8 NOS OF WEIR GATE SIE 2M (WIDTH) X 1M (HEIGHT)


9700

2 NOS OF DE-SILTING GATE SIZE 2M (WIDTH) X 1M (HEIGHT)


500 2000 500 500 2000 500
2500

5000 10000 5000

ELEVATION
20000

250 2000 500 2000 500 2000 500 2000 500 2000 500 2000 500 2000 500 2000 250
1000

1000

1000

1000
3500 500 2000 500 7000 500 2000 500 3500

KEY PLAN
FLOW

MANUAL HOIST SPINDLE

MANUAL HOIST SPINDLE


1050

1000

OPERATING PLATFORM
(RAILING NOT SHOWN)
1700
345 355 1000
FRI = SILL LVL + 9.7M FRL =9.7M

500

Note:-
TOP SEAL LEVL = 8.7M
WEIR GATE
1800

GATE SUPPORTING 1) 8 NOS OF GATE SIZE - 2M (LENGTH) X 1M (HEIGHT) VERTICAL


FRAME SLIDE GATE ARE PROVIDED WITH THE GATE SUPPORTING
FRAME.
1000

FLOW SLIDE GATE IN


STEAM ROD GUIDE CLOSED POSITION 2) THE GATE ARE D/S SEALING TYPE WITH TOP SEAL.

3) THE SCREW HOIST IS PROVIDED WITH MANUAL SPINDLE FOR


SILL LVL = 7.9 RAISING & LOWERING THE GATES.

4) THE GATE SUPPORTING FRAMES ARE EMBEDDED IN O.5M WIDE


RCC PIERS UP TO 1.8M FROM SILL LVL.

DE-SILTING GATE
1850

1) 2 NOS OF DE-SILTING GATES SIZE - 2M (LENGTH) X 1M (HEIGHT)


VERTICAL SLIDE GATE ARE PROVIDED WITH THE GATE
SUPPORTING FRAME.
SIDE ELEVATION AT WEIR GATE
2) THE GATE ARE D/S SEALING TYPE WITH TOP SEAL.
1000
575 3) THE SCREW HOIST IS PROVIDED WITH MANUAL SPINDLE FOR
RAISING & LOWERING THE GATES.

4) THE GATE SUPPORTING FRAMES ARE EMBEDDED IN O.5M WIDE


RCC PIERS UP TO 2.5M FROM SILL LVL.

5) THE OPERATION PLATFORM IS PROVIDED TO OPERATE THE


GATE FROM TOP OF WEIR.

6) AS THE STEM ROD IS VERY LONG, THE STEM ROD GUIDES ARE
PROVIDED AT C/C 1850MM AND EMBEDDED IN WEIR CONCRETE.

Shree Nakoda Infrastructure Private Limited


2500

TOP SEAL LEVL = SILL LVL + 1M


6th Floor, B Block Prakrati Corporate 18/2,
Y.N.Road Indore, Madhya Pradesh India
GATE SUPPORTING
Email-Id : sniplinfo@gmail.com
FRAME

SLIDE GATE IN PROJECT SHUTTER GATE FOR WEIR


CLOSED POSITION

SILL LVL = 0M TITLE GENERAL ARRANGEMENT DRAWING

DRAWN DRG No: SNIPL - SHG - GA - 01 -R1

SIDE ELEVATION AT DE-SILTING GATE CHECKED REV NO : 00 SCALE :NTS

SUBMITTED DATE : NOV 2019

You might also like