NS2-DD09-P0ZEN-740027 HDPE Piping Hydrostatic Test Procedure
NS2-DD09-P0ZEN-740027 HDPE Piping Hydrostatic Test Procedure
FOR INFORMATION
0 03 AUG 2020 L.X. Giang Y.S. Kwon K.Y. Yang FOR INFORMATION
Rev Date Prepared Checked Approved Details of Revision
Owner
Owner’s Engineer
Contractor
Project
1|Page
HDPE Piping Hydrostatic Test Procedure NS2-DD09-P0ZEN -740027
CONTENTS
1. PURPOSE. .............................................................................................................................................................................. 3
2. SCOPE. .................................................................................................................................................................................... 3
3. REFERENCES CODES AND STANDARD. .............................................................................................................. 3
4. WORK PROCEDURE. ....................................................................................................................................................... 3
4.1 PRESSURE WORK FLOW CHART. ............................................................................................................. 3
4.2 PREPARATION WORK. ............................................................................................................................ 3
4.3 FILLING AND VENTING .......................................................................................................................... 4
4.4 TESTING/ PRESSURIZING ....................................................................................................................... 4
4.5 DRAINING. ............................................................................................................................................. 6
4.6 TEST RECORDS...................................................................................................................................... 6
5. SAFETY PREPERATION ................................................................................................................................................. 7
5.1 SAFETY PREPARE. ................................................................................................................................... 7
5.2 HYDRAULIC TEST STAGE. ....................................................................................................................... 7
5.3 EMERGENCY PREPAREDNESS/ RESPONE.................................................................................................. 8
6. ATTACHMENT (JSA & RA)
2|Page
HDPE Piping Hydrostatic Test Procedure NS2-DD09-P0ZEN -740027
1. PURPOSE
The purpose of this procedure is to provide guidelines for pressure test (hydrostatic, pneumatic) of
above ground and underground piping to meet project specification and reference code and
standards for Nghi Sơn 2 BOT Thermal Power Plant Project.
2. SCOPE
This procedure preparation is for HDPE piping pressure test.
- NS2-DD09-P0ZEN-740008 Rev 2: Method Statement for Boiler and Bop Piping Installation
4. WORK PROCEDURE
4.2.1 Document
- The test section of the line has been installed in accordance with approved drawings.
- The joints of the test section shall be complete inspection following with Inspection test plan.
- Construction team shall be marked blinding point, pressure gauge isolation valves and temporary
line(if necessary) on the Drawing.
4.2.2 Equipment
- Valves and pipes for connection with gauges and the pump, safety valves
- Consumables
- Hand tools
- Water shall normally be used as the test medium. Test water shall be clean such as quality for
minimize corrosion of the materials in the piping system.
- Hydrostatic test pressure shall be applied until the piping and its contents are at approximately
the same temperature.
-The minimum test temperature for hydrostatic pressure testing shall not be metal temperatures
below 20C (350F).
- Highest vent point shall be open to remove all air under the water filling stage.
- Construction shall be checked fully overflowing the highest vent point after then monitoring
within minimum 1 minute at highest vent point
- Before Pressurizing
• Construction is completed according to the design requirements.
• System restraints such as thrust restraints, other supports and anchors are in place and
properly cured with the no deflects.
▪ Pressure gauges shall be checked to install such as lowest, highest and end points of
test boundary
▪ Construction shall be checked condition such as hydraulic hose, temporary line and
testing equipment.
4|Page
HDPE Piping Hydrostatic Test Procedure NS2-DD09-P0ZEN -740027
▪ Construction and safety team shall be checked caution tapes in the boundary, if caution
tapes cannot apply instead to use signboard or signalman.
- During Pressurizing:
• User shall be one more venting on the highest vent point by pressure pump with in
2minutes.
• User shall be slowly supplied pressurizing to read the highest point and adjustment
with lower point. During pressurizing lowest point is usually high pressure than
highest point, however User shall be control to supply pressurizing to consider lower
point pressure and does not exceed the capacity of pipe, meter and valve.
• During pressurizing process, if there are any leakages noticed, stop further pressurizing,
mark the leakage locations and carry out inspection. Ensure pipeline strength reliability
before continue pressurizing slowly to expose all the problems till reaching the testing
pressure. Inspect whether the leakages increase and any other new leakages found,
mark all the leakage points, record leakage patterns in order to analyze the causes and
prepare for the repair proposal.
