of the defendant or some other person for
the inspection and approval of the building plans are whose act he must respond; and (3) the connection of
limited to "table inspection" only; that the survey cause and effect between the fault or negligence and the
relocation plan was never submitted for Corinthian's damages incurred.35
approval; that the acceptance of the builder's bond did
not make Corinthian automatically liable for the Undeniably, the perimeter fence of the Cuasos
encroachment and for damages; and that Corinthian encroached on Lot 69 owned by the Tanjangcos by 87
approved the building plan with the good faith and due square meters as duly found by both the RTC and the
diligence required under the circumstances. It, thus, CA in accordance with the evidence on record. As a
concludes that it cannot be held liable to pay five percent result, the Tanjangcos suffered damage in having been
(5%) of the money judgment to the Tanjangcos on deprived of the use of that portion of their lot encroached
account of the encroachment made by the Cuasos. upon. Thus, the primordial issue to be resolved in this
Likewise, it finds no legal basis for the CA to unilaterally case is whether Corinthian was negligent under the
increase the amount of the adjudged rent circumstances and, if so, whether such negligence
from P2,000.00 to P10,000.00 which was not prayed for contributed to the injury suffered by the Tanjangcos.
by the Tanjangcos in their complaint and in the absence
of evidence adduced by the parties.33
A negligent act is an inadvertent act; it may be merely
carelessly done from a lack of ordinary prudence and
On the other hand, the Tanjangcos stand by the ruling of may be one which creates a situation involving an
the CA and opine that Corinthian was negligent in unreasonable risk to another because of the expectable
approving the building plan of the Cuasos. They submit action of the other, a third person, an animal, or a force
that Corinthian's claim that it merely conducts "table of nature. A negligent act is one from which an ordinary
inspections" of buildings further bolsters their argument prudent person in the actor's position, in the same or
that Corinthian was negligent in conveniently and similar circumstances, would foresee such an
unilaterally restricting and limiting the coverage of its appreciable risk of harm to others as to cause him not to
approval, contrary to its own Manual of Rules and do the act or to do it in a more careful manner.36
Regulations; that the acceptance of a builder's bond
does not automatically make Corinthian liable but the
same affirms the fact that a homeowner can hold it liable The test to determine the existence of negligence in a
for the consequences of the approval of a building plan; particular case may be stated as follows: Did the
and that Corinthian, by regularly demanding and defendant in committing the alleged negligent act use
accepting membership dues, must be wary of its that reasonable care and caution which an ordinary
responsibility to protect the rights and interests of its person would have used in the same situation? If not,
members. Lastly, the Tanjangcos contend that a court then he is guilty of negligence. The law, in effect, adopts
can take judicial notice of the general increase in the the standard supplied by the imaginary conduct of the
rentals of real estate, as in this case, where the CA discreet paterfamilias in Roman law. The existence of
considered the value of their lot in the "posh-and-swank" negligence in a given case is not determined by

7
reference to the personal judgment of the actor in the construction work without prior approval
situation before him. The law considers what would be of the Association will be cut-off in
reckless, blameworthy, or negligent in a man of ordinary addition to the sanctions previously
intelligence and prudence, and determines liability mentioned.
according to that standard.37
It goes without saying that this Manual of Rules
By this test, we find Corinthian negligent. and Regulations applies to all - or it does not
apply at all. To borrow a popular expression,
While the issue of Corinthian's alleged negligence is what is sauce for the gander is sauce for the
factual in character,38 a review by this Court is proper goose - or ought to be. To put it matter-of-factly
because the CA's factual findings differ from those of the and bluntly, thus, its so-called "table inspection"
RTC's.39 Thus, after a meticulous review of the evidence approval of the Cuasos’ building plans is no less
on record, we hold that the CA committed no reversible of an approval, as approvals come and go. And
error when it deviated from the findings of fact of the since it is an approval tainted with negligence,
RTC. The CA's findings and conclusions are the necessary and inevitable consequences
substantiated by the evidence on record and are more in which law and justice attach to such negligence
accord with law and reason. Indeed, it is clear that must, as a matter of law and justice, also
Corinthian failed to exercise the requisite diligence in necessarily attach to Corinthian.
insuring that the Cuasos abide by its Manual of Rules
and Regulations, thereby resulting in the encroachment And then again third party defendant-appellee
on the Tanjangcos’ property. Corinthian Garden required the posting of a
builder’s cash bond (Exh. 5-Corinthian) from the
We agree with the CA when it aptly held: defendants-appellants Cuasos and the third-
party defendant C.B. Paraz Construction to
secure the performance of their undertaking.
Corinthian cannot and should not be allowed to
Surely, Corinthian does not imply that while it
justify or excuse its negligence by claiming that
may take the benefits from the Builder’s cash
its approval of the Cuasos’ building plans was
bond, it may, Pilate-like, wash its hands of any
only limited to a so-called "table inspection;" and
responsibility or liability that would or might arise
not actual site measurement. To accept some
from the construction or building of the structure
such postulate is to put a premium on
for which the cash bond was in the first place
negligence. Corinthian was not organized solely
posted. That is not only unjust and immoral, but
for the defendants Cuasos. It is also the
downright unchristian and iniquitous.
subdivision of the plaintiffs-spouses Tanjangcos
- and of all others who have their dwelling units
or abodes therein. Pertinently, its Manual of Under the same parity of reasoning, the
Rules and Regulations stipulates in Section 3 payment by the appellants-Cuasos to the
thereof (under the heading Construction), thus: appellee Corinthian of pre-construction and
membership fees in the Association must
necessarily entail the creation of certain
A. Rules and Regulations
obligations on the part of Corinthian. For duties
and responsibilities always go hand in hand with
No new construction can be rights and privileges. That is the law of life - and
started unless the building plans are that is the law of every civilized society. It is an
approved by the Association and the axiom of equity that he who receives the benefits
appropriate Builder’s cash bond and must share the burdens.40
pre-construction fees are paid. The
Association will not allow the entry of
By its Manual of Rules and Regulations, it is reasonable
construction materials and process
to assume that Corinthian, through its representative, in
identification cards for workers if the
the approval of building plans, and in the conduct of
above conditions are not complied with.
periodic inspections of on-going construction projects
Likewise, all renovations, repairs,
within the subdivision, is responsible in insuring
additions and improvements to a
compliance with the approved plans, inclusive of the
finished house except electrical wiring,
construction of perimeter walls, which in this case is the
will have to be approved by the
subject of dispute between the Tanjangcos and the
Association. Water service connection of
Cuasos.41 It is not just or equitable to relieve Corinthian
a homeowner who undertakes
of any liability when, by its very own rules, it imposes its
8
authority over all its members to the end that "no new must still base its action on the evidence
construction can be started unless the plans are adduced by the parties.
approved by the Association and the appropriate cash
bond and pre-construction fees are paid." Moreover, In Herrera v. Bollos [G.R. No. 138258, January
Corinthian can impose sanctions for violating these 18, 2002], the trial court awarded rent to the
rules. Thus, the proposition that the inspection is merely defendants in a forcible entry case. Reversing
a "table inspection" and, therefore, should exempt the RTC, this Court declared that the reasonable
Corinthian from liability, is unacceptable. After all, if the amount of rent could be determined not by mere
supposed inspection is merely a "table inspection" and judicial notice, but by supporting evidence:
the approval granted to every member is a mere
formality, then the purpose of the rules would be x x x A court cannot take judicial notice
defeated. Compliance therewith would not be of a factual matter in controversy. The
mandatory, and sanctions imposed for violations could court may take judicial notice of matters
be disregarded. Corinthian's imprimatur on the of public knowledge, or which are
construction of the Cuasos' perimeter wall over the capable of unquestionable
property of the Tanjangcos assured the Cuasos that demonstration, or ought to be known to
everything was in order. judges because of their judicial
functions. Before taking such judicial
In sum, Corinthian’s failure to prevent the encroachment notice, the court must "allow the parties
of the Cuasos’ perimeter wall into Tanjangcos’ property – to be heard thereon." Hence, there can
despite the inspection conducted – constitutes be no judicial notice on the rental value
negligence and, at the very least, contributed to the of the premises in question without
injury suffered by the Tanjangcos. supporting evidence.

On the second issue, our ruling in Spouses Badillo v. Truly, mere judicial notice is inadequate, because
Tayag42 is instructive: evidence is required for a court to determine the proper
rental value. But contrary to Corinthian's arguments,
Citing Sia v. Court of Appeals [272 SCRA 141, both the RTC and the CA found that indeed rent was due
May 5, 1997], petitioners argue that the MTC the Tanjangcos because they were deprived of
may take judicial notice of the reasonable rental possession and use of their property. This uniform
or the general price increase of land in order to factual finding of the RTC and the CA was based on the
determine the amount of rent that may be evidence presented below. Moreover, in Spouses
awarded to them. In that case, however, this Catungal v. Hao,43 we considered the increase in the
Court relied on the CA's factual findings, which award of rentals as reasonable given the particular
were based on the evidence presented before circumstances of each case. We noted therein that the
the trial court. In determining reasonable rent, respondent denied the petitioners the benefits, including
the RTC therein took account of the following rightful possession, of their property for almost a decade.
factors: 1) the realty assessment of the land, 2)
the increase in realty taxes, and 3) the prevailing Similarly, in the instant case, the Tanjangcos were
rate of rentals in the vicinity. Clearly, the trial deprived of possession and use of their property for
court relied, not on mere judicial notice, but on more than two decades through no fault of their own.
the evidence presented before it. Thus, we find no cogent reason to disturb the monthly
rental fixed by the CA.
Indeed, courts may fix the reasonable amount of
rent for the use and occupation of a disputed All told, the CA committed no reversible error.
property. However, petitioners herein erred in
assuming that courts, in determining the amount WHEREFORE, the petition is DENIED. The Decision of
of rent, could simply rely on their own the Court of Appeals is AFFIRMED. Costs against
appreciation of land values without considering petitioner.
any evidence. As we have said earlier, a court
may fix the reasonable amount of rent, but it
SO ORDERED.

23 SECOND DIVISION

G.R. No. 179446               January 10, 2011


9
LOADMASTERS CUSTOMS SERVICES, Later on, the said truck, an Isuzu with Plate No. NSD-
INC., Petitioner,  117, was recovered but without the copper cathodes.
vs. Because of this incident, Columbia filed with R&B
GLODEL BROKERAGE CORPORATION and R&B Insurance a claim for insurance indemnity in the amount
INSURANCE CORPORATION, Respondents. of ₱1,903,335.39. After the requisite investigation and
adjustment, R&B Insurance paid Columbia the amount of
DECISION ₱1,896,789.62 as insurance indemnity.

