GE Power Item No.

: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

HRSG Drum End Enclosures

TABLE OF CONTENTS

1.0 INSTRUCTIONS TO SUPPLIER ................................................................................................ 2

2.0 EQUIPMENT FURNISHED BY SUPPLIER ................................................................................ 2

4.0 CONTRACT SPECIFIC DATA .................................................................................................... 5

6.0 PERFORMANCE AND TECHNICAL DATA ............................................................................... 6

4.0 CONTRACT SPECIFIC DATA ................................................................................................. 10

6.0 APPLICABLE SPECIFICATIONS AND DOCUMENTS ........................................................... 10

7.0 DOCUMENTATION REQUIREMENTS................................................................................... 11

Revision History
Rev. Revision Date Created by Checked by Approved by Brief Description
A 19 Jul 2019 AP BC SD Initial issue.

Description Curent Revision


Initial issue.

Page 1 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

1.0 INSTRUCTIONS TO SUPPLIER

1.1 Materials and equipment must be new and of proven design.

1.2 Materials containing asbestos, PCBs, ceramic fiber, or any other hazardous materials are not
allowed. Material safety data sheets shall be submitted for all paint, insulation, and
lubricants.

1.3 All quotations and attachments submitted to the Purchaser shall be in the English language.

1.4 All quotations and inquiries to the Purchaser shall be routed through Purchasing.

1.5 Parts subject to wear, corrosion, deterioration or requiring adjustment, inspection or repair
shall be accessible and capable of reasonably convenient removal, replacement and repair.

1.6 All omissions or exceptions to the requirements of this specification must be included by the
SUPPLIER.

1.7 Optional equipment shall be priced separately.

1.8 The SUPPLIER shall be governed by the regulations, codes, and standards, including their
respective addenda, amendments, and errata in attachment 21000_TECH SUPPLEMENTAL
SPEC – Site Meteorological and Seismic Data. For equipment other than of US origin, foreign
regulations, codes, and standards are subject to Purchaser’s approval.

Component or System Standards for Product Design,


Standards for Materials
Fabrication, and Examination

1. General Codes
Mechanical Design of steel AISC Shapes w/ A992 or
AISC, AWS
structure and ducting A572 Gr. 50 or equivalent
Inspection and Tests AISC, AWS
2. Civil Works
Drum End Enclosure ASCE7-10 ASTM
Steel Structures AISC
Earthquake, seismic ASCE7-10
3. Others
Quality Assurance ISO 9001:2000

2.0 EQUIPMENT FURNISHED BY SUPPLIER

2.1 DRUM END ENCLOSURES


Each end of each steam drum shall be enclosed with an insulated, weatherproof DRUM END
ENCLOSURE suitable for operating and maintenance personnel. There are three (3) drums
per unit and one (4) unit per contract. The HP Drums will have one enclosure for each drum
end while the IP and LP Drums will have one combined enclosure per drum end, for a total of

Page 2 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

four (4) DRUM END ENCLOSURES per unit. The DRUM END ENCLOSURES shall include but
are not limited to the following equipment.

Item Supplier Supplier Not


No. Description GE Base Option EPC Applicable
1 Independent, Self-Supported Structure
Off GEMain Platform, HRSG Drum End X
Enclosure Design
2 Incorporating HRSG Silencers/HRSG Main
Platform Enclosure Steel (see silencer X
listing in section 4.2)
3 HRSG Main Platform Enclosure Design -
Itemized Offer Including:
a.) Steel Structure (Any Steel Required for
Drum End Enclosure) - Design & Materials
b.) Wall Panels
c.) Lighting (Fluorescent Lights, Switches, X
Etc. For Complete System)
d.) Heating/Ventilating
/Louvers/Temperature Controls
e.) Watertight Floor

4 Silencer Support Steel & Canopy X


5 Main Platform Steel, Grating, etc. X
6 HRSG Bottom Enclosure X
7 Insulated Doors including Hinges,
Doorknobs, etc. X

8 Maintenance Door for SCR Catalyst


X
Monorail
9 Windows and Window Penetrations X
10 Flashing/Seals for All Drum End Enclosure
Penetrations X
11 Gutters/Downspouts X
12 Roof Ice Breakers X
13 Lighting - Design & Material Supply X
14 Heating/Ventilating or Louver with
Temperature Controlled Electric Heater - X
Design & Material Supply
15 Conduits Required for Lighting or
Heating/Ventilating X
(Located Inside Drum End Enclosure)
16 Single Junction Box Per Enclosure for
Lighting & Heating/Ventilating X
17 Fire Protection System, if Required by
X
Codes

