Professional Documents
Culture Documents
CARPENTRY
CARPENTRY
CARPENTRY
CARPENTRY:
*DOOR JAMB:
D1 (2 sets): D2 (6 sets):
Header: cutting = 1.10m (3.61’) Header: cutting = 0.90m (2.95’)
Req’d = 2 pc - 2” x 6” x 3.61’ Req’d = 6 pcs - 2” x 6” x 2.95’
Side Jamb: cutting = 2.15m (7.05’) Side Jamb: cutting = 2.15m (7.05’)
Req’d = 4 pcs - 2” x 6” x 7.05’ Req’d = 12 pcs - 2” x 6” x 7.05’
D3 (1 set): D4 (2 sets):
Header: cutting = 1.10m (3.61’) Header: cutting = 2.20m (7.22’)
Req’d = 1 pc - 2” x 6” x 3.61’ Req’d = 2 pcs - 2” x 6” x 7.22’
Side Jamb: cutting = 2.15m (7.05’) Side Jamb: cutting = 2.15m (7.05’)
Req’d = 2 pcs - 2” x 6” x 7.05’ Req’d = 4 pcs - 2” x 6” x 7.05’
SECOND FLOOR:
*Bedroom 1 (4.0m x 4.0m): *Family Room (4.0m x 4.0m)
Primary Ceiling Joists: Primary Ceiling Joists:
Cutting = 4.0m ( 10’) Cutting = 4.0m ( 10’)
4.0 m
1 4.0 m
1
Req’d no of pcs = 0.30 m Req’d no of pcs = 0.30 m
Req’d no of pcs = 15 pcs - 2” x 2” 10’ S4S Req’d no of pcs = 15 pcs - 2” x 2” 10’ S4S
Intermediate Ceiling Joists: Intermediate Ceiling Joists:
Cutting = 4.0m ( 10’) Cutting = 4.0m ( 10’)
4.0 m
1 4.0 m
1
Req’d no of pcs = 0.30 m Req’d no of pcs = 0.30 m
Req’d no of pcs = 15 pcs - 2” x 2” 10’ S4S Req’d no of pcs = 15 pcs - 2” x 2” 10’ S4S
Ceiling: Ceiling:
Areatobe Pr ovidedWithCeiling Areatobe Pr ovidedWithCeiling
Areaof 1Sheet Areaof 1Sheet
Req’d no of sheets= Req’d no of sheets=
4.0 x 4.0 4.0 x 4.0
= 1.20 x 2.4
= 5.56 sheets = 1.20 x 2.4
= 5.56 sheets
Say ≈ 6 sheets - ¼” x 4’ x 8’ Ordinary Plywood Say≈ 6 sheets - ¼” x 4’ x 8’ Ordinary Plywood
FASCIA BOARD:
Width = 12” = 0.30m
Length of Fascia Board = Length of the Gutter
Length of Fascia Board = 68m
LengthofFasciaboard
= 2.4 m
Req’d no of sheets
= 68m x 1 sheet/4 cuts
2.4m
= 7.08 sheets
Say ≈ 8 sheets - ½” x 4’ x 8’ Marine Plywood
MATERIAL COST:
2” x 6” x 6’ S4S = 4 pcs x PHP 630.00/pc = PHP 2,520.00
2” x 6” x 8’ S4S = 26 pcs x PHP 840.00/pc = PHP 21,840.00
2” x 2” x 6’ S4S = 5 pcs x PHP 105.00/pc = PHP 525.00
2” x 2” x 8’ S4S = 49 pcs x PHP 140.00/pc = PHP 6,860.00
2” x 2” x 10’ S4S = 12 pcs x PHP 175.00/pc = PHP 2,100.00
2” x 2” x 14’ S4S = 447 pcs x PHP 245.00/pc = PHP 109,515.00
¼” x 4’ x 8’ Ordinary Plywood = 69 sheets x PHP 420.00/sheet = PHP 28,980.00
¼” x 4’ x 8’ Marine Plywood = 50 sheets x PHP 460.00/sheet = PHP 23,000.00
½” x 4’ x 8’ Marine Plywood = 8 sheets x PHP 720.00/sheet = PHP 5,760.00
= PHP 201,100.00
MANPOWER CAPABILITY:
*For installation of door Jamb:
1 Carpenter can install 40 Bd. Ft. Per day
*For installation of Plywood Ceiling:
1 Carpenter & 1 Helper can accomplish 16㎡ per day
*For installation of ceiling joist:
1 Carpenter & 1 Helper can accomplish 33 Bd. Ft. Per day
*For installation of door jamb:
Using 3 crews:
Accomplishments / day = (Capability of 1 crew per day) x (Number of man)
= 40Bd Ft/day/1man x 3men
= 120 Bd Ft/day
TotalDoorJambBdFT
Accomplishment / day
No of days =
228m 2
= 120BdFt / day
= 2 days
*For installation Plywood Ceiling:
Using 5 crews:
Accomplishments/day = (Capability of 1 crew per day) x (Number of man)
= (16㎡/day/crew) x (5 crews)
= 80㎡/day
TotalCeilingArea
Accomplishment / day
No of days =
345.94m 2
80m 2 / day
=
= 4.5 days
*For installation Ceiling Joists:
Using 5 crews:
Accomplishments/day = (Capability of 1 crew per day) x (Number of man)
= (33Bd Ft/day/1cew) x (5 crews)
= 165Bd Ft/day
TotalCeilingJoisrBdFT
Accomplishments / day
No of days =
3138.68 BdFt
= 165BdFt / day
=19.5 days
MANPOWER COST:
*For installation of door Jamb:
3 Carpenters at PHP 380.00/day for 2 days = PHP 2,280.00
*For installation of Plywood Ceiling:
5 Carpenters at PHP 380.00/day for 4.5 days = PHP 8,550.00
5 Laborers at PHP 366.00/day for 4.5 days = PHP 8,235.00
*For installation of Plywood Ceiling:
5 Carpenters at PHP 380.00/day for 19.5 days = PHP 37,050.00
5 Laborers at PHP 366.00/day for 19.5 days = PHP 35,685.00
= PHP 91,800.00
Total Direct Cost = PHP 292,900.00
PHP 292900.00
2
Direct Unit Cost = 345.94m
= PHP 846.68/㎡
Adjusted Unit Cost = PHP 846.68 x 1.40
= PHP 1,185.352/㎡
Total Adjusted Cost = PHP 1185.352 x 345.94