MENDOZA, J.: R&B Insurance, thereafter, filed a complaint for damages


against both Loadmasters and Glodel before the
Regional Trial Court, Branch 14, Manila (RTC), docketed
This is a petition for review on certiorari under Rule 45 of
as Civil Case No. 02-103040. It sought reimbursement of
the Revised Rules of Court assailing the August 24,
the amount it had paid to Columbia for the loss of the
2007 Decision1 of the Court of Appeals (CA) in CA-G.R.
subject cargo. It claimed that it had been subrogated "to
CV No. 82822, entitled "R&B Insurance Corporation v.
the right of the consignee to recover from the
Glodel Brokerage Corporation and Loadmasters
party/parties who may be held legally liable for the loss."2
Customs Services, Inc.," which held petitioner
Loadmasters Customs Services,
Inc. (Loadmasters) liable to respondent Glodel On November 19, 2003, the RTC rendered a
Brokerage Corporation (Glodel) in the amount of decision3 holding Glodel liable for damages for the loss
₱1,896,789.62 representing the insurance indemnity of the subject cargo and dismissing Loadmasters’
which R&B Insurance Corporation (R&B Insurance)  paid counterclaim for damages and attorney’s fees against
to the insured-consignee, Columbia Wire and Cable R&B Insurance. The dispositive portion of the decision
Corporation (Columbia). reads:

THE FACTS: WHEREFORE, all premises considered, the plaintiff


having established by preponderance of evidence its
claims against defendant Glodel Brokerage Corporation,
On August 28, 2001, R&B Insurance issued Marine
judgment is hereby rendered ordering the latter:
Policy No. MN-00105/2001 in favor of Columbia to
insure the shipment of 132 bundles of electric copper
cathodes against All Risks. On August 28, 2001, the 1. To pay plaintiff R&B Insurance Corporation
cargoes were shipped on board the vessel "Richard the sum of ₱1,896,789.62 as actual and
Rey" from Isabela, Leyte, to Pier 10, North Harbor, compensatory damages, with interest from the
Manila. They arrived on the same date. date of complaint until fully paid;

Columbia engaged the services of Glodel for the release 2. To pay plaintiff R&B Insurance Corporation
and withdrawal of the cargoes from the pier and the the amount equivalent to 10% of the principal
subsequent delivery to its warehouses/plants. Glodel, in amount recovered as and for attorney’s fees
turn, engaged the services of Loadmasters for the use of plus ₱1,500.00 per appearance in Court;
its delivery trucks to transport the cargoes to Columbia’s
warehouses/plants in Bulacan and Valenzuela City. 3. To pay plaintiff R&B Insurance Corporation
the sum of ₱22,427.18 as litigation expenses.
The goods were loaded on board twelve (12) trucks
owned by Loadmasters, driven by its employed drivers WHEREAS, the defendant Loadmasters Customs
and accompanied by its employed truck helpers. Six (6) Services, Inc.’s counterclaim for damages and attorney’s
truckloads of copper cathodes were to be delivered to fees against plaintiff are hereby dismissed.
Balagtas, Bulacan, while the other six (6) truckloads
were destined for Lawang Bato, Valenzuela City. The With costs against defendant Glodel Brokerage
cargoes in six truckloads for Lawang Bato were duly Corporation.
delivered in Columbia’s warehouses there. Of the six (6)
trucks en route to Balagtas, Bulacan, however, only five SO ORDERED.4
(5) reached the destination. One (1) truck, loaded with
11 bundles or 232 pieces of copper cathodes, failed to
deliver its cargo. Both R&B Insurance and Glodel appealed the RTC
decision to the CA.

10
On August 24, 2007, the CA rendered the assailed merchandise. Thus, the diligence required in this case is
decision which reads in part: merely ordinary diligence or that of a good father of the
family, not the extraordinary diligence required of
Considering that appellee is an agent of appellant common carriers.
Glodel, whatever liability the latter owes to appellant
R&B Insurance Corporation as insurance indemnity must R&B Insurance, for its part, claims that Glodel is deemed
likewise be the amount it shall be paid by appellee to have interposed a cross-claim against Loadmasters
Loadmasters. because it was not prevented from presenting evidence
to prove its position even without amending its Answer.
WHEREFORE, the foregoing considered, the appeal is As to the relationship between Loadmasters and Glodel,
PARTLY GRANTED in that the appellee Loadmasters is it contends that a contract of agency existed between the
likewise held liable to appellant Glodel in the amount of two corporations.8
₱1,896,789.62 representing the insurance indemnity
appellant Glodel has been held liable to appellant R&B Subrogation is the substitution of one person in the place
Insurance Corporation. of another with reference to a lawful claim or right, so
that he who is substituted succeeds to the rights of the
Appellant Glodel’s appeal to absolve it from any liability other in relation to a debt or claim, including its remedies
is herein DISMISSED. or securities.9 Doubtless, R&B Insurance is subrogated
to the rights of the insured to the extent of the amount it
paid the consignee under the marine insurance, as
SO ORDERED.5
provided under Article 2207 of the Civil Code, which
reads:
Hence, Loadmasters filed the present petition for review
on certiorari before this Court presenting the following
ART. 2207. If the plaintiff’s property has been insured,
and he has received indemnity from the insurance
ISSUES company for the injury or loss arising out of the wrong or
breach of contract complained of, the insurance
1. Can Petitioner Loadmasters be held liable company shall be subrogated to the rights of the insured
to Respondent Glodel in spite of the fact that against the wrong-doer or the person who has violated
the latter respondent Glodel did not file a the contract. If the amount paid by the insurance
cross-claim against it (Loadmasters)? company does not fully cover the injury or loss, the
aggrieved party shall be entitled to recover the
2. Under the set of facts established and deficiency from the person causing the loss or injury.
undisputed in the case, can petitioner
Loadmasters be legally considered as an As subrogee of the rights and interest of the consignee,
Agent of respondent Glodel?6 R&B Insurance has the right to seek reimbursement from
either Loadmasters or Glodel or both for breach of
To totally exculpate itself from responsibility for the lost contract and/or tort.
goods, Loadmasters argues that it cannot be considered
an agent of Glodel because it never represented the The issue now is who, between Glodel and
latter in its dealings with the consignee. At any rate, it Loadmasters, is liable to pay R&B Insurance for the
further contends that Glodel has no recourse against it amount of the indemnity it paid Columbia.
for its (Glodel’s) failure to file a cross-claim pursuant to
Section 2, Rule 9 of the 1997 Rules of Civil Procedure. At the outset, it is well to resolve the issue of whether
Loadmasters and Glodel are common carriers to
Glodel, in its Comment,7 counters that Loadmasters is determine their liability for the loss of the subject cargo.
liable to it under its cross-claim because the latter was Under Article 1732 of the Civil Code, common carriers
grossly negligent in the transportation of the subject are persons, corporations, firms, or associations
cargo. With respect to Loadmasters’ claim that it is engaged in the business of carrying or transporting
already estopped from filing a cross-claim, Glodel insists passenger or goods, or both by land, water or air for
that it can still do so even for the first time on appeal compensation, offering their services to the public.
because there is no rule that provides otherwise. Finally,
Glodel argues that its relationship with Loadmasters is Based on the aforecited definition, Loadmasters is a
that of Charter wherein the transporter (Loadmasters) is common carrier because it is engaged in the business of
only hired for the specific job of delivering the transporting goods by land, through its trucking service.

11
It is a common carrier as distinguished from a private are delivered, actually or constructively, by the carrier to
carrier wherein the carriage is generally undertaken by the consignee, or to the person who has a right to
special agreement and it does not hold itself out to carry receive them.18
goods for the general public. 10 The distinction is
significant in the sense that "the rights and obligations of Premises considered, the Court is of the view that both
the parties to a contract of private carriage are governed Loadmasters and Glodel are jointly and severally liable
principally by their stipulations, not by the law on to R & B Insurance for the loss of the subject cargo.
common carriers."11 Under Article 2194 of the New Civil Code, "the
responsibility of two or more persons who are liable for a
In the present case, there is no indication that the quasi-delict is solidary."
undertaking in the contract between Loadmasters and
Glodel was private in character. There is no showing that Loadmasters’ claim that it was never privy to the contract
Loadmasters solely and exclusively rendered services to entered into by Glodel with the consignee Columbia or
Glodel. R&B Insurance as subrogee, is not a valid defense. It
may not have a direct contractual relation with Columbia,
In fact, Loadmasters admitted that it is a common but it is liable for tort under the provisions of Article 2176
carrier.12 of the Civil Code on quasi-delicts which expressly
provide:
In the same vein, Glodel is also considered a common
carrier within the context of Article 1732. In its ART. 2176. Whoever by act or omission causes damage
Memorandum,13 it states that it "is a corporation duly to another, there being fault or negligence, is obliged to
organized and existing under the laws of the Republic of pay for the damage done. Such fault or negligence, if
the Philippines and is engaged in the business of there is no pre-existing contractual relation between the
customs brokering." It cannot be considered otherwise parties, is called a quasi-delict and is governed by the
because as held by this Court in Schmitz Transport & provisions of this Chapter.
Brokerage Corporation v. Transport Venture, Inc., 14 a
customs broker is also regarded as a common carrier, Pertinent is the ruling enunciated in the case
the transportation of goods being an integral part of its of Mindanao Terminal and Brokerage Service, Inc. v.
business. Phoenix Assurance Company of New York,/McGee &
Co., Inc.19  where this Court held that a tort may arise
Loadmasters and Glodel, being both common carriers, despite the absence of a contractual relationship, to wit:
are mandated from the nature of their business and for
reasons of public policy, to observe the extraordinary We agree with the Court of Appeals that the complaint
diligence in the vigilance over the goods transported by filed by Phoenix and McGee against Mindanao Terminal,
them according to all the circumstances of such case, as from which the present case has arisen, states a cause
required by Article 1733 of the Civil Code. When the of action. The present action is based on quasi-delict,
Court speaks of extraordinary diligence, it is that extreme arising from the negligent and careless loading and
measure of care and caution which persons of unusual stowing of the cargoes belonging to Del Monte Produce.
prudence and circumspection observe for securing and Even assuming that both Phoenix and McGee have only
preserving their own property or rights.15 This exacting been subrogated in the rights of Del Monte Produce,
standard imposed on common carriers in a contract of who is not a party to the contract of service between
carriage of goods is intended to tilt the scales in favor of Mindanao Terminal and Del Monte, still the insurance
the shipper who is at the mercy of the common carrier carriers may have a cause of action in light of the Court’s
once the goods have been lodged for shipment. 16 Thus, consistent ruling that the act that breaks the
in case of loss of the goods, the common carrier is contract may be also a tort. In fine, a liability for tort
presumed to have been at fault or to have acted may arise even under a contract, where tort is that which
negligently.17 This presumption of fault or negligence, breaches the contract. In the present case, Phoenix and
however, may be rebutted by proof that the common McGee are not suing for damages for injuries arising
carrier has observed extraordinary diligence over the from the breach of the contract of service but from
goods. the alleged negligent manner by which Mindanao
Terminal handled the cargoes belonging to Del Monte
With respect to the time frame of this extraordinary Produce. Despite the absence of contractual relationship
responsibility, the Civil Code provides that the exercise between Del Monte Produce and Mindanao Terminal,
of extraordinary diligence lasts from the time the goods the allegation of negligence on the part of the defendant
are unconditionally placed in the possession of, and should be sufficient to establish a cause of action arising
received by, the carrier for transportation until the same from quasi-delict. [Emphases supplied]
12
In connection therewith, Article 2180 provides: relationship; (2) the object is the execution of a juridical
act in relation to a third person; (3) the agent acts as a
ART. 2180. The obligation imposed by Article 2176 is representative and not for himself; (4) the agent acts
demandable not only for one’s own acts or omissions, within the scope of his authority.22
but also for those of persons for whom one is
responsible. Accordingly, there can be no contract of agency between
the parties. Loadmasters never represented Glodel.
xxxx Neither was it ever authorized to make such
representation. It is a settled rule that the basis for
agency is representation, that is, the agent acts for and
Employers shall be liable for the damages caused by
on behalf of the principal on matters within the scope of
their employees and household helpers acting within the
his authority and said acts have the same legal effect as
scope of their assigned tasks, even though the former
if they were personally executed by the principal. On the
are not engaged in any business or industry.
part of the principal, there must be an actual intention to
appoint or an intention naturally inferable from his words
It is not disputed that the subject cargo was lost while in or actions, while on the part of the agent, there must be
the custody of Loadmasters whose employees (truck an intention to accept the appointment and act on
driver and helper) were instrumental in the hijacking or it.23 Such mutual intent is not obtaining in this case.
robbery of the shipment. As employer, Loadmasters
should be made answerable for the damages caused by
What then is the extent of the respective liabilities of
its employees who acted within the scope of their
Loadmasters and Glodel? Each wrongdoer is liable for
assigned task of delivering the goods safely to the
the total damage suffered by R&B Insurance. Where
warehouse.
there are several causes for the resulting damages, a
party is not relieved from liability, even partially. It is
Whenever an employee’s negligence causes damage or sufficient that the negligence of a party is an efficient
injury to another, there instantly arises a presumption cause without which the damage would not have
juris tantum that the employer failed to exercise resulted. It is no defense to one of the concurrent
diligentissimi patris families in the selection (culpa in tortfeasors that the damage would not have resulted
eligiendo) or supervision (culpa in vigilando) of its from his negligence alone, without the negligence or
employees.20 To avoid liability for a quasi-delict wrongful acts of the other concurrent tortfeasor. As
committed by its employee, an employer must overcome stated in the case of Far Eastern Shipping v. Court of
the presumption by presenting convincing proof that he Appeals,24
exercised the care and diligence of a good father of a
family in the selection and supervision of his
X x x. Where several causes producing an injury are
employee.21 In this regard, Loadmasters failed.
concurrent and each is an efficient cause without which
the injury would not have happened, the injury may be
Glodel is also liable because of its failure to exercise attributed to all or any of the causes and recovery may
extraordinary diligence. It failed to ensure that be had against any or all of the responsible persons
Loadmasters would fully comply with the undertaking to although under the circumstances of the case, it may
safely transport the subject cargo to the designated appear that one of them was more culpable, and that the
destination. It should have been more prudent in duty owed by them to the injured person was not the
entrusting the goods to Loadmasters by taking same. No actor's negligence ceases to be a proximate
precautionary measures, such as providing escorts to cause merely because it does not exceed the negligence
accompany the trucks in delivering the cargoes. Glodel of other actors. Each wrongdoer is responsible for the
should, therefore, be held liable with Loadmasters. Its entire result and is liable as though his acts were the
defense of force majeure is unavailing. sole cause of the injury.

