Professional Documents
Culture Documents
Construction - Sector - Report May 19 EDEL PDF
Construction - Sector - Report May 19 EDEL PDF
Construction - Sector - Report May 19 EDEL PDF
Daylight Again
Rising urbanisation
India’s urban population, which was ~29% as per 2001 census, had crossed the 31% mark by
the time of 2011 census. In 2017, it had surged to 34%, according to the World Bank.
According to a UN survey, by 2030, ~41% of India’s population will reside in urban areas.
While the number of cities with population of over 10mn is expected to increase from two
(Mumbai and Delhi) in 2011 to eight by 2035, the number of cities with a population of over
India’s urban population is 1mn is expected to jump from 59 in 2015 to 78 by 2035.
surging and so is the vehicular
ownership in the country India, along with China, Indonesia, Nigeria, and the US, will lead the world's urban
population surge by 2050. By 2030, urban areas are likely to contribute ~70% to India’s GDP.
Such a sharp rise will exert more pressure on the already overburdened infrastructure.
Similarly, the number of registered two wheelers per 1,000 population has surged from ~37
in 2001 to ~127 in 2015, and is expected to continue growing at a similar pace.
Chart 1: Vehicle ownership (cars and two wheelers) per 1,000 population
160
Vehicle ownership
130
100
70
40
10
2001
2002
2003
2004
2005
2006
2010
2011
2012
2013
2014
2015
2007
2008
2009
The main reason for such a significant rise in private vehicles is the lack of quality public
transport options in urban areas. The share of public transport in overall urban transport in
India is at an abysmally low of 30%.
60
40
20
South Korea
Western
Russia
China
Singapore
UAE
India
Japan
USA
Europe
Other Car Public Transportation Demand-driven modes
Source: Industry data, Edelweiss research
While this is higher than developed countries/regions such as US, Western Europe and UAE
Share of public transport in India (where personal vehicle ownership per capita is much higher), it is lower than peers like
is much below the desired levels Singapore, South Korea, China, Russia and Japan.
The Ministry of Urban Development has published a desirable share of public transport for
different categories of cities based on population. As per the same, the current share of
public transport, i.e. 30%, is significantly lower than the desirable share. This shows that
there is an urgent need to scale up the public transport infrastructure in major cities.
Increasing number of vehicles is This is not just a matter of inconvenience; these high levels of congestion have huge costs
leading to traffic congestion in attached in the form of reduced productivity, fuel waste and accidents. As an example,
Indian cities, leading to reduced recent estimates from the Bengaluru Development Authority, released as part of Master
productivity, fuel waste and Plan 2031, suggests that 11.8mn citizens waste 600mn person-hours annually and almost
accidents ~0.28mn litres of fuel is wasted per hour in Bengaluru city because of congestion.
Government data indicates that the combined costs due to congestion for the four cities of
Delhi, Mumbai, Kolkata and Bengaluru are over USD22bn annually.
In Delhi alone, congestion was estimated to cost the city USD10bn annually. This congestion
also manifests in the form of logistics and freight inefficiency. A recent study estimated huge
loss of ~USD21bn annually in these top four cities on account of delays and additional fuel
consumption due to poor road conditions and frequent halts.
7.5
5.0
2.5
0.0
Delhi Bengaluru Mumbai Kolkata
It is estimated that the transport sector contributes ~14% of the overall air pollution in India.
Diesel generator
9% Dust and
construction
45%
Transport
14%
Waste burning
17%
Source: Industry data, Edelweiss research
According to scientific studies, at lower speeds due to growing congestion, vehicles burn
fuel inefficiently and pollute more per trip. For example, at average trip speeds between 5
and 20km/hr, which is the range of vehicle speeds in major Indian cities, cars pollutant
emissions were 4-8x as much as when the average speed was 55-70km/hr.
Various studies estimate that the use of public transportation can result in 90–95%
reduction in CO, VOCs and 50% reduction in CO2 and NOX emissions compared to private
vehicles.
Over the past few years, multiple Indian cities have joined the metro bandwagon. As on
date, there are 13 operational metro systems in the country, which places it second in the
ranking of countries in the world on the basis of the number of operational metro systems.
0
South Korea
China
India
US
Turkey
Germany
France
Japan
Russia
Brazil
Italy
Iran
Institutional framework
While transportation is a state subject under the Indian constitution, urban transport has
not been defined as a separate subject. Instead, the allocation of subjects between central
and state list is mode-wise. However, as urban transport is closely linked to urban
development, urban transportation is primarily a state subject.
Both central and state
governments play their part in On the other hand, “Metro railway” is a “railway” as per List I, Entry 22 of the Constitution;
developing metro rail projects accordingly, metro rail projects are to be implemented as central sector projects.
Thus, due to the unique nature of metro projects, participation of both central and state
governments becomes crucial to ensure successful implementation of metro projects. In
order to clearly specify the responsibilities of individual shareholders as well as to limit
liabilities of shareholders, generally, a shareholder agreement is signed.
unbundled activities of the proposed metro rail project, wherever feasible, will be
required.
o Equity Sharing Model: In this model, projects will be taken up under equal
ownership of the Centre and the state government concerned through equal
sharing of equity. PPP in some form for implementation, operation & maintenance,
fare collection or any other unbundled activities of the proposed metro rail project,
wherever feasible, will be required. Government of India will provide financial
support to metro rail projects in the form of equity and subordinate debt (for part
of taxes), subject to an overall ceiling of 20% of the cost of the project excluding
private investment, cost of land, rehabilitation and resettlement.
Seeking to ensure financial viability of metro projects, the new Metro Rail Policy requires
states to clearly indicate in the project report the measures to be taken for
commercial/property development at stations and on other urban land and for other
means of maximum non-fare revenue generation through advertisements, lease of space
etc., backed by statutory support.
Metro Rail Policy 2017 has The earlier requirement of a minimum population of 2mn for a city to be considered for a
relaxed the earlier provision of metro rail project has been relaxed. The new policy now states that the requirement of a
requirement of a minimum metro system will depend on the spatial pattern of the city. Cities with a well spread out
population of 2mn for a city to be spatial pattern, even if they have a high population, may not have sufficient number of
considered for a metro rail project corridors with adequate density to justify investments in a metro. On the other hand,
cities with a linear spatial pattern may justify a metro even at lower population levels as
they have fewer corridors and each would have a high traffic density.