Page 3 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

Item Supplier Supplier Not


No. Description GE Base Option EPC Applicable
18 PE Stamping of Steel Erection Documents X
19 Building Permits X
20 Field Erection (on a per diem, time &
X
material basis)
21 Field Erection Supervision (on a per diem,
X
time & material basis)
22 Wall Panel Lifting Beams/Devices
Required for Erection X
23 Hardware for All Supplied Items X
24 Galvanized Supporting Steel X

One end of each steam drum shall be enclosed with a single, insulated, weatherproof drum end
enclosure suitable for operating and maintenance personnel. The enclosure shall include electric
heaters and ventilation. The enclosure shall include all instrumentation and connecting lines that
require freeze protection. A 1-inch (25 mm) blowdown drain line connection shall be provided for
instrumentation in the designated instrumentation areas. The minimum distance between the drum
and the enclosure walls shall be 54-inches (1,372 mm). If the Supplier requires instrumentation on
both ends of the drums, insulated, weatherproof enclosures shall be provided on both ends.

Heating, Ventilation &Air Conditioning (HVAC) (Contract 18.2.9)

The HVAC system is designed by others and is assumed to meet the following criteria:
• Offices, control room and locker rooms are based on the following design criteria:
- Winter Temperature 24°C (75°F)
- Summer Temperature 27°C (80°F)
• Ventilated areas are based on 8°C (14°F) rise above ambient
• HVAC equipment does not contain chlorofluorocarbons (CFCs)
• Batteries for the DC battery systems are located in a ventilated room or
compartment
• Electrical equipment ratings are based on job specific typical maxim um am bient
temperatures. Typical maximum is the ambient temperature that is exceeded
annually less than 2% of the time, as defined by the American Society of Heating,
Refrigerating and Air-conditioning Engineers (ASH RAE). Where the typical
maximum ambient exceeds 40°C (104°F), equipment shall be evaluated relative to
actual operating loads vs. nameplate rating to verify proper sizing.

2.2 LIGHTING

Supplier is to provide adequate fluorescent lighting to meet all industry standards and Ohio
Hannibal code. Lighting is to be complete scope including but not limited to: light fixtures,
bulbs, switches, cable trays/conduit, junction box, drawings, lighting plans, etc. All electric
connections are to terminate in a single junction box per enclosure along with the heating
and ventilation. Supplier’s proposal is to include as much detail as possible to be able to fully
describe the proposed design to the EPC/Owner.

2.3 HEATING/VENTILATION

Page 4 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

Supplier is to provide a complete thermostatically controlled electric HVAC system to


maintain proper indoor ambient conditions within the enclosure within the minimum and
maximum ambient temperature range defined in 21000_TECH SUPPLEMENTAL SPEC. HVAC
is to be complete scope including but not limited to: electric heater, air conditioning, louvers,
thermostat, cable trays/conduits, etc. Supplier’s design is to take the heat generated internal
to the enclosure by the HRSG drums and instruments into account when designing. These
value and assumptions are as follows:

Enclosure Heat Load (kW)


HP Drum, Right Side 2.2
HP Drum, Left Side 2.2
IP/LP Drum, Right Side 4.6
IP/LP Drum, Left Side 4.6

1. Assumed 10% margin.


2. Full drum header surface area used to calculate heat load.
3. 250 W/m2 heat loss assumed for casing, drums, and piping.
4. No HRSG roof heat flow into the enclosure
5. No heat loss or gain is considered for the enclosure. Enclosure heat loss or gain is to be
determined by the vendor.

Supplier’s proposal is to include as much detail as possible to be able to fully describe the proposed
design to the EPC/Owner.

3.0 CONTRACT SPECIFIC DATA

See attachments in Section 6.

Page 5 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

4.0 DESIGN DATA AND PHYSICAL ATTRIBUTES FOR THE BUILDING ( By A&M)

4.1 SKETCHES

All dimensions from the following sketches are preliminary but should be within two (2) inches from
the final dimensions.

