Lusail Stadium Steel Structure Works Preliminary Schedule: Mobilization Demobilization

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

ID Task Görev Adı Duration Start Finish May '18 Jun '18 Jul '18 Aug '18 Sep

Duration Start Finish May '18 Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18
Mode 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15
1 LUSAIL STADIUM STEEL STRUCTURE WORKS PRELIMINARY SCHEDULE224 days Tue 01‐05‐18 Mon 10‐12‐18
2 MOBILIZATION‐DEMOBILIZATION 224 days Tue 01‐05‐18 Mon 10‐12‐18
3 Mobilization 14 days? Tue 01‐05‐18 Mon 14‐05‐18
4 Demobilization 10 days Sat 01‐12‐18 Mon 10‐12‐18
5 PTW Document submittion 85 days? Tue 15‐05‐18 Thu 15‐11‐18
6 Material check, weight registration and stocking 85 days? Tue 15‐05‐18 Thu 15‐11‐18
7 ZONE 5 30 days Sat 19‐05‐18 Sun 17‐06‐18
8 Preparation on ground aseembly area 2 days Sat 19‐05‐18 Sun 20‐05‐18
9 Survey check for all embedded plates & Column Check 2 days Mon 21‐05‐18 Tue 22‐05‐18
10 Preassembly of Truss sections on ground 2 days Wed 23‐05‐18 Thu 24‐05‐18
11 Preassembled Truss Lifting 6 days Sat 26‐05‐18 Thu 31‐05‐18
12 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Sat 26‐05‐18 Sun 27‐05‐18
13 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Mon 28‐05‐18 Tue 29‐05‐18
14 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Wed 30‐05‐18 Thu 31‐05‐18
15 Platform Beams and Other Members Erection 18 days Sat 02‐06‐18 Tue 19‐06‐18
16 Erect the Level 5 Floor Beams and Secondary Members & props if required 4 days Sat 02‐06‐18 Tue 05‐06‐18
17 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Wed 06‐06‐18 Thu 07‐06‐18
18 Erect the Level 6 Floor Beams and Secondary Members & props if required 4 days Fri 08‐06‐18 Mon 11‐06‐18
19 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Tue 12‐06‐18 Wed 13‐06‐18
20 Erect the Level 7 Floor Beams and Secondary Members 4 days Thu 14‐06‐18 Sun 17‐06‐18
21 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Mon 18‐06‐18 Tue 19‐06‐18
22 Alignment & Inspection and handover of Zone 5 2 days Wed 20‐06‐18 Thu 21‐06‐18
23 ZONE 6 30 days Sat 16‐06‐18 Sun 15‐07‐18
24 Preparation on ground aseembly area 2 days Sat 16‐06‐18 Sun 17‐06‐18
25 Preassembly of Truss sections on ground 2 days Mon 18‐06‐18 Tue 19‐06‐18
26 Survey check for all embedded plates & Column Check 2 days Wed 20‐06‐18 Thu 21‐06‐18
27 Preassembled Truss Lifting 6 days Sat 23‐06‐18 Thu 28‐06‐18
28 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Sat 23‐06‐18 Sun 24‐06‐18
29 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Mon 25‐06‐18 Tue 26‐06‐18
30 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Wed 27‐06‐18 Thu 28‐06‐18
31 Platform Beams and Other Members Erection 13 days Sat 30‐06‐18 Thu 12‐07‐18
32 Erect the Level 5 Floor Beams and Secondary Members & props if required 2 days Sat 30‐06‐18 Sun 01‐07‐18
33 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Mon 02‐07‐18 Tue 03‐07‐18
34 Erect the Level 6 Floor Beams and Secondary Members & props if required 2 days Wed 04‐07‐18 Thu 05‐07‐18
35 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Sat 07‐07‐18 Sun 08‐07‐18
36 Erect the Level 7 Floor Beams and Secondary Members 2 days Mon 09‐07‐18 Tue 10‐07‐18
37 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Wed 11‐07‐18 Thu 12‐07‐18
38 Alignment and Inspection and handover of Zone 6 2 days Sat 14‐07‐18 Sun 15‐07‐18
39 ZONE 4 30 days Sat 14‐07‐18 Sun 12‐08‐18
40 Preparation on ground aseembly area 2 days Sat 14‐07‐18 Sun 15‐07‐18
41 Preassembly of Truss sections on ground 2 days Mon 16‐07‐18 Tue 17‐07‐18
42 Survey check for all embedded plates & Column Check 2 days Wed 18‐07‐18 Thu 19‐07‐18
43 Preassembled Truss Lifting 6 days Sat 21‐07‐18 Thu 26‐07‐18
44 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Sat 21‐07‐18 Sun 22‐07‐18
45 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Mon 23‐07‐18 Tue 24‐07‐18
46 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Wed 25‐07‐18 Thu 26‐07‐18
47 Platform Beams and Other Members Erection 13 days Sat 28‐07‐18 Thu 09‐08‐18
48 Erect the Level 5 Floor Beams and Secondary Members & props if required 2 days Sat 28‐07‐18 Sun 29‐07‐18
49 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Mon 30‐07‐18 Tue 31‐07‐18
50 Erect the Level 6 Floor Beams and Secondary Members & props if required 2 days Wed 01‐08‐18 Thu 02‐08‐18
51 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Sat 04‐08‐18 Sun 05‐08‐18
52 Erect the Level 7 Floor Beams and Secondary Members 2 days Mon 06‐08‐18 Tue 07‐08‐18
53 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Wed 08‐08‐18 Thu 09‐08‐18
54 Alignent and Inspection and handover of the Zone 4 2 days Sat 11‐08‐18 Sun 12‐08‐18
55 ZONE 7 30 days Sat 11‐08‐18 Sun 09‐09‐18
56 Preparation on ground aseembly area 2 days Sat 11‐08‐18 Sun 12‐08‐18
57 Preassembly of Truss sections on ground 2 days Mon 13‐08‐18 Tue 14‐08‐18
58 Survey check for all embedded plates & Column Check 2 days Wed 15‐08‐18 Thu 16‐08‐18
59 Preassembled Truss Lifting 6 days Sat 18‐08‐18 Thu 23‐08‐18
60 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Sat 18‐08‐18 Sun 19‐08‐18
61 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Mon 20‐08‐18 Tue 21‐08‐18
62 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Wed 22‐08‐18 Thu 23‐08‐18
63 Platform Beams and Other Members Erection 13 days Sat 25‐08‐18 Thu 06‐09‐18
64 Erect the Level 5 Floor Beams and Secondary Members & props if required 2 days Sat 25‐08‐18 Sun 26‐08‐18
65 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Mon 27‐08‐18 Tue 28‐08‐18
66 Erect the Level 6 Floor Beams and Secondary Members & props if required 2 days Wed 29‐08‐18 Thu 30‐08‐18
67 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Sat 01‐09‐18 Sun 02‐09‐18

