Project Crashing Assignment

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Project Crashing assignment

Submitted by:

Abhilash R J 19002
Kishor M 19027
Mena Suresh 19030

E1 0 L6 26
E2 8 L5 14
E3 16 L4 14
E4 13 L3 21
E5 14 L2 8
E6 26 L1 0
Activity   Time EST EFT LST LFT Total Float
A 1-5 10 0 10 4 14 4
B 1-2 8 0 8 0 8 0
C 2-4 5 8 13 9 14 1
D 2-5 6 8 14 8 14 0
E 2-3 8 8 16 13 21 5
F 3-6 5 16 21 21 26 5
G 5-6 12 14 26 14 26 0
Activity   normal time(weeks) normal crash time crash
cost(Rs) (weeks) cost(Rs)
A 1-5 10 20000 7 30000
B 1-2 8 15000 6 20000
C 2-5 5 8000 4 14000
D 2-4 6 11000 4 15000
E 2-3 8 9000 5 15000
F 3-6 5 5000 4 8000
G 5-6 12 3000 8 4000
    total fixed cost 71000    

activity crash slope time


3333.3333
A 3 3
B 2500 2
C 6000 1
D 2000 2
E 2000 3
F 3000 1
G 250 4

critical path 1-2-5-6(BDG) 26 weeks

Total cost 143800

crash G by 4 times
total cost 133600

Critical path BDG 22 weeks

crash D by 1 times
total cost 132800

critical path BDG 21 weeks

crash B by 2 times
total cost 132200

critical path BDG 19 weeks


All activities on the critical path is crashed for 7 weeks.
Project Crashing is normally done during these conditions:
1. Time to market pressures
2. Unforeseen delays
3. Incentives for early completion
4. Imposed deadlines
5. Pressures to move resources elsewhere

In this case, we crashed the project from 26 weeks to 19 weeks. Also, cost is considered in
this case, we used more resources for the project so that the project could be completed
earlier than predicted. The overall cost of the project is also reduced from Rs.143800/- to
Rs.132200/- after crashing the project.
The company will be benefited in all perspectives, such as new project can be done.