▪ First step: Pressure reaches the Design pressure and then holding 10 minutes to check
without pressure drop.(Refer. 4.6 Test Record in this procedure)
▪ Second step: Pressure reaches the Test pressure (1.5 times design pressure) and then
holding 30 minutes to check pressure drop. (Refer. 4.6 Test Record in this procedure)
▪ Final Step: Pressure drop the Design pressure to check leakage point for all joints such
as weld, bolting and etc. (Refer. 4.6 Test Record in this procedure)
▪ Acceptance criteria: If no leakage point and no pressure drop during the hydro test it is
accepted.
▪ Design pressure is following with attached ISO mark-up drawing section 1 of Test
package.
Sample
DP(bar_g)
5|Page
HDPE Piping Hydrostatic Test Procedure NS2-DD09-P0ZEN -740027
4.5 Draining
- After successful completion of the test, the system shall be depressurized gradually and then
drain completely. The depressurizing rate shall be 3.0 to 5.0 bar (g) per minute.
- After the hydro-test has been completed, pressure shall be released in a manner and at a rate
so as not to endanger personnel or damage equipment’s.
- All vent and drains shall be opened under the draining stage, after draining then air blowing
shall be used to remove remaining water and making dry condition.
- If using water is over 5 tons, water quality should be checked with Third party following with
QCVN 40:2011/BTNMT before discharged. After then Hydro test water should be discharged
to environment, otherwise water is draining to the waste water treatment facility following
with local regulation.
• Date of test
• Test fluid
6|Page
HDPE Piping Hydrostatic Test Procedure NS2-DD09-P0ZEN -740027
5. SAFETY PREPARATION
5.1 SAFETY PREPARE & INSTALLATION SAFETY METHOD.
- Installation of safety facilities when moving aerial places such as scaffolding and side for
hydrotest inspection
- Tag valve (Open and Close) apply to each valve when hydrotest.
- The pressure gauge will install at two location, one lowest point and one highest point. we will
using 02 gauge (The pressure gauge uses a maximum scale of 1.5 to 5 times the pressure test
pressure ).
- Provision of safety protective equipment to hydraulic test workers (seat belt, Safety shoes paid,
hard hat and face protection).
- Establish safety work procedures including risk assessment results for each pressure test and
provide training to the inspectors and others, all hydraulic test workers will be apply safety
training before working.
- Check all safety devices (vents valves, pressure gauges) and valves before water pressure test.
- Confirmation of personnel control in all areas at the start of the water pressure test.
- Establish emergency contact system for critical risk that may occur during hydraulic test.
- Training and training workers for each emergency before starting the hydraulic test.
7|Page
RISK ASSESSMENT AND JOB SAFETY ANALYSIS
Risk Assessment
Risk level Matric:
RISK ASSESSEMENT
BASE RISK
RESIDUAL RISK
(WITHOUT
Cause of (WITH CONTROL)
CONTROL)
Job / Task People at Risk Adverse Mitigating Controls
Risk Residu
Effect L
S1 Rate L2 S2 al Rate
1
(RFN) (RRN)
worker
abnormal
physical Slip/ Check the health condition during
3 2 6 1 1 1
condition ( Trip/Fall the TBM
Drunken &
fatigue)
Workers
Worker not
familiar with
the scope of TBM to be filled and discussed by
1 2 2 1 1 1
works or supervisor to workers
workplace
hazards
checking the access round before
2 4 8
passing the area
Transportat Traffic Designate a signalman when
Collision 3 3 9 1 2 2
ion of accident moving the equipment
equipemnt
keep the speed limited 10km/h
& delivery
of materials Defective/Faul Ensure all required pre-start
Falling
ty machinery checklist are carried out prior to 1 3 3
object
or tools start any work
Only a qualified and Certified
operators. Signalman, riggers
should be in-place
Complied with Vietname Molisa
Heavy
Material regulations with Circular 44
Lifting Falling object 4 4 16 1 3 3
fall Preparation of a lifting plan list and
Works
plans for lifts from 10 tons or
greater.
Do not stand under the load and
working radius of crane
Isolated lifting area and warning
no access
Ensure loads are fixed with Wire
sling correctly
All lifting equipment must be in
good conditions
Experienced lifting supervisors at
all times
Only lifting tools with color
coding following site regulation
allowed to use
All lifting tools must have
identification tag (including serial
number, certification number,
SWL inspection date and due
date)
Check the Windspeed before
Equipme Lifting. Windspeed 10m/s
Collapse nt 2 5 10 Check the ground condition and 2 3 6
collapse level including any type of
matting.
