Weekly Report for SM MOM #112 of RWEP

(2016.10.21 - 2016.10.27)
1. Personnel
1.1 Personnel on Project Management Office (PMO)
No. Position Quantity Company
1 Project Manager 1 CIL
2 Operations Manager 2 CIL
3 Communications Manager 3 CIL
4 Site Manager 1 CNEEC
3 CIL
5 Engineer
7 CNEEC
6 Interpreter 3 CNEEC
7 Designing Representative 1 CNEEC
8 Accountant 1 CNEEC
9 Filing Management 2 CNEEC
10 Reception 2 CNEEC
11 Assistant 1 CNEEC
12 Chef 1 CNEEC
13 Housekeeper 3 CNEEC
14 Security Guard 2 CNEEC
15 Car Driver 2 CNEEC
Subtotal 0

1.2 Personnel for Civil Work on Reppie Site


No Type of Worker Chinese Ethiopian
1 Management 23 2
2 Rebar worker 1 2
3 Woodworker and scaffolder 2 6
4 Concrete worker 1 4
5 Welder 7 4
6 Fitter 2 0
7 Steel Structure flaw detection worker 1 0
8 Site construction helper 0 6
9 Erection worker 7 5
10 Operator 5 2
11 Electric worker 1 0
12 Equipment worker 1 0
13 Handyman 1 5
14 Security guard 0 9
15 Masonry worker 3 5
16 Decoration worker 7 15
Corrosion prevention and waterproof
17 3 10
worker
18 Others (kitchen helper and cleaner) 2 5
Subtotal 0 0

1 / 13
1.3 Personnel for M&E Erection Work on Reppie Site
No Type of Worker Chinese Ethiopian
1 Management 27 0
2 Welder 13 0
3 Fitter 71 0
4 Flaw detection worker 4 0
5 Adjustor 3 0
6 Turbine erection 0 0
7 Electrical erection 28 0
8 Insulation 5
Subtotal 0 0

2. Equipment
No Name Quantity
1. Concrete mixing station(750l) 1
2 Pump truck (37m) 1
3 Tanker (7m³) 2
4 Loader (ZL50) 1
5 Road roller(5T) 1
5 Mortar mixing machine (350) 3
6 Concrete vibrators 10
7 Vibrostand 7
8 Tower crane (MC80A) 1
9 Mobile crane (65t) 1
10 Mobile crane (25t) 1
11 Crawler crane (150t) 1
12 400t crane 1
13 Platform truck (10t) 1
14 Platform truck (5t) 1
15 Winch(JJ.M2t) 1
16 Forklift (3t and 5t) 2
17 Reinforcing steel cutter(6~40) 3
18 Steel bar bender(6~40) 3
19 Steel bar straightener(GF4-40) 1
20 Abrasive wheel cutting machine(CGT1-30) 1
21 Woodworking circular saw(MJ106) 2
22 Wood planer(MB104A) 1
23 Electric hand drill 10
24 Rock drill 1
25 Backhoe excavator(1m³) 3
26 Dump truck (15t) 8
27 Tamping machine 7
28 Breaker 1
29 AC welder (type 500) 8

2 / 13
No Name Quantity
30 DC welder(ZXS-630) 4
31 Electric threading machine(DN15-DN100) 1
32 Trigger squeeze 1
33 Manual pump(4D20Y-100/10) 1
34 Water pump (head 120m) 1
35 Pressure pump( head 50m) 1
36 Hydraulic pipe bender(DN15-DN125) 2
37 Volt-ammeter 1
38 Digital multimeter(F-87) 2
39 Angle grinder (100 and 180) 5
40 Spanner(QL1800 and QL2200) 2
41 Bolt spanner(M24,M20 and M16) 3
42 Diesel generator 4
43 Submerged pump 1
44 Light truck (2.8t) 1
45 Pickup truck 1
46 Electronic scale(200g-30Kg)(Soil test equipment) 1
47 Electronic scale (1Kg) (Soil test equipment) 1
48 Digital Ultrasonic Flaw Detector 1

3. Supply of Material
Material Material Material Material in Sample taken
name delivered consumed stock
Rebar 0t 0.5t 3t No sample was taken.
Cement 40t 5t 60t No need for sample taken.
Gravel 0m³ 15m³ 75m³ No need for sample taken.
Sand 0m³ 40m³ 35m³ No sample was taken.