Setting up of Urban Metropolitan Transport Authority (UMTA) has been made
mandatory. This authority is to prepare ‘Comprehensive Mobility Plans’ for cities for
ensuring complete multi-modal integration for optimal utilisation of capacities.
In order to improve the last mile connectivity, the new policy seeks to focus on a
catchment area of 5km on either side of metro stations requiring states to commit to
provide necessary last mile connectivity through feeder services.
Metro projects in India have generally been undertaken in phases, keeping in mind the huge
investments involved and specific requirements of a network. Even within a particular
phase, more than one line has been constructed, depending upon the need for passenger
connectivity. To this extent, most cities have a dynamic metro network with some phases
already operational and others, either under construction or at planning stages.
The first MRTS project in India was the Kolkata Metro, the master plan for which was
prepared in 1971. While the project’s foundation stone was laid down on December 29,
The success of Delhi Metro has 1972, actual construction of Line 1 began only in 1978. The project started commercial
paved the way for metro rail services in 1984.
revolution in India
The second metro project was the Chennai MRTS, which was planned in the 1970s and
1980s, but taken up for implementation by the railways in 1983–84. The project opened in
1995 and was extended twice in 2004 and 2007.
However, the turning point for MRTS in India came with the Delhi Metro. While planning for
the project had started in 1984, Delhi Metro Rail Corporation (DMRC) was registered under
the Companies Act, 1956, only in May 1995. Construction began in 1998 and first section
became operational in 2002. Currently, Phases I, II and III are operational with Phase IV on
the cards. Currently, Delhi Metro is amongst the top 10 in the world as far as network length
is concerned; its annual ridership was 900mn plus in FY18.
Chart 6: Delhi has the largest operational metro rail network in India
400
320
Length (km)
240
160
80
Lucknow
Gurugram
Chennai
Kochi
Hyderabad
Bengaluru
Ahmedabad
Mumbai
Delhi/NCR
Jaipur
Kolkata
Noida
Nagpur
Operational metro projects in India
Source: Government documents, Edelweiss research
While Delhi boasts of the largest
operational metro rail network in Chart 7: Mumbai has the largest under construction metro rail network in India
the country, Mumbai has the 180
maximum length of metro
144
network under construction
Length (km)
108
72
36
Chennai
Kochi
Hyderabad
Bengaluru
Ahmedabad
Delhi/NCR
Mumbai
Pune
Indore
Jaipur
Kolkata
Bhopal
Nagpur
Navi Mumbai
Fig. 1: Metro rail projects being dveleoped across the length and breadth of the country
Civil construction
Civil construction forms the largest chunk in a metro project (more so if it is an underground
project). Major types of civil work involved in a metro projects include tunneling, viaducts,
stations, depots, etc.
Civil construction forms the
biggest portion of metro rail Civil contracts which involve tunnelling or any other structural work are complex and hence
projects; EPC contracts in this face lower competition. As a result, margins in these contracts are higher compared to usual
space enjoy better working construction contracts. Stations, depots, etc., are more of ‘building’ contracts and hence
capital cycle have lower margins.
In our view, more than margins, the benefit of undertaking metro projects lies in the
relatively better working capital cycle for these projects. With funding secured (from
government and multilateral agencies), agencies which develop metro projects generally
pay contractors on time (i.e., have better payment terms). This results in higher RoCEs for
contractors compared with construction projects in other segments where payment cycles
are longer.
Our analysis of civil construction contracts awarded over the past couple of years indicates
that most projects have been won by Indian companies. However, foreign firms have also
started making their presence felt.
Bengaluru Metro Soma Enterprises, ITD Cementation, NCC, Simplex, HCC, L&T, IVRCL
Mumbai Metro Reliance Infra, Simplex, J Kumar, RCC-MBZ, L&T, Soma, ITD Cementation, TPL, NCC, SEW Infra, Ahluwalia
Contract, GGYHBCL-Neeraj Cement Structural-MPKHS, Continental Engineering
Chennai Metro Gammon, Afcons, NCC, URC Construction, L&T, Consolidated Construction
Hyderabad Metro L&T
Ahmedabad Metro J Kumar, URC Construction, Afcons, L&T, TPL, Ranjit Buildcon, Simplex, DRA – CICO, Pratibha Industries,
Gannon Dunkerly-PSPO
Pune Metro NCC, HCC, J Kumar, TPL
Lucknow Metro L&T, Sam India, TPL, SP Singla
Kochi Metro L&T, Soma Enterprises, Era-Ranken, McNally Bharat, CVCC-VNC
Nagpur Metro NCC, Pratibha Industries, Afcons, ITD Cementation
Indore Metro Dilip Buildcon
Bhopal Metro Dilip Buildcon
Navi Mumbai Metro J Kumar, NCC, San José Constructora
Kolkata Metro Simplex, L&T, Consolidated Construction, ITD Cementation, Afcons
Gurugram Metro NCC, IL & FS
Jaipur Metro DSC Limited, ITD Cementation, Pratibha Industries, BL Kashyap, Continental Engineering, KMV-RVR
Rolling stock
The rolling stock used in various Indian cities uses broad and standard gauge. Apart from
Delhi and Kolkata Metros, which use both these gauges, all other networks use only
standard gauge.
Rolling stock forms 15-20% of As far as Delhi Metro is concerned, while broad gauge was used in Phase I, from Phase II
overall project cost; most contracts lines are using standard gauge rolling stock. In Kolkata, while Line 1 uses broad gauge,
for rolling stock have been won by standard gauge is being used in Line 2.
foreign companies
Rolling stock forms 15-20% of overall project cost. Our analysis of rolling stock orders which
have been awarded so far indicates that these orders are generally awarded 6-12 months
after civil construction starts.
Most contracts in this field have been won by foreign companies like Hyundai Rotem,
Bombardier, Alstom, CSR Nanjing, CRRC, among others. The only Indian player to make its
presence felt is BEML. Titagarh Wagons has also started bidding for metro rail coaches over
the past year. News reports suggest that Maha Metro is setting up its own coach
manufacturing facility in Wardha, where it is planning to manufacture coaches for Pune and
Nagpur Metros.