Ensure that no one touch the load
Squeezed and wire sling before give the
Caught in 5 3 15 2 3 6
by the signal for lifting
sling Use proper hands PPE
Ensure distance between steel
Equipme structure and crane in lifting plan
collision nt 3 5 15 study and communication 2 3 6
collapse between signal man and crane
operator
Put taglines with enough length to
the load from the ground during
lifting for proper guide control.
Squeezed
Ensure that no one stay within the
Caught in by the 4 3 12 2 2 4
restricted area from the load
materials
before lifting.
persons
Sharp Ensure all hand tools are
Major injury 4 2 8 2 2 4
edged inspected and approved.
tools Cut Ensure trained and experienced
injury/ employees are assigned to the job.
Pinch Ensure all hand tools are checked
Point/Def for their good working condition
ected prior to the start of the job by
hand operators or users.
tools/Def Ensure no defected/
ected / handmade/modified tools are
Homema available at site
de /
modified All portable hand tool shall be tie
hand by lanyard for falling protection.
tools
Injury/im Scaffolding inspector shall
property visually inspect the scaffolding is
erected erected as per procedure by
scaffoldi qualified personnel's supervision.
ng, Ensure the materials used for the
partial/co construction are graded.
llapse During inspecting the higher level
scaffoldi platforms Inspector shall maintain
ng, 100% tie-off.
damage All scaffolding shall be inspected
materials after inclement weather or after
or seven days or
3 5 15 1 3 3
structure, if work has been carried out
unqualifi temporary on the structure by a
ed certified scaffolding inspector
personal whose findings shall be recorded
injuried on the scaff tag and in a register
or death, kept by him
unauthori
zed
No person other than a scaffolder
alteration
and/or his helper may be on a
of
scaffold which is
scaffoldi
ng
Cause of Risk Residua
Job / Task People at Risk Adverse L1 S1 Rate Mitigating Controls L1 S1 l Rate
Effect (RFN) (RRN)
Severity S1 : Severity as i
1.Negligible S2 : Severity with mitigating controls in place
2.Slight
3.Moderate
4.Critical/High
5.Catastrophic/Very high
Risk Factor Number ( RFN) Residual Risk number ( RRN)
1-2 Trivial/Acceptable 1-2 Trivial/Acceptable
3.5: Tolerable 3-5 Tolerable
6.-9: Moderate/Acceptable with review 6-9: Moderate/Acceptable with review
10-15 Substantial 10-15: Substantial
16-25:Intolerable/Unacceptable
Method Statement For Boiler & BOP Piping Installation NS2-DD09-P0ZEN-740008
Safety googles: Gloves: Face shield Barricade Lock out: Dust Mask:
needed Tack out:
Safety harness Long sleeves Hearing MSDS Group fault Others
protection need/Review interrupter
Other safety equipment required:
Remark:
LIST OF ALL JOB STEPS LIST OF ALL KNOWN HAZARDS HOW TO ELIMINATE HAZARDS
Transportation of Equipment & Crash/Traffic accident 1. All Truck and trailer operators must
Delivery of Materials Falling materials and equipment from be got EHS conduction from DVN EHS
trailer or truck. training center and had certificate
following Vietnam Molisa regulations
2. Check The access road before
passing area
3.Designate a signalman when moving
equipment
4. Lashings (such as webbing, chains,
cables or clamps) should be in
serviceable condition and be checked for
damage at regular intervals to ensure
their tension has not been lost. Use
sleeves and/or corner protectors to
prevent damage to both the load and the
lashing or sheet if it passes over a sharp
edge or corner.
5. Ropes and buckle straps suspended
from a roof rail and/or the curtains of a
standard curtain-sided vehicle are
generally not suitable for securing a
load.
Heavy lifting work - loading and Potential fatality and serious injury due 1.Regular inspection and maintenance
unloading to lifting work shall be carried out and a register kept
Fatality/Serious injury to workers by a qualitied person, for the lifting
tackle under DVN EHS control.
This equipement checking for
deformation, cracks or any faults
includes: Wire slings, Hooks, Shackles,
swivels, spreader bars, Shear –Legs or
Soft/uneven ground may cause crane similar equipment.
topple 1. Ground bearing to be tested and
Potential fatality to workers property endorsed by competent person.( Crane
damage operators and lifting supervisors ensure
safe condition positioning of crane)
Over loading of crane’s SWL may cause 2.Steel plates to be laid for the
crane toppled positioning of crane, if necessary.
