REINFORCED CONCRETE
ANCHOR BLOCK 01

199
585 585 585 199
585

C C

4.00m DIA. STEEL PIPE

ORIGINAL GROUND 597


597
335
PROPOSED GROUND
335
335
335

B B
REINFORCED CONCRETE
ANCHOR BLOCK 03
ORIGINAL GROUND

138
137

413 412

NOTE:
1. MAINTAIN A MINIMUM OF 300mm CONCRETE
COVER ON ALL ANCHOR BLOCKS.
2. MAINTAIN 1200mm DISTANCE BETWEEN PIPE
AND GROUND.
3. PROVIDE 75mm CLEAR CONCRETE COVER.

UNITED HYDRO ENGINEER PRC NO. 079719 NAME DATE PROPONENT PROJECT TITLE SHEET CONTENT SCHEME No. PROJECT NO.
PTR NO. 4078666 DESIGN RAL 21 MAY 2020 PIPE BEND 01, 02 & 03 DETAILS 1 HEPP-46
POWER BUILDERS DATE 02-21-2019 CADD JCE 26 MAY 2020
MANTUNO MINI-HYDRO PROJECT REV. No.
SHEET NO.
PLACE BAGUIO CITY CHECKED RAL SEPT 2020 LOCATION:
1
RODRIGO A. LIZARDO JR. - MSCE, A.M. ASCE BAMBANG, NUEVA VIZCAYA
T.I.N. 106-635-680 APPROVED RAL SEPT 2020 8 JUN 2020 PS-03