The burgeoning opportunity for rolling stock in India will continue to attract global majors. In
fact, some of them have started manufacturing coaches in India as increased indigenisation
will boost cost savings. For e.g., Bombardier has a plant in Savli (Vadodara), while Alstom has a
plant in Sri City SEZ, Tada.
Systems work
Apart from civil construction and rolling stock, the other major component in the
Like rolling stock, majority of the
development of a metro network is the systems work. This includes signalling &
orders in the systems space have
communication systems, power transmission, track laying, baggage handling system,
been bagged by foreign firms
automation control systems, fare collection systems, etc.
Our analysis of orders awarded in this space indicates that like rolling stock, majority of the
orders in this space have been bagged by foreign firms (sometimes in collaboration with
their Indian arms). Akin to rolling stock contracts, systems works are also awarded 6-12
months after civil construction contracts.
Historically, bulk of the rolling stock and systems contracts have been bagged by foreign
firms. However, this may change in the future pursuant to several government initiatives to
Implementation of the ‘Make in promote the ‘Make in India’ programme. These include stipulating certain mandatory
India’ policy is likely to lead to conditions to be incorporated in tender documents of metro companies for procurement of
increasing indigenisation for metro metro cars and related critical equipment and sub-systems, procurement of only ‘Made in
rail equipments India’ signaling equipment, besides standardising technical parameters for rolling stock
(metro coaches) and signaling equipment.
To develop in-house expertise on long-term basis, metro companies with large size
fleet to undertake in-house maintenance.
Indigenisation of several metro functions has also been prescribed. These relate to
communication systems, managing operational disturbances, time table preparation, fault
reporting, control traction power, maintenance, infrastructure supervision, rolling stock
management, etc.
Opportunity analysis
While calculating the size of the overall opportunity, we have included only those cities
where the DPR has been prepared and the route alignment has been finalised. Thus, cities
like Vijaywada, Vizag, Jaipur (Phase II) and Hyderabad (Phase II), which are at conceptual
Metro rail development is likely to stage and the DPR is yet to be prepared, or whose future is uncertain, have not been
lead to ~INR2500bn orders over included in our analysis.
the next five years; civil
construction orders will form the Other assumptions are:
biggest chunk of this at
We have not included monorail orders as part of this analysis.
~INR1500bn
Of the overall cost, 45% pertains to civil construction, 20% to rolling stock and 15% will
be spent on systems (electrical and communication) work.
Systems and rolling stock contracts will be awarded 6-12 months after the award of civil
construction contracts.
We have not included Meerut Metro, which is currently awaiting the Centre’s approval,
as it is likely to be put on hold in view of the Delhi-Ghaziabad-Meerut Regional Rapid
Transit System (RRTS), that has recently been approved by the central government.
Our analysis indicates that of the overall ~INR2,500bn opportunity, ~INR1,510bn pertains
to civil construction, ~INR440bn to systems i.e., electrical and signalling, while ~INR590bn
is the scope for rolling stock.
In FY20 and FY21, we expect civil construction awards to drive overall project awarding.
However, over the next few years, we expect this trend to shift towards systems and rolling
stock. In FY24, we expect overall project awarding to be driven by systems and rolling stock.
During FY20, Delhi, Mumbai and Bengaluru Metros are expected to drive project awards.
The systems and rolling stock awards are likely to be driven by Mumbai Metro. Civil
construction awards are expected to rise significantly in FY21, with major awarding in
Chennai Metro (Phase II), Mumbai Metro, Delhi Metro and Bengaluru Metro. After FY21,
systems and rolling stock orders are expected to pick up and overtake civil construction
awards by FY23.
We have summarised the tentative time line of project awards (civil construction, systems
and rolling stock contracts) for various metro networks over the next couple of years. We
have further broken down the awards in terms of respective projects for ease of reference.
With respect to civil construction contracts, Delhi, Mumbai and Chennai Metros are
expected to provide the significant near-term opportunity.
As far as systems contracts are concerned, near-term opportunity is in Mumbai Metro (Lines
4 and 6) which are expected to be awarded in FY21. After this, other Mumbai Metro lines, as
well as new projects such as Indore, Bhopal, Meerut and Patna, will come up for awarding.
Rolling stock contracts are likely to follow a similar time line as systems contracts.
Funding of projects
While certain projects have been awarded on PPP mode such as Hyderabad Metro Phase I,
and Pune Metro Line 3, we expect a majority of the projects to be funded by the
government.
News reports indicate that the central government is setting up a fully-owned SPV to house
all its equity and debt investments in metro rail projects across the country. The SPV, which
will be under the Ministry of Housing & Urban Affairs, will also monitor all metro projects.
The SPV will raise funds via a mix of equity, debt and also borrow from external agencies. It
will borrow funds directly from the market or from the state-owned India Infrastructure
Finance Company (IIFCL).
Currently, Delhi Metro is the largest metro rail network in India in terms of the number of
stations, length, ridership as well as the number of lines.
All contracts for this phase have been awarded. While certain lines have been
comissioned, other lines are in various stages of development. Overall, the phase is
scheduled to be completed by 2020.
Phase IV: Significant opportunity in future from an ordering perspective arises from the
planned Phase IV of Delhi Metro. This is a proposed ~105km network with an estimated
overall cost of ~INR468bn. Of this, three lines, with an overall length of ~63km and a
cost of ~INR249bn, have been approved by the Centre, and the balance three lines,
with a length of ~42km and cost of ~INR184bn, are awaiting the Centre’s approval.
This phase is proposed to be completed by 2025, subsequent to which the overall Delhi
Metro will span ~478km.
We expect civil construction awarding between FY20 and FY22 and the rolling
stock/systems awarding in FY23.