Damaged sling –unsecured loose 3.Lifting supervisor to maintain
materials visibility and supervision during lifing
High potential fâtl incident and work.
damage to property. 3.Adhere to approved lifting plan
4. Ensure a valid permit to work
5.All necessary check list to be update
6.Wire slings must be properly stored
off the ground without casing kinking
7.Wire slings must be cleaned and
inspected before and after using.
8The issuing and control of slings shall
be performed by a qualified person.
9.Wire slings and web slings shall be
uniquely membered and a register kept
of all.
10.Besides the regular inspection
following their use, Wire slings and web
sling must be inspected on monthly
basic and the finding entered on the
record sheet.
Worn slings must be cut into two and
properly disposed of: Not allow:
1. Using a wire sling over sharp corner
without padding.
2.Force the sling into position
3.Overload the slings
4.Use a damaged slings, or one that is
Rigging improper method,high potential worn
fatality due to falling object 5.Drag a sling from under the load
6.Allow loads to pass over a slog laying
on the ground
( Tagline to be used at all time during
lifting works) Adhere to the approved
lifting plan)
7.Lifting supervisor to ensure the proper
centre of gravity.
(Lifting supervisor brief the method
statement in TBM)
Suspend the load 300mm above ground
and confirm stability
1.Ensure a valid permit to work is in
placed before work commencement
2.lifting plan placed before lifting
3.Only appreciated and competent
rigger to carry out rigging
4. inspect lifting gear prior to use
5. Any person employed on site as a
rigger shall be trained and experienced
in this capacity.
2riggers working on scaffolding and /or
steel structure must not wear soft shoes
unless they approved steel capped toe
safety type.
Protective gloves must be worn when
handling wire ropes
Grating installation and removal 1.High potential falling object due to fall 1. All workers must be trained by DVN
or material drop down. EHS and comply with safety regulations
with working at height.
1.1 comply with P.T.W ( Grating and
handrail removal permit)
1.2 Before removal grating on the floor
of Boiler must be identified grating’s
location exactly and install hard
barricade for isolated and prevent
worker access.install warning
signalboard “ Warning opening hole
– keep away”
1.3.Workers in this task have to using
the hooks for falling protection -
2.Pinch point, serious injury hand hanging grating during the time remove
or installation.
1.4 All portable hand tool machine or
tools as scratch spanner, or portable
drilling machine must be secure with
lanyards for falling protection.
Ergonomic and manual handling must
be trained and TBM before working in
this task.
Equipment and material preparation 1. Collision between machine, 1.Alway keep the site clear of any
for temporary facilities overturning may cause death or obstruction
permanent injury, collapsed 1.2.Toolbox talks on daily basic
1.3Adequate warning signal
board
2. Unnecessary movements of 1.4 Checklist on all vehicle must be
equipments a person that causes injury provide every day.
1.5 Siren for warning before lifting.
2.Designate a signalman who wear the
hi –vest suite to control the work
2.1 Heavy machinery should have
backward movement warning light
3. Equipment oil leak during operation beacon.
2.2 Equipment used to clear the site
should be controlled and sorted by
banksman
2.3 Provide safe entrance and exit way
for the workers going to the area
2.4 All vehicles entering on the site
must turn on their headlights day and
nighttime
3. Daily check of the equiment prior to
work
Working and operation during night 1.working operation of the equipments 1.Must provide sufficient lightning on
time may cause serious injury to personnel due the entire working area
to: 1.2 All equipments must be ensure all
lights are operation
1.3 Supervisor must always be present
for entire working
1.4 All workers must be wearing proper
PPE ( Hi –Vest)
1.5 First aid box should be prepared for
the first aid in case injury.
1.6.Temporary electrical system must be
used and connect 03 core and separated
distribution panel ( with ELCB with
electrical leakage 30ma) and avoid from
2.Generator (Diesel equiment oil leakage) any water effect
1.7 provide safe access way and exit
access road for the workforces passing
1.8All kinds of electrical cable must be
hanged over ground at least 2m and
must be industrial socket and flugs
3.Chemical storage 2.Daily check of the equipment prior to
start work
2.1.Regular inspection and monitoring
of the equipment prior to use.
2.2 Provide secondary containment
protection under the equipement to
prevent contamination soil by oil
spillage
3.Diezel chemical shell be stored in
secondary containment and MSDS must
be showed and communicated to all
workers who concerned.