At this juncture, the Court clarifies that there exists no There is no contribution between joint tortfeasors whose
principal-agent relationship between Glodel and liability is solidary since both of them are liable for the
Loadmasters, as erroneously found by the CA. Article total damage. Where the concurrent or successive
1868 of the Civil Code provides: "By the contract of negligent acts or omissions of two or more persons,
agency a person binds himself to render some service or although acting independently, are in combination the
to do something in representation or on behalf of direct and proximate cause of a single injury to a third
another, with the consent or authority of the latter." The person, it is impossible to determine in what proportion
elements of a contract of agency are: (1) consent, each contributed to the injury and either of them is
express or implied, of the parties to establish the responsible for the whole injury. Where their
13
concurring negligence resulted in injury or damage to a and never against, statutory law or judicial rules of
third party, they become joint tortfeasors and are procedure."26 The Court cannot be a lawyer and take the
solidarily liable for the resulting damage under Article cudgels for a party who has been at fault or negligent.
2194 of the Civil Code. [Emphasis supplied]
WHEREFORE, the petition is PARTIALLY GRANTED.
The Court now resolves the issue of whether Glodel can The August 24, 2007 Decision of the Court of Appeals
collect from Loadmasters, it having failed to file a cross- is MODIFIED to read as follows:
claim against the latter.1avvphi1
WHEREFORE, judgment is rendered declaring petitioner
Undoubtedly, Glodel has a definite cause of action Loadmasters Customs Services, Inc. and respondent
against Loadmasters for breach of contract of service as Glodel Brokerage Corporation jointly and severally liable
the latter is primarily liable for the loss of the subject to respondent R&B Insurance Corporation for the
cargo. In this case, however, it cannot succeed in insurance indemnity it paid to consignee Columbia Wire
seeking judicial sanction against Loadmasters because & Cable Corporation and ordering both parties to pay,
the records disclose that it did not properly interpose a jointly and severally, R&B Insurance Corporation a] the
cross-claim against the latter. Glodel did not even pray amount of ₱1,896,789.62 representing the insurance
that Loadmasters be liable for any and all claims that it indemnity; b] the amount equivalent to ten (10%) percent
may be adjudged liable in favor of R&B Insurance. Under thereof for attorney’s fees; and c] the amount of
the Rules, a compulsory counterclaim, or a cross-claim, ₱22,427.18 for litigation expenses.
not set up shall be barred.25 Thus, a cross-claim cannot
be set up for the first time on appeal. The cross-claim belatedly prayed for by respondent
Glodel Brokerage Corporation against petitioner
For the consequence, Glodel has no one to blame but Loadmasters Customs Services, Inc. is DENIED.
itself. The Court cannot come to its aid on equitable
grounds. "Equity, which has been aptly described as ‘a SO ORDERED.
justice outside legality,’ is applied only in the absence of,

24 the doctrine of assumption of risk was applicable to the


fatality; and on whether the heirs of the fatality can
recover damages for loss of earning capacity of the latter
THIRD DIVISION who, being then a minor, had no gainful employment.

March 15, 2017 The Case

G.R. No. 164749 By this appeal, the parents of the late Rommel Abrogar
(Rommel), a marathon runner, seek the review and
ROMULO ABROGAR and ERLINDA reversal of the decision promulgated on March l 0,
ABROGAR, Petitioners  2004,1 whereby the Court of Appeals (CA) reversed and
vs set aside the judgment rendered in their favor on May
COSMOS BOTTLING COMPANY and INTERGAMES, 10, 1991 by the Regional Trial Court (RTC), Branch 83,
INC., Respondents in Quezon City2 finding and declaring respondents
Cosmos Bottling Company (Cosmos), a domestic soft-
DECISION drinks company whose products included Pop Cola, and
Intergames, Inc. (Intergames), also a domestic
BERSAMIN, J.: corporation organizing and supervising the 1st Pop Cola
Junior Marathon" held on June 15, 1980 in Quezon City,
solidarily liable for damages arising from the untimely
This case involves a claim for damages arising from the
death of Rommel, then a minor 18 years of age, 3 after
negligence causing the death of a participant in an
being bumped by a recklessly driven passenger jeepney
organized marathon bumped by a passenger jeepney on
along the route of the marathon.
the route of the race. The issues revolve on whether the
organizer and the sponsor of the marathon were guilty of
negligence, and, if so, was their negligence the Antecedents
proximate cause of the death of the participant; on
whether the negligence of the driver of the passenger The CA narrated the antecedents in the assailed
jeepney was an efficient intervening cause; on whether judgment,4 viz.:
14
[T]o promote the sales of "Pop Cola", defendant any of the entries in the '1st Pop Cola Junior Marathon'
Cosmos, jointly with Intergames, organized an or for any damage to the property or properties of third
endurance running contest billed as the "1st Pop Cola parties, which may likewise arise in the course of the
Junior Marathon" scheduled to be held on June 15, race."9Thus, Cosmos sought to hold Intergames solely
1980. The organizers plotted a 10-kilometer course liable should the claim of the petitioners prosper. 10
starting from the premises of the Interim Batasang
Pambansa (IBP for brevity), through public roads and On its part, Intergames asserted that Rommel's death
streets, to end at the Quezon Memorial Circle. Plaintiffs' had been an accident exclusively caused by the
son Rommel applied with the defendants to be allowed negligence of the jeepney driver; that it was not
to participate in the contest and after complying with responsible for the accident; that as the marathon
defendants' requirements, his application was accepted organizer, it did not assume the responsibilities of an
and he was given an official number. Consequently, on insurer of the safety of the participants; that it
June 15, 1980 at the designated time of the marathon, nevertheless caused the participants to be covered with
Rommel joined the other participants and ran the course accident insurance, but the petitioners refused to accept
plotted by the defendants. As it turned out, the plaintiffs' the proceeds thereof;11 that there could be no cause of
(sic) further alleged, the defendants failed to provide action against it because the acceptance and approval of
adequate safety and precautionary measures and to Rommel's application to join the marathon had been
exercise the diligence required of them by the nature of conditioned on his waiver of all rights and causes of
their undertaking, in that they failed to insulate and action arising from his participation in the
protect the participants of the marathon from the marathon;12 that it exercised due diligence in the conduct
vehicular and other dangers along the marathon route. of the race that the circumstances called for and was
Rommel was bumped by a jeepney that was then appropriate, it having availed of all its know-how and
running along the route of the marathon on Don Mariano expertise, including the adoption and implementation of
Marcos A venue (DMMA for brevity), and in spite of all known and possible safety and precautionary
medical treatment given to him at the Ospital ng Bagong measures in order to protect the participants from
Lipunan, he died later that same day due to severe head injuries arising from vehicular and other forms of
injuries. accidents;13 and, accordingly, the complaint should be
dismissed.
On October 28, 1980, the petitioners sued the
respondents in the then Court of First Instance of Rizal In their reply and answer to counterclaim, the petitioners
(Quezon City) to recover various damages for the averred that contrary to its claims, Intergames did not
untimely death of Rommel (i.e.,  actual and provide adequate measures for the safety and protection
compensatory damages, loss of earning capacity, moral of the race participants, considering that motor vehicles
damages, exemplary damages, attorney's fees and were traversing the race route and the participants were
expenses oflitigation).5 made to run along the flow of traffic, instead of against it;
that Intergames did not provide adequate traffic
Cosmos denied liability, insisting that it had not been the marshals to secure the safety and protection of the
organizer of the marathon, but only its sponsor; that its participants;14that Intergames could not limit its liability
participation had been limited to providing financial on the basis of the accident insurance policies it had
assistance to Intergames;6 that the financial assistance it secured to cover the race participants; that the waiver
had extended to Intergames, the sole organizer of the signed by Rommel could not be a basis for denying
marathon, had been in answer to the Government's call liability because the same was null and void for being
to the private sector to help promote sports development contrary to law, morals, customs and public policy; 15 that
and physical fitness;7 that the petitioners had no cause of their complaint sufficiently stated a cause of action
action against it because there was no privity of contract because in no way could they be held liable for
between the participants in the marathon and Cosmos; attorney's fees, litigation expenses or any other relief
and that it had nothing to do with the organization, due to their having abided by the law and having acted
operation and running of the event.8 honestly, fairly, in good faith by according to Intergames
its due, as demanded by the facts and circumstances.16
As counterclaim, Cosmos sought attorney's fees and
expenses of litigation from the petitioners for their being At the pre-trial held on April 12, 1981, the parties agreed
unwarrantedly included as a defendant in the case. It that the principal issue was whether or not Cosmos and
averred a cross-claim against Intergames, stating that lntergames were liable for the death of Rommel because
the latter had guaranteed to hold Cosmos "completely of negligence in conducting the marathon.17
free and harmless from any claim or action for liability for
any injuries or bodily harm which may be sustained by Judgment of the RTC
15
In its decision dated May 10, 1991,18 the RTC ruled as The petitioners contended that the RTC erred in not
follows: awarding damages for loss of earning capacity on the
part of Rommel for the reason that such damages were
WHEREFORE, judgment is hereby rendered in favor of not recoverable due to Rommel not yet having finished
plaintiffs-spouses Romulo Abrogar and Erlinda Abrogar his schooling; and that it would be premature to award
and against defendants Cosmos Bottling Company, Inc. such damages upon the assumption that he would finish
and Intergames, Inc., ordering both defendants, jointly college and be gainfully employed.22
and severally, to pay and deliver to the plaintiffs the
amounts of Twenty Eight Thousand Sixty One Pesos On their part, Cosmos and Intergames separately raised
and Sixty Three Centavos (₱28,061.63) as actual essentially similar errors on the part of the RTC, to wit:
damages; One Hundred Thousand Pesos (₱100,000.00) (1) in holding them liable for the death of Rommel; (2) in
as moral damages; Fifty Thousand Pesos (₱50,000.00) finding them negligent in conducting the marathon; (3) in
as exemplary damages and Ten Percent (10%) of the holding that Rommel and his parents did not assume the
total amount of One Hundred Seventy Eight Thousand risks of the marathon; (4) in not holding that the sole and
Sixty One Pesos and Sixty Three Centavos proximate cause of the death of Rommel was the
(₱178,061,63) or Seventeen Thousand Eight Hundred negligence of the jeepney driver; and (5) in making them
Six Pesos and Sixteen Centavos (₱17,806.16) as liable, jointly and solidarily, for damages, attorney's fees
attorney's fees. and expenses of litigation.23

On the cross-claim of defendant Cosmos Bottling The CA reduced the issues to four, namely:
Company, Inc., defendant Intergames, Inc, is hereby
ordered to reimburse to the former any and all amounts 1. Whether or not appellant Intergames was negligent in
which may be recovered by the plaintiffs from it by virtue its conduct of the "1st Pop Cola Junior Marathon" held on
of this Decision. June 15, 1980 and if so, whether its negligence was the
proximate cause of the death of Rommel Abrogar.
SO ORDERED.
2. Whether or not appellant Cosmos can be held jointly
The RTC observed that the safeguards allegedly and solidarily liable with appellant Intergames for the
instituted by Intergames in conducting the marathon had death of Rommel Abrogar, assuming that appellant
fallen short of the yardstick to satisfy the requirements of Intergames is found to have been negligent in the
due diligence as called for by and appropriate under the conduct of the Pop Cola marathon and such negligence
circumstances; that the accident had happened because was the proximate cause of the death of Rommel
of inadequate preparation and Intergames' failure to Abrogar. 
exercise due diligence;19 that the respondents could not
be excused from liability by hiding behind the waiver 3. Whether or not the appellants Abrogar are entitled to
executed by Rommel and the permission given to him by be compensated for the "loss of earning capacity" of
his parents because the waiver could only be effective their son Rommel.
for risks inherent in the marathon, such a:s stumbling,
heat stroke, heart attack during the race, severe 4. Whether or not the appellants Abrogar are entitled to
exhaustion and similar occurrences;20 that the liability of the actual, moral, and exemplary damages granted to
the respondents towards the participants and third them by the Trial Court.24
persons was solidary, because Cosmos, the sponsor of
the event, had been the principal mover of the event,
and, as such, had derived benefits from the marathon In its assailed judgment promulgated on March 10,
that in turn had carried responsibilities towards the 2004,25 the CA ruled as follows:
participants and the public; that the respondents'
agreement to free Cosmos from any liability had been an As to the first issue, this Court finds that appellant
agreement binding only between them, and did not bind Intergames was not negligent in organizing the said
third persons; and that Cosmos had a cause of action marathon.
against Intergames for whatever could be recovered by
the petitioners from Cosmos.21 Negligence is the omission to do something which a
reasonable man, guided upon those considerations
Decision of the CA which ordinarily regulate the conduct to human affairs,
would do, or doing something which a prudent and
All the parties appealed to the CA. reasonable man would not do.