Apart from Delhi Metro, there is another rail mobility project in the National Capital
Region (NCR) called the Regional Rapid Transit System (RRTS). This is a planned high
speed commuter service along dedicated corridors in NCR. Two lines have been
proposed:
o Delhi-Meerut RRTS: This is a propsoed 82km long corridor connecting Delhi-
Ghaziabad-Meerut at an estimated cost of ~INR303bn. This is expected to start
operations by 2025.
o Delhi-Alwar RRTS: This is a propsoed 164km long corridor connecting Delhi,
Gurgaon, Rewari and Alwar, with a total estimated cost of ~INR370bn. This is
propsoed to be complete by December 2024.
While these dedicated high speed corridors will be integrated with the Delhi Metro,
they form an independent system outside the gambit of metro rail, and hence, we are
not considering these projects in our study.
Bengaluru Metro
Work on a metro network in Bengaluru had started quite early with the DMRC submitting a
DPR in 2003. Construction on Phase I was envisaged to commence in 2005, but was delayed.
Work finally began in 2007 and in October 2011, Bengaluru became the third city in India to
have an operational metro when operations commenced on a 7km stretch. Subsequenrly,
Bengaluru Metro Phase II, costing
over 2014-17, the remaining lines were commissioned, and currently, Phase I of the network
around INR470bn, is currently
is fully operational.
under development
Phase II, spanning ~130km, with a total estimated outlay of ~INR470bn (including the Red
Line extension to the airport and the Outer Ring Road Metro), is under construction and is
expected to be fully operational by 2024.
The project is being implemented by Bangalore Metro Rail Corporation (BMRC), which is
jointly owned (50:50) by central and state governments.
Phase II: This phase, with a total length of ~130km, including the planned airport
extension and the Outer Ring Road Metro, is currently under construction. This phase
consists of construction of two new lines (Yellow and Red) as well as extensions of lines
build in Phase I. This phase also includes a proposed 38km extension of the Red Line to
the Bengaluru International Airport as well as a 17km Outer Ring Road line from Silk
Board – K.R.Puram. This phase is estimated to cost ~INR470bn.
On the civil construction front, while some awarding has been completed, a couple of
packages of the Red Line from Dairy Circle to Nagawara, as well as the airport extension
and the Outer Ring Road line are yet to be awarded. Rolling stock and systems are yet
to be awarded for the entirety of Phase II.
Mumbai Metro
Mumbai is witnessing probably the Mumbai also has ambitious plans to build a metro network within the city. We had
largest and amongst the fastest highlighted in our note earlier that Mumbai is witnessing probably the largest and amongst
metro rail expansion programme in the fastest metro rail expansion programme in the world currently (refer to, Mumbai
the world currently Metro: Opportunities of windfall). The plan is to build a network spanning ~270km across
12 lines. Details of the various lines are:
Line 1: This 11km fully elevated line, which was built on a PPP basis, connects Versova to
Ghatkopar. The project was conceptualised in 1997 and a feasibility study was conducted
Line 2: The project received state government approval in November 2006. Initially, in
August 2009, this project was awarded to a consortium of RInfra (48%), Reliance
Communication (26%) and SNC Lavalin (26%) on PPP basis. However, due to multiple
delays, this agreement was terminated in 2014 by mutual consent. Subsequently,
MMRDA appointed DMRC as a consultant to execute this line and construction
packages were awarded to various contractors.
Line 3: This was originally supposed to be a 20km line connecting Colaba to Bandra.
However, in its final form, it will be a 33km line connecting SEEPZ to Colaba (Mumbai
Metro: On the fast track).
This fully underground line is estimated to cost ~INR300bn and will be built on the
DMRC model. Civil construction packages, worth ~INR181bn, were awarded in October
2015.
Cuffe Parade, Vidhan Bhavan, Churchgate, Hutatma Chowk 4.0 30 L&T - Shanghai Tunnel Engineering Company
CST Metro (C&C) Kalbadevi, Girgaon, Grant Road 4.1 25 HCC - OSJC Moscow Metrostroy
Central Metro, Mahalaxmi, Science Museum, Worli, Acharya Atre Chowk 6.4 26 Soma - DOGUS
The rolling stock contract for this line, for 210 coaches worth ~INR20bn, was awarded
to Alstom in 2017.
Line 4: This is a 35km elevated line from Wadala to Gaimukh (including Line 4A
extension from Kasarvadavali to Gaimukh) with 34 stations and an estimated outlay of
~INR155bn. This line is expected to be completed by 2022.
Rolling stock (216 coaches) and systems contracts are yet to be awarded.
Line 5: This is a proposed 25km elevated line from Thane to Kalyan via Bhiwandi with
17 stations. This project is estimated to cost ~INR84bn. The line was approved by the
Maharashtra Cabinet in October 2017.
We expect civil works awarding in FY21 after the Center’s approval, and subsequently,
we expect rolling stock and systems awarding in FY22.
Line 6: This is a proposed 15km elevated line from Lokhandwala to Kanjurmarg with 13
stations. This project is estimated to cost ~INR67bn.
While JKIL bagged two packages for civil contracts in August 2018, the rolling stock and
systems awarding is pending; we expect the same in FY21.
Line 7: This is a 16km elevated line from Andheri (East) to Dahisar (East) with estimated
cost of ~INR62bn. This line is currently under construction.
The rolling stock contract was awarded to BEML and the systems contract was awarded
to Alstom.
Line 8: This is a 35km proposed line from the Mumbai International Airport (CSIA) to
the upcoming Navi Mumbai airport (NMIA). This line is expected to cost ~INR150bn and
is currently at the concept stage.
Line 9: This is a 14km partly underground line from Dahisar East to Mira-Bhayandar and
also includes the extension of Line 7 from Andheri East to CSIA. This line has been
approved and tenders have been floated for civil construction.
Line 10: This is a 11km proposed elevated line from Gaimukh to Shivaji Chowk (Mira
Road). This is estimated to cost ~INR45bn and is currently at the concept stage.
Line 11: This is a 11km proposed partly underground line from Wadala to CSMT. This is
estimated to cost ~INR87bn and is currently at the concept stage.
Line 12: This is a 21km proposed elevated line from Kalyan to Taloja via Dombivali. This
is estimated to cost ~INR41bn and is currently at the concept stage.
