** Lead chart **

NAME OF WORK:- Rejuvination of traditional, extinct, depleted water sources and water conservation in catchment of
Gaggar khad G.P Katli, Jamun Ki Ser Distt Sirmaur

Carriage of Steel, G.I.Pipe, Cement & Heavy Material from store :-


Divisional Store Road Head Site of work
BY Mechanical Transport By Head Load
42.00 KM 0.500 KM

Carriage of Sand :- Road Head Site of work


Paonta
BY Mechanical Transport By Head Load
89.00 KM 0.500 KM

Carriage of Stone aggregate :-


Paonta Road Head Site of work
BY Mechanical Transport By Head Load
89.00 KM 0.500 KM

Carriage of Stone:- Road Head Site of work


Local
BY Mechanical Transport By Head Load
0.00 KM 0.500 KM

Carriage of Tor Steel :- Road Head Site of work


Divisional Store
BY Mechanical Transport By Head Load
42.00 KM 0.500 KM

Carriage of Brick :- Road Head Site of work


Baddi
BY Mechanical Transport By Head Load
77.00 KM 0.500 KM

Carriage of Soling Stone :- Road Head Site of work


Local
BY Mechanical Transport By Head Load
0.00 KM 0.500 KM

Carriage of MSERW Pipe :-


Gaziabad/Delhi Road Head Site of work
BY Mechanical Transport By Head Load
292.00 KM 0.500 KM

Carriage of MS Flanges :-
Gaziabad/Delhi Road Head Site of work
BY Mechanical Transport By Head Load
292.00 KM 0.500 KM

Carriage of RCC Pipes :- Road Head Site of work

BY Mechanical Transport By Head Load


0.00 KM 0.500 KM

Carriage of Heavy Material (Valves etc) :-


Solan
BY Mechanical Transport By Head Load
60.00 KM 0.500 KM

Certified that the lead taken in the lead chart is shortest and economical routes by all means.

Executive Engineer,
Jal Shakti Vibhag
Nahan
** CARRIAGE OF MATERIALS **
NAME OF WORK :- Rejuvination of traditional, extinct, depleted water sources and water conservation in catchment of Gaggar khad G.P Katli, Jamun Ki
Ser Distt Sirmaur
Cement : Unit : Per Tonne. Steel : Unit : Per Tonne.
LEAD : By Mech. 42.00 Km. LEAD : By Mech. 42.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 124.68 0.00 1 Km. 0 124.68 0.00
2 Km. 0 144.04 0.00 2 Km. 0 144.04 0.00
3 Km. 0 163.18 0.00 3 Km. 0 163.18 0.00
4 Km. 0 181.80 0.00 4 Km. 0 181.80 0.00
5 Km. 1 199.55 199.55 5 Km. 1 199.55 199.55
5- 10 Km. 5 16.42 82.10 5- 10 Km. 5 16.42 82.10
10-20 Km. 10 13.73 137.30 10-20 Km. 10 13.73 137.30
Beyond 20 Km. 22 11.55 254.10 Beyond 20 Km. 22 11.55 254.10
TOTAL : 673.05 TOTAL : 673.05
2) By Head load 2) By Head load
1st. 1 Km. 0 554.05 0.00 1st. 1 Km. 0 1169.72 0.00
1st. 100 Mtr 1 88.03 88.03 1st. 100 Mtr 1 185.84 185.84
Bey:1 Km.Per 1/2Km. 0 277.03 0.00 Bey:1 Km.Per 1/2Km. 0 584.86 0.00
Bey:100 Mtr Per 50 Mtr 8 25.89 207.12 Bey:100 Mtr Per 50 Mtr 8 54.66 437.28
Total : 295.15 Total : 623.12
Sand : Stone aggregate below 40mm :
Unit : Per Cum. Unit : Per Cum.
LEAD : By Mech. 89.00 Km. LEAD : By Mech. 89.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 187.02 0.00 1 Km. 0 187.02 0.00
2km 0 216.06 0.00 2 Km. 0 216.06 0.00
3 Km. 0 244.77 0.00 3 Km. 0 244.77 0.00
4 Km. 0 272.70 0.00 4 Km. 0 272.70 0.00
5 Km. 1 299.32 299.32 5 Km. 1 299.32 299.32
5- 10 Km. 5 24.63 123.15 5- 10 Km. 5 24.63 123.15
10-20 Km. 10 20.59 205.90 10-20 Km. 10 20.59 205.90
Beyond 20 Km. 69 17.32 1195.08 Beyond 20 Km. 69 17.32 1195.08
TOTAL : 1823.45 TOTAL : 1823.45
2) By Head load 2) By Head load
1st. 1 Km. 0 940.32 0.00 1st. 1 Km. 0 940.32 0.00
1st. 100 Mtr 1 149.40 149.40 1st. 100 Mtr 1 149.40 149.40
Bey:1 Km.Per 1/2Km. 0 470.16 0.00 Bey:1 Km.Per 1/2Km. 0 470.16 0.00
Bey:100 Mtr Per 50 Mtr 8 43.94 351.52 Bey:100 Mtr Per 50 Mtr 8 43.94 351.52
Total : 500.92 Total : 500.92
Stone aggregate above 40mm : Building stone :
Unit : Per Cum. Unit : Per Cum.
LEAD : By Mech. 89.00 Km. LEAD : By Mech. 0.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 202.41 0.00 1 Km. 0 202.41 0.00
2 Km. 0 233.84 0.00 2 Km. 0 233.84 0.00
3 Km. 0 264.90 0.00 3 Km. 0 264.90 0.00
4 Km. 0 295.13 0.00 4 Km. 0 295.13 0.00
5 Km. 1 323.94 323.94 5 Km. 0 323.94 0.00
5- 10 Km. 5 26.65 133.25 5- 10 Km. 0 26.65 0.00
10-20 Km. 10 22.28 222.80 10-20 Km. 0 22.28 0.00
Beyond 20 Km. 69 18.75 1293.75 Beyond 20 Km. 0 18.75 0.00
TOTAL : 1973.74 TOTAL : 0.00
2) By Head load 2) By Head load
1st. 1 Km. 0 1016.70 0.00 1st. 1 Km. 0
1016.70 0.00
1st. 100 Mtr 1 161.52 161.52 1st. 100 Mtr 1
161.52 161.52
Bey:1 Km.Per 1/2Km. 0 508.35 0.00 Bey:1 Km.Per 1/2Km. 0
508.35 0.00
Bey:100 Mtr Per 50 Mtr 8 47.51 380.08 Bey:100 Mtr Per 50 Mtr 847.51 380.08
Total : 541.60 Total : 541.60
Soling Stone : Heavy material and pipe below 100 mm :
Unit : Per Cum. Unit : Per Tonne.
LEAD : By Mech. 0.00 Km. LEAD : By Mech. 42.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 220.03 0.00 1 Km. 0 124.68 0.00
2 Km. 0 254.19 0.00 2 Km. 0 144.04 0.00
3 Km. 0 287.96 0.00 3 Km. 0 163.18 0.00
4 Km. 0 320.82 0.00 4 Km. 0 181.80 0.00
5 Km. 0 352.14 0.00 5 Km. 1 199.55 199.55
5- 10 Km. 0 28.97 0.00 5- 10 Km. 5 16.42 82.10
10-20 Km. 0 24.22 0.00 10-20 Km. 10 13.73 137.30
Beyond 20 Km. 0 20.38 0.00 Beyond 20 Km. 22 11.55 254.10
TOTAL : 0.00 TOTAL : 673.05
2) By Head load 2) By Head load
1st. 1 Km. 0 940.32 0.00 1st. 1 Km. 0 686.52 0.00
1st. 100 Mtr 1 149.40 149.40 1st. 100 Mtr 1 109.08 109.08
Bey:1 Km.Per 1/2Km. 0 470.16 0.00 Bey:1 Km.Per 1/2Km. 0 343.26 0.00
Bey:100 Mtr Per 50 Mtr 8 43.94 351.52 Bey:100 Mtr Per 50 Mtr 8 32.08 256.64
Total : 500.92 Total : 365.72
Bricks : Timber :
Unit : Per 1000.Nos. Unit : Per Cum.
LEAD : By Mech. 77.00 Km. LEAD : By Mech. 42.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 467.56 0.00 1 Km. 0 187.02 0.00
2 Km. 0 540.16 0.00 2 Km. 0 216.06 0.00
3 Km. 0 611.93 0.00 3 Km. 0 244.77 0.00
4 Km. 0 681.74 0.00 4 Km. 0 272.70 0.00
5 Km. 1 748.30 748.30 5 Km. 1 299.32 299.32
5- 10 Km. 5 61.57 307.85 5- 10 Km. 5 24.63 123.15
10-20 Km. 10 51.48 514.80 10-20 Km. 10 20.59 205.90
Beyond 20 Km. 57 43.31 2468.67 Beyond 20 Km. 22 17.32 381.04
TOTAL : 4039.62 TOTAL : 1009.41
2) By Head load 2) By Head load
1st. 1 Km. 0 1755.43 0.00 1st. 1 Km. 0 751.99 0.00
1st. 100 Mtr 1 278.89 278.89 1st. 100 Mtr 1 119.47 119.47
Bey:1 Km.Per 1/2Km. 0 877.72 0.00 Bey:1 Km.Per 1/2Km. 0 376.00 0.00
Bey:100 Mtr Per 50 Mtr 8 82.03 656.24 Bey:100 Mtr Per 50 Mtr 8 35.14 281.12
Total : 935.13 Total : 400.59
MSERW Pipe:- MS Flange :-
Unit : MT Unit : MT
LEAD : By Mech. 292.00 Km. LEAD : By Mech. 292.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 124.68 0.00 1 Km. 0 124.68 0.00
2 Km. 0 144.04 0.00 2 Km. 0 144.04 0.00
3 Km. 0 163.18 0.00 3 Km. 0 163.18 0.00
4 Km. 0 181.80 0.00 4 Km. 0 181.80 0.00
50 Km. 1 199.55 199.55 5 Km. 1 199.55 199.55
5- 10 Km. 5 16.42 82.10 5- 10 Km. 5 16.42 82.10
10-20 Km. 10 13.73 137.30 10-20 Km. 10 13.73 137.30
Beyond 20 Km. 272 11.55 3141.60 Beyond 20 Km. 272 11.55 3141.60
TOTAL : 3560.55 TOTAL : 3560.55
2) By Head load 2) By Head load
1st. 1 Km. 0 1169.72 0.00 1st. 1 Km. 0 686.52 0.00
1st. 100 Mtr 1 185.84 185.84 1st. 100 Mtr 1 109.08 109.08
Bey:1 Km.Per 1/2Km. 0 584.86 0.00 Bey:1 Km.Per 1/2Km. 0 343.26 0.00
Bey:100 Mtr Per 50 Mtr 8 54.66 437.28 Bey:100 Mtr Per 50 Mtr 8 32.08 256.64
Total : 623.12 Total : 365.72
Heavy material i.e Valves etc. From Solan:
Unit : Per Tonne.
LEAD : By Mech. 60.00 Km.
By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km.
1 Km. 0 124.68 0.00
2 Km. 0 144.04 0.00
3 Km. 0 163.18 0.00
4 Km. 0 181.80 0.00
5 Km. 1 199.55 199.55
5- 10 Km. 5 16.42 82.10
10-20 Km. 10 13.73 137.30
Beyond 20 Km. 40 11.55 462.00
TOTAL : 880.95
2) By Head load
1st. 1 Km. 0 686.52 0.00
1st. 100 Mtr 1 109.08 109.08
Bey:1 Km.Per 1/2Km. 0 343.26 0.00
Bey:100 Mtr Per 50 Mtr 8 32.08 256.64
Total : 365.72
Carriage of Prepainted Sheet:- DI Pipes 150 mm f :
Unit : Cum Unit : Per 100.Rmt.
LEAD : By Mech. 0.00 Km. LEAD : By Mech. 292.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 124.68 0.00 1 Km. 0 510.99 0.00
2 Km. 0 144.04 0.00 2 Km. 0 590.34 0.00
3 Km. 0 163.18 0.00 3 Km. 0 668.77 0.00
4 Km. 0 181.80 0.00 4 Km. 0 745.07 0.00
5 Km. 0 199.55 0.00 5 Km. 1 817.81 817.81
5- 10 Km. 0 16.42 0.00 5- 10 Km. 5 67.28 336.40
10-20 Km. 0 13.73 0.00 10-20 Km. 10 56.26 562.60
Beyond 20 Km. 0 11.55 0.00 Beyond 20 Km. 272 47.33 12873.76
TOTAL : 0.00 TOTAL : 14590.57
2) By Head load 2) By Head load
1st. 1 Km. 0 1169.72 0.00 1st. 1 Km. 0 2614.44 0.00
1st. 100 Mtr 1 185.84 185.84 1st. 100 Mtr 1 415.38 415.38
Bey:1 Km.Per 1/2Km. 0 584.86 0.00 Bey:1 Km.Per 1/2Km. 0 1307.22 0.00
Bey:100 Mtr Per 50 Mtr 8 54.66 437.28 Bey:100 Mtr Per 50 Mtr 8 122.17 977.36
Total : 623.12 Total : 1392.74
DI Pipes 200 mm f : DI Pipes 250 mm f :
Unit : Per 100.Rmt. Unit : Per 100.Rmt.
LEAD : By Mech. 292.00 Km. LEAD : By Mech. 292.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 851.66 0.00 1 Km. 0 1161.35 0.00
2 Km. 0 983.90 0.00 2 Km. 0 1341.68 0.00
3 Km. 0 1114.62 0.00 3 Km. 0 1519.93 0.00
4 Km. 0 1241.79 0.00 4 Km. 0 1693.34 0.00
5 Km. 1 1363.01 1363.01 5 Km. 1 1858.66 1858.66
5- 10 Km. 5 112.14 560.70 5- 10 Km. 5 152.92 764.60
10-20 Km. 10 93.76 937.60 10-20 Km. 10 127.86 1278.60
Beyond 20 Km. 272 78.89 21458.08 Beyond 20 Km. 272 107.58 29261.76
TOTAL : 24319.39 TOTAL : 33163.62
2) By Head load 2) By Head load
1st. 1 Km. 0 3923.27 0.00 1st. 1 Km. 0 6895.73 0.00
1st. 100 Mtr 1 623.33 623.33 1st. 100 Mtr 1 1095.59 1095.59
Bey:1 Km.Per 1/2Km. 0 1961.64 0.00 Bey:1 Km.Per 1/2Km. 0 3447.87 0.00
Bey:100 Mtr Per 50 Mtr 8 183.33 1466.64 Bey:100 Mtr Per 50 Mtr 8 322.23 2577.84
Total : 2089.97 Total : 3673.43

DI Pipes 300 mm f : DI Pipes 350 mm f :


Unit : Per 100.Rmt. Unit : Per 100.Rmt.
LEAD : By Mech. 292.00 Km. LEAD : By Mech. 292.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 1502.93 0.00 1 Km. 0 2129.14 0.00
2 Km. 0 1736.29 0.00 2 Km. 0 2459.74 0.00
3 Km. 0 1966.97 0.00 3 Km. 0 2786.54 0.00
4 Km. 0 2191.39 0.00 4 Km. 0 3104.46 0.00
5 Km. 1 2405.32 2405.32 5 Km. 1 3407.54 3407.54
5- 10 Km. 5 197.89 989.45 5- 10 Km. 5 280.35 1401.75
10-20 Km. 10 165.46 1654.60 10-20 Km. 10 234.40 2344.00
Beyond 20 Km. 272 139.22 37867.84 Beyond 20 Km. 272 197.22 53643.84
TOTAL : 42917.21 TOTAL : 60797.13
2) By Head load 2) By Head load
1st. 1 Km. 0 8629.12 0.00 1st. 1 Km. 0 12336.89 0.00
1st. 100 Mtr 1 1370.98 1370.98 1st. 100 Mtr 1 1960.07 1960.07
Bey:1 Km.Per 1/2Km. 0 4314.56 0.00 Bey:1 Km.Per 1/2Km. 0 6168.45 0.00
Bey:100 Mtr Per 50 Mtr 8 403.23 3225.84 Bey:100 Mtr Per 50 Mtr 8 576.49 4611.92
Total : 4596.82 Total : 6571.99
DI Pipes 400 mm f : DI Pipes 450 / 500 mm f :
Unit : Per 100.Rmt. Unit : Per 100.Rmt.
LEAD : By Mech. 292.00 Km. LEAD : By Mech. 292.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 2838.86 0.00 1 Km. 0 3649.96 0.00
2 Km. 0 3279.66 0.00 2 Km. 0 4216.71 0.00
3 Km. 0 3715.39 0.00 3 Km. 0 4776.93 0.00
4 Km. 0 4139.28 0.00 4 Km. 0 5321.94 0.00
5 Km. 1 4543.38 4543.38 5 Km. 1 5841.49 5841.49
5- 10 Km. 5 373.80 1869.00 5- 10 Km. 5 480.60 2403.00
10-20 Km. 10 312.54 3125.40 10-20 Km. 10 401.83 4018.30
Beyond 20 Km. 272 262.96 71525.12 Beyond 20 Km. 272 338.10 91963.20
TOTAL : 81062.90 TOTAL : 104225.99
2) By Head load 2) By Head load
1st. 1 Km. 0 14355.76 0.00 1st. 1 Km. 0 19141.01 0.00
1st. 100 Mtr 1 2280.82 2280.82 1st. 100 Mtr 1 3041.09 3041.09
Bey:1 Km.Per 1/2Km. 0 7177.88 0.00 Bey:1 Km.Per 1/2Km. 0 9570.51 0.00
Bey:100 Mtr Per 50 Mtr 8 670.83 5366.64 Bey:100 Mtr Per 50 Mtr 8 894.44 7155.52
Total : 7647.46 Total : 10196.61
GMS Pipes 80 mm f : GMS Pipes 100 mm f :
Unit : Per 100.Rmt. Unit : Per 100.Rmt.
LEAD : By Mech. 42.00 Km. LEAD : By Mech. 42.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 283.89 0.00 1 Km. 0 319.37 0.00
2 Km. 0 327.97 0.00 2 Km. 0 368.96 0.00
3 Km. 0 371.54 0.00 3 Km. 0 417.98 0.00
4 Km. 0 413.93 0.00 4 Km. 0 465.67 0.00
5 Km. 1 454.34 454.34 5 Km. 1 511.13 511.13
5- 10 Km. 5 37.38 186.90 5- 10 Km. 5 42.05 210.25
10-20 Km. 10 31.25 312.50 10-20 Km. 10 35.16 351.60
Beyond 20 Km. 22 26.30 578.60 Beyond 20 Km. 22 29.58 650.76
TOTAL : 1532.34 TOTAL : 1723.74
2) By Head load 2) By Head load
1st. 1 Km. 0 686.52 0.00 1st. 1 Km. 0 1855.60 0.00
1st. 100 Mtr 1 109.08 109.08 1st. 100 Mtr 1 294.82 294.82
Bey:1 Km.Per 1/2Km. 0 343.26 0.00 Bey:1 Km.Per 1/2Km. 0 927.80 0.00
Bey:100 Mtr Per 50 Mtr 8 32.08 256.64 Bey:100 Mtr Per 50 Mtr 8 86.71 693.68
Total : 365.72 Total : 988.50
RCC Pipes 150 mm f : RCC Pipes 250 mm f :
Unit : Per 100.Rmt. Unit : Per 100.Rmt.
LEAD : By Mech. 0.00 Km. LEAD : By Mech. 0.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 510.99 0.00 1 Km. 0 1161.35 0.00
2 Km. 0 590.34 0.00 2 Km. 0 1341.68 0.00
3 Km. 0 668.77 0.00 3 Km. 0 1519.93 0.00
4 Km. 0 745.07 0.00 4 Km. 0 1693.34 0.00
5 Km. 0 817.81 0.00 5 Km. 0 1858.66 0.00
5- 10 Km. 0 67.28 0.00 5- 10 Km. 0 152.92 0.00
10-20 Km. 0 56.26 0.00 10-20 Km. 0 127.86 0.00
Beyond 20 Km. 0 47.33 0.00 Beyond 20 Km. 0 107.58 0.00
TOTAL : 0.00 TOTAL : 0.00
2) By Head load 2) By Head load
1st. 1 Km. 0 2614.44 0.00 1st. 1 Km. 0 6895.73 0.00
1st. 100 Mtr 1 415.38 415.38 1st. 100 Mtr 1 1095.59 1095.59
Bey:1 Km.Per 1/2Km. 0 1307.22 0.00 Bey:1 Km.Per 1/2Km. 0 3447.87 0.00
Bey:100 Mtr Per 50 Mtr 8 122.17 977.36 Bey:100 Mtr Per 50 Mtr 8 322.23 2577.84
Total : 1392.74 Total : 3673.43
ACP Pipes 150 mm f : ACP Pipes 200 mm f :
Unit : Per 100.Rmt. Unit : Per 100.Rmt.
LEAD : By Mech. 0.00 Km. LEAD : By Mech. 0.00 Km.
By Head : 0.50 Km. By Head : 0.50 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 510.99 0.00 1 Km. 0 851.66 0.00
2 Km. 0 590.34 0.00 2 Km. 0 983.90 0.00
3 Km. 0 668.77 0.00 3 Km. 0 1114.62 0.00
4 Km. 0 745.07 0.00 4 Km. 0 1241.79 0.00
5 Km. 0 817.81 0.00 5 Km. 0 1363.01 0.00
5- 10 Km. 0 67.28 0.00 5- 10 Km. 0 112.14 0.00
10-20 Km. 0 56.26 0.00 10-20 Km. 0 93.76 0.00
Beyond 20 Km. 0 47.33 0.00 Beyond 20 Km. 0 78.89 0.00
TOTAL : 0.00 TOTAL : 0.00
2) By Head load 2) By Head load
1st. 1 Km. 0 2614.44 0.00 1st. 1 Km. 0 3923.27 0.00
1st. 100 Mtr 1 415.38 415.38 1st. 100 Mtr 1 623.33 623.33
Bey:1 Km.Per 1/2Km. 0 1307.22 0.00 Bey:1 Km.Per 1/2Km. 0 1961.64 0.00
Bey:100 Mtr Per 50 Mtr 8 122.17 977.36 Bey:100 Mtr Per 50 Mtr 8 183.33 1466.64
Total : 1392.74 Total : 2089.97
ACP Pipes 250 mm f : ACP Pipes 300 mm f :