16
The whole theory of negligence presuppose some Intergames had no choice. It had to comply with it or else
uniform standard of behavior which must be an external the said marathon would not be allowed at all.
and objective one, rather than the individual judgment
good or bad, of the particular actor; it must be, as far as The trial court erred in contending that appellant
possible, the same for all persons; and at the same time Intergames should have looked for alternative places in
make proper allowance for the risk apparent to the actor Metro Manila given the condition set by the Northern
for his capacity to meet it, and for the circumstances Police District, MPF, Quezon City; precisely because as
under which he must act.  Mr. Jose Castro has testified the said route was found to
be the best route after a careful study and consideration
The question as to what would constitute the conduct of of all the factors involved. Having conducted several
a prudent man in a given situation must of course be marathon events in said route, appellant Intergames as
always determined in the light of human experience and well as the volunteer groups and the other agencies
of the acts involved in the particular case. involved were in fact familiar with the said route. And
assuming that there was an alternative place suitable for
In the case at bar, the trial court erred in finding that the the said race, the question is would they be allowed to
appellant Intergames failed to satisfy the requirements of block off the said road from traffic?
due diligence in the conduct of the race.
Also, the trial court erred in stating that there was no
The trial court in its decision said that the accident in adequate number of marshals, police officers and
question could have been avoided if the route of the personnel to man the race so as to prevent injury to the
marathon was blocked off from the regular traffic, instead participants.
of allowing the runners to run together with the flow of
traffic. Thus, the said court considered the appellant The general rule is that the party who relies on
Intergames at fault for proceeding with the marathon negligence for his cause of action has the burden of
despite the fact that the Northern Police District, MPF, proving the existence of the same, otherwise his action
Quezon City did not allow the road to be blocked off from fails.
traffic.
Here, the appellants-spouses failed to prove that there
This Court finds that the standard of conduct used by the was inadequate number of marshals, police officers, and
trial court is not the ordinary conduct of a prudent man in personnel because they failed to prove what number is
such a given situation. According to the said court, the considered adequate.
only way to conduct a safe road race is to block off the
traffic for the duration of the event and direct the cars This court considers that seven (7) traffic operatives, five
and public utilities to take alternative routes in the (5) motorcycle policemen, fifteen (15) patrolmen
meantime that the marathon event is being held. Such deployed along the route, fifteen (15) boyscouts, twelve
standard is too high and is even inapplicable in the case (12) CA Ts, twenty (20) barangay tanods, three (3)
at bar because, there is no alternative route from IBP to ambulances and three (3) medical teams were sufficient
Don Mariano Marcos to Quezon City Hall. to stage a safe marathon.

The Civil Code provides that if the law or contract does Moreover, the failure of Mr. Jose R. Castro, Jr. to
not state the diligence which is to be observed in the produce records of the lists of those constituting the
performance of an obligation that which is expected of a volunteer help during the marathon is not fatal to the
good father of the family shall only be required. case considering that one of the volunteers, Victor
Accordingly, appellant Intergames is only bound to Landingin of the Citizens Traffic Action (CTA) testified in
exercise the degree of care that would be exercised by court that CTA fielded five units on June 15, 1980,
an ordinarily careful and prudent man in the same assigned as follows: (1) at the sphere head; (2) at the
position and circumstances and not that of the cautious finish line; (3) tail ender; (4) & (5) roving.
man of more than average prudence. Hence, appellant
Intergames is only expected to observe ordinary The trial court again erred in concluding that the
diligence and not extraordinary diligence. admission of P/Lt. Jesus Lipana, head of the traffic
policemen assigned at the marathon, that he showed up
In this case, the marathon was allowed by the Northern only at the finish line means that he did not bother to
Police District, MPF, Quezon City on the condition that check on his men and did not give them appropriate
the road should not be blocked off from traffic. Appellant instructions. P/Lt. Lipana in his testimony explained that
he did not need to be in the start of the race because he

17
had predesignated another capable police officer to start It appears that Rommel Abrogar, while running on Don
the race. Mariano Marcos A venue and after passing the
Philippine Atomic Energy Commission Building, was
In addition, this Court finds that the precautionary bumped by a jeepney which apparently was racing
measures and preparations adopted by appellant against a minibus and the two vehicles were trying to
Intergames were sufficient considering the crowd each other. In fact, a criminal case was filed
circumstances surrounding the case. against the jeepney driver by reason of his having killed
Rommel Abrogar.
Appellant Intergames, using its previous experiences in
conducting safe and successful road races, took all the This proves that the death of Rommel Abrogar was
necessary precautions and made all the preparations for caused by the negligence of the jeepney driver. Rommel
the race. The initial preparations included: determination Abrogar cannot be faulted because he was performing a
of the route to be taken; and an ocular inspection of the legal act; the marathon was conducted with the
same to see if it was well-paved, whether it had less permission and approval of all the city officials involved.
corners for easy communication and coordination, and He had the right to be there. Neither can the appellant
whether it was wide enough to accommodate runners Intergames be faulted, as the organizer of the said
and transportation. Appellant Intergames choose the marathon, because it was not negligent in conducting the
Don Mariano Marcos Avenue primarily because it was marathon.
well-paved; had wide lanes to accommodate runners
and vehicular traffic; had less corners thus facilitating Given the facts of this case, We believe that no amount
easy communication and coordination among the of precaution can prevent such an accident. Even if there
organizers and cooperating agencies; and was familiar were fences or barriers to separate the lanes for the
to the race organizers and operating agencies. The race runners and for the vehicles, it would not prevent such
covered a ten-kilometer course from the IBP lane to the an accident in the event that a negligent driver loses
Quezon City Hall Compound passing through the Don control of his vehicle. And even if the road was blocked
Mariano Marcos A venue, which constituted the main off from traffic, it would still not prevent such an accident,
stretch of the route. Appellant Intergames scheduled the if a jeepney driver on the other side of the road races
marathon on a Sunday morning, when traffic along the with another vehicle loses control of his wheel and as a
route was at its lightest. Permission was sought from the result hits a person on the other side of the road.
then Quezon City Mayor Adelina Rodriguez for the use Another way of saying this is: A defendant's tort cannot
of the Quezon City Hall Grandstand and the street be considered a legal cause of plaintiffs damage if that
fronting it as the finish line. Police assistance was also damage would have occurred just the same even though
obtained to control and supervise the traffic. The Quezon the defendant's tort had not been committed.
City Traffic Detachment took charge of traffic control by
assigning policemen to the traffic route. The particular This Court also finds the doctrine of assumption of risk
unit assigned during the race underwent extensive applicable in the case at bar. As explained by a well-
training and had been involved in past marathons, known authority on torts:
including marathons in highly crowded areas. The
Philippine Boy Scouts tasked to assist the police and "The general principle underlying the defense of
monitor the progress of the race; and Citizens Traffic assumption of risk is that a plaintiff who voluntarily
Action Group tasked with the monitoring of the race, assumes a risk of harm arising from the negligent or
which assigned five units consisting of ten operatives, to reckless conduct of the defendant cannot recover for
provide communication and assistance were likewise such harm. The defense may arise where a plaintiff, by
obtained. Finally, medical equipments and personnel contract or otherwise, expressly agrees to accept a risk
were also requested from Camp Aguinaldo, the or harm arising from the defendant's conduct, or where a
Philippine Red Cross and the Hospital ng Bagong plaintiff who fully understands a risk or harm caused by
Lipunan. the defendant's conduct, or by a condition created by the
defendant, voluntarily chooses to enter or remain, or to
Neither does this Court find the appellant Intergames' permit his property to enter or remain, within the area of
conduct of the marathon the proximate cause of the such risk, under circumstances manifesting his
death of Rommel Abrogar. Proximate cause has been willingness to accept the risk.
defined as that which, in natural and continuous
sequence, unbroken by any efficient intervening cause, xxxx
produces injury, and without which the result would not
have occurred.

18
"Assumption of the risk in its primary sense arises by In the decision of the trial court, it stated that the risk
assuming through contract, which may be implied, the mentioned in the waiver signed by Rommel Abrogar only
risk of a known danger. Its essence is venturousness. It involved risks such as stumbling, suffering heatstroke,
implies intentional exposure to a known danger; It heart attack and other similar risks. It did not consider
embraces a mental state of willingness; It pertains to the vehicular accident as one of the risks included in the said
preliminary conduct of getting into a dangerous waiver.
employment or relationship, it means voluntary incurring
the risk of an accident, which may or may not occur, and This Court does not agree. With respect to voluntary
which the person assuming the risk may be careful to participation in a sport, the doctrine of assumption of risk
avoid; and it defeats recovery because it is a previous applies to any facet of the activity inherent in it and to
abandonment of the right to complain if an accident any open and obvious condition of the place where it is
occurs. carried on. We believe that the waiver included vehicular
accidents for the simple reason that it was a road race
"Of course, if the defense is predicated upon an express run on public roads used by vehicles. Thus, it cannot be
agreement the agreement must be valid, and in the light denied that vehicular accidents are involved. It was not a
of this qualification the rule has been stated that a track race which is held on an oval and insulated from
plaintiff who, by contract or otherwise, expressly agreed vehicular traffic. In a road race, there is always the risk of
to accept a risk of harm arising from the defendant's runners being hit by motor vehicles while they train or
negligent or reckless conduct, cannot recover for such compete. That risk is inherent in the sport and known to
harm unless the agreement is invalid as contrary to runners. It is a risk they assume every time they
public policy. voluntarily engage in their sport.

xxxx Furthermore, where a person voluntarily participates in a


lawful game or contest, he assumes the ordinary risks of
"The defense of assumption of risk presupposes: (1) that such game or contest so as to preclude recovery from
the plaintiff had actual knowledge of the danger; (2) that the promoter or operator of the game or contest for injury
he understood and appreciated the risk from the danger; or death resulting therefrom. Proprietors of amusements
and (3) that he voluntarily exposed himself to such risk. x or of places where sports and games are played are not
xx insurers of safety of the public nor of their patrons.

