Work Order - 01
Work Order - 01
To,
Ayaan Construction Date: 22.11.2016
197, Dr. Kudrat-A- Khuda Road, (Judge Goli), Elephant Road
Dhaka-1205
Mobile: +8801713-109710
Work Order
Dear Sir, As per your quotation and negotiation on the 20 th November, 2016 about the unit rate of
¾” LBI Stone. We gladly issuing you the supply order of the same material we negotiated for
(01) Material should be delivered in good condition as per description and within the schedule time
Material should be delivered as per approved sample.
(03) The company has the right to inspect the goods and also has the power to reject the same if
found unspecified inferior materials
(04) Payment shall be made after confirmation of receipt of materials in good condition after 50 MT
(05) Purchased order number should be mentioned on all your delivery challan, invoices and bills
(07) Last date of delivery within 30-11-2016. If the above-mentioned materials are not supplied
within due time This purchase order will be treated as cancelled.
(08) Vehicle Rent will pay to 60% Company after unloaded & 40% pay to Supplier.
Forwarded By Approved By
Shojib Chowdhury Md. Moniruzzaman
Head of Procurement Head of EPC