Chennai Metro
Chennai was the second city in India, after Kolkata, to have a MRTS network. Chennai MRTS
is owned by the Indian Railways and was built at a cost of INR11.7bn. While the project was
taken up for implementation by Railways in 1983-84, construction started in earnest only in
1991. Phase 1 started in 1995 and was the first elevated line in India. Since then, the
network was extended in 2004 and 2007, and currently spans ~20km.
Apart from MRTS, there is a metro system in the city that is partly operational. This metro
system is being developed in two phases.
Phase I: Phase I of the project consists of two lines totalling ~54km, of which ~45km is
currently operational and the balance is expected to be completed in 2020. The Phase I was
developed at a total cost of ~INR191bn.
Work on the project started in 2009. The Blue and the Green lines are currently operational
and the Blue Line Extension is expected to be completed in 2020.
Phase II: Under this phase, three lines spanning 119km have been approved at a total
estimated cost of ~INR690bn:
Line 3: 46km line fron Madhavaram to Siruseri
Line 4: 26km line from Poonamallee to Lighthouse
Line 5: 47km line from Madhavaram to Sholinganallur
Hyderabad Metro
The Hyderabad Metro project was first conceptualised in 2005. A detailed feasibility study
was carried out by DMRC in 2005. The project was approved by the central government in
April 2008. The project was proposed to be built entirely on PPP basis with the state
government holding a minority stake.
The project was first bid out in 2008 with the total cost estimated at ~INR118bn. The central
government had approved a VGF of INR35bn for the project. The project was awarded to a
consortium including Maytas Infra. Instead of asking for a VGF, the consortium had
promised to pay the government INR303.11bn during the concession period (with a present
While Phase I of Hyderabad Metro value of INR12.4bn, discounted at 13.5%). However, following the Satyam controversy and
is currently under development, the inability of the consortium to achieve financial closure, the project was scrapped in July
Phase II is also under consideration 2009.
Fresh bids were invited in July 2010 with an approved project cost as per central
government of INR121.3bn. The maximum amount of VGF on the project was capped at
40% i.e., INR48.5bn.
The project was awarded to Larsen & Toubro (L&T), which won the project by asking for the
least amount of VGF—INR14.58bn (12% of project cost). There were two other bidders for
the project—a consortium of Transstroy India-OJSC Transstroy Russia-CR18G which had
asked for a VGF of INR22bn (18% of project cost) and a consortium including Reliance Infra
which had asked for a VGF of INR29.91bn (25% of project cost).
In addition to the VGF, sops to the developer were provided through a right to commercially
develop land available at depots (212 acres) and 10% of the carpet area of station sites. This
aggregates to a cumulative maximum of 12.5mn sq ft in the case of depots and a cumulative
maximum of 6mn sq ft in the case of stations.
The Hyderabad Metro consisting of three lines stretching 73km is the world’s largest metro
rail project on PPP basis. It has a concession period of 35 years (including five years for
construction) and can be extended by another 25 years. The network consists of the
following lines:
Line 1: 29km line connecting Miyapur and LB Nagar. This line is currently operational.
Line 2: 15km line connecting JBS to Falaknuma. This line is under construction and
expected to be complete by 2022.
Line 3: 28km line connecting Nagole to Raidurg. In this line, the section between Nagole
and HITEC City, spanning 27km, is currently operational. The extension to Raidurg,
which is around a kilometer long, is currently under construction.
Phase II of Hyderabad Metro is also under consideration with various lines spanning 100km
plus being proposed.
Ahmedabad Metro
This is the metro network in Ahmedabad and Gandhinagar. The state government has set up
Metro Link Express for Gandhinagar and Ahmedabad (MEGA) for implementing the project.
Phase I: Phase I of the project consists of two lines spanning 68km with a total estimated
cost of ~INR163bn.
Line 1: This is the East-West corridor from Vastral Gaam to Thaltej Gaam with a length
of 21km and estimated cost of ~INR67bn. This line is proposed to have 18 stations.
Most of this line is elevated.
This line is partially operational (Apparel Park to Vastral Gaam section of 6km) and the
rest is expected to be completed by 2020.
Line 2: This is the North-South corridor from Motera to Gyaspur with a length of
Phase II of Ahmedabad Metro with 18.5km and estimated cost of ~INR40bn.
estimated cost of ~INR55bn has This is an elevated line that is currently under construction and is expected to be
been approved completed by 2020.
The rolling stock order of 96 coaches was awarded to Hyundai Rotem for ~INR18bn. The
systems contracts were awarded to Siemens, Nippon Signal and L&T.
Phase II: Phase II of Ahmedabad Metro consists of two lines with estimated cost of
~INR55bn. This was recently approved by the Union Cabinet. One line with a total length of
21km will connect Motera to Gandhinagar and the other 5.4km line will provide connectivity
to the under development GIFT City.
Pune Metro
Pune Metro is the metro network serving Pune and Pimpri Chinchwad. The network consists
of three lines with a total length of ~55km and total estimated cost of ~INR206bn. Line 1
and 2 form part of Phase I and Line 3 forms part of Phase II.
Line 1: This consists of a 11.6km elevated stretch between Pimpri Chinchwad Municipal
3 lines of Pune Metro are currently Corporation (PCMC) and Shivaji Nagar, and a 5km underground stretch between Shivaji
under development Nagar and Swargate. This line is currently under construction and is expected to be
completed by 2021.
Line 2: This consists of a 14.7km elevated stretch between Vanaz and Ramwadi. This line is
currently under construction and is expected to be completed by 2021.
The rolling stock for Pune Metro Lines 1 & 2 is proposed to be manufactured at
MahaMetro’s proposed Butibori plant (at least 75% of the coaches are proposed to be
manufactured here). As per news reports, MahaMetro’s first preference is to form a joint
venture with a coach manufacturer, but if it does not get any response, it will set up the
plant on its own and proceed with the manufacturing.
Signalling systems orders for Lines 1 & 2, worth ~INR3bn, have been awarded to Alstom.
Line 3: This consists of a 23.3km elevated stretch between Hinjewadi and Shivaji Nagar. This
project has been awarded to a consortium of Tata Realty-Siemens on PPP mode for
~INR83bn. While the EPC component of this project will be handled by Tata Projects, the
rolling stock and systems are likely to be supplied by Siemens, leveraging Siemens’ strong
presence in these segments.