3 / 13
4. Works completion status of this week
4.1 Civil work
Planned
Planned finish
WBS Construction task starting Days Remarks Completion status Next week plan
date
date
1 Main Building
1.1 Tipping Hall
Completed 60% of To complete 100% of
scaffolding for roof scaffolding for roof
internal panel internal panel
Tipping Hall roof
1.1.1 2016/10/11 2016/11/3 24 installation. installation.
panel installation
Completed 45% of To complete 70% of
roof bottom panel roof bottom panel
installation. installation.
Removal of Tower Complete -
1.1.2 2016/11/1 2016/11/5 5 Completed 100%.
Crane ahead of time
Completed 100% for None.
Exterior wall stone-
1.1.10 2016/11/20 2016/12/20 31 sample wall (primer
like coating
and finish paint).
Small
installation( water
supply and Alternate Alternate construction.
1.1.12 2016/10/8 2016/12/30 84
drainage, electrical construction.
lighting, firefighting,
HVAC and lightning

4 / 13
protection
1.2 Waste Bunker
Remaining internal To complete 100%
Started the closing
1.2.2 wall putty work in 2016/10/8 2016/10/20 13 closing of reserved
of reserved holes.
line 23 holes..
L+22.00m remaining To complete 100%.
1.2.3 interior wall putty 2016/10/12 2016/10/20 9 Completed 90%.
work
L0.00m Hall putty -
1.2.16 2016/10/25 2016/10/30 6 -
work
L0.00m line 19~20 To complete 50%.
1.2.20 2016/10/20 2016/11/5 17 Completed 20%.
putty work
Waste Bunker bottom To complete 50%.
1.2.23 L-3.50m sloping 2016/10/25 2016/11/3 10 -
layer
Small In progress. Coordinating and
installation( water alternative
supply and construction.
Coordinating
1.2.29 drainage, electrical 2016/10/11 2017/2/28 141
construction
lighting, firefighting,
HVAC and lightning
protection
Remaining exterior - To complete 10%.
1.2.30 wall plastering and 2016/10/20 2016/11/30 42
putty work

5 / 13
2 Access Ramp

3 Boiler Hall
Remaining To complete 50% for
3.1.1 2016/10/25 2016/11/8 15 -
foundations in Axis A excavation.
Remaining wall -
3.1.4(A
masonry and interior 2016/10/10 2016/10/25 16 Completed 95%
)
plastering
L+3.50m interior To complete 60%
3.1.4 wall surface, ceiling 2016/11/5 2016/11/20 16 Completed 40%.
putty work
Exterior wall putty Discontinuous To complete 10%.
3.1.12 2016/10/20 2017/1/31 104 -
work and painting construction
Small Coordinating
installation( water construction
supply and
Coordinating
3.1.13 drainage, electrical 2016/10/12 2016/12/30 80 -
construction.
lighting, firefighting,
HVAC and lightning
protection
Remaining Completed 100% To completed 100% for
equipment chiseling off for PA PA Fan foundation lean
3.1.14 2016/10/20 2016/11/20 32
foundations in Boiler Fan foundation concrete.
Hall concrete.
Remaining lattice Start in To complete 50% for
3.1.15 2016/11/1 2016/11/30 30 -
columns and steel advance. steel roof truss

6 / 13
roof truss secondary structure
installation installation in Axis F-K.
Completed 100% for -
Slag Pit waterproof
wall cement-based
3.1.18 and anticorrosion 2016/10/10 2016/11/20 41
capillary crystalline
application
application.
4 FGT Equipment Foundation
Newly added Completed 70% for To complete 70% in
4.1 equipment 2016/10/20 2016/10/30 11 - rebar binding and total.
foundation formwork.
4.2 FGT area floor 2016/11/1 2016/11/14 14

5 Turbine Deaerator Bay

6 Main Control Building


To complete 100% for
Fine aggregate L+4.00m fine concrete
6.2.1 2016/10/18 2016/10/21 6 Delayed None.
concrete floors aggregate floor
construction.
6.2.2 Floor tile application 2016/10/16 2016/11/20 37 None To complete 10%.

7 Leachate Treatment Station


7.3 Membrane Treatment Workshop
7.3.1.1 Acid resistant tile 2016/10/11 2016/12/16 67 Discontinuous Started wall tile To complete 50% for
application to rooms construction, application in Acid wall tile in Acid
such as Dosing The Storage Room. Storage Room.
Room, Acid Storage construction

7 / 13
for Membrane
Treatment
Workshop
Room and Membrane
shall wait
Treatment Room
until the
erection work
is completed.
8 Water Pond
Completed 100% for None.
Pond wall
Pond inside wall and waterproof, And
8.1 bottom slab 2016/10/7 2016/10/30 24 100% for bottom
waterproof slab cement-based
capillary crystalline
application.
9 Water Pump Station
Started roof To complete 100% for
9.1.1 Waterproofing layer 2016/11/25 2016/11/30 6 waterproofing roof waterproofing..
application.
Completed 90% for To complete 100% for
Doors and Windows Discontinuous
9.3 2016/10/15 2016/12/30 77 window frames window frames.
installation construction
installation.
10 Cooling Tower
10.1 Collecting Tank 2016/10/20 2016/11/25 37 Completed 100% for To complete 100% for
inside wall and bottom slab leveling bottom slab cement-