"The term 'risk' as used in this connection applies to In McLeod Store v. Vinson 213 Ky 667, 281 SW 799
known dangers, and not to things from which danger (1926), it was held that a boy, seventeen years of age, of
may possibly flow. The risk referred to is the particular ordinary intelligence and physique, who entered a race
risk, or one of the risks, which the plaintiff accepted conducted by a department store, the purpose of which
within the context of the situation in which he placed was to secure guinea fowl which could be turned in for
himself and the question is whether the specific conduct cash prizes, had assumed the ordinary risks incident
or condition which caused the injury was such a risk." thereto and was barred from recovering against the
department store for injuries suffered when, within
catching distance, he stopped to catch a guinea, and
In this case, appellant Romulo Abrogar himself admitted
was tripped or stumbled and fell to the pavement, six or
that his son, Rommel Abrogar, surveyed the route of the
eight others falling upon him. The court further said: "In
marathon and even attended a briefing before the race.
this (the race) he was a voluntary participant. xxx The
Consequently, he was aware that the marathon would
anticipated danger was as obvious to him as it was to
pass through a national road and that the said road
appellant (the department store). While not an adult, he
would not be blocked off from traffic. And considering
was practically 17 years of age, of ordinary intelligence,
that he was already eighteen years of age, had
and perfectly able to determine the risks ordinarily
voluntarily participated in the marathon, with his parents'
incident to such games. An ordinary boy of that age is
consent, and was well aware of the traffic hazards along
practically as well advised as to the hazards of baseball,
the route, he thereby assumed all the risks of the race.
basketball, football, foot races and other games of skill
This is precisely why permission from the participant's
and endurance as is an adult
parents, submission of a medical certificate and a waiver
of all rights and causes of action arising from the
participation in the marathon which the participant or his x x x." 
heirs may have against appellant Intergames were
required as conditions in joining the marathon. In the case at bar, the "1st Pop Cola Junior Marathon"
held on June 15, 1980 was a race the winner of which
was to represent the country in the annual Spirit of
19
Pheidippides Marathon Classic in Greece, if he equals or POP COLA JUNIOR MARATHON', or for any damages
breaks the 29-minute mark for the 10-km. race. Thus, to the property or properties of third parties, which may
Rommel Abrogar having voluntarily participated in the likewise arise in the course of the race.
race, with his parents' consent, assumed all the risks of
the race.  From the foregoing, it is crystal clear that the role of the
appellant Cosmos was limited to providing financial
Anent the second issue, this Court finds that appellant assistance in the form of sponsorship. Appellant
Cosmos must also be absolved from any liability in the Cosmos' sponsorship was merely in pursuance to the
instant case. company's commitment for spo1is development of the
youth as well as for advertising purposes. The use of the
This Court finds that the trial court erred in holding name Cosmos was done for advertising purposes only; it
appellant Cosmos liable for being the principal mover did not mean that it was an organizer of the said
and resultant beneficiary of the event. marathon. As pointed out by Intergames' President, Jose
Castro Jr., appellant Cosmos did not even have the right
to suggest the location and the number of runners.
In its decision it said that in view of the fact that appellant
Cosmos will be deriving certain benefits from the
marathon event, it has the responsibility to ensure the To hold a defendant liable for torts, it must be clearly
safety of all the participants and the public. It further said shown that he is the proximate cause of the harm done
that the stipulations in the contract entered into by the to the plaintiff. The nexus or connection of the cause and
two appellants, Cosmos and Intergames, relieving the effect, between a negligent act and the damage done,
former from any liability does not bind third persons. must be established by competent evidence.

This Court does not agree with the reasoning of the trial In this case, appellant Cosmos was not negligent in
court. The sponsorship contract entered between entering into a contract with the appellant Intergames
appellant Cosmos and appellant Intergames specifically considering that the record of the latter was clean and
states that: that it has conducted at least thirty (30) road races.

1. COSMOS BOTTLING CORPORATION shall pay Also there is no direct or immediate causal connection
INTERGAMES the amount of FIFTY FIVE THOUSAND between the financial sponsorship and the death of
PESOS (₱55,000.00) representing full sponsorship fee Rommel Abrogar. The singular act of providing financial
and in consideration thereof, INTERGAMES shall assistance without participating in any manner in the
organize and stage a marathon race to be called '1st conduct of the marathon cannot be palmed off as such
POP COLA JUNIOR MARATHON. proximate cause. In fact, the appellant spouses never
relied on any representation that Cosmos organized the
race. It was not even a factor considered by the
xxxx
appellants-spouses in allowing their son to join said
marathon.
3. INTER GAMES shall draw up all the rules of the
marathon race, eligibility requirements of participants as
In view of the fact that both defendants are not liable for
well as provide all the staff required in the organization
the death of Rommel Abrogar, appellants-spouses are
and actual staging of the race. It is understood that all
not entitled to actual, moral, exemplary damages as well
said staff shall be considered under the direct employ of
as for the "loss of earning capacity" of their son. The
INTERGAMES which shall have full control over them.
third and fourth issues are thus moot and academic.
xxxx
UPON THE VIEW WE TAKE OF THIS CASE,
THUS, the judgment appealed from must be, as it
5. INTERGAMES shall secure all the necessary permits, hereby is, REVERSED and SET ASIDE, and another
clearances, traffic and police assistance in all the areas entered DISMISSING the complaint a quo. The
covered by the entire route of the '1st POP COLA appellants shall bear their respective costs.
JUNIOR MARATHON.
SO ORDERED.26
12. INTERGAMES shall hold COSMOS BOTTLING
CORPORATION, completely free and harmless from any
Issues
claim or action for liability for any injuries or bodily harm
which may be sustained by any of the entries in the '1st

20
In this appeal, the petitioners submit that the CA gravely The petitioners contend that Intergames was negligent;
erred: that Cosmos as the sponsor and Intergames as the
organizer of the marathon both had the obligation to
A. provide a reasonably safe place for the conduct of the
race byblocking the route of the race from vehicular
traffic and by providing adequate manpower and
x x x in reversing the RTC Decision, (and) in holding that
personnel to ensure the safety of the participants; and
respondent Intergames was not negligent considering
that Intergames had foreseen the harm posed by the
that:
situation but had not exercised the diligence of a good
father of a family to avoid the risk; 28 hence, for such
1. Respondent Intergames failed to exercise the omission, Intergames was negligent.29
diligence of a good father of the family in the conduct of
the marathon in that it did not block off from traffic the
Refuting, Cosmos and Intergames submit that the latter
marathon route; and
as the organizer was not negligent because it had
undertaken all the precautionary measures to ensure the
2. Respondent Intergames' preparations for the race, safety of the race; and that there was no duty on the part
including the number of marshal during the marathon, of the latter as the organizer to keep a racecourse "free
were glaringly inadequate to prevent the happening of and clear from reasonably avoidable elements that
the injury to its participants. would [occasion] or have the probable tendency, to
occasion injury."30
B.
The issue of whether one or both defendants were
x x x in reversing the RTC Decision, (and) in holding that negligent is a mixed issue of fact and law. Does this not
the doctrine of assumption of risk finds application to the restrict the Court against reviewing the records in this
case at bar even though getting hit or run over by a appeal on certiorari  in order to settle the issue?
vehicle is not an inherent risk in a marathon race. Even
assuming arguendo that deceased Abrogar made such The Court can proceed to review the factual findings of
waiver as claimed, still there can be no valid waiver of the CA as an exception to the general rule that it should
one's right to life and limb for being against public policy. not review issues of fact on appeal on certiorari. We
have recognized exceptions to the rule that the findings
C. of fact of the CA are conclusive and binding in the
following instances: (1) when the findings are grounded
x x x in reversing the RTC Decision, (and) in absolving entirely on speculation, surmises or conjectures; (2)
respondent Cosmos from liability to petitioners on the when the inference made is manifestly mistaken, absurd
sole ground that respondent Cosmos' contract with or impossible; (3) when there is grave abuse of
respondent Intergames contained a stipulation discretion; (4) when the judgment is based on a
exempting the former from liability. misapprehension of facts; (5) when the findings of facts
are conflicting; (6) when in making its findings the CA
D. went beyond the issues of the case, or its findings are
contrary to the admissions of both the appellant and the
appellee; (7) when the findings are contrary to the trial
x x x m reversing the RTC Decision and consequently
court; (8) when the findings are conclusions without
holding respondents free from liability, (and) in not
citation of specific evidence on which they are based; (9)
awarding petitioners with actual, moral and exemplary
when the facts set forth in the petition as well as in the
damages for the death of their child, Rommel Abrogar. 27
petitioner's main and reply briefs are not disputed by the
respondent; (10) when the findings of fact are premised
Ruling of the Court on the supposed absence of evidence and contradicted
by the evidence on record; and (11) when the CA
The appeal is partly meritorious. manifestly overlooked certain relevant facts not disputed
by the parties, which, if properly considered, would justify
I a different conclusion.31 Considering that the CA arrived
at factual findings contrary to those of the trial court, our
Review of factual issues is allowed because of review of the records in this appeal should have to be
the conflict between the findings of fact made.
by the RTC and the CA on the issue of negligence

21
Negligence is the failure to observe for the protection of A careful review of the evidence presented, particularly
the interests of another person that degree of care, the testimonies of the relevant witnesses, in accordance
precaution, and vigilance which the circumstances justly with the foregoing guidelines reasonably leads to the
demand, whereby such other person suffers conclusion that the safety and precautionary measures
injury.32Under Article 1173 of the Civil Code,  it consists undertaken by Intergames were short of the diligence
of the "omission of that diligence which is required by the demanded by the circumstances of persons, time and
nature of the obligation and corresponds with the place under consideration. Hence, Intergames as the
circumstances of the person, of the time and of the organizer was guilty of negligence.
place."33 The Civil Code makes liability for negligence
clear under Article 2176,34 and Article 20.35 The race organized by Intergames was a junior
marathon participated in by young persons aged 14 to
To determine the existence of negligence, the following 18 years. It was plotted to cover a distance of 10
time-honored test has been set in Picart v. Smith:36 kilometers, starting from the IBP Lane,38 then going
towards the Batasang Pambansa, and on to the circular
The test by which to determine the existence of route towards the Don Mariano Marcos Highway, 39 and
negligence in a particular case may be stated as follows: then all the way back to the Quezon City Hall compound
Did the defendant in doing the alleged negligent act use where the finish line had been set.40 In staging the event,
that reasonable care and caution which an ordinarily Intergames had no employees of its own to man the
prudent person would have used in the same situation? race,41 and relied only on the "cooperating agencies" and
If not, then he is guilty of negligence. The law here in volunteers who had worked with it in previous
effect adopts the standard supposed to be supplied by races.42 The cooperating agencies included the Quezon
the imaginary conduct of the discreet paterfamilias of the City police, barangay tanods, volunteers from the Boy
Roman law. The existence of negligence in a given case Scouts of the Philippines, the Philippine National Red
is not determined by reference to the personal judgment Cross, the Citizens Traffic Action Group, and the medical
of the actor in the situation before him. The law teams of doctors and nurses coming from the Office of
considers what would be reckless, blameworthy, or the Surgeon General and the Ospital ng Bagong
negligent in the man of ordinary intelligence and Lipunan.43 According to Jose R. Castro, Jr., the
prudence and determines liability by that. President of Intergames, the preparations for the event
included conducting an ocular inspection of the route of
the race,44 sending out letters to the various cooperating
The question as to what would constitute the conduct of
agencies,45 securing permits from proper
a prudent man in a given situation must of course be
authorities,46 putting up directional signs,47 and setting up
always determined in the light of human experience and
the water stations.48
in view of the facts involved in the particular case.
Abstract speculation cannot here be of much value but
this much can be profitably said: Reasonable men We consider the "safeguards" employed and adopted by
govern their conduct by the circumstances which are Intergames not adequate to meet the requirement of due
before them or known to them. They are not, and are not diligence.
supposed to be, omniscient of the future. Hence they
can be expected to take care only when there is For one, the police authorities specifically prohibited
something before them to suggest or warn of danger. Intergames from blocking Don Mariano Marcos Highway
Could a prudent man, in the case under consideration, in order not to impair road accessibility to the residential
foresee harm as a result of the course actually pursued? villages located beyond the IBP Lanc.49
If so, it was the duty of the actor to take precautions to
guard against that harm. Reasonable foresight of harm, However, contrary to the findings of the
followed by the ignoring of the suggestion born of this CA,50 Intergames had a choice on where to stage the
prevision, is always necessary before negligence can be marathon, considering its admission of the sole
held to exist. Stated in these terms, the proper criterion responsibility for the conduct of the event, including the
for determining the existence of negligence in a given choice of location.
case is this: Conduct is said to be negligent when a
prudent man in the position of the tortfeasor would have Moreover, the CA had no basis for holding that "the said
foreseen that an effect harmful to another was route was found to be the best route after a careful study
sufficiently probable to warrant his foregoing the conduct and consideration of all the factors involved." 51 Castro,
or guarding against its consequences. 37 (bold Jr. himself attested that the route had been the best one
underscoring supplied for emphasis) only within the vicinity of the Batasan Pambansa, to wit:

22
COURT most of the races in Manila or elsewhere are being run in
accordance with the flow of the traffic.
q Was there any specific reason from ... Was there any
specific reason why you used this route from Batasan to xxxx
City Hall? Was there any special reason?
ATTY. VINLUAN
a We have, your Honor, conducted for example the Milo
Marathon in that area in the Batasan Pambansa and we q Following the observation of the Court, considering the
found it to be relatively safer than any other areas within local condition, you will agree with me the risks here are
the vicinity. As a matter of fact, we had more runners in greater than in the United States where drivers on the
the Milo Marathon at that time and nothing happened, whole follow traffic rules?
your Honor.52
a That is correct.
The chosen route (IBP Lane, on to Don Mariano Marcos
Highway, and then to Quezon City Hall) was not the only q And because of that fact, it is with all the more reason
route appropriate for the marathon. In fact, Intergames that you should take all necessary precautions to insure
came under no obligation to use such route especially the safety of the runners?
considering that the participants, who were young and
inexperienced runners, would be running alongside
moving vehicles. a That is correct.54