Hence, we are not considering any opportunity from this line for other contractors.
Lucknow Metro
Lucknow Metro consists of a 23km operational North-South corridor and a planned 12km
East-West corridor, that is currently awaiting state cabinet approval.
Construction of the North-South line began on September 27, 2014, with the 8.5km stretch
from Transport Nagar to Charbagh Railway Station beginning commercial operation on
September 5, 2017, making it the fastest built metro rail system in the country. The
complete 23km stretch was inaugurated in March 2019.
North-South corridor: This is a 23km partly underground (19km elevated and 4km
underground) stretch between Amausi (airport) and Munshi Pulla. The total cost for this
project was ~INR69bn and is currently operational.
The rolling stock award worth ~INR11bn for 80 coaches was won by Alstom. Systems
contracts have been awarded to Alstom (signalling), L&T (telecommunications) and Kalindee
(Texmaco Rail) (ballastless tracks).
East-West corridor: This is a planned 12km partly underground stretch between Charbagh
Railway Station and Vasant Kunj. The total cost for this project is expected to be ~INR45bn.
The DPR has been submitted to the state government and approval for the same is awaited.
Kochi Metro
The Kerala state government had asked DMRC to prepare a DPR for the project in 2004. The
project was envisaged on the DMRC model with central and state government participation.
However, it look long for the central government approval to materialise. The project
received approval from the Public Investment Board (PIB) in March 2012 and from the
Union Cabinet in July 2012. It is being implemented by Kochi Metro Rail (KMRL), which was
formed in August 2011. The project is being carried out in two phases:
Phase I: The first phase consists of a 25km stretch between Aluva and Pettah; this
phase is expected to cost ~INR52bn. It includes the following lines:
o Aluva to Palarivattom – 13km stretch that was commissioned in June 2017.
o Palarivattom to Maharaj’s College – 5km stretch that was commissioned in August
Phase II of Kochi Metro with a cost
2017.
of ~INR23bn, has been approved
by the state government and is o Maharaja’s College to Thykkoodam – 5km stretch that is currently under
awaiting the Center’s approval construction and is expected to be completed by June 2019.
o Thykoodam to Pettah – 1km stretch that is currently under construction and is
expected to be completed by June 2020.
Phase IA: This is an extension of the Phase 1 line, extending the line from Pettah to
Tripunithura via SN Junction. This is a 2km extension at a cost of ~INR3bn. This is
currently in the planning stage.
Civil construction contracts for Phase I and IA were awarded to L&T, Soma, CVCC and
Era-Ranken JV. The rolling stock contracts for 75 coaches as well as the systems
contracts (for signalling, train control, telecommunication, automatic fare collection
and power) have been awarded to Alstom.
Phase II: This phase consisting of an 11km stretch between Jawaharlal Nehru Stadium
and Infopark II in Kakkanad, with a total expected outlay of ~INR23bn, has been
approved by the state government and is awaiting the Center’s approval.
Nagpur Metro
The Nagpur Metro system consists of a 90km metro network, of which 13.5km is
operational, 28.5km is under construction and 48km is being planned. The network has
been planned in two phases:
Phase I: This phase is a 42km network with 40 stations and a total estimated cost of
~INR87bn. Part of this line (13.5km) is operational and balance is expected to be completed
by 2022.
A 13.5km stretch between Sitabuldi and Khapri, with 11 stations, was inaugurated in March
2019 and is currently operational.
Phase II: This phase consists of a planned network of 48km, with an estimated cost of
Phase II of Nagpu Metro with a ~INR112bn. The following lines are proposed to be included in this phase:
cost of ~INR112bn, has been Lokmanya Nagar – Hingna: 6.6km
approved by the state government Wasudeo Nagar – Wadi: 4.5km
and is awaiting the Center’s
Automotive Square - Kanhan River: 13km
approval
Prajapati Nagar - Transport Nagar: 5.5km
MIHAN – MIDC: 18.7km
This phase has been approved by the state government and is awaiting central
government’s approval.
Noida Metro
The Noida Metro network consists of one line (Aqua Line) from Sector 51 to Depot, with a
total length of 29.7km serving 21 stations. This is fully complete and is currently operational.
It was built at a total cost of ~INR55bn.
Phase II is on the cards and has been approved by the state government and is currently
awaiting the Center’s approval. This phase consists of a 15km line from Noida Sector 71 to
Knowledge Park V in Greater Noida, with nine stations, at an estimated cost of ~INR26bn.
A line connecting Greater Noida to the proposed airport at Jewar has also been proposed
and the DPR has been prepared for the same. This is proposed to be a 36km line with 25
stations, at an estimated cost of ~INR57bn.
Table 28: Total opportunity from Noida Metro Phase II and airport extension
Ordering scope (INR bn) FY20 FY21 FY22 FY23 FY24 Total
Civil construction 0 6 6 13 13 37
Systems 0 0 0 4 0 4
Rolling stock 0 0 0 5 0 5
Total 0 6 6 22 13 47
Source: Edelweiss research
Indore Metro
Indore Metro system is currently under construction. The total system consists of a network
length of 104km with estimated cost of ~INR268bn.
The first corridor, which is a 32km ring line starting and ending at Bengali Square, has been
approved by the Centre. This line has 30 stations and is expected to cost ~INR75bn.
Construction has commenced on a 5km stretch between ISBT and Mumtaj Bag Colony, for
Metro rail projects in Indore and
which the civil construction has been awarded to Dilip Buildcon for a total cost of ~INR2bn.
Bhopal are currently under
development
The remaining corridors, totalling up to ~72km, with an estimated cost of ~INR193bn have
been given an “in-principle approval” by the Union Finance Ministry and are awaiting
approvals from the finance ministry’s Public Investment Board, after which it will be sent to
the Union Cabinet for approval.
Bhopal Metro
The Bhopal Metro is under construction with a total proposed length of 95km and a total
estimated cost of ~INR225bn. This system has been divided in to two phases:
Phase I: This phase consists of two corridors with a total length of 28km and estimated cost
of ~INR69bn. This phase has been approved by the Centre and construction has
commenced. The two corridors in this phase are:
Corridor 1: AIIMS to Karond Circle (15km)
Corridor 2: Ratnagiri Tiraha to Bhadbhada Square (13km)
The civil construction contract for a 6km stretch between AIIMS and Subhash Nagar
(excluding stations) has been bagged by Dilip Buildcon for ~INR2bn and construction has
commenced.