Görev Özet Etkin Olmayan Kilometre Taşı Yalnızca Süre Yalnızca başlangıç Dış Kilometre Taşı Elle İlerleme
Proje: Lusail Program Yucel MS
Bölme Proje Özeti Etkin Olmayan özeti Elle Zamanlanmış Görev Özet Toplaması Yalnızca Bitiş Son Tarih
Tarih: Sun 04-03-18
Kilometre Taşı Etkin Olmayan Görev Elle Oluşturulmuş Görev Elle Oluşturulmuş Özet Dış Görevler İlerleme

Sayfa 1
ID Task Görev Adı Duration Start Finish May '18 Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18
Mode 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15
68 Erect the Level 7 Floor Beams and Secondary Members 2 days Mon 03‐09‐18 Tue 04‐09‐18
69 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Wed 05‐09‐18 Thu 06‐09‐18
70 Alignent and Inspection and handover of the Zone 7 2 days Sat 08‐09‐18 Sun 09‐09‐18
71 ZONE 3 30 days Sat 08‐09‐18 Sun 07‐10‐18
72 Preparation on ground aseembly area 2 days Sat 08‐09‐18 Sun 09‐09‐18
73 Preassembly of Truss sections on ground 2 days Mon 10‐09‐18 Tue 11‐09‐18
74 Survey check for all embedded plates & Column Check 2 days Wed 12‐09‐18 Thu 13‐09‐18
75 Preassembled Truss Lifting 6 days Sat 15‐09‐18 Thu 20‐09‐18
76 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Sat 15‐09‐18 Sun 16‐09‐18
77 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Mon 17‐09‐18 Tue 18‐09‐18
78 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Wed 19‐09‐18 Thu 20‐09‐18
79 Platform Beams and Other Members Erection 13 days Sat 22‐09‐18 Thu 04‐10‐18
80 Erect the Level 5 Floor Beams and Secondary Members & props if required 2 days Sat 22‐09‐18 Sun 23‐09‐18
81 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Mon 24‐09‐18 Tue 25‐09‐18
82 Erect the Level 6 Floor Beams and Secondary Members & props if required 2 days Wed 26‐09‐18 Thu 27‐09‐18
83 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Sat 29‐09‐18 Sun 30‐09‐18
84 Erect the Level 7 Floor Beams and Secondary Members 2 days Mon 01‐10‐18 Tue 02‐10‐18
85 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Wed 03‐10‐18 Thu 04‐10‐18
86 Alignent and Inspection and handover of the Zone 3 2 days Sat 06‐10‐18 Sun 07‐10‐18
87 ZONE 1 30 days Sat 06‐10‐18 Sun 04‐11‐18
88 Preparation on ground aseembly area 2 days Sat 06‐10‐18 Sun 07‐10‐18
89 Preassembly of Truss sections on ground 2 days Mon 08‐10‐18 Tue 09‐10‐18
90 Survey check for all embedded plates & Column Check 2 days Wed 10‐10‐18 Thu 11‐10‐18
91  Preassembled Truss Lifting 6 days Sat 13‐10‐18 Thu 18‐10‐18
92 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Sat 13‐10‐18 Sun 14‐10‐18
93 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Mon 15‐10‐18 Tue 16‐10‐18
94 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Wed 17‐10‐18 Thu 18‐10‐18
95 Platform Beams and Other Members Erection 18 days Sat 20‐10‐18 Tue 06‐11‐18
96 Erect the Level 5 Floor Beams and Secondary Members & props if required 4 days Sat 20‐10‐18 Tue 23‐10‐18
97 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Wed 24‐10‐18 Thu 25‐10‐18
98 Erect the Level 6 Floor Beams and Secondary Members & props if required 4 days Fri 26‐10‐18 Mon 29‐10‐18