8 / 13
layer and 20% for based capillary
bottom slab cement-based crystalline application.
waterproof capillary crystalline
application.
14 Whole Plant Underground Pipe Network
Underground pipe To complete 50%.
network at eastern
Completed 30% for
14.1 side of Water Pond 2016/10/15 2016/12/30 77
excavation.
and Water Pump
Station
Underground pipe To complete 100% for
Completed 70% for
network at western western side
14.2 2016/10/12 2016/12/30 80 western side
and southern side of excavation.
excavation.
Turbine Hall

15 Whole Plant Cable Trench

C o m p l e t e d 1 0 0 % oTo
f complete 50% for
Cable trench from c a b thel sectionealong t
Main Control Building e x c a v a t i o n a n d l e a n Water Pond from Main
to Water Pump Discontinuous c o n c Control
r Building
e t to e a
15.1 2016/10/12 2016/11/20 39
Station, construction W a t e r P o nWater
d Pump
f r Station.
o m
And from Turbine Main C ontrol
B uilding
Hall to Switchyard t o W a t e r P u m p
Station.

9 / 13
4.2 Erection Work
WBS Construction task Planned Planned Days Remarks Completion status and the
starting finish date reason of unfinished works

10 / 13
date
2.1.2.3 #2 Boiler steam and water Completed 80%.
2016/6/16 2016/11/17 155
system erection
#2 Boiler platform staircase Completed 80%.

2.1.3.1 #1 Dust Remover body 2016/10/10 2016/11/20 Completed 50%.


42
erection
2.2.3.2 High pressure water supply Completed 90%.
2016/6/30 2016/8/3 35
pipeline installation
2.2.4.8 #1 Turbine circulating Completed 60%
2016/7/22 2016/8/3 25
water pipe erection
2.3 Electrical system erection 2016/4/27 2017/3/31 339
2.3.3 132kV power distribution Complete 50%.
2016/7/22 2017/10/31 102
unit erection
2.3.11.3 Cable laying 2016/7/15 2016/12/31 170
Switchyard cable laying Completed 20%.
3 Leachate Equipment
erection
3.1 Nitrification Tank erection 2016/7/15 2016/12/15 Completed 80%

Anaerobic Tank erection Completed 30%

11 / 13
5. Inspection plan for next week
5.1 Civil Work
Construction area Sub-divisional Work Planned inspection date
1. Water Pump Station Roof waterproofing layer basic 28th October, 2016
layer treatment
2. Waste Bunker Interior putty work basic layer 30th October, 2016
treatment
3. Plant cable trench Rebar and formwork 2nd November, 2016
4. Drainage well side wall and top Rebar and formwork 3rd November, 2016
slab

5.2 Erection Work


5.2.1 Mechanical erection work
None
5.2.2 Electrical erection work
Area Inspection or Test Work Planned inspection date
1. 10kV switchgear digital relays Routine testing 2nd November to 6th
November, 2016
2. DC&UPS System Routine testing 31st October, 1st
November,2016

6. HSE
HSE is under control this week and no accident or injury was reported. Special personal was assigned to
clear, sort out and store the removed materials from Main Building area, such as the scaffolding formwork
and timber. A safety meeting was held every morning from Monday to Friday. Keep pressure on
supervision of various violations and correct behaviors or places that violate regulations.

Detailed safety measures have been taken this week as follows,

1. Continue cleaning up construction materials at site and sort them out.


2. Safety supervision and protections on high-elevation activities.
3. Cleaning of site road.
4. Drain away water from site area.
5. Strengthen instruction and supervision on site activities.

12 / 13
7. Transport and delivery

Shipment No. Items ATD/ETD ATA/ETA Status


(Djibouti)
th
26 Air pre-heater (was shut out on Jun 6), valves, steam July 9, 2016 Aug 03, 8 containers arrived.
soot-blower, pipes, windows and doors, etc. (Shanghai) 2016 Truck loading for bulk cargo
(101 packages and 8 containers in total) is undergoing. 98 packages
arrived.
th
27 Casting material, refractory bricks, anchor, calcium Aug 8, 2016 Sep 04, Closed.
silicate board, flue gas on-line monitoring system (Shanghai) 2016
(26 containers in total)
th
28 Windows and doors, working tools and equipment, Aug 15, 2016 Sep 18, Unloaded at the Djibouti
small distribution boxes, SNCR (Tianjin) 2016 port. 28-1 and 28-2 arrived.
(5 containers in total)
th
29 Windows and doors, laboratory equipment, meters, Aug 18, 2016 Sep 25, Unloaded at the Djibouti
valves (Shanghai) 2016 port. Custom transit is
(9 containers in total) undergoing.
th
30 Lighting, boiler parts, valves, electric throttle, tools Sep 1, 2016 Sep 21, Unloaded at the Djibouti
(6 containers in total) (Shanghai) 2016 port. Custom transit for 30-
1 is undergoing.
st
31 Ash conveyor Sep 1, 2016 Sep 27, Unloaded at the Djibouti
(4 packages in total) (Shanghai) 2016 port. Custom transit is
undergoing.
nd
32 Truck scale Sep 21, 2016 TBC On the sea.
(12 packages in total) (Shanghai)

13 / 13