Professional Documents
Culture Documents
SHE Plan
SHE Plan
SHE Plan
CHAPTER Page:
1. GENERAL 2
2. SHE LEGISLATION 3
3. SITE ACCESS AND CONTROL 4
4. SITE REGULATIONS 6
5. SAFETY PRECAUTIONS 8
6. INDIVIDUAL ACTION 9
7. WORKING WITH TOOLS, EQUIPMENT AND MEANS 9
8. CONTRACTOR FACILITIES 12
9. FIRE PREVENTION AND PROTECTION 13
10. PERMIT REGULATIONS 14
11. FIRST AID - INJURIES 15
12. EMERGENCY RESPONSE 16
APPENDICES:
A SAFETY SIGNS 19
B PERMIT TO WORK 20
1. GENERAL
1.1 INTRODUCTION
This safety manual contains the minimum set of safety rules and procedures. In addition, all safety rules
and procedures of the local and central Government Authorities of Viet Nam shall be adhered to.
Safety rules and procedures are an integral part of each job and must be carried out fully. Any exception
to the rules and procedures, during the course of any job, must have prior written authorisation.
Staff and workers of Contractors who exhibit a poor attitude toward safe work and safety procedures will
not be acceptable. Employees leaving this job due to safety violations will not be allowed to return to
work without proper authorisation.
Each contractor, civil consultant & VBL Project team, in the role of Consultant Representative for site
supervision and project management, will take and active role in ensuring that the Contractors will be
operating in accordance with strict safety procedures.
1.2 SCOPE
These regulations apply to Contractors working at the construction site of VBL Da Nang at Da Nang
City/ Viet Nam.
The Contractors and their personnel, including all Sub-Contractors and their personnel, shall comply
with the rules and regulations of the Installation SHE Plan including applying Site Regulations.
Each Contractor shall be responsible for the safety of his own staff workers and Sub-Contractors staff
and workers on the Works and should have its own specialised Safety Rules to carry out Contractor
specialised works.
Each Contractor shall appoint a Contractor’s Representative. Ditto shall submit personnel details of a
senior member of his supervisory staff who is nominated as the Contractor's Safety Officer.
1.3 DEFINITIONS
Site: A production facility that is identified by physical, geographical or logical segmentation.
Installation: An event on Site to realise an Investment Project.
Contractor: Suppliers of Plant & Machinery and adhering provisions for the Installation.
Consultant: External Consultant – Main Contractor – for Civil Works.
Project Responsible: HSC responsible /representative for the Project including Installation.
Installation Manager: Responsible for the Installation regarding the daily operations on Site.
Resident Engineer: The engineer that monitors the Civil Works in Investment Projects on
behalf of the Project Responsible.
Site Representative: The person(s) authorised to represent the Site for a certain subject
(Safety /Security Officer, Chief Engineer, Brewery Manager, Training
Manager).
Installation Representative: The Overall Responsible on Site during the Installation. The Installation
Manager, Resident Engineer and Project Responsible in descending order
shall be the designated Installation Representatives.
Contractor’s Representative: The person authorised in writing by a Contractor to be responsible for the
work on a full-time basis, and who can be contacted at any time.
Consultant’s Representative: Ditto for Main Contractor – the Civil Consultant.
Zoeterwoude, V-PVH Print date : 18-Oct-2013
Page : 2 of 19
SHE Plan
2. SHE LEGISLATION
Appendix A reflects an overview of Safety Signs deriving from ISO 3864, see also paragraph 7.10
for additional instructions on the usage of chemicals.
NO TRESPASSING
Contact guards for entrance permit
This means that everybody should register themselves (and their vehicle if applicable) to obtain a permit
at the guardhouse which is located at the main gate. Group transportation like vans and trucks are not
allowed to enter with persons inside. Persons should get off and get in/outside the gate and walk.
All employees/workers/vehicles entering or leaving the site may be subjected to inspection by authorised
guards or personnel of the Site.
1 Workers Passes
See for the obtaining of a Workers Pass at paragraph 3.2. At the end of each day this pass should be
handed-in at the guardhouse when leaving the site. The next day the same pass has to be collected again
by informing the guard about your personnel number.
2 Visitors Passes
Visitors for the site must obtain a “Visitors pass”. This procedure must be followed for every visit. When
they register their personal name, company name, identification card number /business number /card and
purpose of the visit, they will receive a temporaryVisitors Pass with a unique number.
The visitors must present themselves immediately to the Installation Representative. The pass shall be
handed-in at the guardhouse when leaving the Site. The Officers register date, arrival and departure time.
3 Car Passes
In principle cars /trucks should be parked outside the Site. But in case a vehicle needs to enter, a “car
pass” must be obtained before entering. When the numberplate, name of owner/company has been
registered, the Officer will handout a Car Pass with a unique number. The pass should be positioned
behind the front window screen (right hand side) to be seen clearly. The Car Pass has to be handed-in at
the guardhouse when leaving the site. The Officers register date, arrival and departure time.
For cars which should enter the Site regularly, like for VBL Da Nang and Installation Manager, this car
pass will be personal / permanent and therefore can remain in the car when leaving the Site. Only the
Installation Representative is authorised to decide which cars will get a permanent pass.
4 Office Passes
Only the Site Office Personnel who wear an official Site Office Pass with photograph and who also have
a permanent Car Pass are allowed in without registration. Other Site Office Personnel should apply for a
Visitors Pass (see item 2). If they need to enter by car they should also obtain for a Car Pass (see item 3).
4.6 RADIATION
All governmental laws pertaining to the use, storage or handling of a radiation source must be complied
with. The Installation Representative must be notified prior to any radiological work being commenced.