Phase II: Phase II is expected to span 67km with a total estimated outlay of ~INR156bn. This
phase was recently given an “in-principle approval” by the Union Finance Ministry, and is
awaiting approvals from the finance ministry’s Public Investment Board, after which it will
be sent to the Union Cabinet for approval.
Navi Mumbai
The Navi Mumbai Metro is an under construction project that is being planned and
constructed by the City and Industrial Development Corporation (CIDCO). The system is
planned to consist of three lines with a total length of 23km and estimated cost of
~INR76bn.
Although the Maharashtra government has released a 106.40km master plan comprising six
lines, news report suggest that it is unlikely that this will be followed. New metro lines are
expected to be announced once construction for the Navi Mumbai Airport project is kick-
started.
The rolling stock contract for Line 1 was awarded to CSR Zhuzhou at a cost of
~INR3bn and the systems conrtact was awarded to Ansaldo STS.
Line 3: Interlink between Pendhar and MIDC: This is a 2km linking line that will be
built at an estimated cost of INR6bn subsequent to the completion of Line 1.
Agra Metro
The proposed metro network in Agra consists of two lines with an overall length of 30km
Metro projects in Agra, Kanpur and
and a total estimated cost of ~INR85bn. The project has been approved by the Union
Patna with a cumulative
Cabinet. The two lines are:
investment of ~INR340bn have
been approved by the Center Line 1: Sikandra to Taj East Gate – 14km line with an 8km underground section and 6km
elevated section.
Kanpur Metro
Kanpur Metro is a planned with a network length of 32km and total estimated cost of
~INR120bn. This project was recently approved by the central government.
Patna Metro
Patna Metro (Phase I) consists of a 31km partly underground network, with a total
estimated cost of ~INR134bn. This project recently received the Union Cabinet approval and
consists of two lines:
Line 1: Danapur to Mithapur – This is a 17km line, which is mostly underground (11km)
and partly elevated (5km) and comprises of 11 stations (tree elevated and eight
underground).
Line 2: Patna Junction to ISBT – This is a 14km line, which is mostly elevated (10km) and
partly underground (5km) and comprises of 12 stations (nine elevated and three
underground).
Future phases include a 13km line from Mithapur to Didarganj and a 11km line from Bypass
Chowk to Kurji. These are in the conceptual stage as of now and therefore, have not been
considered for our analysis.
Guwahati Metro
Guwahati Metro is a proposed system spanning 65km with a total estimated cost of
~INR180bn. This project has been approved by the state government and is currently
awaiting the Centre’s approval. It consists of four corridors:
Line 1: Dharapur to Narangi – This is a 27km elevated line with 22 stations
Line 2: MG Road to Khanapara – This is a 10km underground line with 10 stations
Line 3: Jalukbari to Khanapara – This is a 19km elevated line with 14 stations
Line 4: ISBT to Paltanbazar – This is a 9km elevated line with 8 stations
Surat Metro
Surat Metro is a 40km partly underground metro system with a total estimated cost of
~INR120bn. This project has been approved by the Union cabinet and consists of two lines:
Line 1: Sarthana to Dream City – This is a 22km line comprising of an underground
section of 6km and an elevated corridor of 15km connecting 20 metro stations
Line 2: Saroli to Bhesan – This is a 9km completely elevated corridor that will connect
18 Metro stations.
Other Cities
Apart from the cities mentioned above where the development of metro network is
planned or already underway, there are multiple cities where rapid transit systems have
been proposed, and either feasibility studies are proposed to be done/are underway or the
DPR is being prepared. These cities include Gorakhpur, Nashik, Vijaywada, Vizag,
Coimbatore, Jabalpur, Gwalior, Srinagar, Bareili, Prayagraj, Ranchi, Dehradun etc. Therefore,
there is significant opportunity going ahead as these plans come to fruition.
Edelweiss Securities Limited, Edelweiss House, off C.S.T. Road, Kalina, Mumbai – 400 098.
Board: (91-22) 4009 4400, Email: research@edelweissfin.com
ADITYA
Digitally signed by ADITYA NARAIN
DN: c=IN, o=EDELWEISS SECURITIES LIMITED,
Aditya Narain ou=HEAD RESEARCH, cn=ADITYA NARAIN,
serialNumber=e0576796072ad1a3266c27990
f20bf0213f69235fc3f1bcd0fa1c30092792c20,
Head of Research
NARAIN
postalCode=400005,
2.5.4.20=6b7d777d3c8c77e0e2c454e91543f9
f4d9b8311cf0678cd975097fc645327865,
aditya.narain@edelweissfin.com st=Maharashtra
Date: 2019.05.06 18:20:07 +05'30'
Recent Research
Date Company Title Price (INR) Recos
15-Feb-19 Ahluwalia One-off quarter; order intake 261 Buy
Contracts surge continues;
Result Update
14-Feb-19 NBCC Subsidiaries drag margins; 49 Reduce
Result Update
13-Feb-19 J Kumar Strong performance 121 Under
Infraprojects continues; Result Update Review
All price charts cannot be included given the large number of companies in our coverage. Specific charts may be available upon request.
This Report has been prepared by Edelweiss Securities Limited in the capacity of a Research Analyst having SEBI Registration
No.INH200000121 and distributed as per SEBI (Research Analysts) Regulations 2014. This report does not constitute an offer or
solicitation for the purchase or sale of any financial instrument or as an official confirmation of any transaction. Securities as
defined in clause (h) of section 2 of the Securities Contracts (Regulation) Act, 1956 includes Financial Instruments and Currency
Derivatives. The information contained herein is from publicly available data or other sources believed to be reliable. This report is
provided for assistance only and is not intended to be and must not alone be taken as the basis for an investment decision. The
user assumes the entire risk of any use made of this information. Each recipient of this report should make such investigation as it
deems necessary to arrive at an independent evaluation of an investment in Securities referred to in this document (including the
merits and risks involved), and should consult his own advisors to determine the merits and risks of such investment. The
investment discussed or views expressed may not be suitable for all investors.