Intergames further conceded that the marathon could xxxx


have been staged on a blocked-off route like Roxas
Boulevard in Manila where runners could run against the COURT:
flow of vehicular traffic.53 Castro, Jr. stated in that regard:
xxxx
COURT TO WITNESS
Q In your case in all the marathons that you had
q What law are you talking about when you say I cannot managed, how many cases have you encountered
violate the law? where the routes are blocked off for vehicular traffic?

a The police authority, your Honor, would not grant us A These are the International Marathon, Philippines
permit because that is one of the conditions that if we Third World Marathon and the Milo Marathon. We are
are to conduct a race we should run the race in blocking them to a certain length of time.
accordance with the flow of traffic.
Q What was the purpose of blocking the routes? Is it for
q Did you not inform the police this is in accordance with the safety of the runners or just a matter of
the standard safety measures for a marathon race? convenience?

a I believed we argued along that line but but (sic) again, A In blocking off the route, Your Honor, it is light easier
if we insist the police again would not grant us any for the runners to run without impediments to be
permit like ... except in the case of Roxas Boulevard rendered by the people or by vehicles and at the same
when it is normally closed from 8 a.m. when you can time it would be also advantageous if the road will be
run against the flow of traffic. blocked off for vehicle traffic permitted to us by the traffic
authorities.
q You were aware for a runner to run on the same route
of the traffic would be risky because he would not know Q So, in this case, you actually requested for the traffic
what is coming behind him? authorities to block off the route?

a I believed we talked of the risk, your Honor when the A As far as I remember we asked Sgt. Pascual to block
risk has been minimized to a certain level. Yes, there is off the route but considering that it is the main artery to
greater risk when you run with the traffic than when you Fairview Village, it would not be possible to block off the
run against the traffic to a certain level, it is correct but route since it will cause a lot of inconvenience for the
other people in those areas and jeepney drivers.

23
Q In other words, if you have your way you would have ATTY. LOMBOS:
opted to block off the route.
xxxx
A Yes, Your Honor.
Q You also said that if you block off one side of the road,
Q But the fact is that the people did not agree. it is possible that it would be more convenient to hold the
race in that matter. Will you tell the Honorable Court if it
A Yes, Your Honor, and it is stated in the permit given to is possible also to hold a race safely if the road is not
us.55 blocked off?

Based on the foregoing testimony of Castro, Jr., A Yes, sir.


Intergames had full awareness of the higher risks
involved in staging the race alongside running vehicles, Q How is it done.
and had the option to hold the race in a route where
such risks could be minimized, if not eliminated. But it A You can still run a race safely even if it is partially
did not heed the danger already foreseen, if not blocked off as long as you have the necessary
expected, and went ahead with staging the race along cooperation with the police authorities, and the police
the plotted route on Don Mariano Marcos Highway on assigned along the route of the race and the police
the basis of its supposedly familiarity with the route. assigned would be there, this will contribute the safety of
Such familiarity of the organizer with the route and the the participants, and also the vehicular division, as long
fact that previous races had been conducted therein as there are substantial publicities in the newspapers,
without any untoward incident56 were not in themselves normally they will take the precautions in the use of the
sufficient safeguards. The standards for avoidance of particular route of the race. 
injury through negligence further required Intergames to
establish that it did take adequate measures to avert the Q Let me clarify this. Did you say that it is possible to
foreseen danger, but it failed to do so. hold a marathon safely if you have this traffic assistance
or coordination even if the route is blocked or not
Another failing on the part of Intergames was the patent blocked?
inadequacy of the personnel to man the route. As borne
by the records, Intergames had no personnel of its own A It is preferable to have the route blocked but in some
for that purpose, and relied exclusively on the assistance cases, it would be impossible for the portions of the road
of volunteers, that is, "seven (7) traffic operatives, five to be blocked totally. The route of the race could still be
(5) motorcycle policemen, fifteen (15) patrolmen safe for runners if a proper coordination or the agencies
deployed along the route, fifteen (15) boy scouts, twelve are notified especially police detailees to man the
(12) CATs, twenty (20) barangay tanods, three (3) particular stage.58
ambulances and three (3) medical teams"57 to ensure the
safety of the young runners who would be running
alongside moving vehicular traffic, to make the event Sadly, Intergames' own evidence did not establish the
safe and well coordinated. conduct of proper coordination and instruction. Castro,
Jr. described the action plan adopted by Intergames in
the preparation for the race, as follows:
Although the party relying on negligence as his cause of
action had the burden of proving the existence of the
same, Intergames' coordination and supervision of the COURT
personnel sourced from the cooperating agencies did not
satisfy the diligence required by the relevant a Did you have any rehearsal let us say the race was
circumstances. In this regard, it can be pointed out that conducted on June 15, now before June 15 you call a
the number of deployed personnel, albeit sufficient to meeting of all these runners so you can have more or
stage the marathon, did not per se ensure the safe less a map-up and you would indicate or who will be
conduct of the race without proof that such deployed stationed in their places etc. Did you have such a
volunteers had been properly coordinated and instructed rehearsal?
on their tasks.
WITNESS
That the proper coordination and instruction were crucial
elements for the safe conduct of the race was well a It is not being done, your honor, but you have to
known to Intergames. Castro, Jr. stated as much, to wit: specify them. You meet with the group and you tell them
24
that you wanted them to be placed in their particular a I can only remember his name ... his family name is
areas which we pointed out to them for example in the Esguerra.
case of the Barangay Tanod, I specifically assigned
them in the areas and we sat down and we met. q How about with the Tanods?

COURT a With the Tanods his name is Pedring Serrano.

q Did you have any action, plan or brochure which would q And with the Boys Scouts? (sic)
indicate the assignment of each of the participating
group? a And with the Boys Scouts of the Phils. (sic) it is Mr.
Greg Panelo.
WITNESS
COURT
a Normally, sir, many of the races don't have that except
when they called them to meeting either as a whole q When did you last meet rather how many times did you
group or the entire cooperating agency or meet them per meet with Esguerra before the marathon on June 15?
group.
WITNESS
COURT
a The Citizens Traffic Action Group, your honor, had
q Did you have a check list of the activities that would been with me m previous races.
have to be entered before the actual marathon some
kind of system where you will indicate this particular
activity has to be checked etc. You did not have that? COURT

WITNESS q I am asking you a specific question. I am not interested


in the Citizen Traffic Action Group. The marathon was on
June 15, did you meet with him on June 14, June 13 or
q Are you asking, your honor, as a race director of I will June 12?
check this because if I do that, I won't have a race
because that is not being done by any race director
anywhere in the world? a We met once, your honor, I cannot remember the date.

COURT q You don't recall how many days before?

I am interested in your planning activities. a I cannot recall at the moment.

q In other words, what planning activities did you perform q How about with Mr. Serrano, how many times did you
before the actual marathon? meet with him before the race?

a The planning activities we had, your honor, was to a If my mind does not fail me, your honor, I met him
coordinate with the different agencies involved informing twice because he lives just within our area and we
them where they would be more or less placed. always see each other.

COURT q How about with Panelo, how many times did you meet
him?
q Let us go to ... Who was supposed to be coordinating
with you as to the citizens action group who was your ... a With Mr. Panelo, I did not meet with them, your honor.
you were referring to a person who was supposed to be
manning these people and who was the person whom q Was there an occasion where before the race you met
you coordinate with the Traffic Action Group? with these three people together since you did not meet
with Panelo anytime? Was there anytime where you met
WITNESS with Serrano and Esguerra together?

WITNESS
25
a No, your honor. COURT

COURT Proceed.

g When you met once with Esguerra, where did you ATTY. VINLUAN
meet? What place?
q Following the question of the Court Mr. Castro, did you
a I cannot recall at the moment, your honor, since it was meet with Lt. Depano of the Police Department who
already been almost six years ago. were supposed to supervise the police officers assigned
to help during the race?
g How about Serrano, where did you meet him?
a I did not meet with him, sir.
a We met in my place.
q You did not meet with him?
q From your house? He went in your house?
a I did not meet with him.
a Yes, your honor.
q In fact, ever before or during the race you had no
q So you did not have let us say a ... you don't have occasion to talk to Lt. Depano. Is that correct?
records of your meetings with these people?
a That is correct, sir.
WITNESS
ATTY. VINLUAN
a With the Citizens Traffic Action, your honor?
Based on the question of the Court and your answer to
COURT the question of the Court, are you trying to say that this
planning before any race of all these groups who have
committed to help in the race, this is not done in any part
a Yes.
of the world?
WITNESS
WITNESS
a I don't have, your honor.
a In the latter years when your race became bigger and
bigger, this is being done now slowly.
COURT
ATTY. VINLUAN
q Because you are familiar, I was just thinking this is an
activity which requires planning etc., what I was thinking
q But for this particular race you will admit that you failed
when you said this was never done in any part of the
to do it when you have to coordinate and even have a
world but all activities it has to be planned. There must
dry run of the race you failed to do all of that in this
be some planning, now are you saying that in this
particular race, yes or no?
particular case you had no written plan or check list of
activities what activities have to be implemented on a
certain point and time, who are the persons whom you a Because there was ...
must meet in a certain point and time.
COURT
WITNESS
It was already answered by him when I asked him. The
a Normally, we did not have that, your honor, except the Court has ... Everybody has a copy how of this time
check list of all the things that should be ready at a planner. Any activity or even meeting a girlfriend or most
particular time prior to the race and the people to be people plan.
involved and we have a check list to see to it that
everything would be in order before the start of the race. A TTY. F .M. LOMBOS

