Charge Pump Starting and Establish Short Oil Once Through Bypassing Reactor (Can Be Done With Step 14)
Charge Pump Starting and Establish Short Oil Once Through Bypassing Reactor (Can Be Done With Step 14)
Sl No Activities 3 6 9 12 15 18 21 23 24 25 26 29 30 33
16 Introducing FLO to reactor (once through) @ 140-160m3/h. Hold for prewetting the catalyst (4hrs).
Once splitter bottom liquid is free from dirt/debris, establish recycle mode and start increasing the bed temperature @
17 20deg.C/hr to 200deg.C. (5hrs appr.x) Hot bolting to be done at 190deg.C (appr. Time is 3hrs)
Low temperature sulfiding (pretreating bed 230°C) & Cracking bed 205 deg.C Max. Increase Cracking bed temperature
18 from 205 to 230deg.C @ 6deg.C/hr after achieving 3000ppm H2S min in recycle gas
19 Hold 230deg.C in all bed till H2S exceeds 10000ppm in recycle
20 Increase temperature of 1st and 2nd bed to 315deg.C @ 14deg.C/hr and 3rd/4th to 290deg.C @8deg.C/hr
21 Hold high temperature sulfiding for 4hrs (DMDS injection to be completed)
22 Stop recycle & start Phase out with VGO. Check bottom sulfur and route to IFO if possible
Establish recylce with 10m3/h fresh and 10m3/h bleed before increasing the temperature. Increase temperature of 1st
23 and 2nd bed to 345deg.C @ 8deg.C/hr and 3rd/4th to 330deg.C @8deg.C/hr