7/28/2020 Yahoo Mail - RE: WORKING PLAN (ETP-WAREHOUSE UNDERGROUND PIPING)

RE: WORKING PLAN (ETP-WAREHOUSE UNDERGROUND PIPING)

From: Felipe Jr. Babag (felipe.babag@rhdhv.com)

To: bagualjanler@yahoo.com; jimmyaustria917@gmail.com

Cc: renatojkk@yahoo.com; adperez@agacons.com; leejeff1415@gmail.com; delunajohnrey24@yahoo.com;


klat.aci@gmail.com; shairajaron27@gmail.com; gerardo.jr.rubillos@rhdhv.com; siravitp@scg.com;
chanachn@scg.com; hilario.arevalo.tomenio@rhdhv.com; john.christian.valenzuela@rhdhv.com;
teddy.tubay@rhdhv.com; wachisan@scg.com; pornchko@scg.com

Date: Monday, July 27, 2020, 12:04 PM GMT+8

Dear Sir Jimmy and Sir Dodgie:

ALL document requested on your company should go to a strick evaluation from your team specially your QA
QC and safety.. The requirement from the above subject is not simple as the title imply.

The working plan submitted by your team for underground piping is POORLLY PLANNED ( see attached document)..
In the absence of your QC manager may I request the project manager to step up on this kind of issue..

For the resubmission of document we expect the following to be included:

1. List of materials to used ( should be available on site prior to start of work)


2. List of equipment to be used ( date of mobilization or availability on site)
3. Method of statement / safety plan for excavation ( this should be approved prior to excavation)
4. Working plan:
a. Underground routeway
b. Location of equipment for lifting
c. Location of pipe fabrication and welding (it is not possible to do pipe welding connection
on the excavation area).. It has to be done above ground until hydrotesting to ensure
quality of connection.. Rainy season and high water table on these area
5. List of manpower
6. Excavation until backfilling should be the shortest possible duration…
7. Schedule of work should be continuous , No Gap and synchronized..

I hope everything is clear..

Regards:

Bong

1/2
7/28/2020 Yahoo Mail - RE: WORKING PLAN (ETP-WAREHOUSE UNDERGROUND PIPING)

From: Jhonler Bagual <bagualjanler@yahoo.com>


Sent: Saturday, July 25, 2020 10:13 AM
To: Felipe Jr. Babag <felipe.babag@rhdhv.com>
Cc: Jimmy Austria <jimmyaustria917@gmail.com>; Renato Del Rosario <renatojkk@yahoo.com>; Dodgie Perez
<adperez@agacons.com>; Jefrey Estrada <leejeff1415@gmail.com>; John Rey De Luna
<delunajohnrey24@yahoo.com>; King Lat <klat.aci@gmail.com>; Shaira Jaron <shairajaron27@gmail.com>
Subject: WORKING PLAN (ETP-WAREHOUSE UNDERGROUND PIPING)

Dear Sir Bong,

Kindly see attached working plan for ETP-Warehouse underground piping.

For our common reference.

Thanks and regards.

Jhonler P. Bagual
Project In-Charge - Fire Protection System

Agacons Construction Inc.

This email and any attachments are intended solely for the use of the addressee(s); disclosure or copying by others
than the intended person(s) is strictly prohibited. If you have received this email in error, please treat this email as
confidential, notify the sender and delete all copies of the email immediately

ETP-Working plan for underground piping ( comment).pdf


176.9kB

2/2