The necessary distance to radiation source should be taken care of, see ISO 5579.
4.9 HYGIENE
The Contractor shall maintain good hygiene at Site, which shall involve.
- Provision of and maintenance of adequate numbers of toilets, washbasins and showers for all
workers; these areas shall be kept clean at all times.
- Provision of adequate canteens for his staff and workers.
- Prevention of unhealthy site conditions, such as puddles that attract mosquitoes, wasteheaps that
attract flies.
- Cleaning of the Site and of buildings and structures on a regular basis, and removal of waste and
debris from the Site.
- Provision of adequate septic tanks for all temporary toilets and regular cleaning of the septic tanks;
these devices shall meet the requirements of the government or as applicable for the region.
- Contractor's staff and workers are not permitted to eat or take a rest at work areas.
Zoeterwoude, V-PVH Print date : 18-Oct-2013
Page : 7 of 19
SHE Plan
5. SAFETY PRECAUTIONS
6. INDIVIDUAL ACTION
6.2 SMOKING
Smoking is not permitted where any on site except in special designated areas. The Brewery under
special permits MAY declare temporary buildings used by a Contractor safe areas. Smoking in vehicles
on the site is not permitted. Smoking areas will be so designated by Brewery-approved signs.
Smoking shall not be permitted in any building under construction, but a designated location close to the
construction area may be approved.
6.3 MISCELLANEOUS
Horseplay, fighting, gambling in any form is not allowed.
Running at the job site must be avoided except in case of emergency.
Staff and workers must not make inoperative safety devices or operate safety devices such as relief
valves, gate valves, electrical and mechanical interlocks, guards, electrical switches, etc.
Unsafe shortcuts, such as walking on pipelines, sliding down pipes or stanchions, cutting corners through
plants, which are not the work location, must be avoided.
Tools, materials or equipment must not be dropped or thrown from a height to a lower level.
When chemical type goggles are in use, the headband must be around the back of the head, not around
the safety helmet.
Workers with long hair or wearing a necklace are not allowed to work near rotating machinery, workers
hair shall be tied back and held in a net.
Workers who are required to work on electrical systems are not allowed to wear rings watches with metal
band, or metal bracelets.
Hard hats must not be decorated, defaced or damaged in any way.
In addition to any specific requirements noted on permits, the practices from chapter 8 shall be followed:
7. WORKING WITH TOOLS, EQUIPMENT AND MEANS
7.2 ORDERLINESS
Orderliness is a basic requirement and must be maintained at all times. Special attention must be given to
maintaining clear walkways and roadways, removal of trash, removal of slipping and tripping hazards,
and proper storage of materials.
No material or equipment shall be moved onto the site without permission of the Installation
Representative. The only material or equipment that will be allowed in any active work area will be that
material immediately processed into the work.
7.5 CHEMICALS
- Label all containers or chemicals correctly.
- For Safety Signs, according to ISO 3864, see Appendix A
- Do not take food or drink into places where hazardous chemicals are used or stored.
- Paste warning notices on containers of hazardous chemicals.
- Use personal protection equipment and clothing provided when handling chemicals.
- Observe personal hygiene
- Whenever there is any injury caused by chemicals, seek first aid treatment at once.
An updated register of chemicals should be available at the Safety Officer (or replacer).
7.6 LADDERS
- Straight and extension ladders must be tied-off at the top.
- Stepladders must be fully opened and set on a level surface.
- Work facing the ladder, with both feet on the rungs.
- Stay off the platform and top of stepladders.
- All ladders must be of proper length for the job and in good condition.
- The area around the bottom of all ladders must be free from slippery substances and tripping hazards.
- Preference is given to wooden ladders. Fibreglass ladders may be used with prior approval from
Installation Representative.
8. CONTRACTOR FACILITIES
8.1 SHEDS
Each Contractor shall provide suitable offices, change sheds and lunch sheds for own use and the use of
his Sub-Contractors. The location and duration of such sheds is at the Installation Representative.
8.2 AMENITIES
Washing, Toilets, Messing
Contractors shall provide their own amenities for their own stall and workers. This will include toilet
facilities and a Contractor must arrange any disposal services required.
8.3 HOUSEKEEPING
The basic foundation for a safe, healthy and pleasant place to work is good housekeeping.
A clean and orderly place produces a pleasant atmosphere and increases the pride and morale of workers.
On the other hand, bad housekeeping will contribute to low morale, a drop in production and furthermore
increase the accident rate.
All Contractors shall observe the following rules:
- Gangways in the working area to be kept clear at all time.
- Waste materials left under machines and pathways must be cleaned up daily.
- Never throw or scatter rubbish around the site, in buildings and working areas. All rubbish and
waste materials shall be put into bins provided.
- Return tools and equipment in their proper place after use.
Corrosive
Poisonous
Highly Poisonous
Flammable
Highly flammable
Harmful
Irritating
Explosive
Oxidation
Environmental pollutant
Warning
Danger of explosion
Hot surface
Safe condition
Emergency shower
Eye wash
PERMIT TO WORK
Title : _______________________________
Company : _______________________________
NOTE:
______________________________________________________________________________
A "Permit to Work" is required for all hazardous operations.
This permit should be kept in the possession of the operative to whom it is issued whilst working on the operation detailed on it,
or in the location to which it applies should more than one operation be involved.
This permit is only valid for the operation, location and period of time specified on it and is subject to any additional safety
conditions stated herein.
Operations covered by this permit will be stopped if this permit cannot be produced an inspection by authorised personnel at the
location of the operation.
The issue of this permit does not absolve the Contractor from any contractual obligation, particularly with reference to safety on
site of own personnel, other personnel and the works in general.