All hazardous waste must be collected
and keep inside the hazardous waste
disposal bin and handover to DVN EHS
to treatment by the Nghison
Environment company following
Vietnam environment regulations.
Welding and cutting work Electrical shock, fire, burn to body and All workers must be trained with special
injury to eye may cause death or hot work training from DVN EHS
permanent injury training center and also equipped with
Fire accident due to electrical wire aging PPE as: Safety mask for face protection
during welding and face mask for welding or cutting,
leather gloves,Arpon.
1. Proper earthing and connection of
welding machines and generators.
2.Flash bask arrestor and Gas flow
regulator should be installed to Gas
cylinder and cutting gears or cutting
torch prior to using cutting.
2.1. Must be used fire blanket to isolated
welding area and used ask tray for
prevent welding slags drop.
2.2. fire watchman should be available
at welding area
2.3. Portable fire firefighting
extinguisher must be available at
workplace.
2.3. All flammable and combustion
materials should be moved way from
welding or gas cutting area at least from
5m to 10m depend on actual location at
workplace and ensure method for
isolated with fire hazards.
Working on scaffolding Potential incident and fatality and 1.Make sure all workers who working at
serious injury due to falling from height height must be trained safety induction
by DVN EHS training and
also must be got safety certificated for
Cir: 44 following MOLISA and
DOLISA Vietnam regulations.
1.2 Must be sured all workers must be
weared safety harness and used 100% tie
off all the time when they are working at
height.
1.3 Scaffolding system must be install
and dismantling by competent persons
and all scaffolders must be got qualified
and trained by DVN EHS department.
1.4 Scaffolding have to reach up with
DVN EHS standards
( Supervisors and EHS supervisors must
be inducted and training to all workers
who is working at height)
1.5 All scaffolding system must be
inspected by scaffolding supervisor and
inspector and apply with scaffolding
tags. ( Green – Yellow – Red)
2. All workers must be followed and
comply with Safety rules and principles
as: Climb on the ladder must be
complied with three points principle.
2.1.Do not face away from the ladder
while carrying out work from the ladder
2.2 Do not stand close than 900mm to
the top of ladder
3.Lifeline must be designed allowable
carrying load capacity
3.2 Using fall arrestor device( Rope
grap) using for vertical lifeline
applicated on ladders (Nylon rope
diameter with 16)
3.3 Lifeline system must be done before
working
Horizontal lifeline must be used wire
rope Min 10 Max 12
4. Ladders must be inspected frequently
before working and those which have
developed defects must be withdraw
from service for repair or destruction
and tagged marked as ( Dangerous not
use)
4.2 Damaged ladders or missing rungs,
broken with side rails or other faulty
equipment must be not used.
Improvised repair are not allowed
Confined space entry work Death due to reduced oxygen 1.All workers who working inside
concentration confined space must be attend and
Or toxic gas. safety training at DVN EHS training
center and must be carry out before
working
2.Complied with PTW following DVN
EHS procedures.
3. before entering confined space must
be using ventilation air force for gas
monitoring and using multi-gas device 4
in 1 for checking ( Apply with oxygen
form 19.5% to 23.5%) and checking
every 02 hours one time ( but no limited
for checking atmosphere inside confined
space following DVN EHS requested or
instructed on site)
4. Establish for communication system
from inside and outside of confined
space.
5. Do not working alone and at least
working inside confined space 03
persons.
6. Establish a tripod and pulley for
rescues in case emergency
When workers working inside must be
used safety harness for rescues reasons
and ERT member must be available
during the time workers working inside
and comply with Emergency procedure
of DVN EHS.
Hydraulic & Pneumatic pressure 1. Lack of knowledge and misunderstand 1“ special training course for high
testing about hazards pressure test by DVN’s EHS” Comply
Workers may be get injury or potential with DVN’EHS procedure
injury, falling at height, explosion Hydraulic & Pneumatic pressure testing
shall only be carried out by competent
personnel
1.2 Visibly identify the hazard on the
cover, DANGER – High pressure
testing in progress – unauthorised
person keep out (Barricades, Signs, ).
2.Damaged tools and equipment may be 2.1All tools and equipment must be
lead worker to injury checked and stamped by HSSE
Explosion of Nitrogen cylinders (as a department
result of toppling over or being struck) - All gauges, Air compressor, air tank,
Uncontrolled release of Nitrogen or pump hose for pressure test must be had
missile calibration certificate from the third
party and checked by Dvn’EHS
department and stamped.