99 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Tue 30‐10‐18 Wed 31‐10‐18
100 Erect the Level 7 Floor Beams and Secondary Members 4 days Thu 01‐11‐18 Sun 04‐11‐18
101 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Mon 05‐11‐18 Tue 06‐11‐18
102 Alignent and Inspection and handover of the Zone 1 2 days Wed 07‐11‐18 Thu 08‐11‐18
103 ZONE 8 29 days Sat 03‐11‐18 Sat 01‐12‐18
104 Preparation on ground aseembly area 2 days Sat 03‐11‐18 Sun 04‐11‐18
105 Preassembly of Truss sections on ground 2 days Mon 05‐11‐18 Tue 06‐11‐18
106 Survey check for all embedded plates & Column Check 2 days Wed 07‐11‐18 Thu 08‐11‐18
107 Preassembled Truss Lifting 6 days Sat 10‐11‐18 Thu 15‐11‐18
108 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Sat 10‐11‐18 Sun 11‐11‐18
109 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Mon 12‐11‐18 Tue 13‐11‐18
110 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Wed 14‐11‐18 Thu 15‐11‐18
111 Platform Beams and Other Members Erection 13 days Sat 17‐11‐18 Thu 29‐11‐18
112 Erect the Level 5 Floor Beams and Secondary Members & props if required 2 days Sat 17‐11‐18 Sun 18‐11‐18
113 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Mon 19‐11‐18 Tue 20‐11‐18
114 Erect the Level 6 Floor Beams and Secondary Members & props if required 2 days Wed 21‐11‐18 Thu 22‐11‐18
115 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Sat 24‐11‐18 Sun 25‐11‐18
116 Erect the Level 7 Floor Beams and Secondary Members 2 days Mon 26‐11‐18 Tue 27‐11‐18
117 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Wed 28‐11‐18 Thu 29‐11‐18
118 Alignent and Inspection and handover of the Zone 8 2 days Fri 30‐11‐18 Sat 01‐12‐18
119 ZONE 2 30 days Thu 01‐11‐18 Fri 30‐11‐18
120 Preparation on ground aseembly area 2 days Thu 01‐11‐18 Fri 02‐11‐18
121 Preassembly of Truss sections on ground 2 days Sat 03‐11‐18 Sun 04‐11‐18
122 Survey check for all embedded plates & Column Check 2 days Mon 05‐11‐18 Tue 06‐11‐18
123 Preassembled Truss Lifting 6 days Thu 08‐11‐18 Tue 13‐11‐18
124 Lifting the truss no 1 on plinth and connect to the embedded plate at level 4+ 2 days Thu 08‐11‐18 Fri 09‐11‐18
125 Lifting the truss no 2A on plinth and connect to the embedded plate at level 4+ 2 days Sat 10‐11‐18 Sun 11‐11‐18
126 Lifting the truss no 2B on plinth and connect to the embedded plate at level 4+ 2 days Mon 12‐11‐18 Tue 13‐11‐18
127 Platform Beams and Other Members Erection 13 days Thu 15‐11‐18 Tue 27‐11‐18
128 Erect the Level 5 Floor Beams and Secondary Members & props if required 2 days Thu 15‐11‐18 Fri 16‐11‐18
129 Bolt tightening at Level 5 Floor Beams and secondary Members 2 days Sat 17‐11‐18 Sun 18‐11‐18
130 Erect the Level 6 Floor Beams and Secondary Members & props if required 2 days Mon 19‐11‐18 Tue 20‐11‐18
131 Bolt tightening at Level 6 Floor Beams and secondary Members 2 days Thu 22‐11‐18 Fri 23‐11‐18
132 Erect the Level 7 Floor Beams and Secondary Members 2 days Sat 24‐11‐18 Sun 25‐11‐18
133 Bolt tightening at Level 7 Floor Beams and secondary Members 2 days Mon 26‐11‐18 Tue 27‐11‐18
134 Alignent & Inspection and Handover of the Zone 2 2 days Thu 29‐11‐18 Fri 30‐11‐18