This information is strictly confidential and is being furnished to you solely for your information. This information should not be
reproduced or redistributed or passed on directly or indirectly in any form to any other person or published, copied, in whole or in
part, for any purpose. This report is not directed or intended for distribution to, or use by, any person or entity who is a citizen or
resident of or located in any locality, state, country or other jurisdiction, where such distribution, publication, availability or use
would be contrary to law, regulation or which would subject ESL and associates / group companies to any registration or licensing
requirements within such jurisdiction. The distribution of this report in certain jurisdictions may be restricted by law, and persons
in whose possession this report comes, should observe, any such restrictions. The information given in this report is as of the date
of this report and there can be no assurance that future results or events will be consistent with this information. This information
is subject to change without any prior notice. ESL reserves the right to make modifications and alterations to this statement as
may be required from time to time. ESL or any of its associates / group companies shall not be in any way responsible for any loss
or damage that may arise to any person from any inadvertent error in the information contained in this report. ESL is committed
to providing independent and transparent recommendation to its clients. Neither ESL nor any of its associates, group companies,
directors, employees, agents or representatives shall be liable for any damages whether direct, indirect, special or consequential
including loss of revenue or lost profits that may arise from or in connection with the use of the information. Our proprietary
trading and investment businesses may make investment decisions that are inconsistent with the recommendations expressed
herein. Past performance is not necessarily a guide to future performance .The disclosures of interest statements incorporated in
this report are provided solely to enhance the transparency and should not be treated as endorsement of the views expressed in
the report. The information provided in these reports remains, unless otherwise stated, the copyright of ESL. All layout, design,
original artwork, concepts and other Intellectual Properties, remains the property and copyright of ESL and may not be used in
any form or for any purpose whatsoever by any party without the express written permission of the copyright holders.
ESL shall not be liable for any delay or any other interruption which may occur in presenting the data due to any reason including
network (Internet) reasons or snags in the system, break down of the system or any other equipment, server breakdown,
maintenance shutdown, breakdown of communication services or inability of the ESL to present the data. In no event shall ESL be
liable for any damages, including without limitation direct or indirect, special, incidental, or consequential damages, losses or
expenses arising in connection with the data presented by the ESL through this report.
We offer our research services to clients as well as our prospects. Though this report is disseminated to all the customers
simultaneously, not all customers may receive this report at the same time. We will not treat recipients as customers by virtue of
their receiving this report.
ESL and its associates, officer, directors, and employees, research analyst (including relatives) worldwide may: (a) from time to
time, have long or short positions in, and buy or sell the Securities, mentioned herein or (b) be engaged in any other transaction
involving such Securities and earn brokerage or other compensation or act as a market maker in the financial instruments of the
subject company/company(ies) discussed herein or act as advisor or lender/borrower to such company(ies) or have other
potential/material conflict of interest with respect to any recommendation and related information and opinions at the time of
publication of research report or at the time of public appearance. ESL may have proprietary long/short position in the above
mentioned scrip(s) and therefore should be considered as interested. The views provided herein are general in nature and do not
consider risk appetite or investment objective of any particular investor; readers are requested to take independent professional
advice before investing. This should not be construed as invitation or solicitation to do business with ESL.
Additional Disclaimers
This report is intended for distribution by Edelweiss Securities Limited only to "Major Institutional Investors" as defined by Rule
15a-6(b)(4) of the U.S. Securities and Exchange Act, 1934 (the Exchange Act) and interpretations thereof by U.S. Securities and
Exchange Commission (SEC) in reliance on Rule 15a 6(a)(2). If the recipient of this report is not a Major Institutional Investor as
specified above, then it should not act upon this report and return the same to the sender. Further, this report may not be copied,
duplicated and/or transmitted onward to any U.S. person, which is not the Major Institutional Investor.
In reliance on the exemption from registration provided by Rule 15a-6 of the Exchange Act and interpretations thereof by the SEC
in order to conduct certain business with Major Institutional Investors, Edelweiss Securities Limited has entered into an
agreement with a U.S. registered broker-dealer, Edelweiss Financial Services Inc. ("EFSI"). Transactions in securities discussed in
this research report should be effected through Edelweiss Financial Services Inc.
In the United Kingdom, this research report is being distributed only to and is directed only at (a) persons who have professional
experience in matters relating to investments falling within Article 19(5) of the FSMA (Financial Promotion) Order 2005 (the
“Order”); (b) persons falling within Article 49(2)(a) to (d) of the Order (including high net worth companies and unincorporated
associations); and (c) any other persons to whom it may otherwise lawfully be communicated (all such persons together being
referred to as “relevant persons”).
This research report must not be acted on or relied on by persons who are not relevant persons. Any investment or investment
activity to which this research report relates is available only to relevant persons and will be engaged in only with relevant
persons. Any person who is not a relevant person should not act or rely on this research report or any of its contents. This
research report must not be distributed, published, reproduced or disclosed (in whole or in part) by recipients to any other
person.
This report is intended for distribution by ESL only to "Permitted Clients" (as defined in National Instrument 31-103 ("NI 31-103"))
who are resident in the Province of Ontario, Canada (an "Ontario Permitted Client"). If the recipient of this report is not an
Ontario Permitted Client, as specified above, then the recipient should not act upon this report and should return the report to
the sender. Further, this report may not be copied, duplicated and/or transmitted onward to any Canadian person.
ESL is relying on an exemption from the adviser and/or dealer registration requirements under NI 31-103 available to certain
international advisers and/or dealers. Please be advised that (i) ESL is not registered in the Province of Ontario to trade in
securities nor is it registered in the Province of Ontario to provide advice with respect to securities; (ii) ESL's head office or
principal place of business is located in India; (iii) all or substantially all of ESL's assets may be situated outside of Canada; (iv)
there may be difficulty enforcing legal rights against ESL because of the above; and (v) the name and address of the ESL's agent for
service of process in the Province of Ontario is: Bamac Services Inc., 181 Bay Street, Suite 2100, Toronto, Ontario M5J 2T3 Canada.