26
If your honor please, before we proceed ... the ambulances, we have the Boy Scouts, we have the
CT A, we have the police, so it was very obvious that
WITNESS there was a plan of action but not written because I know
pretty well exactly what to do. I was dealing with people
who have been doing this for a long period of time. 60
In the latter years, your honor, when your race became
bigger and bigger, this is being done now slowly.
While the level of trust Intergames had on its volunteers
was admirable, the coordination among the cooperating
q For this particular race you will admit that you failed to
agencies was predicated on circumstances unilaterally
do it?
assumed by Intergames. It was obvious that Intergames'
inaction had been impelled by its belief that it did not
a Because there was no need, sir.59 need any action plan because it had been dealing with
people who had been manning similar races for a long
Probably sensing that he might have thereby period of time.
contradicted himself, Castro, Jr. clarified on re-direct
examination: The evidence presented undoubtedly established that
Intergames' notion of coordination only involved
ATTY. LOMBOS informing the cooperating agencies of the date of the
race, the starting and ending points of the route, and the
Q Now, you also responded to a question during the places along the route to man. Intergames did not
same hearing and this appears on page 26 of the conduct any general assembly with all of them, being
transcript that you did not hold any rehearsal or dry run content with holding a few sporadic meetings with the
for this particular marathon. Could you tell the Court why leaders of the coordinating agencies. It held no briefings
you did not hold any such rehearsal or dry run? of any kind on the actual duties to be performed by each
group of volunteers prior to the race. It did not instruct
A Because I believe there was no need for us to do that the volunteers on how to minimize, if not avert, the risks
since we have been doing this for many years and we of danger in manning the race, despite such being
have been the same people, same organization with us precisely why their assistance had been obtained in the
for so many years conducting several races including first place.
some races in that area consisting of longer distances
and consisting of more runners, a lot more runners in Intergames had no right to assume that the volunteers
that areay (sic) so these people, they know exactly what had already been aware of what exactly they would be
to do and there was no need for us to have a rehearsal. I doing during the race. It had the responsibility and duty
believe this rehearsal would only be applicable if I am to give to them the proper instructions despite their
new and these people are new then, we have to experience from the past races it had organized
rehearse. considering that the particular race related to runners of
a different level of experience, and involved different
ATTY. LOMBOS weather and environmental conditions, and traffic
situations. It should have remembered that the personnel
manning the race were not its own employees paid to
q You also stated Mr. Castro that you did not have any
perform their tasks, but volunteers whose nature of work
action plan or brochure which you would indicate, an
was remotely associated with the safe conduct of road
assignment of each of the participating group as to what
races. Verily, that the volunteers showed up and
to do during the race. Will you please explain what you
assumed their proper places or that they were sufficient
meant when you said you have no action plan or
in number was not really enough. It is worthy to stress
brochure?
that proper coordination in the context of the event did
not consist in the mere presence of the volunteers, but
WITNESS included making sure that they had been properly
instructed on their duties and tasks in order to ensure the
a What I mean of action plan, I did not have any written safety of the young runners.
action plan but I was fully aware of what to do. I mean,
those people did not just go there out of nowhere. It is relevant to note that the participants of the 1st Pop
Obviously, there was an action on my part because I Cola Junior Marathon were mostly minors aged 14 to 18
have to communicate with them previously and to tell years joining a race of that kind for the first time. The
them exactly what the race is all about; where to start; combined factors of their youth, eagerness and
where it would end, and that is the reason why we have inexperience ought to have put a reasonably prudent
27
organizer on higher guard as to their safety and security Did the negligence of Intergames give rise to its liability
needs during the race, especially considering for the death of ommel notwithstanding the negligence of
Intergames' awareness of the risks already foreseen and the jeepney driver?
of other risks already known to it as of similar events in
the past organizer. There was no question at all that a In order for liability from negligence to arise, there must
higher degree of diligence was required given that be not only proof of damage and negligence, but also
practically all of the participants were children or minors proof that the damage was the consequence of the
like Rommel; and that the law imposes a duty of care negligence. The Court has said in Vda. de Gregorio v.
towards children and minors even if ordinarily there was Go Chong Bing:64
no such duty under the same circumstances had the
persons involved been adults of sufficient discretion. 61 In x x x Negligence as a source of obligation both under the
that respect, Intergames did not observe the degree of civil law and in American cases was carefully considered
care necessary as the organizer, rendering it liable for and it was held:
negligence. As the Court has emphasized in Corliss v.
The Manila Railroad Company,62  where the danger is
great, a high degree of care is necessary, and the failure We agree with counsel for appellant that under the Civil
to observe it is a want of ordinary care under the Code, as under the generally accepted doctrine in the
circumstances. 63 United States, the plaintiff in an action such as that
under consideration, in order to establish his right to a
recovery, must establish by competent evidence:
The circumstances of the persons, time and place
required far more than what Intergames undertook in
staging the race. Due diligence would have made a (1) Damages to the plaintiff.
reasonably prudent organizer of the race participated in
by young, inexperienced or beginner runners to conduct (2) Negligence by act or omission of which defendant
the race in a route suitably blocked off from vehicular personally or some person for whose acts it must
traffic for the safety and security not only of the respond, was guilty.
participants but the motoring public as well. Since the
marathon would be run alongside moving vehicular (3) The connection of cause and effect between the
traffic, at the very least, Intergames ought to have seen negligence and the damage." (Taylor vs. Manila Electric
to the constant and closer coordination among the Railroad and Light Co., supra, p. 15.)
personnel manning the route to prevent the foreseen
risks from befalling the participants. But this it sadly In accordance with the decision of the Supreme Court of
failed to do. Spain, in order that a person may be held guilty for
damage through negligence, it is necessary that there be
II an act or omission on the part of the person who is to be
charged with the liability and that damage is produced by
The negligence of Intergames as the organizer the said act or omission.65 (Emphasis supplied)
was the proximate cause of the death of Rommel
We hold that the negligence of Intergames was the
As earlier mentioned, the CA found that Rommel, while proximate cause despite the intervening negligence of
running the marathon on Don Mariano Marcos A venue the jeepney driver.
and after passing the Philippine Atomic Energy
Commission Building, was bumped by a passenger Proximate cause is "that which, in natural and
jeepney that was racing with a minibus and two other continuous sequence, unbroken by any new cause,
vehicles as if trying to crowd each other out. As such, the produces an event, and without which the event would
death of Rommel was caused by the negligence of the not have occurred."66 In Vda. de Bataclan, et
jeepney driver. al. v. Medina,67  the Court, borrowing from American
Jurisprudence, has more extensively defined proximate
Intergames staunchly insists that it was not liable, cause  thusly:
maintaining that even assuming arguendo  that it was
negligent, the negligence of the jeepney driver was the "* * * 'that cause, which, in natural and continuous
proximate cause of the death of Rommel; hence, it sequence, unbroken by any efficient intervening cause,
should not be held liable. produces the injury and without which the result would
not have occurred.' And more comprehensively, 'the
proximate legal cause is that acting first and producing

28
the injury, either immediately or by setting other events intervening events, but by their character and the natural
in motion, all constituting a natural and continuous chain connection between the original act or omission and the
of events, each having a close causal connection with its injurious consequences. When the intervening cause is
immediate predecessor, the final event in the chain set in operation by the original negligence, such
immediately effecting the injury as a natural and negligence is still the proximate cause; x x x If the party
probable result of the cause which first acted, under guilty of the first act of negligence might have anticipated
such circumstances that the person responsible for the the intervening cause, the connection is not broken; x x
first event should, as an ordinarily prudent and intelligent x. Any number of causes and effects may intervene, and
person, have reasonable ground to expect at the if they arc such as might with reasonable diligence have
moment of his act or default that an injury to some been foreseen, the last result is to be considered as the
person might probably result therefrom."68 proximate result. But whenever a new cause intervenes,
which is not a consequence of the first wrongful cause,
To be considered the proximate cause of the injury, the which is not under control of the wrongdoer, which could
negligence need not be the event closest in time to the not have been foreseen by the exercise of reasonable
injury; a cause is still proximate, although farther in time diligence, and except for which the final injurious
in relation to the injury, if the happening of it set other consequence could not have happened, then such
foreseeable events into motion resulting ultimately in the injurious consequence must be deemed too remote; x x
damage.69 According to an authority on civil law: 70"A x.72 (bold underscoring supplied for emphasis)
prior and remote cause cannot be made the basis of an
action, if such remote cause did nothing more than An examination of the records in accordance with the
furnish the condition or give rise to the occasion by foregoing concepts supports the conclusions that the
which the injury was made possible, if there intervened negligence of Intergames was the proximate cause of
between such prior or remote cause and the injury a the death of Rommel; and that the negligence of the
distinct, successive, unrelated and efficient cause, even jeepney driver was not an efficient intervening cause.
though such injury would not have happened but for
such condition or occasion. If no damage exists in the First of all, Intergames' negligence in not conducting the
condition except because of the independent cause, race in a road blocked off from vehicular traffic, and in
such condition was not the proximate cause. And if an not properly coordinating the volunteer personnel
independent negligent act or defective condition sets manning the marathon route effectively set the stage for
into operation the circumstances which result in injury the injury complained of. The submission that
because of the prior defective condition, such act or Intergames had previously conducted numerous safe
condition is the proximate cause." races did not persuasively demonstrate that it had
exercised due diligence because, as the trial court
Bouvier adds: pointedly observed, "[t]hey were only lucky that no
accident occurred during the previous marathon races
In many cases important questions arise as to which, in but still the danger was there."73
the chain of acts tending to the production of a given
state of things, is to be considered the responsible Secondly, injury to the participants arising from an
cause. It is not merely distance of place or of causation unfortunate vehicular accident on the route was an event
that renders a cause remote. The cause nearest in the known to and foreseeable by Intergames, which could
order of causation, without any efficient concurring cause then have been avoided if only Intergames had acted
to produce the result, may be considered the direct with due diligence by undertaking the race on a blocked-
cause. In the course of decisions of cases in which it is off road, and if only Intergames had enforced and
necessary to determine which of several causes is so far adopted more efficient supervision of the race through its
responsible for the happening of the act or injury volunteers.
complained of, what is known as the doctrine of
proximate cause is constantly resorted to in order to And, thirdly, the negligence of the jeepney driver, albeit
ascertain whether the act, omission, or negligence of the an intervening cause, was not efficient enough to break
person whom it is sought to hold liable was in law and in the chain of connection between the negligence of
fact responsible for the result which is the foundation of Intergames and the injurious consequence suffered by
the action.71 Rommel. An intervening cause, to be considered
efficient, must be "one not produced by a wrongful act or
xxxx omission, but independent of it, and adequate to bring
the injurious results. Any cause intervening between the
The question of proximate cause is said to be first wrongful cause and the final injury which might
determined, not by the existence or non-existence of reasonably have been foreseen or anticipated by the
29
original wrongdoer is not such an efficient intervening Furthermore, where a person voluntarily participates in a
cause as will relieve the original wrong of its character lawful game or contest, he assumes the ordinary risks of
as the proximate cause of the final injury."74 such game or contest so as to preclude recovery from
the promoter or operator of the game or contest for injury
In fine, it was the duty of Intergames to guard Rommel or death resulting therefrom. Proprietors of amusements
against the foreseen risk, but it failed to do so. or of places where sports and games are played are not
insurers of safety of the public nor of their patrons.
III
In Mc Leod Store v. Vinson 213 Ky 667, 281 SW 799
(1926), it was held that a boy, seventeen years of age, of
The doctrine of assumption of risk
ordinary intelligence and physique, who entered a race
had no application to Rommel
conducted by a department store, the purpose of which
was to secure guinea fowl which could be turned in for
Unlike the R TC, the CA ruled that the doctrine of cash prizes, had assumed the ordinary risks incident
assumption of risk applied herein; hence, it declared thereto and was barred from recovering against the
Intergames and Cosmos not liable. The CA rendered the department store for injuries suffered when, within
following rationalization to buttress its ruling, to wit: catching distance, he stopped to catch a guinea, and
was tripped or stumbled and fell to the pavement, six or
In this case, appellant Romulo Abrogar himself admitted eight others falling upon him. The comi further said: "In
that his son, Rommel Abrogar, surveyed the route of the this (the race) he was a voluntary participant. x x x The
marathon and even attended a briefing before the race. anticipated danger was as obvious to him as it was to
Consequently, he was aware that the marathon would appellant (the department store). While not an adult, he
pass through a national road and that the said road was practically 17 years of age, of ordinary intelligence,
would not be blocked off from traffic. And considering and perfectly able to determine the risks ordinarily
that he was already eighteen years of age, had incident to such games. An ordinary boy of that age is
voluntarily participated in the marathon, with his parents' practically as well advised as to the hazards of baseball,
consent, and was well aware of the traffic hazards along basketball, football, foot races and other games of skill
the route, he thereby assumed all the risks of the race. and endurance as is an adult
This is precisely why permission from the participant's
parents, submission of a medical certificate and a waiver x x x."
of all rights and causes of action arising from the
participation in the marathon which the participant or his
In the case at bar, the "1st Pop Cola Junior Marathon"
heirs may have against appellant Intergames were
held on June 15, 1980 was a race the winner of which
required as conditions in joining the marathon.
was to represent the country in the annual Spirit of
Pheidippides Marathon Classic in Greece, if he equals or
In the decision of the trial court, it stated that the risk breaks the 29-minute mark for the 19-km. race. Thus,
mentioned in the waiver signed by Rommel Abrogar only Rommel Abrogar having voluntarily participated in the
involved risks such as stumbling, suffering heatstroke, race, with his parents' consent, assumed all the risks of
heart attack and other similar risks. It did not consider the race.75
vehicular accident as one of the risks included in the said
waiver.
The doctrine of assumption of risk means that one who
voluntarily exposes himself to an obvious, known and
This Court does not agree. With respect to voluntary appreciated danger assumes the risk of injury that may
participation in a sport, the doctrine of assumption of risk result therefrom.76 It rests on the fact that the person
applies to any facet of the activity inherent in it and to injured has consented  to relieve the defendant of an
any open and obvious condition of the place where it is obligation of conduct toward him and to take his chance
carried on. We believe that the waiver included vehicular of injury from a known risk, and whether the former has
accidents for the simple reason that it was a road race exercised proper caution or not is immaterial. 77 In other
run on public roads used by vehicles. Thus, it cannot be words, it is based on voluntary consent, express or
denied that vehicular accidents are involved. It was not a implied, to accept danger of a known and appreciated
track race which is held on an oval and insulated from risk; it may sometimes include acceptance of risk arising
vehicular traffic. In a road race, there is always the risk of from the defendant's negligence, but one does not
runners being hit by motor vehicles while they train or ordinarily assume risk of any negligence which he does
compete. That risk is inherent in the sport and known to not know and appreciate.78 As a defense in negligence
runners. It is a risk they assume every time they cases, therefore, the doctrine requires the concurrence
voluntarily engage in their sport. of three elements, namely: (1) the plaintiff must know
30
that the risk is present; (2) he must further understand its The sponsorship of the marathon by Cosmos was limited
nature; and (3) his choice to incur it must be free and to financing the race. Cosmos did nothing beyond that,
voluntary.79According to Prosser:80 "Knowledge of the and did not involve itself at all in the preparations for the
risk is the watchword of assumption of risk." actual conduct of the race. This verity was expressly
confirmed by Intergames, through Castro, Jr., who
Contrary to the notion of the CA, the concurrence of the declared as follows:
three elements was not shown to exist. Rommel could
not have assumed the risk of death when he participated COURT
in the race because death was neither a known nor
normal risk incident to running a race. Although he had q Do you discuss all your preparation with Cosmos
surveyed the route prior to the race and should be Bottling Company?
presumed to know that he would be running the race
alongside moving vehicular traffic, such knowledge of a As far as the Cosmos Bottling Company (sic) was a
the general danger was not enough, for some authorities sponsor as to the actual conduct of the race, it is my
have required that the knowledge must be of the specific responsibility. The conduct of the race is my
risk that caused the harm to him. 81 In theory, the responsibility. The sponsor has nothing to do as well as
standard to be applied is a subjective one, and should be its code of the race because they are not the ones
geared to the particular plaintiff and his situation, rather running. I was the one running. The responsibility of
than that of the reasonable person of ordinary prudence Cosmos was just to provide the sponsor's money.
who appears in contributory negligence.82 He could not
have appreciated the risk of being fatally struck by any
moving vehicle while running the race. Instead, he had COURT
every reason to believe that the organizer had taken
adequate measures to guard all participants against any q They have no right to who (sic) suggest the location,
danger from the fact that he was participating in an the number of runners, you decide these yourself without
organized marathon. Stated differently, nobody in his consulting them?
right mind, including minors like him, would have joined
the marathon if he had known of or appreciated the risk a Yes, your honor.86
of harm or even death from vehicular accident while
running in the organized running event. Without We uphold the finding by the CA that the role of Cosmos
question, a marathon route safe and free from was to pursue its corporate commitment to sports
foreseeable risks was the reasonable expectation of development of the youth as well as to serve the need
every runner participating in an organized running event. for advertising its business. In the absence of evidence
showing that Cosmos had a hand in the organization of
Neither was the waiver by Rommel, then a minor, an the race, and took part in the determination of the route
effective form of express or implied consent in the for the race and the adoption of the action plan, including
context of the doctrine of assumption of risk. There is the safety and security measures for the benefit of the
ample authority, cited in Prosser, 83 to the effect that a runners, we cannot but conclude that the requirement for
person does not comprehend the risk involved in a the direct or immediate causal connection between the
known situation because of his youth,84 or lack of financial sponsorship of Cosmos and the death of
information or experience,85and thus will not be taken to Rommel simply did not exist. Indeed, Cosmos' mere
consent to assume the risk. sponsorship of the race was, legally speaking, too
remote to be the efficient and proximate cause of the
Clearly, the doctrine of assumption of risk does not apply injurious consequences.
to bar recovery by the petitioners.
V
IV
Damages
Cosmos is not liable for the negligence
of Intergames as the organizer Article 2202 of the Civil Code  lists the damages that the
plaintiffs in a suit upon crimes and quasi-delicts can
Nonetheless, the CA did not err in absolving Cosmos recover from the defendant, viz.:
from liability.
Art. 2202. In crimes and quasi-delicts, the defendant
shall be liable for all damages which are the natural and