Görev Özet Etkin Olmayan Kilometre Taşı Yalnızca Süre Yalnızca başlangıç Dış Kilometre Taşı Elle İlerleme
Proje: Lusail Program Yucel MS
Bölme Proje Özeti Etkin Olmayan özeti Elle Zamanlanmış Görev Özet Toplaması Yalnızca Bitiş Son Tarih
Tarih: Sun 04-03-18
Kilometre Taşı Etkin Olmayan Görev Elle Oluşturulmuş Görev Elle Oluşturulmuş Özet Dış Görevler İlerleme

Sayfa 2
Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20
22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04

Görev Özet Etkin Olmayan Kilometre Taşı Yalnızca Süre Yalnızca başlangıç Dış Kilometre Taşı Elle İlerleme
Proje: Lusail Program Yucel MS
Bölme Proje Özeti Etkin Olmayan özeti Elle Zamanlanmış Görev Özet Toplaması Yalnızca Bitiş Son Tarih
Tarih: Sun 04-03-18
Kilometre Taşı Etkin Olmayan Görev Elle Oluşturulmuş Görev Elle Oluşturulmuş Özet Dış Görevler İlerleme

Sayfa 3
Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20
22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04

Görev Özet Etkin Olmayan Kilometre Taşı Yalnızca Süre Yalnızca başlangıç Dış Kilometre Taşı Elle İlerleme
Proje: Lusail Program Yucel MS
Bölme Proje Özeti Etkin Olmayan özeti Elle Zamanlanmış Görev Özet Toplaması Yalnızca Bitiş Son Tarih
Tarih: Sun 04-03-18
Kilometre Taşı Etkin Olmayan Görev Elle Oluşturulmuş Görev Elle Oluşturulmuş Özet Dış Görevler İlerleme

Sayfa 4