All coupling from hydraulic pump
connected to hose must be using Hose
restraints for protection.
All Nitrogen cylinders must be kept
upright, secured from falling and
protected from accidental impact.
Do not enter a closed space if you
suspect that nitrogen may be present
following a leak or release.
3. Wrong test pressure. 3. Check with supervisor before
Incomplete test pack. mobilizing equipment & ensure the test
No proper coordination among team item is correctly identified.
members, insufficient information to Ensure the test pressure is verified by
concerned parties, TBM not done before QA/QC Dept.
start of the activity, incomplete All hydro-Testing team must be trained
attendance of key personnel on site and understand about method statement
for Hydro - Test.
4.Hazardous activities without sufficient 4. No permit - no work. . Ensure a valid
preparation & safety measures. P.T.W
Inadequate safety control measures due Read and understand permit prior to
to the delay of securing work permits commencement of work.
Specific requirements of PPE not Ensure compliance with permit
established requirements.
Safe access and egress to work surface Permit requestor to supply relevant P &
area not clearly define ID's with Blanks List.
Adhere to Permit-to-Work system in
compliance with safe work practices,
wear the required personal protection
aside from the basic PPE, complete
supervision by key personnel on site,
provide full safety coverage from start
to finish
5. Test package not clearly identified due to
wrong information
5. Test package not clearly identified due to
wrong information
Delay of work permit issuance because of
unsafe site condition
Delay of work permit issuance because of
Test gaskets and blinds not the correct type and unsafe site condition
classification Test gaskets and blinds not the correct type
and classification
6. Personnel injury due to exposure to 6. Bunt off area and erect signs at least
high pressure water and associated 2m around test zone.
‘flying’ debris’ etc Warn personnel.
Inadequate barricading of the test area
with incomplete signage Only authorized personnel to be in the
No corrective action on the unsafe vicinity.
conditions observed Ensure correct test gauges are used.
Test area not define to keep out workers Ensure correct equipment is checked
and traffic entering the controlled area before use.
Unauthorized entry of some discipline Check all flanges and spades for leaks
into the test area which may result to before pressurizing.
undesirable situation Do not check for leaks with bare hands,
avoid close contact.
Install hard barricade around the
potential hazard points of accidental
pressure release
Placement of warning signboards and
close supervision of competent person
on site
Entry should be close to personnel with
no direct involvement on the test as
well as construction equipment.
7. Effected to environment at workplace 7. De – pressured water be drained to
waste water treatment pond. The water
shall be treated by the third party
( Environment company)
radioactive substances Persons receiving excessive exposure to Registered under Radiation Protection
radiation; Regulations following Vietnamese
Radiation levels not being monitored; regulations
Operatives not wearing dose badges; Exempt from registration
Sources and containers not properly Registered under Radiation Protection
maintained and sealed; Regulations (check local regulations)
Persons not wearing personal protective Where practicable, exposure to be
equipment restricted by shielding and containment
Effects which appear during lifetime of of radioactive substances (eg. carrying
exposed individual and include: out radiography in a suitable enclosure
Radiological dermatitis; and using suitable collimators).
Loss of hair;Skin burns, which are slow Exposure to be restricted by provision
to heal and may become malignant; of a safe system of work, including
Anemia; controlled and supervised areas marked
Cataractand by barriers and notices.
Bone cancer. Persons likely to receive specified
minimum dose to be designated
classified persons and wear suitable
film badges or dosimeters and be
medically examined.
The appointment of a radiation
protection officer and supervisor.
Information, instruction and training to
persons working with ionizing radiation
and others concerned with the work.
Where practicable, radioactive
substances to be in the form of sealed
sources and leaks tested regularly.
Records of quantities and locations of
radioactive substances to be kept.
Radioactive substances not in use
should be kept in suitable receptacles
which should be marked if transported.
Monitoring instruments should be
provided.
Any significant losses or spillage to be
reported to the relevant authorities in
the country of operation.
Other relevant legislation and
regulations should be referred to and
compiled with where appropriate
Emergency procedure must be revised
to accommodate the risk of losing
harmful radio active sources or being
unable to reel isotopes back into their
protective containment.
Rescues in emergency case Fatal or death for worker if not in time Any case in emergency contact to
DVN’EHS Department and LILMA
HSSE Department with Telephone
number: 0974.39.33.99 or DVN EHS
023.7386.2595
Following procedures and actions are to
be followed
in a case a victim is to be rescued from
an enclosed space: