Project Crashing Assignment
Project Crashing Assignment
Project Crashing Assignment
Submitted by:
Abhilash R J 19002
Kishor M 19027
Mena Suresh 19030
E1 0 L6 26
E2 8 L5 14
E3 16 L4 14
E4 13 L3 21
E5 14 L2 8
E6 26 L1 0
Activity Time EST EFT LST LFT Total Float
A 1-5 10 0 10 4 14 4
B 1-2 8 0 8 0 8 0
C 2-4 5 8 13 9 14 1
D 2-5 6 8 14 8 14 0
E 2-3 8 8 16 13 21 5
F 3-6 5 16 21 21 26 5
G 5-6 12 14 26 14 26 0
Activity normal time(weeks) normal crash time crash
cost(Rs) (weeks) cost(Rs)
A 1-5 10 20000 7 30000
B 1-2 8 15000 6 20000
C 2-5 5 8000 4 14000
D 2-4 6 11000 4 15000
E 2-3 8 9000 5 15000
F 3-6 5 5000 4 8000
G 5-6 12 3000 8 4000
total fixed cost 71000
crash G by 4 times
total cost 133600
crash D by 1 times
total cost 132800
crash B by 2 times
total cost 132200
In this case, we crashed the project from 26 weeks to 19 weeks. Also, cost is considered in
this case, we used more resources for the project so that the project could be completed
earlier than predicted. The overall cost of the project is also reduced from Rs.143800/- to
Rs.132200/- after crashing the project.
The company will be benefited in all perspectives, such as new project can be done.