31
probable consequences of the act or omission any mere mistake resulting from inexperience,
complained of. It is not necessary that such damages excitement, or confusion, and more than mere
have been foreseen or could have reasonably been thoughtlessness or inadvertence, or simple
foreseen by the defendant. inattention.89 The RTC did not recognize the right of the
petitioners to recover the loss of earning capacity of
Accordingly, Intergames was liable for all damages that Rommel. It should have, for doing so would have
were the natural and probable consequences of its conformed to jurisprudence whereby the Court has
negligence. In its judgment, the RTC explained the unhesitatingly allowed such recovery in respect of
award of damages in favor of the petitioners, as follows: children, students and other non-working or still
unemployed victims. The legal basis for doing so is
Article 2206 (l) of the Civil Code,  which stipulates that
As borne by the evidence on record, the plaintiffs
the defendant "shall be liable for the loss of the earning
incurred medical, hospitalization and burial expenses for
capacity of the deceased, and the indemnity shall be
their son in this aggregate amount of ₱28,061.65
paid to the heirs of the latter; such indemnity shall in
(Exhibits "D'', "D-1" and "D-2"). In instituting this case,
every case be assessed and awarded by the court,
they have paid their lawyer ₱5,000 as initial deposit, their
unless the deceased on account of permanent physical
arrangement being that they would pay attorney's fees to
disability not caused by the defendant, had no earning
the extent of 10% of whatever amount would be awarded
capacity at the time of his death."
to them in this case.

Indeed, damages for loss of earning capacity may be


For the loss of a son, it is unquestionable that plaintiffs
awarded to the heirs of a deceased non-working victim
suffered untold grief which should entitle them to recover
simply because earning capacity, not necessarily actual
moral damages, and this Court believes that if only to
earning, may be lost.
assuage somehow their untold grief but not necessarily
to compensate them to the fullest, the nominal amount of
₱l00,00.00 should be paid by the defendants. In Metro Manila Transit Corporation v. Court of
Appeals,90 damages for loss of earning capacity were
granted to the heirs of a third-year high school student of
For failure to adopt elementary and basic precautionary
the University of the Philippines Integrated School who
measure to insure the safety of the participants so that
had been killed when she was hit and run over by the
sponsors and organizers of sports events should
petitioner's passenger bus as she crossed Katipunan
exercise utmost diligence in preventing injury to the
Avenue in Quezon City. The Court justified the grant in
participants and the public as well, exemplary damages
this wise:
should also be paid by the defendants and this Court
considers the amount of ₱50,000.00
Compensation of this nature is awarded not for loss of
87 earnings but for loss of capacity to earn money.
as reasonable.
Evidence must be presented that the victim, if not yet
employed at the time of death, was reasonably certain to
Although we will not disturb the foregoing findings and complete training for a specific profession. In People v.
determinations, we need to add to the justification for the Teehankee,  no award of compensation for loss of
grant of exemplary damages. Article 2231 of the Civil earning capacity was granted to the heirs of a college
Code  stipulates that exemplary damages are to be freshman because there was no sufficient evidence on
awarded in cases of quasi-delict if the defendant acted record to show that the victim would eventually become
with gross negligence. The foregoing characterization by a professional pilot. But compensation should be allowed
the RTC indicated that Intergames' negligence was for loss of earning capacity resulting from the death of a
gross. We agree with the characterization. Gross minor who has not yet commenced employment or
negligence, according to Mendoza v. Spouses training for a specific profession if sufficient evidence is
Gomez,88 is the absence of care or diligence as to presented to establish the amount thereor. 91 (bold
amount to a reckless disregard of the safety of persons underscoring supplied for emphasis)
or property; it evinces a thoughtless disregard of
consequences without exerting any effort to avoid them.
In People v. Sanchez,92  damages for loss of earning
Indeed, the failure of Intergames to adopt the basic
capacity was also allowed to the heirs of the victims of
precautionary measures for the safety of the minor
rape with homicide despite the lack of sufficient evidence
participants like Rommel was in reckless disregard of
to establish what they would have earned had they not
their safety. Conduct is reckless when it is an extreme
been killed. The Court rationalized its judgment with the
departure from ordinary care, in a situation in which a
following observations:
high degree of danger is apparent; it must be more than

32
Both Sarmenta and Gomez were senior agriculture Net Earning Capacity = Life Expectancy x [Gross Annual
students at UPLB, the country's leading educational Income less Necessary Living Expenses ]96
institution in agriculture.1âwphi1 As reasonably assumed
by the trial court, both victims would have graduated in Life expectancy is equivalent to 2/3 multiplied by the
due course. Undeniably, their untimely death deprived difference of 80 and the age of the deceased. Since
them of their future time and earning capacity. For these Rommel was 18 years of age at the time of his death, his
deprivation, their heirs are entitled to compensation. life expectancy was 41 years. His projected gross annual
xxxx. However, considering that Sarmenta and Gomez income, computed based on the minimum wage for
would have graduated in due time from a reputable workers in the non-agricultural sector in effect at the time
university, it would not be unreasonable to assume that of his death,97then fixed at ₱l4.00/day, is ₱5,535.83.
in 1993 they would have earned more than the minimum Allowing for necessary living expenses of 50% of his
wage. All factors considered, the Court believes that it is projected gross annual income, his total net earning
fair and reasonable to fix the monthly income that the capacity is ₱l13,484.52.
two would have earned in 1993 at ₱8,000.000 per month
(or ₱96,000.00/year) and their deductible living and other Article 2211 of the Civil Code expressly provides that
incidental expenses at ₱3,000.00 per month (or interest, as a part of damages, may be awarded in
₱36,000.00/year).93 (bold underscoring supplied for crimes and quasi-delicts at the discretion of the court.
emphasis) The rate of interest provided under Article 2209 of
the Civil Code  is 6% per annum  in the absence of
In Perena v. Zarate,94 the Court fixed damages for loss stipulation to the contrary. The legal interest rate of
of earning capacity to be paid to the heirs of the 15-year- 6% per annum  is to be imposed upon the total amounts
old high school student of Don Bosco Technical Institute herein awarded from the time of the judgment of the
killed when a moving train hit the school van ferrying him RTC on May 10, 1991 until finality of
to school while it was traversing the railroad tracks. The judgment.98 Moreover, pursuant to Article 221299 of
RTC and the CA had awarded damages for loss of the Civil Code, the legal interest rate of 6o/o per
earning capacity computed on the basis of the minimum annum is to be further imposed on the interest earned
wage in effect at the time of his death. Upholding said up to the time this judgment of the Court becomes final
findings, the Court opined: and executory until its full satisfaction.100

x x x, the fact that Aaron was then without a history of Article 2208 of the Civil Code  expressly allows the
earnings should not be taken against his parents and in recovery of attorney's fees and expenses of litigation
favor of the defendants whose negligence not only cost when exemplary damages have been
Aaron his life and his right to work and earn money, but awarded.1âwphi1 Thus, we uphold the RTC's allocation
also deprived his parents of their right to his presence of attorney's fees in favor of the petitioners equivalent to
and his services as well. x x x. Accordingly, we 10% of the total amount to be recovered, inclusive of the
emphatically hold in favor of the indemnification for damages for loss of earning capacity and interests,
Aaron's loss of earning capacity despite him having been which we consider to be reasonable under the
unemployed, because compensation of this nature is circumstances.
awarded not for loss of time or earnings but for loss of
the deceased's power or ability to earn money. WHEREFORE, the Court PARTLY AFFIRMS the
decision promulgated on March 10, 2004 to the extent
The petitioners sufficiently showed that Rommel was, at that it absolved COSMOS BOTTLING COMPANY,
the time of his untimely but much lamented death, able- INC. from liability; REVERSES and SETS ASIDE the
bodied, in good physical and mental state, and a student decision as to INTERGAMES,
in good standing.95 It should be reasonable to assume INC., and REINSTATES as to it the judgment rendered
that Rommel would have finished his schooling and on May 10, 1991 by the Regional Trial Court, Branch 83,
would turn out to be a useful and productive person had in Quezon City subject to
he not died. Under the foregoing jurisprudence, the the MODIFICATIONS that INTERGAMES, INC. is
petitioners should be compensated for losing Rommel's ORDERED TO PAY to the petitioners, in addition to the
power or ability to earn. The basis for the computation of aw3:rds thereby allowed: (a) the sum of ₱l13,484.52 as
earning capacity is not what he would have become or damages for the loss of Rommel Abrogar's earning
what he would have wanted to be if not for his untimely capacity; (b) interest of 6% per annum on the actual
death, but the minimum wage in effect at the time of his damages, moral damages, exemplary damages and loss
death. The formula for this purpose is: of earning capacity reckoned from May 10, 1991 until full
payment; (c) compounded interest of 6% per

33
annum from the finality of this decision until full payment;
and (d) costs of suit.

SO ORDERED.

34

You might also like