Unit : Per 100.Rmt. Unit : Per 100.Rmt.
LEAD : By Mech. Km. LEAD : By Mech. 0.00 Km.
By Head : Km. By Head : 0.00 Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 1161.35 0.00 1 Km. 0 1502.93 0.00
2 Km. 0 1341.68 0.00 2 Km. 0 1736.29 0.00
3 Km. 0 1519.93 0.00 3 Km. 0 1966.97 0.00
4 Km. 0 1693.34 0.00 4 Km. 0 2191.39 0.00
5 Km. 0 1858.66 0.00 5 Km. 0 2405.32 0.00
5- 10 Km. 0 152.92 0.00 5- 10 Km. 0 197.89 0.00
10-20 Km. 0 127.86 0.00 10-20 Km. 0 165.46 0.00
Beyond 20 Km. 0 107.58 0.00 Beyond 20 Km. 0 139.22 0.00
TOTAL : 0.00 TOTAL : 0.00
2) By Head load 2) By Head load
1st. 1 Km. 0 6895.73 0.00 1st. 1 Km. 0 8629.12 0.00
1st. 100 Mtr 0 1095.59 0.00 1st. 100 Mtr 0 1370.98 0.00
Bey:1 Km.Per 1/2Km. 0 3447.87 0.00 Bey:1 Km.Per 1/2Km. 0 4314.56 0.00
Bey:100 Mtr Per 50 Mtr 0 322.23 0.00 Bey:100 Mtr Per 50 Mtr 0 403.23 0.00
Total : 0.00 Total : 0.00
ACP Pipes 350 mm f : Heavy material i.e. Valves :
Unit : Per 100.Rmt. Unit : Per Tonne.
LEAD : By Mech. 25.00 Km. LEAD : By Mech. Km.
By Head : 0.60 Km. By Head : Km.
1) By Mech. Nos. Rate/ Km. 1) By Mech. Nos. Rate/ Km.
1 Km. 0 2129.14 0.00 1 Km. 0 124.68 0.00
2 Km. 0 2459.74 0.00 2 Km. 0 144.04 0.00
3 Km. 0 2786.54 0.00 3 Km. 0 163.18 0.00
4 Km. 0 3104.46 0.00 4 Km. 0 181.80 0.00
5 Km. 1 3407.54 3407.54 5 Km. 0 199.55 0.00
5- 10 Km. 5 280.35 1401.75 5- 10 Km. 0 16.42 0.00
10-20 Km. 10 234.40 2344.00 10-20 Km. 0 13.73 0.00
Beyond 20 Km. 5 197.22 986.10 Beyond 20 Km. 0 11.55 0.00
TOTAL : 8139.39 TOTAL : 0.00
2) By Head load 2) By Head load
1st. 1 Km. 0 12336.89 0.00 1st. 1 Km. 0 686.52 0.00
1st. 100 Mtr 1 1960.07 1960.07 1st. 100 Mtr 0 109.08 0.00
Bey:1 Km.Per 1/2Km. 0 6168.45 0.00 Bey:1 Km.Per 1/2Km. 0 343.26 0.00
Bey:100 Mtr Per 50 Mtr 10 576.49 5764.90 Bey:100 Mtr Per 50 Mtr 0 32.08 0.00
Total : 7724.97 Total : 0.00
ACP Pipes 350 mm f :
Unit : Per 100.Rmt.
LEAD : By Mech. 25.00 Km.
By Head : 0.60 Km.
1) By Mech. Nos. Rate/ Km.
1 Km. 0 8501.09 0.00
2 Km. 0 9821.09 0.00
3 Km. 0 11125.91 0.00
4 Km. 0 12395.27 0.00
5 Km. 1 13605.36 13605.36
5- 10 Km. 5 1119.36 5596.80
10-20 Km. 10 935.91 9359.10
Beyond 20 Km. 5 787.45 3937.25
TOTAL : 32498.51
2) By Head load
1st. 1 Km. 0 2631.97 0.00
1st. 100 Mtr 1 418.15 418.15
Bey:1 Km.Per 1/2Km. 0 1315.99 0.00
Bey:100 Mtr Per 50 Mtr 10 122.99 1229.90
Total : 1648.05