HP Right Side:

Page 6 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

HP Left Side:

Page 7 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

IP/LP Right Side:

Page 8 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

IP/LP Left Side:

1. The supplier is to provide cost optimal solution for building layout. The following dimensions
are preliminary:

Enclosure Width (mm) Length (mm) Height (mm)


HP Drum Right Side 3900 5000 4500
HP Drum Left Side 3900 5000 4500
IP/LP Drum Right Side 7000 5000 4500” to 5000
IP/LP Drum Left Side 7000 5000 4500” to 5000

The minimum distance between the drum end and the opposite enclosure wall shall be 1,372 mm.

Page 9 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

2. Platform arrangement is preliminary and shall be optimized by GE/Supplier.

4.2 PENETRATIONS

Enclosure Penetration Dimension


HP Drum Right Side HP Drum TBD; Drum OD 90.441” (w/o insul), insul thk TBD
HP Drum Left Side HP Drum TBD; Drum OD 90.441” (w/o insul), insul thk TBD
IP Drum TBD; Drum OD 68.598” (w/o insul), insul thk TBD
IP/LP Drum Right Side
LP Drum TBD; Drum OD 109.024” (w/o insul), insul thk TBD
IP Drum TBD; Drum 68.598” (w/o insul), insul thk TBD
LP Drum TBD; Drum 109.024” (w/o insul), insul thk TBD
IP/LP Drum Left Side
LP_DRUM_FEEDWATER
10” Nom Pipe Dia, 1” insul thk
(LHS)
CRH STEAM LHS Side 20” Nom Pipe Dia, 3.5” insul thk
Support Column TBD
1. Penetration coordinates to be provided by GE.
2. Utilities (EPC supplied cable trays, conduits, etc.) to be provided later.
3. Small bore piping penetrations to be provided late
4. Thermal movements for all piping and drum penetrating the enclosure to be provided later.
Supplier shall take these movements into account when designing the flashing/bellows.

4.3 DOORS

1. There will be a total of two (2) doors in each of the Drum End Enclosure.

5.0 ELECTRICAL REQUIREMENTS

1. See Attached EGM-00062-E000

6.0 APPLICABLE SPECIFICATIONS AND DOCUMENTS

1. General Arrangements EGM-00062-D500-0001 to 0004


2. P&IDs EGM-00062-D600-0011 to 0016
3. Platforms EGM-00062- 3d Model.
4. Summary of Mechanical Design Parameters EGM-00062-SZ00-0201
5. HRSG Structural Steel General Notes EGM-00062-D5D0-2002
6. Platforms, Stairs, Ladders, and Handrails EGM-00062-D5H3-2003 to 2005
7. 21000_Tech Supplemental Spec 21000_Tech Supplemental Spec
8. HRSG Arrangement of 78” ID HP Steam Drum EGM-00062-D5A1-1400
9. HRSG Arrangement of 66” ID IP Steam Drum EGM-00062-D5A2-1410
10. HRSG Arrangement of 108” ID LP Steam Drum EGM-00062-D5A3-1420
11. Painting Specification EGM-00062-SZM0-1705

Page 10 of 11
GE Power Item No.: EGM-00062-SZW0-1203
Project: Parnaiba Date: 31- Jul- 2019
Project No.: EGM-00062 Rev.: A
Document Type: N

7.0 DOCUMENTATION REQUIREMENTS

7.1 The following documents and information must be provided:

1. Erection General Arrangements


2. Shop Detail Drawings
3. 3D Model
4. Erection Drawings – with State of Texas PE Stamp Option
5. Steel Loads on HRSG Structure
6. Product Data Sheets for All Items Supplied
7. MSDS for All Items Supplied
8. Lighting Wiring Diagrams
9. Heating/Ventilation/Temperature Control System Wiring Diagrams
10. Component Drawings for All Items Supplied
11. Instruction Manuals for All Items Supplied
12. Erection Procedure Including Lifting Instructions Covering All Items Supplied
13. Equipment List in Customer Supplied Format
14. Electrical Load List in Customer Supplied Format
15. Hardware List
16. Drawing List

Page 11 of 11